Sei sulla pagina 1di 69

CONSTRUCTION OF ROADS AND INFRAESTRUCTURE IN

AL KHEESA NORTH AND EAST


(RAWDAT AL HAMAMA DISTRICT)
PACKAGE 01
PROJECT ID: IA 13/14 C 006 ST

Construction Health, Safety & Security Plan

Document Identification Number:

Project Ref: No. / Doc Ref: No. IA/13-14/C/006/ST

Issue Number (Revision)

Rev-2

Date:

Date 18/04/2015

DOCUMENT AUTHORISATION SHEET

The Client:

Ashghal

Document Title

Construction Health, Safety & Security Plan

PREPARED BY:
Name:

Enrique Fajardo

Position:

Safety Manager

Date:

18/04/2015

Signature

CHECKED BY:
Name:

Eng.Salameh Haddadin

Position:

Project Manager

Date:

18/04/2015

Signature

DISTRIBUTION
THE MASTER COPY IS TO BE LOCATED AT THE SITE OFFICE, OR FOR TRANSIENT SITES AT ANOTHER
NOMINATED EASILY ACCESSIBLY LOCATION
Copy
Number

Assigned To
Name

Role

Master

Project Manager

QA/QC

General Manager

Managing Director

HSE Director

Financial Director

Project Engineer

Site Manager

Client

Site Office

Company

10

Issue Record
Rev

Date

02/01/2014

18/01/2014

Description of Changes/Amendments

By
Enrique
Fajardo

General statement of health and safety principles,


Material Safety Data Sheets disposal and brief and
name of the services providers ( existing utilities)
included.

Enrique
Fajardo.

Approval

Contents
1

EXECUTIVE SUMMARY ............................................................................................................................. 1

INTRODUCTION ........................................................................................................................................ 1

HEALTH & SAFETY PLAN APPROVAL AND REVIEW .................................................................................... 2


3.1
CHANGE AND REVISION MANAGEMENT ........................................................................................................... 2
3.1.1
Forecast Changes ............................................................................................................................ 2
3.1.2
Management & Revision of this Health & Safety Plan .................................................................... 2
3.1.3
Document Retention and Updating ................................................................................................ 2

DESCRIPTION OF THE PROJECT ................................................................................................................. 3


4.1
INTRODUCTION AND BACKGROUND ................................................................................................................. 3
4.1.1
The Parties Involved in the Work .................................................................................................... 3
4.2
NATURE AND SCOPE OF THE WORK TO BE CARRIED OUT ...................................................................................... 3
4.2.1
Introduction .................................................................................................................................... 3
4.2.2
The Nature and Extent of the Work ................................................................................................ 4
4.2.3
Significant Types of Work Activity/Material/Environmental Factors to be Managed .................... 4
4.3
LOCATION OF THE PROJECT AND EXTENT OF THE SITE .......................................................................................... 4
4.4
EXISTING ENVIRONMENT, SURROUNDING LAND AND ITS USE ............................................................................... 5
4.4.1
Existing Structures .......................................................................................................................... 5
4.4.2
Ground Conditions .......................................................................................................................... 5
4.4.3
Potential Contamination ................................................................................................................. 5
4.4.4
Existing Utilities............................................................................................................................... 5
4.5
SITE ACCESS, COMPOUND AND STORAGE ......................................................................................................... 6
4.5.1
Site Compound ................................................................................................................................ 6
4.5.2
Site Access ....................................................................................................................................... 6
4.5.3
Storage and Distribution of Materials ............................................................................................ 6
4.5.4
Welfare Facility Services ................................................................................................................. 6
4.6
PROJECT PROGRAMME, TIMESCALES AND PHASING ............................................................................................ 7
4.6.1
Phasing of the Work........................................................................................................................ 7

RESTRICTIONS AFFECTING THE PROJECT .................................................................................................. 7


5.1
IDENTIFIED RESTRICTIONS .............................................................................................................................. 7
5.1.1
Restrictions on Access ..................................................................................................................... 7
5.1.2
Restrictions on the Work Site .......................................................................................................... 8
5.1.3
Environmental Impacts ................................................................................................................... 8
5.1.4
Noise, Dust, Smoke, Odours, Fumes and Vibration ......................................................................... 8
5.1.5
Programme or Phasing Restrictions, Possessions and Disconnections ........................................... 8
5.1.6
Access to Client Controlled Areas .................................................................................................... 9
5.1.7
Utilities and Services ....................................................................................................................... 9

IDENTIFICATION OF ROLES ....................................................................................................................... 9


6.1
ROLES ....................................................................................................................................................... 9
6.1.1
Site Safety Committee ................................................................................................................... 10
6.2
ROLES AND RESPONSIBILITIES ....................................................................................................................... 10
6.3
AUTHORITY TO STOP WORK......................................................................................................................... 11

COMMUNICATION ................................................................................................................................. 11

7.1
HEALTH AND SAFETY COMMUNICATION (USE TRANSLATION WHERE REQUIRED) ..................................................... 13
7.2
MEETINGS ................................................................................................................................................ 13
7.3
REGULAR BRIEFINGS ................................................................................................................................... 12
7.4
DOCUMENTATION...................................................................................................................................... 12
7.4.1
Method Statements and Work Plans ............................................................................................ 12
7.5
DISPLAY OF NOTICES .................................................................................................................................. 14
7.6
INDUCTION ............................................................................................................................................... 13
7.6.1
Sub Contractor Induction .............................................................................................................. 15
7.6.2
Visitors to Site ............................................................................................................................... 15
7.7
CONSULTATION WITH PERSONNEL ON SITE ..................................................................................................... 15
7.8
CONTINUING LIAISON ................................................................................................................................. 16
7.8.1
Information for Neighbours and Others ....................................................................................... 16
7.9
CO-ORDINATION OF WORK ON SITE .............................................................................................................. 16
7.9.1
Arrangements for Co-operation .................................................................................................... 16
7.9.2
Integration of Safe Working Practices .......................................................................................... 16
8

MONITORING ARRANGEMENTS ............................................................................................................. 17


8.1
SITE INSPECTION ........................................................................................................................................ 17
8.1.1
Safety Tours .................................................................................................................................. 17
8.1.2
Site Inspections ............................................................................................................................. 17
8.1.3
Audit of records ............................................................................................................................. 17
8.2
PROJECT SAFETY REVIEW............................................................................................................................. 18
8.3
RECORDS ................................................................................................................................................. 18

CONSTRUCTION RISK MANAGEMENT .................................................................................................... 18


9.1
CONSTRUCTION RISK SUMMARY ................................................................................................................... 18
9.1.1
Responsibilities.............................................................................................................................. 19
9.1.2
Project Wide Hazards .................................................................................................................... 19
9.2
RISK ASSESSMENTS AND METHOD STATEMENTS .............................................................................................. 19
9.2.1
Method statements ...................................................................................................................... 17
9.2.2
Risk Assessments........................................................................................................................... 17
9.3
RESIDUAL HAZARD/RISK LOG ....................................................................................................................... 20

10 HEALTH & SAFETY FILES.......................................................................................................................... 20


10.1

DEVELOPED HEALTH & SAFETY FILE FOR THIS PROJECT ...................................................................................... 20

11 ACCESS AND EGRESS .............................................................................................................................. 21


11.1 SITE ACCESS AND SECURITY.......................................................................................................................... 21
11.1.1 General Site Entry ......................................................................................................................... 21
11.1.2 Visitors .......................................................................................................................................... 21
11.2 WORK PERMITS AND AUTHORITIES ............................................................................................................... 22
12 TRAFFIC MANAGEMENT ......................................................................................................................... 22
12.1.1 Traffic Management Records ....................................................................................................... 23
12.2 MOVEMENT OF HEAVY PLANT...................................................................................................................... 23
13 MATERIALS AND STORAGE ..................................................................................................................... 23
13.1 MATERIALS, PLANT, EQUIPMENT AND DEBRIS ................................................................................................. 23
13.1.1 Delivery, Handling and Disposal of Materials, Plant and Equipment ........................................... 23
13.1.2 Storage General ......................................................................................................................... 24

ii

13.1.3 Storage of Gas Cylinders Other than Below Ground Locations .................................................. 24
13.1.4 Storage of Combustible Materials - General ................................................................................. 24
13.2 DISPOSAL OF WASTE .................................................................................................................................. 24
13.3 HAZARDOUS SUBSTANCES ........................................................................................................................... 24
13.4 MATERIALS AND SUBSTANCES IDENTIFIED. ...................................................................................................... 25
14 PLANT, EQUIPMENT AND METHODS ...................................................................................................... 25
14.1 PLANT AND EQUIPMENT.............................................................................................................................. 25
14.2 LIFTING EQUIPMENT................................................................................................................................... 25
14.3 ACCESS EQUIPMENT (WORK PLATFORMS, SCAFFOLDS, LADDERS ETC) ................................................................... 26
14.3.1 Scaffolds & Work Platforms .......................................................................................................... 26
14.3.2 Ladders.......................................................................................................................................... 26
14.4 OTHER..................................................................................................................................................... 26
14.4.1 Anti-Static Precautions ................................................................................................................. 26
14.4.2 Cable Avoiding Tools ..................................................................................................................... 26
14.4.3 Signs and Advertising .................................................................................................................... 26
14.4.4 Personal Stereos, Radios etc. ........................................................................................................ 26
14.5 WORK TASKS ............................................................................................................................................ 27
14.5.1 Working at Height......................................................................................................................... 27
14.5.2 Removal of Tanks and Pipes Which May Have Contained Flammable Liquids or Gases .............. 27
14.5.3 High Temperature and Abrasive Processes on Paintwork ............................................................ 27
14.5.4 Demolition .................................................................................................................................... 27
14.6 FENCES AND HOARDINGS ............................................................................................................................. 27
14.7 LIGHTING ................................................................................................................................................. 27
14.7.1 Temporary Lighting and Power Supplies....................................................................................... 28
14.7.2 Screening of Lights ........................................................................................................................ 28
14.7.3 Lighting of public places................................................................................................................ 28
14.8 NOISE PERSON EXPOSURE ........................................................................................................................ 28
14.9
TEMPORARY WORKS .............................................................................................................................. 28
14.9.1
Construction Regulations and False Work ................................................................................ 29
14.9.2
Temporary Footways ................................................................................................................ 29
15 EMERGENCY ARRANGEMENTS ............................................................................................................... 33
15.1 FIRST AID, FIRE FIGHTING AND EMERGENCY ARRANGEMENTS ............................................................................ 33
15.2 FIRST AID ................................................................................................................................................. 33
15.2.1 General Arrangements .................................................................................................................. 33
15.2.2 Accident Book ............................................................................................................................... 34
15.3 FIRE AND EMERGENCY ................................................................................................................................ 34
15.3.1 Fire Precautions Management ...................................................................................................... 34
15.3.2 Halon ............................................................................................................................................. 35
15.3.3 Hot Work and Other Fire Hazardous Operations in Sub-Surface High Fire Risk Locations ........... 35
15.3.4 Fire Watchmens Attendance ........................................................................................................ 35
15.3.5 Fire Detectors and Alarms ............................................................................................................. 35
15.4 EMERGENCY CONTACTS AND ASSISTANCE ....................................................................................................... 36
15.5 REPORTING OF ACCIDENTS, INCIDENTS AND DANGEROUS OCCURRENCES .............................................................. 30
15.5.1 Accident / Incident Reporting ....................................................................................................... 36
15.5.2 Accident / Incident Investigation .................................................................................................. 37
16 ENVIRONMENT ...................................................................................................................................... 37
17 COMPETENCE MANAGEMENT ................................................................................................................ 38

iii

17.1 KEY SAFETY PERSONNEL .............................................................................................................................. 38


17.2 TRAINING REQUIREMENTS ........................................................................................................................... 38
17.3 VERIFICATION OF INFORMATION AND TRAINING............................................................................................... 39
17.4 DRUGS AND ALCOHOL ................................................................................................................................ 40
17.5 MEDICAL CONDITIONS ................................................................................................................................ 40
17.5.1 Hearing Aids .................................................................................................................................. 40
17.5.2 Fitness for work ............................................................................................................................. 40
17.6 WORKING TIME......................................................................................................................................... 40
17.7 KNOWLEDGE AND UNDERSTANDING OF ENGLISH ............................................................................................. 41
18 SELECTION OF SUB-CONTRACTORS, MATERIALS AND PLANT ................................................................. 41
18.1.1
18.1.2
18.1.3
18.1.4

Personnel ...................................................................................................................................... 41
Contractors & Sub-contractors ..................................................................................................... 41
Materials & Methods .................................................................................................................... 41
Plant .............................................................................................................................................. 42

19 PERSONAL PROTECTIVE EQUIPMENT ..................................................................................................... 42


19.1.1

Implementation ............................................................................................................................ 42

20 SITE RULES ............................................................................................................................................. 42


21 WELFARE ................................................................................................................................................ 43
22 APPLICABLE REGULATIONS, RULES AND GUIDELINES ............................................................................. 43
22.1 LEGISLATION, REGULATIONS, RULES AND GUIDELINES ....................................................................................... 43
22.2 STANDARD FORMS ..................................................................................................................................... 44
22.2.1 Register of Site Forms ................................................................................................................... 44
23 HEALTH AND SAFETY POLICY STATEMENT .............................................................................................. 45
24 GENERAL STATEMENT OF HEALTH AND SAFETY PRINCIPLES .................................................................. 41
25 DRAWINGS ............................................................................................................................................. 42
26 CONTROLLED UPDATE LOG FOR CONSTRUCTION HEALTH AND SAFETY PLAN REVISION ISSUE ............ 42
27 REGISTER OF RISK ASSESSMENTS ........................................................................................................... 42
28 REGISTER OF METHOD STATEMENTS ..................................................................................................... 42
29 REGISTER OF SITE SURVEY REPORTS....................................................................................................... 43
30 REGISTER OF TRAFFIC MANAGEMENT PLANS, DOCUMENTS & DRAWINGS ............................................ 43
31 REGISTER OF SITE ACCESS PLANS ........................................................................................................... 43
32 REGISTER OF CONTACTS ......................................................................................................................... 43
33 ORGANISATION CHARTS ........................................................................................................................ 44
34 INTERFACES ............................................................................................................................................ 44
35 REGISTER OF MEETINGS ......................................................................................................................... 45
35.1
35.2

SAMPLE SITE SAFETY MEETING AGENDA ........................................................................................................ 45


REGISTER OF MEETINGS .............................................................................................................................. 45

