Sei sulla pagina 1di 5

Main Client:

Main Contractor:

Subcontractor:

British Petroleum
(BP)

(CCC) Consolidated
Contractors Company

PIONEER WATER
TANKS LLC

Project Name:

Document Number:

PWT-RAMS-0200-211-00

CENTRAL PROCESSING FACILITIES BP KHAZZAN

Revision
No.

00

Date.

20-Oct-2014

RISK ASSESSMENT & METHOD STATEMENT


PIONEER WATER TANKS LLC
P O Box: 110810, Abu Dhabi, UAE

Tel No +971 2 555 1855: Fax No. +971 2 555 1755

PWT-RAMS-0200-211-00
INSTALLATION OF WATER TANKS

SI

Description

Names

01

Approved BY

GABY AWAD

02

Pre & Rev BY

WasiUllah Zeeshan

Designation
Managing
Director
QHSE
Engineer

Date

Sign

21/10/2014
20/10/2014

Notice
All rights reserved. These materials are confidential and proprietary to
PIONEER WATER TANKS LLC. No part of these materials should be reproduced,
published in any form by any means (electronic or mechanical, including photocopy
or any information storage or retrieval system), nor should the materials be disclosed
to third parties without express written authorization of PINOEER WATER TANKS LLC

Page 1 of 5

Main Client:

Main Contractor:

Subcontractor:

British Petroleum
(BP)

(CCC) Consolidated
Contractors Company

PIONEER WATER
TANKS LLC

PWT-RAMS-0200-211-00

1.

Revision
No.

Project Name:

Document Number:

CENTRAL PROCESSING FACILITIES BP KHAZZAN

00

Date.

20-Oct-2014

INTRODUCTION

A Pioneer Water Tank is formed by a series of cylindrical rings layers (Made from Zincalime Steel).
Each layer consists a number of individually curved panels which are lapped and bolted together at
the vertical and horizontal edges.

2.

WATER TANK DETAILS


Tank diameter:
Tank height
Gross Capacity

3.

20.47 m
8.35 m
2747 m3

12.28 m
4.20 m
498 m3

INSTALLATION OF WATER TANK

Cylindrical ring layers are bolted together and installed over a Reinforced Concrete Ring
Beam Foundation filled with compacted clean sand.
Curved panels forming the top ring layer are bolted together at the vertical and horizontal
edges and installed on to the concrete ring beam foundation.
Hot Dipped Galvanized Steel trusses and SHS Reinforcement hoops are secured at the top
ring layer over which roof panels are fastened.
A Geotextile woven fabric underlay is installed over the compacted clean sand base floor to
cover any foreign particles/debris.
An impermeable, Fiber Reinforced PVC Food Grade Liner is installed over the Geotextile
fabric underlay and is connected inside the tanks shell.
Roof Access Hatch/Manhole is installed.
External ladder (HDG) is attached.
Inlet, Outlet, Overflow and drain Nozzles are fixed as per requirements.
The Mechanical Jacking System is attached to the tanks wall using the wall structures bolting
connections and is bolted at the base plate to the concrete ring beam foundation.
The ring layers are progressively added in and raised using the Mechanical Jacking System,
no scaffolding or working at heights is required.
On completion, the Installation Report is to be signed in the presence of the PWT Site
Technician.

__________________________________________________________________________________________

Page 2 of 5

Main Client:

Main Contractor:

Subcontractor:

British Petroleum
(BP)

(CCC) Consolidated
Contractors Company

PIONEER WATER
TANKS LLC

Document Number:

PWT-RAMS-0200-211-00

4.

Project Name:

CENTRAL PROCESSING FACILITIES BP KHAZZAN

Revision
No.

00

Date.

20-Oct-2014

COMMISSIONING OF WATER TANK

Before filling the water, ensure all pipe-works leading into the tanks have been provided with
proper ground support. Piping without support should not be connected directly to the tank
structure without prior discussion and agreement with Pioneer Water Tanks (PWT).
Outlet(s) and Interconnection (if any) should be closed prior to filling the tanks.
Ensure that there is no debris or foreign particles inside the tanks prior to commencing with
the filling process.
Inform PWT Site Technician of readiness to fill the tanks.
After approval from the PWT Site Technician, commence with filling the tanks to a height of
one meter.
Keep the tanks water level at one meter overnight. Inspect for any signs of leakage
particularly at the flanges/ interconnections (if any). If there are any signs of leakage, the
PWT site Technician is to be notified immediately and filling to cease until further
consultation and a course of action has been agreed upon.
If after visual inspection the water level remains at 1 meter, resume filling the tank to the
Overflow level.
Continue to inspect the tanks while filling. If there are any visible signs of leakage, the PWT
site Technician is to be notified immediately and filling to cease until further consultation and
a course of action has been agreed upon.
The PWT Site Technician is to be informed upon completion of the filling process.
The Installation Report is to be signed in the presence of the PWT Site Technician.

