Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Rev. No. : 0
Date : March 2013
Date
Summary of Revision
Review
By
Mar 2013
First Version
Date
Approval
By
Date
CONTENTS
1
BACKGROUND ...........................................................................................................1
10
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
Appendix H
Appendix I
Figure 1
Figure 2
Figure 1
BACKGROUND
Waste to municipal landfill is a pressing and critical issue in Hong Kong and
construction waste is a sensitive topic that raises much attention. About 25% of the
waste to Hong Kong landfills is construction waste. In simple terms, the generation
and management of waste for Gammon impacts profitability, productivity and is an
added logistical burden; it is also associated with housekeeping and safety.
Gammons quantity (tonnes) of landfill waste has increased from 26,000 tonnes in
2007 to 35,800 tonnes in 2012 (+37.7%) and the majority of waste disposed of in
municipal landfill representing 2.5% of Hong Kong total.
Figure 1: Total tonnage disposed by division
Landfill Disposal
30000
25000
20000
15000
10000
5000
0
GCL %
Total HK
2007
2008
2009
2010
2011
2.3%
1.5%
2.5%
2.3%
3.7%
BDG
CVL
E&M
FDN
2012
SGP
As the majority comes from building type works, a workgroup comprised of Building,
Environment and Procurement has developed actions towards achieving significant
reductions.
30.03
30
Ban of inert
waste to landfill
25
20
15
10
5
Baseline
4.13
5.3
3.72
3.31
Target
2.89
0
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
This Waste Management Handbook (WMH) aims to provide each project team with
practical and achievable guidelines for achieving waste reduction target of the
Sustainability Vision of gammon Building Home. The Handbook includes:
Project organisation structure setting out the roles and responsibilities of the
respective project team member responsible for waste management and
appropriate mitigation measures;
An analysis of timing and types of C&D materials to be generated in the
course of the execution of the Works;
The steps required to implement a site waste management plan;
Suggestion of waste reduction measures;
A monitoring and reviewing proposal to ensure that the requirements of the
site waste management plan are properly implemented; and
Contact details for waste recyclers in Hong Kong.
Procurement strategy
Education
Incentives to subcontractors
5.3 Foremen
Foremen are responsible for the following duties in relation to environmental control:
i.
ii.
ii.
iii.
iv.
v.
Regular Review
Planning of
manpower
Management
Cycle
Planning of
logistic &
resources
Set waste
diversion target
Rethink
Reduce
Lean Construction
- adopting designs using thinner internal walls and floor slabs and
reducing foundation size which could minimize the amount of raw
materials being used and thus reduce the amount of waste
Recycle
Reuse
Rethink
Reduce
Reuse
Recycle
On-Site Sorting
- avoiding mixing of construction materials and conduct sorting on-site as
early as once the waste are produced when the construction labours
are doing their tasks
10
The execution team shall arrange regular inspection to inspect the site to ensure
satisfactory performance on compliance with the waste management plan with due
regards to the followings:
i.
inert C&D materials suitable for recycling into aggregates are recovered and
delivered to designated recycling facilities as notified by the Architect or the
Public Fill Committee (Port Works Division of CED);
if the Contract involves demolition works, appropriate sequential demolition
has been employed to facilitate recovering as much as possible reusable and
recyclable materials;
a disposal recording system is operating satisfactorily for recording C&D
materials removed from the Site; and
on-site sorting of C&D materials is properly carried out to recover inert C&D
materials and reusable and/or recyclable materials before disposal.
ii.
iii.
iv.
Environmental Engineer shall keep adequate and proper records such as delivery
dockets and measurement records relating to the implementation of the waste
management plan. All waste treatment should be properly recorded by receipt,
photo, delivery form and summary, supporting document should also be provided
for individual waste.
Smart Waste Account was introduced to all projects for tracing back the quantities
of waste to public fill, landfill and designated areas. Data analysis charts are also
provided for project team to review. Environmental Performance Data (EPD) will be
used to record all waste removed off site each month. The estimated and actual
quantities of wastes that will be generated each month from the project will be
reported in a monthly basis.