36 NOTIFICATION FORM ............................................................................................................................. 46

iv

37 REGISTER OF SITE NOTICES ..................................................................................................................... 47


38 REGISTER OF TOOLBOX TALKS / SITE BRIEFINGS .................................................................................... 47
39 REGISTER OF INDUCTIONS ..................................................................................................................... 47
40 SCHEDULE OF SITE INDUCTION INFORMATION ...................................................................................... 47
41 EMERGENCY CONTACTS AND ASSISTANCE ............................................................................................. 48
41.1 EMERGENCY CONTACTS .............................................................................................................................. 48
41.2 FIRST AID ................................................................................................................................................. 49
41.2.1 First Aiders .................................................................................................................................... 49
41.2.2 Fixed Location first aid boxes ........................................................................................................ 49
41.3 FIRE PREVENTION ...................................................................................................................................... 49
41.3.1 Fire Wardens ................................................................................................................................. 49
41.3.2 Fixed Location fire fighting equipment ......................................................................................... 49
41.4 EMERGENCY ARRANGEMENTS FOR THE SITE .................................................................................................... 50
42 RESIDUAL RISK REGISTER ....................................................................................................................... 51
43 MATERIALS & SUBSTANCES CONTROL MEASURES .............................................................................. 51
44 WORK PERMITS AND WORKING PROCEDURES....................................................................................... 51
44.1
44.2

GENERAL WORK PERMIT ARRANGEMENTS ..................................................................................................... 51


REGISTER OF WORK PERMITS ........................................................................................................................ 52

45 REGISTER OF INSPECTIONS & AUDITS .................................................................................................... 52


46 REGISTER OF WASTE TRANSFER NOTES .................................................................................................. 52

EXECUTIVE SUMMARY

This document is the Construction Health and Safety Plan of Combined Group Company for
Trading & Contracting W.L.L & Sacyr Construction JV (CGC-SACYR JV), for Road and
infrastructure project in Al Kheesa North and East (Rawdat Al Hamama District). It has been prepared
in accordance with the requirements of the Occupational Health, Safety, Environmental and Welfare
regulations of Qatar.
The project Roads and Infrastructure in Al Kheesa North and East (Rawdat Al Hamama District),
Package 01 is located approximately 10km north of central Doha between the existing Al Khor
Expressway and Al Shamal (North) Road in the Al Daayen Municipality and within the Qatar Area
referencing System (QARS) Zone 70.
The entire site is 1365 hectares (ha) and will accommodate approximately 4000 residential properties
and associated neighborhood development. The site is currently under a process of development with
approximately 800 properties under construction. There are no existing roads within the site, although
there are existing temporary access roads and some others are currently under construction. The
project has been split into three Packages to facilitate a phased design and construction process to
expedite construction.
Package 01 is located in the south east quadrant of the site with an area of 153 hectares,
representing an area of approximately 11% of the entire project. The project will provide infrastructure,
roads, drainage and utilities, for approximately 600 residential plots, with an internal and perimeter
highway network of roads in varying corridor widths. The proposed road network will contain
roundabouts and a number of simple priority junctions, including right-in/right-out junctions.
Normal working hours, weekend and national holiday will be followed as per labour law and any
overtime will be done only after getting necessary approvals.

INTRODUCTION

This document is the CGC-SACYR JOINT VENTUREs Construction Health and Safety Plan prepared
in accordance with the Qatar Construction Specifications 2010. This plan has been prepared by CGC
SACYR JV for this project, to address the health, safety and welfare requirements of the project.
The CGC-SACYR JV develop this plan and keep it up to date throughout the project. All those
involved in this project shall comply with this plan, and provide the Client with information they have,
which is required to keep this plan up to date and effective.
This project shall be designed and constructed in such a way that the risks to the health and safety of
all persons engaged in its construction, future use, cleaning, maintenance and demolition are
eliminated or reduced to an acceptable level.
This document is based upon the Qatar Construction Specifications 2010.It is not intended that this
document will reproduce detailed procedures and arrangements that are contained within other
relevant documents. However, it does give information on which detailed procedures and
arrangements are applicable, and where they can be found.
This is a living document and is subject to revision at any time.
Project personnel and Contractors taking part in site works will be required to comply with the
contents of this document.

QCS (Qatar Construction Specifications 2014)

Labor Law 14 of the year 2004

Qatar Traffic Law No. 19 of the year 2007

Environmental Protection Law No. 30 of the year 2002

CDD (Civil Defense Department) Fire Safety Handbook

Workers Rights Booklet 2009 (National Human Rights Committee)

HEALTH & SAFETY PLAN APPROVAL AND REVIEW

3.1
3.1.1

Change and Revision Management


Forecast Changes

This is a dynamic document that can be expected to change once approved for use. It is designed to
be updated throughout the course of the project. For larger projects information for some activities will
only be included closer to the time of the activity. Development of the design, unforeseen conditions,
further information, changing circumstances, personnel or plant, changes to the scope of work,
materials or methods, legislation or regulations may necessitate some changes to this plan.
3.1.2

Management & Revision of this Health & Safety Plan

The Safety Manager will review this Health and Safety Plan to ensure that it is up-dated to reflect
changes to the organisation, processes, scope of works and to incorporate new hazards or legislative
requirements.
This plan will be reviewed at least annually, or more frequently following changes to legislative
requirements.
3.1.3

Document Retention and Updating

Once approved, any material revisions to this document must be authorised by the Project Manager /
Safety Manager, and circulated to all on the distribution list.
Supplemental documents may be approved at a local level, following the correct procedure, e.g.
method statements and risk assessments, and then circulated to all on the distribution list.
The Master Copy of this document will be kept at site. If the site is transient the Safety Manager will
nominate another convenient, secure, location accessible by the site staff. The Master Copy will be
updated on a daily basis and shall contain the original copies of forms and certificates etc. all risk
assessments, method statements and other information that is generated for the project. This
additional information (risk assessments, method statements etc.) shall be copied periodically to the
others on the distribution list, by the Safety Manager. This shall be recorded in the controlled update
log, see section 26.
The Master Construction Health and Safety Plan is the responsibility of the Safety Manager who shall
ensure that due process is followed, that the plan is kept up to date, and that the instructions it
contains are followed.

In the occasion that two versions of this plan do not match over and above revision delays, the
Master Copy shall be deemed correct.

DESCRIPTION OF THE PROJECT

4.1

Introduction and Background

Project : Roads and Infrastructure in Al Kheesa North and East (Rawdat Al Hamama District),
Package 01.
4.1.1

The Parties Involved in the Work

Client : Public works authority - (Infrastructure affairs (Road Section )


Management : Parsons Brinkerhoff
Consultant

: Hyder consulting

Contractor

: Joint venture of Combined group C. Trading & Contracting W.L.L and


Sacyr Constructions. S.A (CGC - SACYR JV)

4.2
4.2.1

Nature and Scope of the Work to be carried out


Introduction

Location:

Al Kheesa North and East (Rawdat Al Hamama District), Doha.

Contract Value:

QRs 313,000,000/-

Period of the contract:

16 months.

Commencement Day:

5 Jan. 2014

Description of the works:


The project will provide infrastructure, roads, drainage and utilities, for approximately 4000 residential
properties and associated neighborhood development. The site is currently under a process of
development with approximately 800 properties under construction. There are no existing roads within
the site, although there are existing temporary access roads and some others are currently under
construction. The project has been split into three Packages to facilitate a phased design and
construction process to expedite construction.
Package 01 is located in the south east quadrant of the site with an area of 153 hectares,
representing an area of approximately 11% of the entire project. The project will provide infrastructure,
roads, drainage and utilities, for approximately 600 residential plots, with an internal and perimeter
highway network of roads in varying corridor widths. The proposed road network will contain
roundabouts and a number of simple priority junctions, including right-in/right-out junctions.
Normal working hours, weekend and national holiday will be followed as per labour law and any
overtime will be done only after getting necessary approvals.

4.2.2

The Nature and Extent of the Work

Road and infrastructure works.


4.2.3

Significant Types of Work Activity/Material/Environmental Factors to be Managed

The key safety issues to be addressed on the project are as follows.

4.3

Excavations

Confined space work

Micro tunnelling work

Workshop/laydown area activities

Asphalt work

Working adjacent to live electrical equipment

Working at height

Working at night / Lighting

Mobile cranes

Plant

Housekeeping / Waste management

Location of the Project and Extent of the Site

The project Roads and Infrastructure in Al Kheesa North and East (Rawdat Al Hamama District),
Package 01 is located approximately 10km north of central Doha between the existing Al Khor
Expressway and Al Shamal (North) Road in the Al Daayen Municipality and within the Qatar Area
referencing System (QARS) Zone 70.
Package 01 is located in the south east quadrant of the site with an area of 153 hectares,
representing an area of approximately 11% of the entire project. The project will provide infrastructure,
roads, drainage and utilities, for approximately 600 residential plots, with an internal and perimeter
highway network of roads in varying corridor widths. The proposed road network will contain
roundabouts and a number of simple priority junctions, including right-in/right-out junctions.
Please refer to section 34 for further details regarding project interfaces.

4.4

Existing Environment, Surrounding Land and its Use

The information in this section is to the best of our knowledge at this time. This information has been
considered when control measures were formulated for the construction works. Adjacent Premises &
Use
Types of premises include:

Local residents villas

Mosque

Under construction villas

Under construction school

4.4.1

Existing Structures

Refer to the contract drawings for more details:

Local residents villas

Mosque

4.4.2

Ground Conditions

The ground is expected to be stable similar to other excavations carried out in the area. If it is known
to be unstable, so additional measures will be required during excavation. (Such as access route for
Lorries will be temporarily diverted away from the edge of the excavation.)
4.4.3

Potential Contamination

Ground / soil contamination from unexpected spillage of hydraulic oil, lubricating oil, etc., from mobile
equipments during operation on site may happen. To control spillage on ground, drip-trays shall be
kept at locations where equipments are in operation. Oil if spilled, the contaminated soil shall be
collected and kept in a common bound at yard area. Arrangement for disposing the collected
contaminated soil at Municipality approved disposal areas shall be done coordinating with concerned
municipality dept./Environmental dept..
4.4.4

Existing Utilities

The term Utility means all underground and over-head services; such as electricity, gas, water, storm
water drain, foul sewer and telecommunication services; it includes impressed current and sacrificial
anode systems. Buried utilities are widespread; it shall be assumed they are present unless and until
proven otherwise.
The exact location and depth of utilities must be verified using appropriate methods, prior to ground
penetration by mechanical means at any location.
The location and depth of known existing utilities may be shown on the project utility drawings but are
not limited to these drawings. Copies of these record drawings are available from client project
office/safety file for inspection. It is the responsibility of the contractor carrying out the work to obtain
additional drawings from the utility companies and any other third parties to ensure availability of the
latest, most accurate information. It should be noted that the locations shown on the drawings may
not be accurate and will always require on site verification.
Prior to commencing works on site it shall be the responsibility of the Contractor to satisfy himself that
all utilities on site have been located, identified and marked, and disconnected or diverted as required,
prior to commencing work in the particular area in question.
Excavations will be controlled by a permit to dig system.
The CGC-SACYR JV will record details of all changes that have been carried out during
diversionary/installation works, details of any additional utilities not shown on the drawings, and of
actual locations of utilities if different to that shown. This information shall be forwarded to the utility
owner and to the office/designer to be compiled as part of the as-built drawings.

Types of existing utilities known to be in the area comprise:

Underground electrical cables

Underground water services

(Refer to drawings for further details)


The Companies that provide this services to the sites area are Qtel and Kahramaa.

4.5
4.5.1

Site accesses, Site Office Compound, and Material Storages.


Site Access

JV will implement security arrangements to secure the safety and health of any authorized visitor and
where reasonably practicable, prevent access to the site for any unauthorized person.
JV and its subcontractors will ensure that their respective visitors are safety inducted from Site HSE
Office with a briefing designed to inform the visitor of the site hazards and precautions necessary
during their visit
JV and its subcontractors should ensure that the visitors are accompanied by their representatives
throughout the visit, equipped with the appropriate personnel protective equipment and provided with
necessary information regarding the hazards existing in the areas of visit .and precautions to be
taken.
4.5.2.

Site Office Compound

The site office compound include the offices of CGC-SACYR JV, Offices for Hyder, Parsons and
Ashghal. The site office compound is protected with fencing / hoardings and the entry-exit gates are
provided which are controlled by Security personnel round the clock.
4.5.3 Storage and Distribution of Materials.
Adjacent to the site office compound, a Material Store and Storage yard is provided outside the site
office hoarding fence. This storage yard is also protected with Hoardings and security gate. A store
keeper is assigned who is responsible for keeping account of the materials and its issue / distribution.
JV and its subcontractors should ensure that the visitors are accompanied by their representatives
throughout the visit, equipped with the appropriate personnel protective equipment and provided with
necessary information regarding the hazards existing in the areas of visit .and precautions to be
taken.
4.5.4

Welfare Facility Services

4.5.4.1 Toilets.
Toilets are provided in site offices and yard area behind the site offices.
For the workers on site, portable toilets are provided at different locations of the site and regular
clearing of wastes from the toilet is carried out by a sewage tanker.
4.5.4.2 Washing facilities.

Near the mosque at site office; a washing facility s provided with platform and water taps and it is
connected to drainage tank. This is apart from the washing facilities provided in site office and toilet
facilities at site areas.
4.5.4.3 Rest shelters.
A large air conditioned rest shelter is provided at the yard area behind site office for the welfare of
workers and charge hands.
Temporary rest shelters shall be provided at various locations of the site with sitting benches, toilet
facilities and drinking water.
4.5.4.4 Drinking water for site workers.
Drinking water tank and water coolers are installed at the yard behind site office for the welfare of
workers. Cold and fresh drinking water from these water coolers shall be supplied to various locations
of site in portable water coolers in pick- up vehicles available on the site.
At site office drinking water dispensers are available for employees in office and supervisory staff.
4.5.4.4 First aid center at site office.
A first aid room with a qualified male nurse is provided in the yard area just behind the site office. It is
planned to provide first aid training to more people from office and site areas.
First aid medicines are available with the male nurse. More first aid boxes will be allocated at
controlled locations of the site for ready use in case of injuries.
Sickness problems and serious injury cases will be referred to Hospital immediately by the site nurse.

4.6

Project Programme, Timescales and Phasing

4.6.1

Phasing of the Work

The Roads and Infrastructure in Al Kheesa North and East (Rawdat Al Hamama District) project will
be in 1 phase and the planned start and completion dates are:
Commencement Date: 05-01-201
Completion Date: 16 Months.

