Background & Project Outline


Effective reproductive health care services must be given primacy to
ensure the birth and care of healthy children and to promote
responsible parenting
The supply of a turn-key OSD facility for the tableting of oestradiol as
a oral contraceptive
The facility is recommended as a modular facility in order to ascertain
predictability, quality and delivery time
The facility meet the regulatory requirements of WHO & EMA
It is a green field arrangement to be set up at site within a time
period of 14 months.
KeyPlants All rights reserved

Scope of Work

Design &
Engineering
Signing of
Contact

IN ESTONIA

AT SITE

Procurement
Modules
Construction
Installation of
equipment
IQ & GMP
Inspection
Plant
Disassembly

Signing of
Contract
Warehouse &
Shipment
Administr. bldg
Reassembly
Foundation and
of Plant
sewage system
Operator
Electricity and
Training
water supply
Commissioning
IQ OQ
Validation/PQ

KeyPlants All rights reserved

Operation
Production

Containment in OSD Production

Risk assesment
GMP and containment
Protect the product
Protect the employees

KeyPlants All rights reserved

Potency OEL

KeyPlants All rights reserved

Specific for High OEL


American and European personal safety
requirements at high product Operating
Exposure Levels (OEL levels) the process shall
be closed in isolators or the operator should
have full protection breathing suites.

KeyPlants All rights reserved

General Recomendations

Detailed Design documents needs to show


clearly how the requirements for both product
protection and containment are fulfilled.
Documents that support this are:
Gowning procedures
HVAC Zoning drawings, showing on layout which
area each AHU is serving
Pressurization drawings showing the relative room
pressure on the layout.

KeyPlants All rights reserved

OSD Project Example


Design of a contained hormone facility comprising of:

Production (Process) area


Clean utilities
IPC lab
QC lab
Warehouse and packaging
Lockers

Delivery time 14.5 months after start of Detailed


Design
Earthquake safe

KeyPlants All rights reserved

Process Plant Description


Two storied modular building, in total: 540 m2 (9 modules),
(Ground floor: 300 m2, first floor: 240 m2)
Contained OSD facility (Oestradiol Hormon)
HVAC and utility generation and distribution
Stand alone facility (all process and utility equipment incl.)
Adjacent support functions: Emergency Power & Process
Waste Water Treatment

KeyPlants All rights reserved

Dispensing
API dispensing in isolator
Excipients dispensing under LAF

KeyPlants All rights reserved

Blending and Granulation

KeyPlants All rights reserved

Sieving

KeyPlants All rights reserved

Tabletting

KeyPlants All rights reserved

Coating

KeyPlants All rights reserved

Sorting

KeyPlants All rights reserved

Blister Packaging

KeyPlants All rights reserved

Layout Ground Floor

KeyPlants All rights reserved

Detail design in 3D

KeyPlants All rights reserved

Equipment Installations

KeyPlants All rights reserved

Containment Ground Floor

KeyPlants All rights reserved

Layout First Floor

KeyPlants All rights reserved

Utility Installations

KeyPlants All rights reserved

Transport

KeyPlants All rights reserved

Site Assembly

KeyPlants All rights reserved

Time Schedule

KeyPlants All rights reserved

Important features

Short delivery time (6 - 10 months faster than alternatives)


Predictable schedule
Fixed price
Process and project experience
Modular construction guarantee earthquake safe
pharmaceutical production buildings
Risk with contractor
Guaranteed quality through off-site construction
IQ majority finalised off-site
Possibility for tech transfer training off-site

= over-all very favourable (VPN value)/total project economy.


KeyPlants All rights reserved

Example: profit from earlier start up

Product annual sales


20 M (10M x 2) with a Gross Margin of 50%
Production Up-Time 48 weeks/year
20 M/48 weeks = 0,42 M/week
50% GM = 0,21 M/week

Incremental Revenue with faster delivery


6 Months = 24 weeks = 5 M
12 Months = 48 weeks = 10 M

KeyPlants All rights reserved

Value proposition
Time
Shorter time to market
(6-24 months faster than conventional)
Deferred investment decision
More time for process development

Optimized cGMP Process Solutions & Lay-out


Predictability
On Budget
Completion as scheduled
Limited customer resources

Quality & Documentation (GMPs)


Faster Return-on-Investment (ROI)

KeyPlants All rights reserved