9.3 Waste Audit
The waste reduction should be assessed in two ways:
Project-wise
Targeting the waste management on site and seeking out or developing
ways to divert waste from disposal
11
Building Home
The overall waste reduction would be reviewed regularly. The waste data of
building projects would be used to calculate the landfill waste intensity
(tonnes of landfill waste per HK$ 1million turnover). The Interim Review will
be carried in mid-2013, end-2013, 2015 and 2017.
A mix of both approaches should be considered using the waste reduction hierarchy
to set priorities.
10 TRAINING AND PROMOTION
The environmental engineer shall arrange and provide training on waste
management in the site-specific induction and its refresher training for all persons
employed by the Contractor or his sub-contractor on the Works or in connection
with the Contract. The training should cover the waste management policy, targets,
measures for on-site sorting of C&D materials and measurement on waste
management performance on the Site.
The environmental engineer is allowed to develop and provide toolbox talks for the
topic on on-site sorting of C&D materials to promote the workers' awareness on
handling, sorting, reuse and recycling of C&D materials. Training material for
environmental toolbox talks with regard to waste management shall be prepared by
the environmental engineer and disseminated to supervisor/foremen and
subcontractor's representatives for conducting tool-box talks to all workers or
labourers at regular intervals.
To motivate subcontractors participation, Waste Management Key Performance
Index (WMKPI) should be introduced to rank subcontractors on performance
indicators tracked across implementation of waste management, Appendix I. Set
some standards and common vision so that subcontractors have more
understanding of our objectives and follow easily. Project team and Operation team
would help in the assessment by reporting subcontractors performance to
environmental engineer. The index and rating can be different from each project
according its statues. Best subcontractor of the month in waste management could
be awarded to praise their effort.
12
APPENDIX A
Cost saving from waste minimization
APPENDIX B
Figure of different projects
J3338 Proposed Residential Development at RBL 224, 53 Stubbs Road, The Peak, Hong Kong
12-storey residential building (10-storey super flats & 2-storey duplex units) with swimming pools (2 nos. at
podium floor and 3 nos. at roof)
Contract Sum: HK$515,138,000.00
Landfill Waste Intensity: 1.6 tonne/HK$ 1M turnover
APPENDIX C
Waste generated at different
construction stage
Site Setup
&
Demolition
Foundation
and
Underground
Works
Superstructure
Site Office
Furniture and Containers
after use
Piling
Soil, Marine mud
Temp wood
Grouting
Cement Bag
Formwork
Waste timber
Site Hoarding
Waste concrete
Demolition
Building Debris
Facilities, Furniture
Drainage & Underground
Substructure
works
Soil, Marine mud
Soil, Marine mud
Cable, cable drum
Waste timber
Waste concrete, metallic pipe &
Packaging waste in ELS
waste timber
Concreting
Scaffolding
Plastering
Waste concrete
Slump test concrete
Concrete cube
Bamboo
Metal Scaffold
Dust Screen
Miscellaneous
Packaging waste
Wrapping sheet
Broken concrete
Cement Bag
Chemical containers
Plastic (barrier)
Waste block
E&M Installation
Curtain wall
Air duct
Insulation
Trunking and pipe
Fitting for E&M services
Timber packaging
Domestic waste
De
m
ol
it
2010 Gammon Construction Limited. All Rights Reserved
us
eo
an
ell
sc
Mi
io
n
Packaging waste
Plastic (barrier)
Site Setup
Facilities
Setup
Disused
facilities / furniture
Domestic waste
Office Furniture
Container
ru
st
u
ct
re
Foundation &
Underground
works
Wasted Timber*
b
Su
Surplus grout
Pi
lin
g
Cement bag
Underground utilities
& drainage
Temp wood
Metallic pipe
Packaging waste
Waste timber
Co
k
r
nc
re
wo
tin
m
r
g
Fo
Superstructure
Sc
i ng g
af
r
fo
ste intin
ld
a
l
in
P Pa
g
&
Waste concrete/
cement/instant mortar
Metal Scaffolding
Wooden pallets
Dust screen
Bamboo
Chemical containers
Cement Bag
In
2010 Gammon Construction Limited. All Rights Reserved
ll
wa l
in al
rta s w
Cu las
/g
Insulation
st E&M
al
la
tio
n
Air duct
Sealant, adhesive
Interior/ exterior
fitting
timber packaging
Plywood
APPENDIX D
Project Specific Waste Management
Plan Template
Building Project
COPYRIGHT
28/F Devon House, Taikoo Place, 979 Kings Road, Hong Kong
Tel.: (852) 2516-8823
Rev. No. :
Effective Date :
Page No.