RESTRICTIONS AFFECTING THE PROJECT

5.1
5.1.1

Identified Restrictions
Restrictions on Access

All movement of vehicles and pedestrians on the site shall be in accordance with the locally
established rules or restrictions. Arrangements for access and movement shall be briefed to the work
teams prior to entering the site for the first time.
Public rights of way, accommodation level crossings and bridges shall be used only in the way they
are intended to be used by the public. If they are to be used in any other manner, this can only occur

with prior written consent. Structural assessment of bridges will be carried out if construction plant or
vehicle material loads are particularly high.
Further details regarding access to the site can be found in the Traffic Management Plans see
sections 12 & 30.
5.1.2

Restrictions on the Work Site.

Only the authorised employees of CGC-SACYR JV, its Subcontractors and Representatives of
Hyder, Parsons, Ashghal and visitors related to these companies/authorities are allowed to enter the
site. Before proceeding to Construction site areas. All such employees/ visitors shall report to the site
office, undergo Safety Induction and wear appropriate PPE. All visitors should also follow the same
requirement and they shall visit the site only if the concerned department manager allow them
engaging a representative to accompany the visitor.
The above said employees / subcontractor employees are allowed to work on the site during the
working time permitted by CGC-SACYR JV which in turn comply with the work timings permitted by
Qatar Labour Laws and Government Directives from time to time ( such as during Hot weather
conditions, Ramadan period, etc.).
Unauthorised employees are not allowed to drive any vehicles / drive and operate mobile equipment
on the site. Work areas restricted with sign boards, barricades, lifting areas and heavy equipment
operation areas and critical work areas are not allowed to be entered by anybody including
employees; without permission of authorised officials / supervisors.
Employees / people assigned to work on site are not allowed to go into any houses / villas and their
compounds nearby for any purpose such as drinking water, taking rest etc.
Similarly employees including that of subcontractors are not allowed to go / enter any public offices,
control rooms, utility rooms, etc., existing inside or near the worksite.
Consuming / Handling alcohol on the site is strictly prohibited. Similarly smoking is not allowed on site
except designated smoking areas. Workers are allowed to use the toilet facilities provided on site; no
open areas / external partys facilities shall be used.
5.1.3

Environmental Impacts

Potential health, safety and environmental hazards are identified and recorded for existing operations,
products, business developments, acquisitions, modifications, new projects, closures and
divestments. This process takes into account risks to personnel, facilities, the public, customers and
the environment.
5.1.4

Noise, Dust, Smoke, Odours, Fumes and Vibration

The methods of work adopted for the site works shall minimise the effect of noise, dust, smoke,
odours and fumes upon all personnel carrying out the work, visitors, and neighbours.
5.1.5

Programme or Phasing Restrictions, Possessions and Disconnections

Where works will require equipment disconnections to assist in the safe installation, testing and
commissioning of the equipment, the Safety Manager shall ensure they are obtained.

5.1.6

Access to Client Controlled Areas

Not Applicable.
5.1.7

Utilities and Services

For details of utilities and services on site please refer to section 4.4.5.

IDENTIFICATION OF ROLES

A clear and structured cascade of safety responsibilities is essential to effective management of


safety on the project and for ensuring the appropriate checks and balances are established within the
framework of the project.

6.1

Roles

The following roles are as defined in the Qatar Construction Specifications 2010
Role

Duty Holder

Client

PWA

Clients
Agent

PARSON

Engineer
HYDER
CONSULTI
NG

HYDER
CONSULTING

Principal
Contractor

CGC

Contractor

SACYR

Contact
Person

Position

Contact Details
Address : P.Box # 22188
Tel 44950000
Fax : 44950999
E-mail
th

Mr.
Brinkerhoff

Address: 5 Floor,
Faisal Tower # 2,Doha
Tel 44351601
Fax
E-mail
Construction
Director

Address : Al Jassim Tower


Building #8 12th Floor
Ibn Hayyan Street
Bin Mahmoud South
(Area 23)
Doha, Qatar
Tel 44745000
Fax : 44745001
E-mail

Eng.Salame
h Haddadin

Project Manager

Address: P.B # 23756


Tel 44570570
Fax : 44664999
E-mail:qatar@cgc-kw-.com

Jose
Olivn

General
Manager

Address: P.B 3 30790,Doha


Tel : 44122161
Fax: 44122471
E-mail: jolivan@sacyr.com

Luis

See also section 4.1.1 for a list of designers/disciplines, and section 32 for contact details.
6.1.1

Site Safety Committee

The purpose of our safety and health committee is to participate in the implementation of the safety
and health system in JV.
Our committee will be comprised of management and employee representatives. Our committee will
meet monthly.
Committee members are: Project Manager, Operation Manager, QA/QC Manager, HSE Site
Manager, Managers / Engineers heading different sub functions, Plant and machinery in charge,
subcontractors representative and employee Representative.
The HSE committee headed by the Project Manager as Chairman will organize a committee meeting
once in a forth night to review HSE related issues. The Safety Manager which served as a Secretary
will circulate the agenda of the meeting at least seven working days in advanced on the scheduled
date of the meeting to all members.
The agenda of the meeting comprised the following:
Confirmation of minutes.
Chairmans review / overview of the site HSE performance / condition.
Previous fortnight HSE statistics.
Incident / accident investigation / dangerous occurrence / near misses reports.
Site HSE inspection.
Subcontractors HSE issues.
Safety presentation of members.
Reports from the client.
Matters arising.
And any other business.
Review the goals and objectives.
The Safety Manager will circulate copies of the minutes to the members for review and action.
Refer to section 7.7 Consultation with Personnel on Site.

6.2

Roles and Responsibilities

Matrix of Roles and Responsibilities for Al KHEESA Project Site Works:


The RASCI (Responsible Accountable Support Consult Inform) Matrix below
summarises the responsibilities of relevant personnel and entities responsible for the works.

10

11

HSE Manager/ Site Manager

Supervisors

All Construction Personnel

R
R
R
R
R
R
R
R
I
R
R
R
S

C
S
S
R
A
R
S
S
A
R
A
R
A

C
S
S
R
R
R

C
S
S
S
S
S

C
S
S
S
S
S

C
S
S
S
S
S

S
R
R
R
R
R

S
R
R
R
R
R

S
R
R
S
S
S

S
S
R
S
S
S

R
R
R
R

A
R
R
A

S
R
R
R

S
R
R
R

R
R
R
R

I
R
R
I

Visitors

HSE Director

HSE administration, documentation and record submission for


contract completion documentation.
Toolbox Talks, Daily Briefings.
JSA and Last Minute TRA.
Proper use of PPE.
Availability of proper PPE to workforce.
Supply and maintenance of safety equipment and materials
relevant to the contract scope.
Implementation of safe systems of work.
Implementation and administration of site permit to work
system.
Application and acceptance of permits on site and enforcing
of permit regulations.
Reporting of all accidents, incidents, near misses and Risk

Project Manager

Execution of work in accordance with HSE Policies,


Standards, Regulation and Law.
Site HSE Performance.
Ensure all individuals are held accountable for their actions
with regards HSE Policies/Rules.
Ensure that all significant HSE risks have been identified and
that procedures have been implemented to reduce risks to as
low as is reasonably practicable.
Set HSE Supervision levels.
Set site Policies and Procedures.
Site security programme.
Implementation of Approved HSE plan.
Review and Update of HSE plan.
Training and Training Resources.
Review and approval of CVs of HSE personnel.
Client Site Audit, Review and Inspection Schedule
Company Site Audit, Review and Inspection Schedule
Performing Inspections.
Site inductions
HSE Co-ordination Meetings
Company HSE Plans, RAMS and TRAs
Review of Company HSE Plans, RAMS and TRAs

CGC-SACYR JVNAME

CGC-SACYR JV

HSE Director

HSE Manager/ Site Manager

Supervisors

All Construction Personnel

A
A
A

A
R
R

A
A
S

A
S
R

A
S
R

A
R
R

I
-

S
C
R

R
R
R

R
C
-

S
S
-

S
S

Visitors

Project Manager

Observations to the CGC-SACYR JV contractor.


Investigation of all incidents/accidents to a level appropriate to
the actual/potential consequence rating.
Stop use and removal of all unsafe tools and equipment from
site into quarantine.
Correct use of all tools and equipment.
Intervention when HSE regs are compromised.
Follow at all times HSE rules and regulations.
Ensure that there is no horse play, short-cuts and at risk
behaviours.
Monthly and weekly HSE reports to CGC-SACYR JVNAME
Ensure the correct levels of competence and training for
persons under their control/supervision.
HSE Action tracking register.
Rolling HSE Programme based on the action tracking register
Reviews and approvals of COMPANY NAME. HSE personnel.
Performs only work for which they are competent and trained
to do so in a safe manner.

CGC-SACYR JVNAME

CGC-SACYR JV

The Safety Manager is the CGC-SACYR JVs local representative. He is responsible for ensuring
local compliance with all statutory requirements.
Contractors/Supervisors will be responsible on a day-to-day basis for the supervision of the individual
sites assigned to them and for ensuring that their arrangements for carrying out activities comply with
the requirements of this plan.
The Project Manager will be responsible for appointing suitably qualified personnel to supervise site
activities.
Onsite activities will be carried out in accordance with method statements which will be prepared prior
to carrying out the activity. These method statements will be prepared in accordance with the Safety
Management System, and they shall address the findings of the activitys risk assessments.
For more information see section 9.2 Method Statements

12

6.3

Authority to Stop Work

If unsafe working practices are detected the following have the authority to stop work:

The Client/Clients representative, the CGC-SACYR JV Safety Manager or Safety Officers and
any person who feels at risk with the activity taking place.

The Project Manager or Safety Manager can stop work, and should inform the CGC-SACYR JV if
Subcontractors are acting unsafely, and should withdraw all staff from the area.

Site workers can refuse to undertake work they deem to be unsafe.

Site supervisors should stop work they deem to be unsafe.

ALL staff should report unsafe practice to their superior as soon as possible.

Once stopped, the work should be re-assessed and any additional control measures required to make
the work safe should be implemented before the work is continued. The Safety Manager and the
CGC-SAYCR JV should be informed, so that any investigations necessary to ensure that the situation
is not repeated can be carried out.

7
7.1

COMMUNICATION
Health and Safety Communication (Use translation where required)

The means for communicating health and safety information to all members of the project team is by a
combination of:

Meetings

Regular safety briefings/ Tool Box Talks

Documentation

Office and site notice boards (pictorial where possible)

Inductions

Method statements, work plans and pre-work briefings

7.2

Meetings

There will be a pre-commencement meeting followed by regular site meetings. Site meetings will take
place at least monthly and more often as required. Safety and welfare will be an agenda item. These
meetings will include all relevant personnel including CGC-SACYR JV, Subcontractors, Clients
representative and neighbours if appropriate, and will include the Project Manager and Safety
Manager. A sample agenda is included in section 35.1, if this is incorporated into another regular
meeting; the items shown are the minimum.

7.3

Regular Briefings

The CGC- SACYR JV circulates information to be briefed to all employees on a regular basis. The
Project Director has regular cascaded team briefings with the department heads to encourage two
way communications about matters concerning safety. The safety briefing is then cascaded down
through the project team by further briefings by the department heads to their relevant teams.

13

Regular briefings will also be held on site regarding particular safety issues for the site, (toolbox talks).
A range of tool box talk cards (task, safety and environmental topics) will be prepared and distributed.
All managers and supervisors will undertake regular tool box talks prior to commencing work as a
means to consolidate knowledge. Both the person delivering such and the Site Safety Team maintain
records of tool box talks given.
Please refer to section 38 for a record of toolbox talks.
If an event occurs which either has the potential or has resulted in serious injury or loss the Safety
Manager will prepare a briefing. This will assist in sharing facts and lessons learnt from the
incident/accident. The Project Manager will ensure that this information is brought to the attention of
all personnel working on the project, including sub-contractors.

7.4

Documentation

This Construction Health and Safety Plan will be issued as a controlled document and will be
available at the site office. It will also be issued on a controlled basis to contractors. It will be brought
to the attention of all personnel as part of the induction.
The Safety Manager will maintain a limited safety information library relevant to the work of the project
at site. Requests for general safety information and access to the safety library should be made
through the Safety Manager.
7.4.1

Method Statements and Work Plans

Method statements, risk assessments, and safety briefing notes will be filed in the appropriate
appendix to this plan, and the register completed. Copies shall be given to individuals during work
briefings as appropriate.
Method statements will include means of integrating safe working practices, contract specifications,
procedures and details of other contractors activities that will be undertaken to support the project.
The Project Manager will ensure method statements from contractors are submitted for approval,
explaining the work being undertaken and their control measures in place to safely carry out the work.

7.5

Display of Notices

The following notices shall be displayed prominently in the site offices and on the safety notice board,
and shall include but not be limited to:

`The major accident/emergency plan

Emergency procedures and contact numbers

Site rules

Hazard warning signs and COSHH label posters

Access restriction/pedestrian and traffic routings

Map of evacuation routes and muster points

Names and photos of appointed Fire Wardens, First Aiders etc.

Safety Notices Circulars and posters

14

Local Safety Policy Statement

The Safety Manager is responsible for establishing the material to be displayed on notice boards and
is also responsible for maintenance of all site safety notice boards.
A register of notices will be maintained in section 37.

7.6

Induction

All personnel working on the project will receive a project specific induction. The induction briefing will
cover but will not be limited to the following:

An overview of the project

General Health and Safety, Environment and Quality issues

Site Rules

Reporting of Accidents, Incidents and Hazards.

PPE

Required Competence and certification

Working Hours

All staff shall be briefed and provided with a copy of the site briefing pack prior to the commencement
of work on site, or prior to a new individual staring work on the site.
Details of emergency procedures and arrangements will be included in the site briefing pack.
An activity specific site safety briefing will be given by the engineer or supervisor in charge of work
prior to work commencing.
The site induction will be used to ensure that all specific site safety issues are communicated to
personnel, visitors and Contractors involved in the site works.
The site safety briefing will be used to ensure that all work task specific safety issues are
communicated to personnel, visitors and Contractors involved in the works.
7.6.1

Sub-Contractor Induction

Where casual sub-contract labour is used they will be inducted to the site prior to commencing work
for the first time. The Safety Manager is responsible for ensuring that inductions take place. It is the
responsibility of the sub-contractors employer to agree arrangements for inductions with the Safety
Manager in good time. The Safety Manager will make available to all Sub-Contract firms a
Construction Health and Safety induction program.
7.6.2

Visitors to Site

Refer to section 11.1.2 Visitors Access and Egress.

