Sei sulla pagina 1di 20

Feedback Seminar on

Energy-efficiency potential in South Africa

Loss Reduction & Reliabilityy


Improvement in Distribution
S t
System
January 2008

Tokyo
y Electric Power Company
p y
(JICA Study Team)
Koichi HOSHI
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Image of Distribution Loss


Energy Sent-out from HV/MV Substations

System Loss

Metered End-user Consumption


(energy sold)
Uncollected
Bills

Collected Bills
Bill d Energy
Billed
E

Technical
Loss

Nontechnical
Loss

{(Energy Sent from S/S


Billed Energy)
Technical Losses}

Financial
Loss
(Billed Energy
Collected Bills)

Commercial Loss
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Transmission & Distribution Loss


International Comparison of Line Loss
()
10
9
8
7
6
5
4
3
2
1
0

9.1

8.0
6.7
5.2
4.6
3.8

TEPCO
(2002)

U.K.

U.S.A.

FRANCE

(2000)

(1999)

(1998)

GERMANY
(2000)

SOUTH AFRICA
(2008)

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

FY

Transmission & Distribution Loss


TEPCOs historical trend of Loss
((%))

30

Newly Installation and Capacity Upgrading of Substations


25
20

T&D Lines Upgrading (3.3kV 6.6kV, 66kV 154kV)


15
10

4.6%

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

20
005

20
000

19
995

19
990

19
985

19
980

19
975

19
970

19
965

19
960

19
955

19
950

FY

Types of Distribution System Loss


Technical
Loss

Conductor
Resistance Loss
Corona Loss or
Leakage (very few)

Transformer
Core Loss
Copper Loss

Mostly losses come from conductor.


conductor Countermeasures advisable.
advisable

Nontechnical
Loss

Financial
Loss

Non Technical Loss


Inaccurate
I
M
Metering
i
Defective Meter
Tampering/Pilferage

C
Commercial
i lL
Loss

Financial Loss
Uncollected Revenue
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Countermeasures for Distribution Loss


(Focusing on the Technical Loss)

Leveling distribution system loads by


network re-configuration(for MV, LV system)
Power factor correction by capacitor placement
Install new feeders
Install new transformers
Build a substation
Re-conductoring
(Replace with larger cross section conductor)
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Overview of Countermeasures
1. Leveling of distribution system loads
by network re-configuration
Basic Idea
Some loads in the heavyy loaded feeder shifted to
another lightly loaded feeder
Sectionalizing switchgear allocation for load shift (new
interconnection between feeders may be required)
Optimal switching allocation may be done by distribution
system
t
analysis
l i software
ft
Comments
First step for loss reduction with less investment
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Image of Load Leveling


Substation B
Load 1
Load 2

Load 3

Substation A

Feeder B

Feeder A

Load 4

MV System Re-configuration
Feeder C

Load 5

Substation C

Substation B
Load 1

Load 2

Load 3

Feeder A

Note:

Substation A

After re-configuration, loss reduction


in feeder A may have much more
impact on the total system loss than
the loss increase in feeder B & C.

Feeder B

Load 4

Feeder C

Load 5

Substation C
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Overview of Countermeasures
2. Power factor correction by capacitor placement
Basic Idea
Improvement of power factor reduces power flow in a feeder
feeder.
Thus, system loss reduction achieved
Power factor improved
p
byy compensating
p
g the reactive power
p
Image of Reactive Current Compensation
Ic(Reactive
(
Current))
Ic

Load

Load

Load

Load

Load

Load

Capacitor

Reactive Current
Ic
IIc
c
Sending
End

Compensation

Without Capacitor
With Capacitor

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

Receiving
End 9

Overview of Countermeasures
3 Install
3.
I
ll new feeders/transformers/substations
f d /
f
/ b
i
Basic Idea
Heavy
H
lloaded
d d area to
t be
b supplied
li d by
b new feeder
f d so that
th t
existing feeder supplies less loads (for new feeder install,
sometimes ne
new HV/MV ttransformer
ansfo me needed)
New substation to be built in the center of high load density
area so that existing feeder supplies less loads
Comments
Building
B ildi new facilities(feeders,
f iliti (f d
transformers,
t
f
substations)
b t ti
)
requires a certain level of investment. Impact of loss
reduction and investment must be carefully considered.
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

10

Evaluation of Loss Reduction Measures


High

Total Cost = Cost of Loss Reduction


+ (Lost) Economic Value of Energy Loss
Optimal point

Cost

Cost of Loss Reduction


(Investment)
(Lost) Economic Value
of Energy Loss *

Low

Input of loss reduction measures

When Cost of Loss Reduction > Economic Value of Reduced


Energy Loss,
the loss reduction measure is considered feasible
Determine the most effective measures and their respective input
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

