Cost Estimating
by Bill Manfredonia, CPE, Cost Calculations, Inc.(http://www.costcalculationsinc.com) / Joseph P. Majewski, FCPE, P.E., JPM Construction Consultants,
Inc.(http://jpmconstructionconsultants.com/) / Joseph J. Perryman, Donnell Consultants, Inc.(http://www.dcicost.com)
Last updated: 05-28-2010
INTRODUCTION
Accurately forecasting the cost of future projects is vital to the survival of any business or organization contemplating future construction. Cost
estimators develop the cost information that business owners or managers, professional design team members, and construction contractors need
to make budgetary and feasibility determinations. From an Owner's perspective the cost estimate may be used to determine the project scope or
whether the project should proceed. The construction contractor's cost estimate will determine the construction bid or whether the company will bid
on the construction contract.
There were about 198,000 cost estimators in 1994 according to the U.S. Department of Labor, Bureau of Labor Statistics, 2006-2007 Occupational
Outlook Handbook, Cost Estimators, of which 58% work in the construction industry, 17% are employed in manufacturing industries, and the
remaining 25% elsewhere. Most construction estimators have considerable experience gained through working in the building construction industry.
This guide will be confined to cost estimating in the building construction industry.
Construction cost estimators can be contractually hired in many different ways. They may be employed by the owner's representative/project
manager, employed by the construction manager, employed as a member of a professional design team, or separately hired by the owner. They
estimate building costs through all the stages of design and the construction of the project. On large projects it is common for estimators to
specialize in disciplines that parallel design discipline specialization.
It is very important to have the cost estimator involved right from the start of the project to ensure that the project budget reflects the decisions made
by the rest of the project team throughout the integrated design process(engage_process.php).
DESCRIPTION
A. Professional Behavior Expected of the Cost Estimator
Ethics: The practice of construction estimating is a highly technical and professional discipline. It also involves abiding by certain standards of
ethical conduct and moral judgment that go beyond the technical aspects of the discipline. Estimators are often the most familiar with the
complete project. They must exercise sound moral and professional judgment at all times when preparing the project estimate. Estimators
sometime receive pressure from other members of the construction team to make expedient short-term decisions that can result in an unsound
bid. Resistance to this type of pressure is a part of the estimator's job. Examples of expedient behavior litter the history of inaccurate
construction estimating. Deficient estimates can also cause strife and litigation between members of the construction team. The American
Society of Professional Estimators (ASPE)(http://www.aspenational.com/) has stated the following ethical, moral and technical precepts as
basic to the practice of estimating. See the ASPE Code of Ethics(http://www.aspenational.org//Upload/FilesMenuInternals
/CODE_of_ETHICS.pdf) (PDF 510 KB, 4 pgs).
Integrity: Estimators are expected to use standards of confidentiality in a manner at least equal to that of other professional societies. The
estimator shall keep in strictest confidence information received from outside sources. The practice, commonly called "bid peddling", is a
breach of ethics and is condemned by the ASPE and that of other societies and construction organizations.
Judgment: Judgment is a skill obtained by estimators through proper training and extensive experience. Estimators should always use sound
judgment and common sense when preparing estimates. Proper use of judgment may mean the difference between profit and loss for the
company or client.
Attitude: Estimators should approach each estimate with a professional attitude and examine in thorough detail all areas of the work. They will
set aside specific times each day for entry of estimate quantities and data without interruption. Total mental concentration is a basic
requirement for preparing accurate cost estimates.
Thoroughness: An estimator will allow enough time to research and become familiar with the background and details of the project and then
promptly complete the quantity survey. They will review the various aspects of the project with the other disciplines involved. The estimator with
the most thorough knowledge of a project best serves the owner and project team, and has the best competitive advantage when preparing a
bid.
http://www.wbdg.org/design/dd_costest.php
1 of 6
C. Levels of Estimate
As a project is proposed and then developed, the estimate preparation and information will change based on the needs of the Owner/Client
/Designer. These changes will require estimates to be prepared at different levels during the design process with increasing degrees of information
provided. It should also be noted that within each level of estimate preparation, not all portions of the design would be at the same level of
completeness. For example, the architectural design may be at 80% complete while the mechanical design is only 50% complete. This is common
through the design process, but should always be noted in the estimate narrative.
In addition to construction costs, estimates for process or manufacturing areas require information related to the involved processes such as
product line capacity, process layout, handling requirements, utility requirements, materials and storage required, service requirements, flow
diagrams, and raw materials access.