7.7

Consultation with Personnel on Site

The CGC-SACYR JV recognises that improvement in health and safety performance can only be
achieved if there is a full commitment from all personnel at every level of the organisation. The CGC-

15

SACYR JV encourages and values input from its personnel in the process of continued improvement
of its working procedures. The regular briefings provide an opportunity for consulting and coordinating the views of personnel on the project, and encourage personnel to raise safety concerns
with their supervisor/manager.
The Project Director will encourage the appointment of Local Safety representatives.
The Safety Manager will ensure that regular consultation is carried out between managers and staff
representatives. Local Safety Representatives are encouraged to participate in safety initiatives (e.g.
meeting agenda items, risk assessments, PPE trials, and confidential feedback).
For more details on the safety duties and responsibilities of positions identified on the organisation
chart see 6.2 Roles and Responsibilities.

7.8
7.8.1

Continuing Liason
Information for Neighbours and Others

The Safety Manager will identify all interfaces, and where necessary, meet with neighbours or others
affected by the work, to provide information or gather information. This information will be shared with
Planning Engineer. Records will be kept of meetings and decisions reached.
Refer to section 34 for project interfaces.

7.9
7.9.1

Co-ordination of Work on Site


Arrangements for Co-operation

Coordination and cooperation is an important factor in implementing safety requirements on site. To


develop and enhance this between construction team and HSE department, discussion on site
matters will be conducted through the following meetings.
7.9.1.1 .HSE Meeting for Construction Site Team Biweekly
(Participants Construction Engineers and Senior site supervisory staff & HSE Manager, HSE Officers)
7.9.1.2 . HSE Management Meeting - Once in a month / If needed for any critical issues.
Participants: Project Construction Director, Construction Managers, HSE Manager &Sr. HSE Officers
7.9.1.3. Pre-discussion for Arranging Road Diversions/Traffic Management Plan - As per need.
(Concerned Construction Manager, Engineers, HSE Manager, Safety Officers.)
7.9.2

Integration of Safe Working Practices.

For integrating safety requirements in construction activities, the following actions will be done.
7.9.2.1 Risk assessments will be prepared for all method Statements. This will be distributed among
all Site Engineers and Supervisors their knowledge and implementation. Safety Officers to monitor
guide implementation of preventive / control measures suggested in the Risk Assessments.
7.9.2.2 Job specific Safety Trainings will be conducted for critical jobs / as per need.

16

7.9.2.3. Weekly Tool Box Meetings Once in a week By Safety Officers to enhance knowledge on
safety requirements for on-going site works and to motivate them to follow safe working practices..
7.9.2.4. Daily Job & Safety Briefings - By each Foreman at the starting of work every day. To facilitate
this, brief safe procedures for various tasks will be prepared and given to Foremen.

MONITORING ARRANGEMENTS

8.1

Site Inspection

Health and Safety on the project will be monitored by a combination of:

Site inspection

Statistical Review

Audit

In order to promote consistent good practice and safety discipline the site inspections and audits may
be conducted without prior notification to the Project Manager, Subcontractors or work teams.
Monitoring and auditing is intended to promote continuous improvement of safety and the elimination
of accidents and incidents.
The Subcontractors will carry out their own monitoring. The CGC-SAYCR JV will ensure that
monitoring and auditing activities are organised and implemented by Subcontractors also.
For identification of the audit schedule and the audit team please refer to section 44.
8.1.1

Safety Tours

The CGC-SAYCR JV Safety Manager will walk round site every day and will conduct formal
inspections once per week and additionally during high risk work. Additionally Safety Officers will
undertake their own safety tours.
The Project Manager will undertake a safety tour once per month, as a minimum.
The Project Director will undertake a minimum of four tours per annum.
8.1.2

Site Inspections

Site inspections shall be used to check all aspects of the working methods and the working
environment. If appropriate this shall include brief interviews of the work teams to determine the
effectiveness of communication on site.
The schedule of site inspections will be determined by the nature, scale and extent of the project
work, but will typically be a minimum of once per week.
Refer to section 44 for the schedule for site inspections, and records of site inspections carried out.
8.1.3

Audit of Records

The Safety Manager will audit JVs records as part of their regular site inspection regime. If the
inspections indicate short comings then a more in-depth audit will be undertaken and an action plan of

17

remedial action determined and implemented. A review audit to ensure the corrective action has been
taken will be scheduled for a predetermined period thereafter.
The Client may also carryout additional audits, which are independent of the project. Full co-operation
will be given to the client.

8.2

Project Safety Review

The Safety Manager will carry out a review of the site works at four-weekly intervals and issue a
report for the Project Manager. The Project Manager will review and collate the safety performance
indicator information required each four-week period. The safety performance indicator information
will include proactive and reactive metrics as specified from time to time by HSE Manager.
Areas identified as importing unacceptable risk, or areas with a history of repeated non-compliance
will be targeted and remedial action introduced by the Project Manager and/or the Corporate HSE
Manager.

8.3

Records

Following HSE Records will be kept by HSE Dept of CGC-SACYR JV


Data shall include, but is not limited to:

Accident/incident statistics.

Accident/incident reports

Site safety reports

HSE communications

Refer to section 23.2 for standard record keeping forms.

CONSTRUCTION RISK MANAGEMENT

Risk assessments will be carried out for all activities, documented and filed in section 27, and the
project Risk Assessment Register updated.
Any significant residual risks, or hazards for which a particular action is required, shall be recorded in
the Residual Risk Register, section 42, and signed off when complete. The Safety Manager shall
reference and update this list with regard to all activities.
Method statements will be developed for all activities, documented and filed in section 28, and the
project Method Statement Register updated.

9.1

Construction Risk Summary

For details of summary work categories that could present risk please refer to 4.2.3. Further guidance
can also be found in sections 42 & 0, regarding types of hazard, and actions required to manage
them.

18

9.1.1

Responsibilities

Before site work starts, the Project


hazards. Where a hazard has been
risks associated with it. The work
precautions that are to be taken.
legislation.

Manager shall ensure that surveys are carried out to identify


identified, a suitable arrangement will be made to manage the
teams will be briefed about the hazards identified and the
The arrangements will take into account all relevant Qatar

Refer to section 29 for the site survey register.


The prime responsibility for ensuring the health and safety of employees rests with their respective
supervisor.
Before work commences, it is the personal responsibility of the appropriate supervisor to satisfy
himself that safety precautions are taken to establish general safety at and in the vicinity of the work
place.
Subsequent to the commencement of work, the person in charge shall ensure that conditions which
ensure general safety are maintained. In addition, this person shall also ensure that conditions of
other adjacent work areas are not adversely affected by the activities for which they are responsible.
9.1.2

Project Wide Hazards

Traffic, Vehicle movements, reversing operations, Mobile equipment operations, deep excavation,
lifting operations, work at height, buried services, working with sewage etc.

Heat / Heat stress from exposure to high temperature and humidity.

Flammables like diesel, oil, Cutting gas cylinders etc..

Paints, adhesives and chemicals for construction activities.

Electricity

Muscular-skeletal Hazards e.g. Slips, Trips, Falls, Manual Handling

Confined Spaces.

Refer to section 42 for control measures for materials and substances.

9.2
9.2.1

Method Statements and Risk Assessments.


Method Statements

Method Statements will be prepared by CGC-SACYR JV or their subcontractors, for each activity to
be conducted on the site. This will include the scope of the work, responsibilities of employees
involved, materials, equipment and tools to be used, Work Procedure, Quality requirements and
testing procedures and will essentially include a Risk Assessment for that activity.
Method statements must be approved by Project Manager prior to work commencing. A copy shall be
included with the Master Construction Safety and Health Plan.
9.2.2

Risk Assessments

The Safety Manager is responsible for ensuring Risk Assessments are carried out for each activity
referring the Method Statements Based upon the details and work procedures given in the Method

19

Statements and further discussions with construction department for any clarifications; a Risk
Assessment will be prepared and attached with the Method Statement.
A Risk Assessment will

Identify what hazards and associated risks are/may be present

Identify the precautions are to be taken when faced with those hazards

Identify who will provide those precautions

Identify the emergency actions available/ required.


All unplanned situations or activities that have not been previously assessed, but that may give
rise to risk, must be assessed before work is started/continued.

Please refer to section 27 for register of risk assessments for this project.
Please refer to section 28 for register of method statements for this project.

Method statements shall be prepared by CGC-SACYR JV, or their sub-contractors as required, prior
to work commencing. Method statements must be approved by Project Manager prior to work
commencing. A copy shall be included with the Master Construction Safety and Health Plan.
See 3.1.3 Document Retention and Updating for notes regarding master plan.

9.3

Residual Hazard / Risk Log

A Residual Hazard log/ Risk Log will be prepared during the project; it will identify those hazards and
associated risks that require continuing management or will require to be signed off by a competent
person.

10 HEALTH & SAFETY FILES


The Construction Occupational Health, Safety Environmental and Welfare regulations of Qatar
requires that a Health and Safety File be developed and maintained for the project. The preparation of
the Health and Safety File is the responsibility of the Engineer. Contractors and Designers have a
responsibility to co-operate and provide any relevant information to the Engineer.

10.1 Developed Health & Safety File for this Project


Health and Safety File information shall be prepared throughout the project, and handed over as
appropriate stages are completed. Any remaining information shall be handed over no later than
completion of the project. The Project Director shall ensure that information for the health and safety
file is prepared and that all the relevant details are included. It should be handed over to the Project
Manager to be forwarded to the Engineer.
Information contained in the file must include that which will assist persons carrying out construction
work on the structure at any time after completion of the current project and could include:

20

As built drawings, calculations and plans used and produced throughout the construction,
installation or demolition process along with the design criteria;

General details of the construction methods and materials used, including type of material and
location used;

Details of the structures equipment and maintenance facilities;

Maintenance procedures and requirements for the structure;

Details of the location and nature of utilities/services and their maintenance/isolation, including
emergency and fire-fighting systems, equipment, routes, procedures etc.

Details of hazardous substances and safety data sheets;

Load bearing details shoring, retaining walls, piling, basements, walls, trusses and thrust blocks
etc.

Extent of foundations.

Archaeological data relating to health and safety issues.

For further information on the requirements for the project health and safety file contents,
responsibilities and format please refer to the specific project requirements document/contractual
requirement.

11 ACCESS AND EGRESS


11.1 Site Access and Security
11.1.1 General Site Entry
All site staff and visitors shall sign in upon arrival and sign out upon departure, (except in an
emergency).
The Safety Manager shall conduct surveillance checks to ensure that this procedure is adhered to.
The traffic management and site plans shall identify approved access points that shall be used. No
other accesses are permitted. Any evidence of persons gaining access by other routes must be
reported to the Site Safety/Project Manager.
No person shall be permitted access to the site without the correct PPE. The Safety Manager will
make an appropriate quantity of PPE available for visitors.
11.1.2 Visitors
All visitors to site must identify themselves to Security and/or Site Manager immediately upon arriving
at the access point/designated control point. The Site Manager/Supervisor must ensure that such
visitors are in possession of the relevant certification and safety equipment.
All visiting staff to the site shall be briefed upon arrival of any particular health and safety hazards on
site, prior to allowing them access to the work location. This shall be known as site induction.
If additional competencies are required to enter the site, or any particular area of the site, the visitor
must possess these competencies. If they do not, they shall not be granted access, no matter how
short the period of the visit.

21

Deliveries to depots and work sites will be under control and supervision at all times. This will be
arranged by the Safety Manager.
Refer to 7.6 for details of site induction.

11.2 Work Permits and Authorities


Certain types of work or areas in which the work will be carried out require a permit to work system,
as part of the safety management arrangements. The Safety Manager shall ensure that these areas
and types of work are identified and the appropriate arrangements are implemented.
The Safety Manager shall also, by surveillance checks and inspection, check that these arrangements
are adhered to.
Where a permit to work is required, NO WORK SHALL BE CARRIED OUT WITHOUT THE
REQUIRED PERMITS. Where an individual knowingly works without a permit, they shall be
permanently dismissed from site.
Details of work permit systems operating on the site will be communicated at the site induction.
Permits to work will be documented, and the work team will be briefed.
Please refer to section 43 for permit to work arrangements and a register of permits.

12 TRAFFIC MANAGEMENT
The Safety Manager shall be responsible for the design and implementation of all traffic safety
management arrangements within the site and any affected areas outside of the site. He shall also be
responsible for all associated consultations and for obtaining the necessary approvals/permits for the
arrangements.
If work on the public highway is required, it is the Safety Managers responsibility to ensure that the
traffic management plan is acceptable to the local authority responsible for the road.
The traffic management plan shall be complied with, by all site personnel and visitors. It shall cover all
expected work activities, delivery and storage areas, and it shall be expanded and/or amended to
cover new or altered activities as they arise.
The traffic management plans shall also provide for the requirement that the entrances and roads are
kept clean and clear of obstructions, and prevent the spillage or deposit of clay, rubble or other debris
on the entrance and other roads throughout the contract period.

Arrangements for road traffic and pedestrians

Arrangements for material delivery, removal, handling and storage

Access and egress points

Locations for unloading

Layout and storage areas

22

Traffic routes

12.1.1 Traffic Management Records


Traffic management assessments will be documented and filed in section 30, and the project Traffic
Management Register updated. (This register shall include all relevant documentation, drawings,
plans, assessments, permits, etc.)

12.2 Movement of Heavy Plant


The JV will ensure the following:
All equipment and operators must have valid third party certificate in addition to registration /
insurance and license.
Only safe and well maintained plant and equipment shall be allowed to operate on any of the sites.
All operators of heavy plant such as earth movers, piling rigs etc. shall be medically fit. Over 18
years of age and be thoroughly trained and experienced to operate the equipment.
No unauthorized person shall be allowed to ride on plant.
The operators shall conduct daily inspections of their respective items of plant with the results of
these inspections being recorded and records kept available for inspection by the employers
representative.
All mobile heavy plant shall be equipped with at least one dry powder fire extinguisher carried at a
suitable position so as to ensure its easy availability.
Whenever heavy plant is operating in congested areas, thoroughly trained and experienced banksman shall be deployed to control the plant and personnel movement and interface.
Any waste engine oil and filters following any on site servicing and maintenance shall be removed
from the site and disposed of in an environmentally conscious manner at authorized disposal
locations.
All drums of fuel oil shall be stored on drip trays or the fuel shall be kept in bunded bulk storage fuel
tanks with quantities stored being kept to a minimum.
The storage areas shall have dry powder fire extinguishers positioned in close proximity to their
locations for use in an emergency.