Effective Date
Summary of Revision
Rev. No. :
Effective Date :
Page No.
Contents
Section
Description
1.
Background
2.
3.
4.
Organization Structure
5.
Analysis of Waste
6.
7.
8.
Appendices
Description
Appendix A
Appendix B
Figure
Figure 1
Description
Temporary on Site Sorting Facilities
ii
Rev. No. :
Effective Date :
Page No.
1.
Background
Environmental protection and sustainable development are part and parcel of the daily
operations of the Gammon Construction Limited (referred to hereinafter as the GCL).
GCL will initiate appropriate actions in order to minimize, and where possible eliminate,
the environmental impact arising from the construction of this project.
(Project description)
2.
Rev. No. :
Effective Date :
Page No.
3.
3.1
Hierarchy
The various waste management options shall be categorised in terms of preference
from an environmental viewpoint. The options considered to be more preferable have
the least impacts and are more sustainable in the longer term. Hence, the hierarchy of
waste management is as follows:
Rethink is careful planning at the design and drawing stages. It is at this stage
that the greatest reductions in waste can be achieved.;
Reduce waste by eliminating over-ordering of construction materials, waste is
avoided and costs are reduced both in terms of purchasing of raw materials and
in disposing of waste.;
On site, the Reuse and Recycle of materials should be maximized to avoid
Disposal; and
Treatment and disposal, according to relevant laws, guidelines and good practice.
This hierarchy shall be used to evaluate waste management options, thus allowing
maximum waste reduction.
4.
Organization Structure
The project organisation with respect to waste management works is outlined in the
following sections.
4.1
Project Manager
The Project Manager is responsible to the Contract Manager for overall planning, site
operations, appointment of committee members for waste management, staff
supervision control co-ordination and external liaison. He is ultimately responsible for all
aspects of waste management issues within the Project, which they achieve by
implementation of the WMH.
He is also responsible for provision of necessary support to the environmental engineer
for the preparation and review of waste management and arrangement of site staff to
Rev. No. :
Effective Date :
Page No.
4.2
Site Agent
He shall have the following duties in relation to environmental control:
i.
ii.
iii.
iv.
v.
4.3
Foremen
Foremen are responsible for the following duties in relation to environmental control:
i.
ii.
Rev. No. :
Effective Date :
Page No.
4.4
Environmental Engineer
The Environmental Engineer shall oversee the implementation and the performance of
the WMH and shall also be responsible for:
i.
ii.
iii.
iv.
v.
4.5
5.
Analysis of Waste
5.1
Foundation / ELS
Activities
Site hoarding
Waste concrete
Demolition
Protection
Temp Wood
Grouting
Cement bag
Excavation
Excavated materails
Steel platform
Steel
Rev. No. :
Effective Date :
Page No.
6.
6.1
This section is the measures taken in Design and Planning Stage and Procurement
that is more focusing on Rethink and Reduce. Waste Management Handbook, Section
8 & Appendix E)
For example, the formworks will be designed to maximise the use of standard wooden
panels so that high reuse levels can be achieved. More durable alternatives such as
reusable metal formwork, falsework, trench supports and the like shall be optimized for
use in repetitive areas to increase the potential for reuse, if applicable.
Precast unit or pre-fabricated unit is also encouraged to adopt since it will reduce the
wastage from the waste generation on site. BIM application is also an effective tool to
avoid the wastage due to crushing of E&M services.