__________________________________________________________________________________________

Page 3 of 5

Main Client:

Main Contractor:

Subcontractor:

British Petroleum
(BP)

(CCC) Consolidated
Contractors Company

PIONEER WATER
TANKS LLC

Document Number:

Project Name:

PWT-RAMS-0200-211
5.

CENTRAL PROCESSING FACILITIES BP KHAZZAN

Revision
No.

00

Date.

20-Oct-2014

RISK ASSESSMENT
Hazard Description

Persons / Groups Exposed

Confined Space leading


to loss of consciousness or
asphyxiation due to lack of
oxygen and or dehydration

Supervisors
EHS Officer
Workers

Jacking System / - While

Supervisors
Workers

erecting; modifying or
dismantling Jacking system;
carrying out the task would be
a possible injury due to
manual winching

Details Of Any Existing Controls

Additional Control Measures

Working in confined space shall be


monitored and supervise throughout
the Installation work.
Tool box talk to be completed
highlighting all hazards associated
with the task.
Task Specific PPE Site minimum
PPE, glove, Safety glasses, safety
shoes.
Only suitably competent personnel to
be allowed to undertake the task.
When erect; modify or dismantle of
jacking system shall be monitored
and supervised.
Check cables for wear & tear before
winching the jacks

13

Certified portable equipment.


Flash lights.
Ventilation (Specify natural or
mechanical).
Non Sparking tools.

Gloves shall be worn

Action

Timing
Relative to
Task

Supervisor

Prior to the
task
commencing

Supervisor

During
work task

All

During
work task

All

During
work task

Falling objects while carrying


out the task leading to possible
injury due to falling objects
Lifting Activities of equipment
leading to possible injury due to
falling objects

Supervisors
EHS Officer
Workers
Supervisors
Workers

Tools to be carried in tool bags


Hand lines to be used

Barrier off work area whilst


working on the trusses

Only suitably competent personnel to


be allowed to undertake tasks

Task Specific PPE Site


minimum PPE, glove, Safety
glasses, safety shoes.

Manual Handling of equipment


& portable tools could cause
crushing, strains, bruising & cuts

Supervisors
EHS Officer
Workers

Only suitably competent personnel to


be allowed to undertake tasks

All

During
work task

Suitable PPE To be worn whilst


working on tasks
Never overload the Fork Truck or
trailer.
Load to be secured before it is moved.

All

Before/Duri
ng Working
task

Transport of fittings and panels


using forklift truck.

Driver
Supervisor
Worker

PAGE 04 OF 05

Main Client:

Main Contractor:

Subcontractor:

British Petroleum
(BP)

(CCC) Consolidated
Contractors Company

PIONEER WATER
TANKS LLC

Document Number:

Project Name:

PWT-RAMS-0200-211

Potential Severity

Risk Factor

Revision
No.

CENTRAL PROCESSING FACILITIES BP KHAZZAN

00

Date.

20-Oct-2014

H = Potential Severity

P = Probability

R = Risk Factor (H x P)

Assessment Approved By:


WASIULLAH
ZEESHAN

5
4

5
4

10
8

15
12

20
16

25
20

Fatality

Highly Unlikely

14

Low

3
2
1

3
2
1
1

6
4
2
2

9
6
3
3

12
8
4
4

15
10
5
5

4
3
2
1

Major Disabling, permanent ill-health.


Intermediate Possible lost time.
Minor Minor treatment, no lost time.
Negligible/None

2
3
4
5

Remote
Possible
Probable
Certainty

5 12
15 25

Medium (Judgement needed)


High

Date:20/10/2014

QHSE MANAGER

____________________ Date: _______

Probability
POTENTIAL SEVERITY x PROBABILITY = RISK FACTOR

PAGE 05 OF 05

Potrebbero piacerti anche