13 MATERIALS AND STORAGE


13.1 Materials, Plant, Equipment and Debris
13.1.1 Delivery, Handling and Disposal of Materials, Plant and Equipment
The materials, plant, equipment and debris associated with this project will be actively managed on a
day to day basis by the Site Manager.
Further details regarding the delivery routes and storage areas identified please refer to section 12 &
section 30, traffic management and site plans.

23

For further details regarding methods of work, handling and storage please refer to section 0, risk
assessments section 27 and method statements section 28.
13.1.2 Storage General
The Safety Manager shall continually monitor the project to ensure that materials are stored in an
orderly fashion, for example, that stacked materials are stable and not liable to fall, or cause a trip
hazard.
13.1.3 Storage of Gas Cylinders Other than Below Ground Locations
Gas Cylinders will be stored and Transported in accordance with the guidelines for storage and
handling of Gas Cylinders in QCS 2010.
Cylinder trolleys shall be used to move gas cylinders.
13.1.4 Storage of Combustible Materials - General
If combustible materials are to be used the storage and use of the materials shall comply with the
requirements in the material safety data sheet. The Safety Manager shall ensure that this assessment
is carried out and actions are implemented accordingly.

13.2 Disposal of Waste


All waste shall be segregated and disposed separately at designated disposal areas for each type of
wastes approved by Government / Municipality. A licensed contractor shall be appointed for this
purpose and the waste disposal notes shall be retained. The Safety Manager shall ensure that
resources are made available for suitable storage and disposal of material. Refer to section 45 for
register of waste transfer notes.
The Site Stores/ Safety Manager shall identify and shall make any special arrangements for the
disposal of special waste; and consignment notes shall be retained. Instructions for the handling of
such waste shall be included in the method statement, and the work teams briefed as normal.
Resources shall be used efficiently to reduce the amount of waste produced in the first place;
materials will be reused wherever possible, if this in not possible then they will be recycled, with
disposal being the final option.

13.3 Hazardous Substances


The Site Stores/ Safety Manager shall ensure that substances hazardous to health are identified,
along with the appropriate control measures.
Material safety data sheets shall be obtained for all substances in use as part of this project. The Site
Stores/ Safety Manager shall ensure that methods of work, storage and disposal used on site for
these materials are compatible with the requirements stated in the data sheets, and industrial best
practice. A method statement shall be prepared, used and kept for the materials/substances in use.
The Site Stores/ Safety Manager shall ensure that material safety data sheets are obtained for all
substances hazardous to health, which are to be installed, or are discovered in the structure as part of
this project, for inclusion in the Health & Safety File.

24

Material Safety Data Sheets will be placed on COSHH (Control of Substances Hazardous for Health)
assessments and then briefed to the person undertaking the works.

13.4 Materials and Substances Identified.


Please refer to section 0 for details of the materials and substances identified, and the required
control measures. These control measures will be included in the relevant work method statement

14 PLANT, EQUIPMENT AND METHODS


14.1 Plant and Equipment
The Safety Manager shall ensure that relevant legislation, regulations or standards shall be fully
complied with when selecting and using plant, equipment and tools for use during this project.
It is the responsibility of the relevant work manager or supervisor to select the plant, equipment and
tools used on the site. Its suitability for the job at hand must be considered, and only appropriate
plant, equipment and tools shall be used.
Plant, equipment and tools shall be formally inspected as a minimum at the periods required by
legislation. It shall be inspected for general condition on a daily basis prior to use, and any suspect
equipment shall not be used until fully inspected and passed fit for use. Maintenance, inspection or
testing of plant, equipment and tools will only be carried out by competent persons appointed by the
Mechanical Manager.
A site register of plant, equipment and tools will be kept and cross referenced with the records of
inspections and any maintenance work required on the plant, equipment and tools.
A tagging system will be used to identify equipment that should not be used.

14.2 Lifting Equipment


The Safety Manager shall ensure that relevant legislation, regulations or standards shall be fully
complied with.
Lifts, Hoist, Cranes and Other Lifting Appliances will be inspected and tested in accordance with the
requirements of the regulations. Use, maintenance, inspections and testing of lifting equipment will
rd
only be carried out by 3 party competent persons approved by the Safety Manager.
Safety Manager shall ensure that suitable arrangements are in place for the management of chains
and slings. These shall be individually identified and stored in such a way as to prevent their damage,
in appropriate use or misuse.
Damaged lifting equipment, chains and slings shall not be used under any circumstances. Damaged
chains and slings will be clearly identified and quarantined for disposal.

25

14.3 Access Equipment (work platforms, scaffolds, ladders etc)


14.3.1 Scaffolds & Work Platforms
If scaffolding or other work platforms are required on this project then the erection, dismantling and
inspection of them shall be carried out by competent persons approved by the Safety Manager.
All scaffolds and other work platforms shall be designed, constructed, used and dismantled in
accordance with CITB standards. Prior to the erection and use of scaffolding and other work platforms
the Safety Manager] shall ensure that a suitable safe system of work e.g. Scaff-tag has been devised
for the work. Scaffolding and work platforms will be inspected at intervals specified by the Safety
Manager. As a minimum inspections of shall occur weekly. Additionally inspections will occur after
significant additions or alterations and after any event that may have affected strength or stability of
the scaffolding or other work platform.
14.3.2 Ladders
If work is required with ladders on this project then they will be used in accordance with and CITB
standards. The Site Manager shall ensure all ladders are fit for purpose, and free from defects. Prior
to the use of the ladders the Site Manager shall ensure that a suitable safe system of work has been
devised for the work.

14.4 Other
14.4.1 Anti-Static Precautions
Anti-static precautions may be required when working in equipment rooms. Where required, the Site
Electrical Manager will specify the anti-static precautions to be taken.
Anti-static precautions will comply with current best practice.
14.4.2 Cable Avoiding Tools
Cable Avoiding Tools (CATs) shall be used where necessary, as part of a safe system of work prior to
any excavation or ground penetration. Prior to their use the person in charge of the work will
determine if the use of the CAT will interfere with any Safety Critical Equipment in the vicinity (for
example near hospital, airport equipment); where this is the case then work shall be halted until the
situation has been reviewed and a safe system of work agreed with all parties affected by the use of
the CAT.
CATs shall only be used by competent persons appointed by the JVs Construction Manager.
14.4.3 Signs and Advertising
The Client will be responsible for determining if it is appropriate to allow advertising on site hoarding.
This will be co-ordinated with the local authorities. Any advertising method, SHALL NOT be allowed to
introduce additional risk to the work site e.g. extra loading on scaffolds.
14.4.4 Personal Stereos, Radios etc.
Project personnel and visitors shall not bring onto the sites the following:

Personal Stereos

Radios

26

Use of radios, hearing aids and mobile telephones (cellular telephones) is forbidden where they could
prevent the user from acting safely. Mobile telephones shall be turned off in hazardous areas.

14.5 Work Tasks

14.5.1 Working at Height


A specific risk assessment and method statement will be developed for the work.
14.5.2 Removal of Tanks and Pipes Which May Have Contained Flammable Liquids or Gases
A specific risk assessment and method statement will be developed for the work, please refer to
sections 27 and 28.
14.5.3 High Temperature and Abrasive Processes on Paintwork
Older structures such as bridges, buildings etc, may have protective and decorative coatings
containing substantial quantities of lead. Additionally some corrosion protective coatings may contain
hexavalent chromium (chromates). Existing metalwork and woodwork may have been coated at some
time with lead-based paints.
The structure shall be assessed by the Construction Manager (competent Engineer) and Safety
Manager prior to carrying out any process that may cause a high temperature. This includes
processes such as welding, cutting, flame cleaning, or abrasive processes, such as disk grinding and
cutting with power tools. If required suitable control measures shall be implemented. These measures
will be specified in the activity method statement.
14.5.4 Demolition
Demolition is regarded as high risk work. It shall be carried out in accordance with BS 6187 The
Code of Practice for Demolition, with regard to the Guidance Note GS29, Health and Safety in
Demolition Work.
The method statement shall include details of any temporary works proposed, together with
appropriate design checks, certificates, calculations and drawings.
The Project Manager shall ensure that this work is carried out by, and supervised by, competent
persons.

14.6 Fences and hoardings


Visible warning lights shall be fixed to all hoarding erected on roads or pavements which shall be
illuminated throughout the hours of darkness and at times of poor visibility.

14.7 Lighting
The Safety Manager shall ensure that lighting is adequate for all works on the project. Additional
lighting will be provided if required.

27

14.7.1 Temporary Lighting and Power Supplies


Location of lighting and routing of cables shall ensure that walkways and work areas are maintained
and tripping hazards are reduced to a minimum.
14.7.2 Screening of Lights
Lighting shall be positioned in such a way that it does not interfere with others, for example oncoming
road traffic or train drivers.
14.7.3 Lighting of public places
Where hoarding or other construction activity obstructs or reduces existing lighting levels below that
required for emergency escape, additional lighting shall be provided.

14.8 Noise Person Exposure


The Safety Manager shall ensure that no persons are exposed to excessive noise. If necessary the
Safety Manager shall arrange for noise level monitoring, and shall implement the appropriate control
measures. If required the Safety Manager shall acquire the appropriate hearing protection equipment.
If hearing protection is required, individuals are required to wear it.
Please also refer to PPE section 20.
The location of the site and the impact of noise on neighbours shall also be considered.

14.9 Temporary Works


All temporary works shall be designed and assessed by a competent person. Design assessment,
calculations, method, drawings and specifications shall be carried out and checked in accordance with
normal design practice.
Methods, drawings and specifications shall be submitted to the Project Engineer, and where
applicable also approved by the Clients representative for approval.
Temporary works shall only be carried out in accordance with the approved methods, drawings and
specifications.
Temporary works include:

Methods of excavation

Methods of erection

Methods of demolition

Temporary loading applied to elements of the permanent way

Loadings applied to elements of partially constructed permanent way

28

14.9.1 Construction Regulations and False Work


False work includes any temporary structure used to support any permanent structure during its
erection or demolition, until it becomes self-supporting.
False work shall be inspected irrespective as to whether it is used as a man supporting platform, or is
being erected or dismantled.
The Site Engineer shall implement an inspection regime appropriate to the structure.
Please refer to section 44 for inspection records and section 23.2 for site forms.
14.9.2 Temporary Footways
All temporary footways, ramps, stairs, landings and platforms shall be fit for purpose, and where
possible shall be made from sound non-slip materials with no wide joints or rough edges.
Equipment shall be kept clear of access ways. Electric and other cables shall be routed to avoid
tripping hazards, and if necessary shall be suitably boarded or protected.
The Safety Manager shall ensure that this happens. Housekeeping will be monitored during the
regular formal inspections, and through observation on a day to day basis.

15 ARRANGEMENTS FOR CONTROLLING SIGNIFICANT SITE RISKS


1.1. Dealing with Services
1.1.1. As with all sites there is a risk due to site services such as electrical cabling and gas lines. It
is not expected that there will be any need to excavate or drill in areas where there are buried
services; however there are a number of existing pipe bridges carrying overhead services
which will need to be considered in relation to deliveries of plant and equipment to the project,
and when planning lifts.

1.2. Stability of Structures during Construction Work


1.2.1. Temporary supports, such as bracing, guys or stays, must be used during the erection of any
structure which may be unstable or liable to collapse before it is completed. Additionally,
where any work is carried out which is likely to adversely affect the foundations or stability of
any existing building or structure (or one under construction), all practicable precautions, such
as shoring, must be taken.

1.3. Preventing falls


1.3.1. Efforts will be made to avoid working at height activities where possible; however in some
cases this will not be possible. In such cases a specific risk assessment shall be carried out
in compliance with the Work at Height Regulations QCS 2014.

1.3.2.

1.4.

All personnel working at height will be experienced and where required will have received the
necessary training. Additional task specific PPE and equipment will be provided for the
activity and will be in possession of the relevant certifications.

Work with or near fragile materials

29

1.4.1.

Working on fragile roofing materials must be avoided. If this is not possible then measures
should be taken to ensure safe access for personnel. This will include the use of roof boards
to spread the weight, and guard rails installed to provide good hand holds and provide edge
protection.

1.5. Control of lifting operations


1.5.1. The Company Appointed Person shall be responsible for lifting operations on site. The
Company shall ensure that the lifting activity to be carried out is adequately planned and
carried out in accordance with lifting plan and lifting permit.

1.5.2.

The Appointed Person is responsible for the production of the following documentation:
i)
A method statement / lift plan and a task risk assessment for all routine lifting
operations
ii)
A specific method statement / task risk assessment is made for heavy, critical and/or
complex lifts. The Method Statements and Task Risk Assessment will follow the
issue, revision implementation process described earlier in this section.
iii)
Risk Assessments/Lifting Plans for all lifting operations shall address the following:
a)
The potential for falling objects
b)
Method of communication between the lifting team
c)
Safe positioning of personnel
d)
Load path, snagging and obstruction hazards
e)
Suitability of equipment, SWL, centre of gravity and rigging arrangements
f)
Forces generated when using mobile lifting equipment
g)
Effect of weather conditions on the load
h)
Ground loadings
i)
Potential for collision with other cranes operating in close proximity

1.5.3.

All personnel shall be kept clear of the intended drop zone of the item to be lifted, and the
path of the load as it is moved into position. Hard barriers and warning signs shall be placed
to identify the restricted areas. Tag lines must be fixed to all loads and used to prevent the
load from turning or swinging, and assist with positioning.