The following descriptions constitute the different levels of an estimate. Estimates within each of these levels may be prepared multiple times during
the design process as more information becomes available or changes are made to the scope. As the level of the estimate increases it will become
more detailed as more information is provided; "unknowns" are eliminated; fewer assumptions are made; and the pricing of the quantities become
more detailed. Contingencies for the aforementioned will be reduced as more design documentation is produced.
The levels of the construction cost estimate correspond to the typical phases of the building design and development process and are considered
standards within the industry. These levels are as follows:
Level 1 - Order of Magnitude
The purpose of the Level 1 estimate is to facilitate budgetary and feasibility determinations. It is prepared to develop a project budget and is based
on historical information with adjustments made for specific project conditions. Estimates are based on costs per square foot, number of cars/rooms
http://www.wbdg.org/design/dd_costest.php
2 of 6
http://www.wbdg.org/design/dd_costest.php
3 of 6
EMERGING ISSUES
Computers and Building Information Models (BIM)(/bim/bim.php)
Computers have played an increasingly larger role in cost estimation for complex calculations as the design and construction industry has become
more computerized. For example, to undertake a parametric analysis (a process used to estimate project costs on a per unit basis, subject to the
specific requirements of a project), cost estimators will often use a computer database containing information on costs and conditions of many other
similar projects and geographic locations.
BIM is a simple concepta master, intelligent data model, resulting in an as-built database that can be readily handed over to the building operator
upon completion of commissioning. The BIM standard could someday integrate CAD data with product specifications, submittals, shop drawings,
project records, as-built documentation and operations information, making printed O&M and Systems manuals virtually obsolete. The technology
has moved forward, but the industry's ability to absorb these IT advances has yet to change. Clearly, if BIM offers a genuine solution to reduce
errors and rework, while improving building operations, it will eventually change the way all project team members develop and share information
over facility life-cycle phases.
http://www.wbdg.org/design/dd_costest.php
4 of 6
MAJOR RESOURCES
Publications
American Society of Professional Estimators
Awards Guidelines
Estimating Today NewsletterBack Issues Inside
Estimating Today Rate Card
Gek Study GuideOrder Online
Logosheet
Recommended Bidding Procedures
Standard Estimating PracticeOrder Online
Building News International(http://www.bnibooks.com/)
From Concept to BidSuccessful Estimating Methods by John D. Bledsoe, PhD, PE. Kingston, MA: R.S. Means Company, Inc., 1992.
GCCRGGeneral Construction Cost Review Guide
GSA Project Estimating Requirements
R.S. Means(http://www.rsmeans.com/index.asp)
Professional Associations
American Society of Professional Estimators (ASPE)(http://www.aspenational.org/)
Association for the Advancement of Cost Engineering International (AACEI)(http://www.aacei.org/)
International Cost Engineering Council(http://www.icoste.org/)
Royal Institution of Chartered Surveyors (RICS UK)(http://www.rics.org/uk)
Society of Cost Estimating and Analysis (SCEA)(http://www.sceaonline.net/)
WBDG
Design Objectives
Cost-Effective Branch(cost_effective.php)
Cost Estimating Software(/resources/estimating.php?r=dd_costest)
ProEst
ProEst Estimating - General Construction Version, General Contractors, Residential Builders and any other contractor that performs
general construction work
ProEst Estimating - Electrical Construction Version, Electrical Contractors including Residential, Commercial and VDV Contractors
ProEst Estimating - Mechanical Construction Version, Mechanical Contractors including Piping, Plumbing and HVAC
ProEst Digitizer Takeoff
RS Means Databases, National pricing databases
Computer Guidance Corporation, Invitation to Bid
Deneb Software, WinJob, Estimating & Accounting
Quest Solutions
Quest EstimatorDigitized takeoff for pricing out all types of cost items, and for printing out your final bid
Quest EarthworkCut-and-fill measuring software
Quest RoadworkCut and fill quantities for highway and roadway projects
Quest TrenchworkCalculate cut and fill quantities for underground projects
Quest Cross SectionsCalculate cut and fill quantities in cross-section view
http://www.wbdg.org/design/dd_costest.php
5 of 6
Tools
GSA Sustainable Facilities Tool (SFTool)(http://sftool.gov/explore/green-building/section/10/hvac/integrative-design-process)SFTool's
immersive virtual environment addresses all your sustainability planning, designing and procurement needs.
National Institute of Building Sciences(http://www.nibs.org/) | An Authoritative Source of Innovative Solutions for the Built Environment
1090 Vermont Avenue, NW, Suite 700 | Washington, DC 20005-4950 | (202) 289-7800 | Fax (202) 289-1092
2015 National Institute of Building Sciences. All rights reserved. Disclaimer(/about.php)
http://www.wbdg.org/design/dd_costest.php
6 of 6