11

TEPCO Loss Reduction Experiences


Loss Reduction & Reliability Improvement in Jamaica
Cli
Client:
Marubeni,
M b i Jamaica
J
i Public
P bli Service
S i (JPS)
Period: Aug 2007 July 2008
Power Distribution System Loss Reduction(Phase II)
Client: Electricite du Laos/World Bank
Period: Mar 2007 Dec 2008 ((Phase II))
Period: Mar 2004 Mar 2005 (Phase I)
Feasibility Study on Loss Reduction of Distribution Network
Client: National Electric Power Co. Jordan/JICA
Period: Sep 1999 Oct 2000

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

12

Reliability Indices
SAIDI : System Average Interruption Duration Index
(Annual Average Interruption Duration per Customer)
SAIDI=

Interruption Duration Number of Interrupted Customers


Total Number of Customers

TEPCO = 3 minutes
SAIFI : System Average Interruption Frequency Index
(Annual Average Interruption Frequency per Customer)
SAIFI=

Total Number of Interrupted Customers


Total Number of Customers

TEPCO = 0. 04 times
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

13

Distribution Network in TEPCO


T i l Multi-Divided
Typical
M lti Di id d and
d Multi-Connected
M lti C
t d System(Standard
S t (St d d C
Configuration)
fi
ti )
2nd. section

1st. section

3rd. section

3rd. section

Distribution Line

Feeding Point
Feeding Point

2nd. section

1st. section
Open

Open

F di Point
Feeding
P i t

Close

3rd. section

Close

1st section
2nd. section

3rd section
3rd.

: Feeding Cable from Substation


: Section Switch (Closed)
:Section Switch (Open) = Interconnection Switch

Image of Control Center with DAS

: Distribution Line

Flexible network to demand growth


Restored automatically (Distribution
Automation System(DAS))
Section switch remote operation capability
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

14

Distribution Network in Urban Area


22kV Main/Stand-by Switching System for Urban Area
Service Substation

22kV

22kV Distribution Line

Customer

Customer

Customer

Customer

Steps to Restore
Customer

Customer

Customer

Customer

Step 1

Step 2
O
Outage

O
Outage

Main
Customer

Customer

Customer

Standby

Main
Load

Load

Standby

Customer

Line fault !
Customer

Customer

CB on main line is opened

Customer
Customer

Step 3
Main
Load

Standby
Applied in urban area with large customers
After 4 sec, CB on standby line is closed
2 li
line service
i drops
d
Automatic switching when one line contingency
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

15

Equipment for Reliability Improvement


Items of Lightning Protection on Overhead Network

Line Arrester

Overhead Grounding Wire

6.6kV

LBS with Built-in Arrester

Inside of
Pole mounted Transformer

Discharge Clamp Insulator


Pole Transformer with Built-in Arrester
Built in Arrester
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

16

Non-interruption Work Method


MV Non-interruption Methods
- Temporary switch method
- MV by-pass method
- Temporary interconnection method
LV Non-interruption Methods
- Temporary switch method
- Temporary transformer method
Generating Vehicle (Generator) Method

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

17

Various Methods for reduction of outage time


IIntroduction
t d ti
off Live
Li Li
Line Di
Distribution
t ib ti
Work
W k
By using By-Pass Cables & By-Pass Switches, Planned Outage is

avoided. (Work Area is by-

passed.)
Low voltage (LV) supply is continued by connecting to a neighboring LV system or temporary transformers.
Work Area
Power Source
By-pass Switch (MV)
Line Switch

By-Pass Cable

B
By-pass
C bl (MV)
Cable

Temporary Transformer
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

By-Pass Switch
18

Effect of Non-interruption Work Method


Reduction of Planned Outage Duration
80
66

69

50

68
60

60

The planned outage time has


Been decreased drastically by
introducing Non
Non-interruption
interruption
work method since 1985.

56

48

48
43

44

39

40

34

30

2 2

199
92

199
93

199
94
199
95

199
96

199
97

199
98

199
99

200
00

199
91

199
90

198
89

10

198
88

20

198
87

198
86

198
85

198
84

198
83

198
81
198
82

198
80

197
79

197
78

197
77

197
76

0
197
75

M
Minutes
s

70

Year
Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

19

TEPCOs Power Supply Reliability


SAIDI

Minutes/customer/year
140
120

Forced O utage
g
P lanned O utage
Total

122

Introduction of Live-Line Work Method


100

100
91

87

80

76

Transformer with built-in Lightning Arrester


60
40
Heavy Snow

20
2 1

8 3
2006

2005

2004

2003

2002

2001

2000

1999

1998

1997

1996

1995

1994

1993

1992

1991

1990

1989

1988

1987

1986

1985

1984

1983

1982

3
2007

Year

Copyright 2009, Tokyo Electric Power Co, Inc. All rights reserved

20

Potrebbero piacerti anche