1.6. The maintenance of plant and equipment


1.6.1. An inspection schedule shall be developed on site for all equipment in order to ensure that all
equipment is in compliance with both the relevant QCS 2014 and client regulations, as well
as the contractors site specific regulations. From the CGC-SACYR JV contractors HSE
plan this is to cover as a minimum:
i)
Site plant and vehicles
ii)
Lifting equipment including cranes, lifts, chains, blocks etc
iii)
Access equipment including ladders and stepladders
iv)
Scaffolding including easy-fix self-build towers
v)
Safety harnesses, lanyards, anchor points and running lines
vi)
Fall harnesses complete with shock-absorber and lanyards
vii)
Electrical tools
viii) Other portable tools such as pneumatic tools, abrasive wheels and cartridge tools
ix)
Any equipment specifically requiring inspection under national / local legislation

30

x)

Any equipment requiring routine inspection by a competent person according to the


manufacturers operating instructions. Additionally, each contractor shall ensure that:
a)
All vehicle / equipment operators are competent and licensed.
b)
All equipment used is in compliance with UK certification and legislation
requirements
c)
Powered tools and equipment are only used by operatives trained in their
use.
d)
Tools and equipment have been inspected prior to use on site, including
hired tools and equipment. Inspection shall always be carried out by a
competent person. For portable electrical tools this will be by a qualified
electrician. A site specific quarterly colour coding system will be used.
e)
Equipment is individually numbered, labelled and registered.
f)
No modified equipment is brought on-site unless the modification has been
approved by a competent person (i.e. typically the equipment supplier or
vendor or an engineer).
g)
Inspection systems meet the manufacturers or suppliers specifications
h)
Records of inspections are maintained.
i)
Equipment is identified with the relevant colour code

1.7. Work where there are poor ground conditions


1.7.1. Care will be taken to assess the ground conditions in the work area with respect to the use of
plant and other equipment. If the ground conditions are unsuitable alternative work methods
will be sought, or corrective action shall be undertaken/requested from the CGC-SACYR JV
Contractor.

1.8. Storage of materials (particularly hazardous materials) and work equipment


1.8.1. Before any potentially hazardous substance is brought onto site a COSHH assessment will
be carried out based on the products Material Safety Data Sheet. These documents will be
submitted to the CGC-SACYR JV Project HSE Manager for approval prior to the substance
being brought onto site. The assessment will cover the safe storage of the substance,
handling and disposal procedures, as well as relevant treatment procedures in case of
personal injury.

1.8.2.

The COSHH assessment will comply with the UK COSHH regulations, as will the handling of
the material on site. It is a requirement of the client that only the amount of chemicals
required on site for daily usage be allowed (unless authorised otherwise). All containers will
be clearly marked to identify their contents. Certain chemicals are required to be kept safely
stored in specific locations on site. The CGC-SACYR JV will notify Company of these
locations and requirements on submission of the COSHH assessment/MSDS.

1.9. Confined Space Working


1.9.1. All confined space working on the project shall be in accordance with the QCS 2014, the
basic requirements of which are:
i)
ii)

Preventing the need for entry


Identification of hazards and assessment of risks associated with Confined Spaces.

31

iii)
iv)

1.9.2.

Introduction of a safe system of work


Emergency Procedures (including training)

Prior to any entry the following must be in place:


i)
Correct training of all personnel both making the entry and performing standby duties.
ii)
Formulation of a specific RAMS package for the confined space entry and works to be
carried out within.
iii)
Formulation of a specific rescue plan in case personnel working within the confined
space get into difficulties.
iv)
Provision of all required PPE and safety equipment identified as necessary in the
RAMS (includes, but is not limited to, gas monitors, Tripod etc).
v)
Submission of all documents and training certificates to the CGC-SACYR JV for
approval.
vi)
Valid Confined Space Work Permit.

1.10. High Risk Activities


1.10.1. The following is a list of some of the potential high risk activities for which task specific RAMS
is required. These are in addition to the standard Permit to Work system and will be enforced
by the CGC-SACYR JV Contractor. The list covers all tasks that are likely to involve
COMPANY NAME, but is by no means exhaustive.
i)
All Confined Space Work
ii)
Work with ionising radiations (Radiography)
iii)
Work that requires changing flow of vehicles or pedestrian traffic
iv)
Any direct mechanical or electrical tie-ins to live or previously live systems
v)
Critical lifting Operations
vi)
Pressure testing, hydrostatic / pneumatic air.
vii)
Work involving the assembly or dismantling of heavy prefabricated components.
viii) Any work on roofs, fragile or otherwise
ix)
Any work at height including steel erection, roofing and erection/dismantling of
scaffolding
x)
Work within operating plant
xi)
Activities that expose employees to hazardous chemicals or biochemical substances
xii)
Hot Work
xiii) 2 Tier working

1.11. Pressure Testing


1.11.1. Prior to any pressure testing taking place the testing procedures shall be submitted to the
consultant for review and approval. Detailed RAMS packages will also be submitted for
review and will detail the proposed work, working medium, pressures, barrier distances and
personnel to be involved in the works.

1.11.2. All personnel involved in the pressure testing works shall be fully briefed on all procedures
and RAMS and shall sign onto the RAMS log sheet to indicate that they understand the
procedures etc, and that they will abide by the safe working practices outlined within.

32

1.11.3. All pressure testing works will be closely monitored by the Company supervisor at all times to
ensure that safe working practices are meticulously followed.

16 EMERGENCY ARRANGEMENTS
Please refer to section 41.4 for specific emergency plans and arrangements developed for this site.

16.1 First Aid, Fire Fighting and Emergency Arrangements


The Safety Manager shall assess the site to determine the first aid and fire fighting requirements as
civil defence fire dept. Detailed site specific records of the assessment will be held in the site office.
As a minimum the following information will be retained:

Quantity and type of first aid boxes required

Names and photographs of first aiders

Quantity and type of fire extinguishers required.

Names and photographs of fire wardens

Other equipment and arrangements required

Emergency evacuation protocol

Incident reaction protocol

On shared sites the Consultant will comply with any existing arrangements provided they are suitable
and sufficient for the work. If existing arrangements are not satisfactory then prior to work
commencing the Safety Manager shall agree with the other site occupants suitable arrangements for
the duration of the work.

16.2 First Aid


16.2.1 General Arrangements
A first aid box shall be provided in the main site office, and at all mobile sites.
The Safety Manager shall ensure that the contents are replaced as necessary.
Please refer to section 41.2 for the name of the first aiders and the location of the first aid box/boxes.
This information will be briefed to all new staff and it will be posted on the site safety notice boards.
An assessment of the type of work, number of people employed and remoteness of accident and
emergency services will be made in order to decide on the adequacy of emergency arrangements.
Where action is required additional to the standard site arrangements, these will be detailed on the
method statements.
Please refer to section 28 for method statements.
The Safety Manager is responsible for ensuring the adequate provisions of first aid equipment and
suitably trained First Aiders in accordance with the Health and Safety (First Aid) Regulations.

33

The Consultant will maintain records of trained and certified first aiders. Please refer to section 0 for
more details regarding training records.
16.2.2 Accident Book
The safety Manager will ensure that accident books are available at all sites and offices. All accidents
and incidents, regardless of severity, must be recorded in the relevant section of the accident book.
All accident/incident reporting forms are to be forwarded to the Safety Manager.
All accidents or injuries shall be recorded in the accident book by the Safety Manager, and reported to
the Client

16.3 Fire and Emergency


The aim of emergency prevention and preparedness on the Project will be to reduce the risks
associated with emergencies by identifying potential hazards and instigating preventative controls. JV
will comply with the requirements of the Site Emergency Response Plan and Procedures and produce
an Emergency Response Plan. As part of the Site Induction Programme personnel will be made
aware of the requirements of this plan and associated procedures.
Emergency Preparedness Procedure together with a schedule of emergency drills will be
conducted regularly. Such drills are scheduled to ensure that Emergency Staff members are
prepared to properly function in their assigned role.
The effective implementation of this Emergency Preparedness Procedure is achieved by
providing training and guidelines in the event of an emergency that could endanger life, property
and the environment.
Records of scheduled emergency drills are kept to ensure HSE compliance.
The Emergency Preparedness Organization will implement suitable procedures to cater for
emergency situations, including rescue and recovery operations. It is envisaged that the major
rescue and emergency force will be the Government Agency Services.
In addition to the above, the Emergency Response Plan will:
describes how the emergency response is initiated and how the emergency teams are activated;
specifies command, control and communications arrangements;
identifies the roles and responsibilities of all personnel likely to be at the site of the emergency or
involved in the response;
Identifies muster points;
includes a person nominated as the site Emergency Control Officer;
Identifies emergency equipment available and personnel trained in its use; and
JV will cooperate and participate in Emergency Response Training exercises as required.
Some of the potential emergency situations are below and all the persons working at site will be
trained and necessary information will be communicated in accordance with emergency
situation: Excavation collapse, vehicle accident, Fire and explosion, Medical emergency.

16.3.1 Fire Precautions Management


Appropriate fire management systems will be developed for project site locations, from the findings of
specific fire risk assessments. This shall be in accordance with the requirements of the Civil Defence
Fire Department, and filed in the risk assessment section 27.

34

Staff will be nominated and trained to undertake the role of Fire Warden at all sites. Fire fighting
equipment will be procured, installed and maintained, subject to the findings of the risk assessment,
or the requirements of any building fire certificate, either existing or to be applied for.
The Safety Manager is responsible for ensuring the adequate provisions of fire prevention equipment
and suitably trained Fire Wardens in accordance with the Regulations.
Please refer to sections 41.3 for the names of the fire wardens and the location of the fire fighting
equipment. This information will be posted on the site safety notice boards.
The Consultant will maintain records of trained and certified fire wardens. Please refer to section 0 for
more details regarding training records.
16.3.2 Halon
Fire fighting equipment brought onto site shall not contain Halon.
16.3.3 Hot Work and Other Fire Hazardous Operations in Sub-Surface High Fire Risk
Locations
Hot works will not be carried out without the appropriate risk assessment and method statements. Hot
work will require a hot work permit.
Where possible all hot work and fabrication will be carried out on the surface. Where this is not
possible then hot work will not be carried out until the risk assessment has been reviewed by the
Safety Manager and a safe system of work confirmed by him.
If hot work is to take place below ground all other work below ground will be halted until the hot work
is completed. Only essential personnel may be present below ground during the hot work. Hot work
will not take place in areas open to the public.
16.3.4 Fire Watchmens Attendance
A suitably trained fire watchman, with the appropriate fire fighting equipment will be provided at each
hot work location, and for a period of 1 hour after completion.
Minimum equipment per hot work location:

1 x 6 kg DCP fire extinguisher

1 x 2.2 Kg CO2 fire extinguisher

1 x fire blanket

1 x approved means of communication to raise the alarm

16.3.5 Fire Detectors and Alarms


The emergency arrangements for the site will take into account the existence of fire detection and
alarms on the site. Where there are none, if it is not appropriate to install them, then the method of fire
detection and alarm to the site, and adjacent area shall be detailed in the emergency arrangements,
please refer to section 41.4.

35

16.4 Emergency Contacts and Assistance


Please refer to section 41.1 for emergency contact details.
The emergency telephone numbers, contacts and action plans should be displayed on the site safety
notice boards.
Further detailed instructions will be included in the method statements for the work.
Communication with emergency services will be via the most suitable method for the site, e.g. via
mobile telephone if no other means are available. This shall be checked prior to work commencing by
the supervisor.

16.5 Reporting of Accidents, Incidents and Dangerous Occurrences


An accident is an unplanned, uncontrolled event giving rise to death, injury (including assaults),
occupational ill health or other loss (for example, fires and explosions, train accidents, infrastructure
failures, property damage, environmental loss).
An incident is an unplanned, uncontrolled event, which under different circumstances, could have
resulted in an accident (also known as a near miss)
The Safety Manager is responsible for ensuring that the reporting and investigation protocols are
correctly implemented and for ensuring that the appropriate managers are made aware of accidents
and incidents as soon as possible.
All other employees and contractors are responsible for informing a responsible person, of an
accident, incident or dangerous occurrence, in accordance with the procedure in section 41.4. (A
summary of this will be posted on site safety notice boards, and the process included in the site
induction.)
16.5.1 Accident / Incident Reporting
Where accidents, incidents or disease are reportable to the Authorities, it is the employers
responsibility to submit to the Authorities, a completed copy of the relevant HSE notification; Report of
Injury or Dangerous Occurrence or, Report of Case of Disease
All accidents MUST be reported to the Clients Safety Manager, by the Consultant and the
contractors. Any reportable accidents/dangerous occurrences will be investigated and a report
submitted by the Safety Manager, if/when required.
Reporting procedures shall fully comply with legislative, and the Clients requirements.
Additional references:
Accident reporting procedure SMS
Accident Investigation Procedure SMS
Monthly Safety Returns SMS

36

16.5.2 Accident / Incident Investigation


The Safety Manager shall ensure the appropriate level of investigation is undertaken and will review
and approve all completed reports, recording that actions are complete and closed out.
The Safety Manager will ensure full co-operation with any accident investigation & follow up.
All accident and incidents no matter how minor will be investigated so that an analysis can be carried
out to identify particular trends. If a trend is found the activity/operation will be reviewed to ensure that
the methods of work and any control measures previously implemented are adequate. The output
from the trend analysis will be discussed at the 4 weekly project safety briefings.

17 ENVIRONMENT
The Safety Manager shall be responsible for the design and implementation of all environmental and
waste management arrangements within the site and any affected areas outside of the site. He shall
also be responsible for all associated consultations and for obtaining the necessary approvals/permits
for the arrangements.
If work on the public highway is required, it is the Safety Managers responsibility to ensure that the
environmental and waste management plan is acceptable to the local authority responsible for the
roads.
The environmental and waste management plan shall be complied with by all site personnel and
visitors. It shall cover all expected work activities, delivery and storage areas, and it shall be expanded
and/or amended to cover new or altered activities as they arise.
The environmental and waste management plans shall also provide for the requirement that the
entrances and roads are kept clean and clear of obstructions, and prevent the spillage or deposit of
clay, rubble or other debris on the entrance and other roads throughout the contract period.
JV will implement work practices aimed at ensuring that the environmental impact of construction,
pre-commissioning and commissioning activities is kept below the level as indicated in the
Environmental Impact Assessment (EIA), thus being in compliance with the applicable environmental
standards and regulations.
Air Quality Control
Dust and sand emissions in populated and sensitive areas will be kept to a minimum by proper
mitigation measures, (e.g. adequate water spraying for activities that may generates huge amount
of Dusts.)
Waste Management
Solid and liquid waste and liquid effluent generated during construction and pre-commissioning
activities shall be properly separated and disposed of according to waste disposal requirements. A
specific procedure will describe sources, quantities and characteristics of waste generated and
guidelines for handling, transport, storage and disposal of waste will be recommended.
Spill Management
All environmental incidents (e.g. spills, releases) will be reported to the Safety Manager.

37

A specific procedure describes the action to be taken to prevent spills and releases, pollution
response action in the event of a land spill, according the size of the spill, and action to be
implemented for handling, reporting and notifying spills.
The following shall be under the Project Director responsibility:

Inspection of good housekeeping in working areas during day-to-day operations.


Identification and classification of waste, as well as maintaining a Waste Register.
Estimation of distinguishable produced waste volumes.
Ensure that all Subcontractors are aware of the Waste Management Procedure(s) by providing
them Waste Management Training and Toolbox Talks and through Poster information
campaign.
Subcontractors in charge of waste management and disposal are provided with required
licenses from local authorities.
Ensure that all environmental accidents (spills and/or releases) are properly managed,
investigated and reported.
Management of Hazardous Waste / procedures will be developed and will be discussed with
Supervisors concern in the area.
Waste disposal log will be maintained.

18 COMPETENCE MANAGEMENT
18.1 Key Safety Personnel
The CGC-SAYCR JV maintains details of qualifications, training, experience and competence of all
the clients personnel employed on the project in safety related duties. Relevant records are available
for inspection on request at our company offices.
Subcontractors shall maintain their own records of qualifications, training, experience and
competence of their own employees. Copies of these records shall be made available to the Project
Manager as required.
The names of the personnel in charge of work at the sites and other individuals with a responsibility
for advising on specific actions concerning safety will be finalised at the pre-commencement meeting.
Once confirmed by the meeting the finalised list of names will be appended to this document and
displayed prominently in the Site Office.

18.2 Training requirements


The individual employers are responsible for the training of their personnel and ensuring they are
competent to fulfil their assigned duties.
The training shall comply with any relevant health and safety training requirement, legislation or best
practice.
Contractors training arrangements are checked during the procurement supplier check process and
confirmed during subsequent project audits and inspections.
The Safety Manager will ensure that all people on site have been provided with training and
information about the project taking into account arrangements for specific awareness training.

38

The Safety Manager will ensure that the personnel and sub-contractor personnel have the necessary
competency skills and certification prior to permitting them to work on site.
When undertaking site inspections spot checks will be made on certification of personnel on site to
confirm their certification is adequate and in date.
The [Project Manager] shall ensure that summary records are available on site.

18.3 Verification of Information and Training


Records of training and competence qualifications will be held by the company. Access to these
records will be available for the Project Manager to review as required. Details of agency staff are
held at their offices.
For certain activities where competence is proved by certificate staff must be in a position to produce
them for inspection when requested.
Sub-contract labour (individuals) should ensure that the relevant certificates and documentation is
registered on site prior to work on site. This will be inspected by the Safety Manager or work
supervisor as appropriate.
Where work packages are sub-contracted the contractor shall ensure the validity of their own staff
credentials. However records shall be made available for inspection and audit if requested.
Records may be requested and audited at any phase during the project to ensure that standards are
maintained.
Where appropriate national record databases will be checked to verify information. This will be done
by the Safety Manager as appropriate.
The tables below details the minimum required competence levels for all trades and activities
expected on site.
Position/Trade
Crane Operators
Heavy equipment Operator
Rigger
Banksman/Slinger/Signaller
Welder
Site Nurse
Scaffolding supervisor
Electrician
Confined space supervisor

Certification
rd
Valid Qatar license and 3 party certification.
rd
Valid Qatar license and 3 party certification.
rd
3 party certification.
Internal training
3rd party certification.
MOH Certification
3rd party certification.
Internal training
3rd party certification.

Activity
Confined Space Entries,
Erection and dismantling of scaffold and

Certification
Accredited Training
Accredited Training

39

mobile scaffold towers,


The use of Welding Machines,
The use of Cutting/Burning Equipment,
Working at Height,
First Aid Training

Accredited Training
Accredited Training
Internal training
Accredited First Aid Training

18.4 Drugs and Alcohol


The CGC-SAYCR JV has a clearly defined policy on abuse of alcohol, drugs and other substances or
medications which can impair the performance of duties which have a relation to safety at work.
Illegal drugs are not allowed onto any site and will not be tolerated; criminal acts involving illegal drugs
will be notified to the police. Consumption of alcohol on any work site is not permitted. Personnel
presenting themselves for work in an intoxicated or otherwise unfit state as a result of alcohol or drugs
are a danger to themselves and others and they will be required to leave the site. Where a client has
a more stringent requirement then this will also be adhered to.
All relevant legislation relating to the use and misuse of substances of abuse will be complied with.
This policy will be complied with by all personnel. Sub-contractors will be made aware of the policy
and the consequences of non-compliance. All project personnel will be made aware of the policy and
reminded of it at regularly held tool box safety talks, briefings etc specified in Section 7.
It is the Safety Managers responsibility to ensure that the drugs and alcohol policy is implemented on
site.

18.5 Medical Conditions


The QCS 2010 has strict medical standards for all personnel working on sites; additionally some
Consultants make enforce stricter standards. The Consultants standards will be adhered to and where
a client has a more stringent requirement then this will also be adhered to. Contractors shall not
employ on the site any personnel suffering from any medical condition, or taking any medication, that
may affect their own safety or that of others.
It is the responsibility of the individual employers to ensure that their personnel meet the standards
required.
18.5.1 Hearing Aids
Hearing aids may be permitted provided that such use does not compromise the safety of the
individual or their co-workers. The Safety Manager shall assess whether additional arrangements are
required for such workers and shall implement any arrangements required.
18.5.2 Fitness for work
Personnel shall be fit for the work they are to undertake. If persons are suspected to be under the
influence of alcohol or drugs, they will be sent home and will be subject to disciplinary action.

18.6 Working Time


Working hours will be daylight only, otherwise notified.

40

Working hours will comply with the requirements of the Working Time Regulations Qatar labour law.
The Site Manager shall require documentary evidence of adherence to these requirements to be
produced for inspection, and also carry out random check of records of hours worked.
Special regard must be paid to the problem of staff working on more than one project to ensure that
working hours and rest period requirements are not contravened, in this situation records of other
work performed may be required.
Travelling time of more than one hour from base or home (as appropriate) will considered as work and
shall be deducted from the time available for work on site.

18.7 Knowledge and Understanding of English


To ensure clear communication and understanding of information on the project all personnel are
required to be able to speak and understand English to a standard appropriate to the task they are
required to perform. In exceptional circumstances, it may be necessary to use workers that are unable
to speak English; these may only be used if agreed in advance by the Site Manager In such
circumstances, there must be in place a satisfactory means of communication for command and
control of these workers.

19 SELECTION OF SUB-CONTRACTORS, MATERIALS AND PLANT


The Supply Chain Manager is responsible for managing the procurement system and liaising with
department heads when assessing potential suppliers or reviewing the effectiveness of existing
suppliers.
Contractors and suppliers will be selected from an approved list maintained by the procurement
department. Contractors and suppliers, which are not on the approved list, will be subject to a vendor
assessment process prior to any award.
Regular audits will be carried out to ensure robust purchasing and maintenance procedures are
followed.
19.1.1 Personnel
All project staff will be selected for their competence to do the job required of them. The company
maintain competency records, the Safety Manager/Project Manager has access to these when
selecting and scheduling work and individuals.
19.1.2 Contractors & Sub-contractors
All contractors will be required to comply with the requirements of the Clients safety and
environmental procedures and the requirements of this Construction Health and Safety Plan. Only
Contractors from the approved suppliers list will be used.
19.1.3 Materials & Methods
All suppliers will be required to supply relevant health and safety information. This will include where
relevant, information on transport, storage and carriage with associated hazard and safety data
sheets, and COSHH assessments. Where appropriate details of weight and centre of gravity shall
also be supplied.

41

The designer shall liaise with the construction contractors to ensure that an appropriate construction
method can be employed. The Planning Supervisor is responsible for ensuring this happens.
19.1.4 Plant
The Mechanical Manager and the Safety Manager are responsible for checking plant and machinery
and shall ensure:

It is suitable for the intended task

It is only used for the intended purpose

It is only operated by competent licensed persons

The correct documentation is available; subject to appropriate inspection and calibration.

20 PERSONAL PROTECTIVE EQUIPMENT


Systems of work must be designed to avoid, as far as is reasonably practicable, the use of PPE. PPE
shall only be used if it can be demonstrated that the only method of work makes it unavoidable using
the hierarchy of control measures described in the Occupational Health, Safety, Environmental and
Welfare regulations of Qatar
Where PPE is issued it shall meet with the requirements of the Occupational Health, Safety,
Environmental and Welfare regulations of Qatar.
Where PPE is specified it shall be recorded in the relevant Method Statement, which shall state what
PPE is to be used and under what conditions. It is the responsibility of all levels of management, and
all individuals concerned to ensure that the requirements are fulfilled.
20.1.1 Implementation
The Safety Manager shall check by site observation and inspection that person protective equipment
is being worn and is in good condition.
The three-strike rule applies to PPE, if an individual repeatedly abuses, misuses, or does not
use PPE as required, they will be removed from site by the Safety Manager, and shall not work
on the site again.

21 SITE RULES
The following site rules are site-specific rules based on risk assessments. ADD more as necessary.
Site rules must identify required actions or behaviours. Also consider if rules are required to manage:
Emergency procedure, Permits to work, Provision of required safety controls, Access and
movements, Alcohol and drugs, General conduct and co-operation, Specific security arrangements

SITE RULES
DOS

WEAR PPE AS NECESSARY HARD HAT, SAFETY BOOTS & HIGH VISIBILITY CLOTHING
MUST BE WORN AT ALL TIMES

42

OBSERVE VEHICLE MOVEMENT RESTRICTIONS BOTH ON-SITE AND ON PUBLIC ROADS

ONLY USE PROPER MEANS OF ACCESS & EGRESS. ENSURE SITE SECURITY IS
MAINTAINED

COMPLY WITH PERMIT ARRANGEMENTS

KEEP THE SITE TIDY MAINTAIN HIGH STANDARDS OF HYGIENE

FAMILIARIZE YOURSELF WITH EMERGENCY PROCEDURES INCLUDING ACCIDENT


REPORTING ARRANGEMENTS

DONTS

DONT EXPOSE YOURSELF OR OTHERS TO RISK. IF YOU HAVE DOUBTS ABOUT THE
SAFETY OF A TASK ASK

DONT UNDERTAKE ANY TASK YOURE NOT AUTHORISED OR COMPETENT TO DO

DONT EAT OR DRINK OTHER THAN IN DESIGNATED AREAS WASH YOUR HANDS
BEFORE EATING.

DONT MISUSE TOOLS OR OTHER EQUIPMENT YOU MAY INTRODUCE A RISK TO


OTHERS

DONT LEAVE HAZARDS UNPROTECTED COVER EXCAVATIONS, FENCE UNSAFE


AREAS.

DONT LEAVE VEHICLES UNATTENDED UNLESS SECURED.

22 WELFARE
The Client recognise that the key to achieving healthy and safe working conditions is to ensure that
health and safety issues are planned, organised, controlled, monitored and reviewed. Site work will
not commence until suitable arrangements are in place.
Welfare facilities as required under the Construction Occupational Health, Safety, Environmental and
Welfare regulations of Qatar, will consider actual site requirements, their location on site and regular
maintenance during the planning and preparation stage of the project. The facilities must reflect the
site size, work duration, nature of the work and numbers of people who will use them. Special
attention will be given for sites where additional health risks may be present (e.g. drainage works,
dirty work).
The Project Manager will ensure that suitable welfare facilities are made available for all personnel on
site and will manage the delivery, maintenance and regular emptying of facilities.
All necessary arrangements will be planned in advance; personnel will not be left to make their own
arrangements.

23 APPLICABLE REGULATIONS, RULES AND GUIDELINES


23.1 Legislation, Regulations, Rules and Guidelines
The procedures contained in this plan do not prejudice any statutory requirements and guidance that
are in force at any time during this project.

43

All relevant Occupational Health, Safety, Environmental and Welfare regulations of Qatar, shall be
complied with.
Guidance on legislation and codes of practice can be obtained from Company Safety Advisers.

23.2 Standard Forms


Standard forms will be required for certain activities and equipment on site. Those required for this
project are:

Scaffolds and mobile working platforms

Excavations, shafts, earthworks, underground works or tunnels

Cofferdams and caissons

Electrical isolation

Hot works

Lifting equipment and cranes

Mobile working platforms

Accident/incident statistics and normalising data

Accident/incident reports

Site safety reports

HSE communications

23.2.1 Register of Site Forms


Reference Number

Type of form / Title


description if necessary)

44

(Including

additional

Rev

24 HEALTH AND SAFETY POLICY STATEMENT

45

PREVENTION POLICY SACYR


SACYR operates in five business areas, such as: construction, services, concessions, property development and estate,
therefore there is a great variety of jobs, due to diversity of these activities.
SACYR has a main objective is to get that all the Group's activities are considered, from the time of planning and during
implementation, the necessary measures to avoid risks that could appear on the origin and development of it and, for the risks
considered unavoidable, put all the preventive and protective measures necessary to protect health and safety of our
employees and partners.
When planning a job, we not only think quickly and efficiently but also the safest way of going about it.
Security must be inherent and intrinsic to developing any job, both in its beginning and and the procedure to be developed.
Consequently, SACYR bets on INTEGRATED SAFETY and establishes a Risk Prevention Policy which main objective is to
promote the improvement of work conditions and the level of protection, safety and health of its employees.
To achieve this target, we must be aware of our duties and responsibilities and how to deal with them,always seeking a
continuous improvement in preventive action, bearing in mind that this can only be achieved through information, training and
staff participation at all levels.
Therefore, SACYR is committed to develop throughout its Organization, its Occupational Risk Prevention Policy through the
following actions:
- Placing Prevention training at all levels, as one of the main objectives, so that the Preventive Policy is known and taken on by
all.
-Keeping the Prevention Plans updated and operating in all our workplaces, in order to achieve a continuous improvement of
the Management System established.
-Analyzing risk situations and accidents that have occurred, not assuming them as part of the work but obtaining corrective
actions through their analysis. These must be known and implemented to eliminate or minimize the risk of accidents to achieve
safe work conditions.
- Achieving integration of subcontractors and suppliers in a common compromise to improve occupational safety.
- Checking both the observance of legal requirements that affect us in every activity, as well as those established to achieve the
proposed targets for each Group company.
- Keeping up to date so our Manual as our Procedures that derive from it.
The Management of SACYR understands that occupational risk prevention, in order to achieve the highest levels of safety,
must come from the company human team, so it encourages everyone to understand and integrate the previous guidelines into
his working style.
Madrid, October 1st, 2012

46

Manuel Manrique Cecilia


Chairman of SACYR

25 GENERAL STATEMENT OF HEALTH AND SAFETY PRINCIPLES

Goals, Objectives, Targets.


It is crucial to the success of the projects that everyone involved understands why good Health and
Safety is required, how everyone can play a part and what the consequences of unsafe working will
be. Health and Safety within the JV is led from the top, with a commitment to the project to make it
accident and incident free Zero Harm is the objective.
The requirements of the CPHSP supplement the duties detailed within Qatar Construction
Specification 2010 and the Project Delivery Management System (PDMS) for the Local Roads and
Drainage Programme (LRDP).
CGC-Sacyr will liaise with the GEC and the PMC to share information regarding health and safety
issues, training, Safety Alerts and initiatives to promote the Zero Harm ethos.

Zero Harm is defined as:


Zero fatalities
Zero permanently disabling injuries
Zero injuries to members of the public
Zero long term harm to health
Accident Frequency Rate <0.1, while aiming for Zero AFR
It is crucial to the success of the projects that everyone involved understands why good Health and
Safety is required, how everyone can play a part and what the consequences of unsafe working will
be.
CGC Sacyr senior management will ensure the following.
Monitor and advise on the quality of the site safety induction, its compliance with QLL 2004 (46/99)
and its relevance to the on-going works, taking into account ;

The provision made for different languages and levels of literacy.

Evidence of understanding the purpose and content of the induction.

The standard of presentation and commitment of the contractors


representative.

A clear message is given regarding the ZERO HARM philosophy and PWA
requirements.

The Contractors requirements and Safety Policy is explained.

The roles, responsibilities and expectations of each person.

47

Site Rules

Accident or Incident reporting and First Aid provision

Welfare provision and transportation arrangements.

25 DRAWINGS
Project Drawing Register
This drawing register is included to ensure that relevant drawings not currently on site can be
obtained. Standard document management procedures should be followed to ensure that the
drawings on site are kept up to date.
Drawing Number

Title
(Including
additional
description if necessary)

Rev

Contact
Department
Company

/
/

26 CONTROLLED UPDATE LOG FOR CONSTRUCTION HEALTH AND SAFETY


PLAN REVISION ISSUE
Log Issue

Documents attached
Reference

Title

Rev

27 REGISTER OF RISK ASSESSMENTS


Reference Number

Title (Including additional description if necessary)

Rev

28 REGISTER OF METHOD STATEMENTS


NB Method statements should include details of emergency arrangements. Where the standard site
arrangements are sufficient, this can be noted.

48

Reference Number

Title (Including additional description if necessary)

Rev

29 REGISTER OF SITE SURVEY REPORTS


Reference Number

Title (Including additional description if necessary)

Rev

30 REGISTER OF TRAFFIC MANAGEMENT PLANS, DOCUMENTS & DRAWINGS


Reference Number

Title (Including additional description if necessary)

Rev

31 REGISTER OF SITE ACCESS PLANS


Reference Number

Title (Including additional description if necessary)

Rev

32 REGISTER OF CONTACTS
Name

Company &
Title

Job

Location

Contact Details
Address
Tel
Fax
E-mail
Address
Tel
Fax
E-mail

49

Name

Company &
Title

Job

Location

Contact Details
Address
Tel
Fax
E-mail

33 ORGANISATION CHARTS

GENERAL MANAGER
Head
PROJECT MANAGER

ENVIRONMENTAL

HSE

DEPARTMENT HSE
MANAGER

Office

TRAFFIC CONTROL
OFFICER

MANAGER

NURSE

Environment
Officer

Environment
Officer

Safety
Officer

Traffic

Safety
Officer

Safety
Officer

50

Safety
Officer

Traffic

34 INTERFACES
The following interfaces have been identified; measures have been put in place to identify additional
interfaces if they arise. Co-operative measures have been introduced to ensure that such interfaces
do not import risk.
The following are contacts for the identified construction interfaces. The Site Manager is responsible
for management of interfaces. The Site Manager shall identify new interfaces, and those identified by
others should be reported to him/her:
Reference

Description

Duration /
Dates

51

Contact Person

Contact Details

Reference

Description

Duration /
Dates

Contact Person

Contact Details

Qatar municipality

Throughout

Manager
Name

Address
Tel
Fax
E-mail

35 REGISTER OF MEETINGS
35.1 Sample Site Safety Meeting Agenda
Attendees
For Client

Project Supervisor (construction stage), Resident Engineer or Project


Manager.

For Consultant

Safety Manager, Site Management Personnel (if available).


Other Invitees where appropriate.

Agenda

Matters arising from previous meeting not covered by agenda

Issues emerging from site safety inspection reports

Accidents and incidents lessons learnt

Cross-project issues sharing of good practice / lessons learnt

Interface issues

Forward programme risks

Additional items submitted

Any other business not included above

Proposed meetings management


Meetings to be held monthly (as a minimum) at Project offices. Minutes to be produced and circulated
electronically for approval within 5 working days.

35.2 Register of Meetings


Reference Number

Title (Including additional description if necessary)


Pre-Commencement Meeting

52

Rev

36 NOTIFICATION FORM

SMS SITE SAFETY STATISTICS


CONSOLIDATED (Inclusive of Sub Contractors)

Monthly Incident Statistics

26-Jan-15

26-Feb-15

26-Mar-15

26-Apr-15

to

to

to

to

25-Feb-15

25-Mar-15

25-Apr-15

6-May-15

582

643

15,714

14,296

141,426

128,664

Lost Time Incident LTI ( 3


days and more)

Total Lost Days (Incl


wkends/Hols)

404,406

533,070

Project Name: AL KHEESA


Site Staff
Total Labour Work Days this month

INCIDENT / ACCIDENT
RATES

LOST TIME INCIDENTS

Total Labour Work Hrs (Man Hrs


Worked)

Man hours worked since


last LTI

LTI Frequency Rate (LTIFR)


ZERO HARM

0.07

0.0640

LTI Severity rate

2.29

2.105

Incidence Frequency Rate

0.06

0.064

Reportable Incidents
Category 1 (fatality)
Category 2 (Lost Time Incident)
Category 3 (FA, Med, RWC)

53

Category 4 (Damage or loss)


Total Recordable Incidents
Total Reportable Incidents
Category 5 (Occ Health)
Dehydration cases
Dont Walk By Target Zero

Incident Frequency Rates


TRec IF TARGET: IS
TRep IF TARGET: IS

Frequency = Incidents x 100,000


cumulative man hours

ENVIRONMENT: GENERAL WASTE


AMOUNT

This Month

Last month

Cumulative

This Month

Last month

Cumulative

Cubic Metres
HAZARDOUS WASTE
AMOUNT
Cubic Meters
FORMAL SITE INSPECTION STATUS
ZONE

AREA

TYPE

DATE

PM/SA

37 REGISTER OF SITE NOTICES


Reference Number

Title (Including additional description if necessary)

Rev

38 REGISTER OF TOOLBOX TALKS / SITE BRIEFINGS


Reference Number

Title (Including additional description if necessary)

54

Rev

39 REGISTER OF INDUCTIONS
Reference Number

Title (Including additional description if necessary)

Rev

40 SCHEDULE OF SITE INDUCTION INFORMATION


Prior to commencing work briefing for all staff and contractors will include details of significant site
risks or issues, and site rules. The following is a schedule of contents for the site briefing pack. (All
documents will be at the latest revision.)
This list is a minimum and must be expanded and amended for each project/task.

Site access arrangements

Local rules

List of site specific health, safety and welfare issues

General site hazards on site.

Identity of key personnel and contacts

Emergency arrangements

Emergency Service Contact Details

Consultant Emergency Contact Details

Client Contact arrangements

Reference to location of emergency telephones

Procedure to be followed and action to be taken in the event of having to


make an emergency telephone call.

Address and telephone of local Accident and Emergency Hospital


o

Contact arrangements for the Electrical Control Operator

Emergency contact details for Utilities

Contact arrangements for environmental emergencies

On call contact arrangements

First aid arrangements

Details of First Aiders on site

Location of First Aid equipment

Welfare arrangements

Fire Precautions and Prevention methods on site

Location and type of fire fighting equipment

Details of Fire Wardens on site

55

Any other relevant information

Permits to work arrangements operating on the site. (Including that a breech of permit to work
arrangements is potentially a dismissible offence.)

Any Special site safety arrangements (e.g. confined spaces, working at heights).

Mention that Construction Health and Safety Plan exists and where it is kept

41 EMERGENCY CONTACTS AND ASSISTANCE


41.1 Emergency Contacts
Name

Job Title

Location

Contact Details

Eng.Salameh
Haddadin

Project Manager

Office

Address
Tel 50305855
Fax
E-mail:s.haddadin@cgckw.com

Al-Ahli Hospital.

Address: Al-Ahli Hospital.

Ahmed Bin Ali Street.

Ahmed Bin Ali Street.

P.O.Box 6401

P.O.Box 6401

Doha, Qatar

Doha, Qatar

Al Ahli Hospital

Tel: +97448988888
Fax: +97444898989
E-mail:
info@ahlihospital.com
Eng. Nassim
Omari

Construction
Manager

Office

50299578

Eng.Ruben
Estraviz

Deputy Project
Manager

Office

77514135

Eng.Enrique
Fajardo

H S E Manager

Office

77663921

Mr.Julius
Vincent

H S E Officer

Office

77134184

Mr.Loveson
Glariyans

Senior H S E
Officer

Office

33428557

56

Name

Job Title

Location

Contact Details

Mr. Julius
Vincent

H S E Officer

Office

77134184

Mr. John
Godstime

H S E Officer

Office

50458568

Mr. Faisal Butt

H S E Officer

Office

66592293

Mr. Conrad

HSE Officer (
night Shift)

Office

66998768

Mr.Jibin

Male Nurse

Office

77479922

41.2 First Aid


41.2.1 First Aiders
Name

Certificate Expiry Date

Contact Details

Mr.Jibin

30/04/2017

77479922

Location Reference Number

Type / Description

Location

001

0.25lt eye wash x 3

In chemical stores

002

Full First Aid Box

At site clinic

Name

Job title

Contact Details

Mr. Julius Vincent

H S E Officer

77134184

Mr. John Godstime

H S E Officer

50458568

Mr. Faisal Butt

H S E Officer

66592293

41.2.2 Fixed Location first aid boxes

41.3 Fire Prevention


41.3.1 Fire Wardens

57

41.3.2 Fixed Location fire fighting equipment


Reference Number

Type / Description

Location

001

9lt Foam Spray

Near diesel tank, lay down


area

002

Fire fighting pump

Near site office car parking

Temporary fire points will be easily identifiable, and will comprise:

2 x 9lt foam AFFF spray fire extinguisher

1 x 2.5kg CO2 fire extinguisher

41.4 Emergency Arrangements for the Site


JV ensure that arrangements and procedures are in place to manage emergencies and mitigate their
effects
The following emergency situations should be considered when operating in road construction:

Traffic Vehicular Accident/Incident;


Damage to utilities (water/electric lines/telephone lines/pipes);
Fire/Gas leaks; and
Chemical and fuel spills and leaks.

ALL ACCIDENTS ARE SERIOUS THE DEGREE OF


HARM OR DAMAGE IS PURELY A MATTER OF
CHANCE
The flow chart shown below demonstrates who needs to be advised,
important telephone numbers and timescales. This diagram should be
read in connection with existing accident reporting and investigation
procedures 3001 & 3002.
SCALE OF ACCIDENT
HIGH reportable
accidents & dangerous
occurrences as defined in
legislation.

REPORT TO:
IMMEDIATELY to Qatar authorities, by
Site Manager, phone xxx / fax xxx.
Written report as soon as practicable.
IMMEDIATELY Direct to Client Site
Manager or supervisor on site & by phone
to Consultant xxx.

MEDIUM Accidents
causing injury beyond
minor first-aid, accidents
that potentially could have
been HIGH, incidents that
could foreseeably have led
to a dangerous occurrence

58

As quickly as possible to Client Site


Manager or supervisor on site, before the
end of the shift / as quickly as possible to
Consultant phone xxx with follow-up
written reports as soon as practicable.

LOW Minor injury not


requiring anything more
than first-aid, minor
accidental property damage,
notable incidents where the
outcome could have been
more serious and there are
lessons to be learnt.

As quickly as possible to Consultant Site


Manager or supervisor on site. Issues to
be discussed at weekly safety meetings
[Project manager]. Project/Site Manager to
provide weekly summaries to Client.

42 RESIDUAL RISK REGISTER


ELEMENT

ACTIVITY

CONTROL MEASURES

NOTES

42. MATERIALS & SUBSTANCES CONTROL MEASURES


The following will be updated as and when materials are brought to site / store.
Reference Number

Substance / Title (Including additional description if


necessary)

59

Rev

43. WORK PERMITS AND WORKING PROCEDURES


The Safety/ Project Manager has carried out a risk assessment for this project, and determined that
permit to work arrangements, or special procedures that are required for certain activities. The
following sections specify the permit-to-work systems and other special procedures for different
activities identified and in place on this project.

43.1 General Work Permit Arrangements


A permit-to-work system is a formal written system used to control certain types of work that are
potentially hazardous.
The following details are common to all types of permit:
Permits shall be applied for well in advance of the work required, to ensure that other activities that
may be affected can be re scheduled.
The permit to work will only be issued close to the time of the work to be carried out. This is to ensure
that all factors are considered, and reduces the likelihood of unforeseen events being overlooked.
This period is determined by the engineering judgement of the person signing the permit, and may
vary during the course of the project depending on the type of permit, and other works on site at the
time.
The Safety Manager shall sign work permits.
If individuals are nominated to sign work permits, note their names and the type of permit they can
sign.
A copy of the permit shall be kept by the team undertaking the work. The original shall be filed here
and recorded in the register.
Permits to work must include the following characteristics:

Date & time specific (set period of time on a particular date)

For nominated persons

Unique numbering system

State location of entry/machine/activity to be carried out

Cross reference other permits as appropriate

Clearly identify precautions (e.g. lock of equipment)

Where to file and who gets copies

43.2 Register of Work Permits


Reference Number

Type of permit / Title


description if necessary)

60

(Including

additional

Rev

44 REGISTER OF INSPECTIONS & AUDITS


Reference Number

Type of inspection / Title (Including additional


description if necessary)

Rev

45 REGISTER OF WASTE TRANSFER NOTES


Reference Number

Material Disposed Of

Forms
Brief incident investigation
Full accident incident investigation
Risk assessment
Risk assessment guide
Weekly safety check list
Managers inspection report
Monthly safety statistics report
Monthly medical report
Material safety data sheet (MSDS) sample

61

Date

Potrebbero piacerti anche