6.2
Hard Rock and Large Broken Concrete suitable for Reuse on the Site or recycling
at a designated location;
Residue Concrete
Metals;
Timber waste;
The planning of logistic routine for the waste collection from different floor should be
considered, refuse chute, jump lift and hoist. Landfill waste, recyclables and inert waste
should be transported down separately to avoid contamination.
Rev. No. :
Effective Date :
Page No.
Waste facilities to facilitate on-site sorting, collection and temporary storage of waste
materials is continued to maintain. The waste facilities including the following:
1.
2.
3.
4.
5.
Sufficient space for temporary storage of C&D materials will be identified and provided
to facilitate collection and/or sorting on the Site. Except for those inert C&D materials
to be reused on the Site, all other C&D materials off the Site will be removed as soon
as practicable to optimise the use of the on-site storage space.
As presented in the Waste Management Hierarchy, the GCL accords the highest
priority to managing waste through reduction at source. To this end, the following
measures shall be implemented.
Management of construction materials such that over-ordering, poor storage and
maintenance, mishandling as well as improper operation procedures shall be
avoided;
Restriction on use of hardwood such that softwood, metal props and/or
proprietary steel system shall be considered for falsework and the shoring of
trenches and pits;
The formwork shall be designed to maximise the use of standard wooden panels
so that high reuse levels can be achieved. More durable alternatives such as
steel formwork or plastic facing shall be considered for repetitive areas to
increase the potential for reuse;
C&D materials shall be, as much as possible and practicable, separated into
reusable items and materials to be disposed of or recycled. It shall be conducted
at the immediate working area to avoid loss / leakage and cross contamination
during handling;
All C&D materials arising from or in connection with the construction and
demolition work shall be sorted on-site and be separated into different categories
for disposal at landfills, public filling areas, or reuse and recycling as appropriate.
The sorting area may be revised from time to time in order to suit the construction
activities;
Useful materials such as timber, rubble and steel / metal shall be segregated for
reuse. For example formwork and timber shall be cleaned for reuse, off-cuts of
reinforcement shall be sorted into usable lengths and short off cuts stacked for
scrap metal. Where it is no longer reusable, scrap steel and metal items will be
collected by recycling companies;
Segregated materials shall be temporarily stored at designated areas for reuse
on site. Steel will be stored at the reinforcement yards, timber at the formwork
yard and rubble in a stockpile (either covered or sprayed to control dust).
Cardboard and paper packaging recovered from site shall be properly stockpiled
in dry condition and covered;
The remaining non-reusable C&D materials shall be sorted on-site into the inert
portion (e.g. rock, brick, bituminous material, concrete and soil, etc.) as the
public fill and the non-inert portion (e.g. timber, vegetation and paper, etc.) as
the C&D waste. All inert C&D materials shall be broken down according to the
Rev. No. :
Effective Date :
Page No.
6.4
Recycling
To minimise the amount of waste disposal to landfills, the general refuse shall be
reused and recycled as much as practical. Waste sorting and segregation shall be
carried out in accordance with the following categories for recycling:
Steel Bars
Rubber;
Paper;
Metal (i.e. aluminium can, steel metal, ferrous metal, and non-ferrous metal).
Equipment and material packaging (ie paper and cardboard) will be recovered, properly
stockpiled in dry and covered condition to prevent cross contamination by other C&D
materials. Particular attention will be paid to avoid cross contamination in the course of
collecting paper for recycling. Arrangements will be made with recycling contractors to
ensure that recyclable materials sorted from the Site are collected with reasonable care.
Rev. No. :
Effective Date :
Page No.
Proposed types of waste facilities, waste handler and collection frequency are given
below. (Please refer to Waste Management Handbook, Section 7.3 and Appendix D)
Waste Categories
General
waste
Waste handler*
packing Confidential
Materials
Destruction Service Limited
or other recycled company
registered under EPD for
collection of waste paper
collect
Collection Frequency**
Wastage of steel
Subcontractor
scrap metals.
Surplus concrete
Gammon
Timber
Wai
Timber
should
be
collected by timber recycle
plant for recycle.
After
Plastic
*
*
to
Treatment approach
7.
7.1
Rev. No. :
Effective Date :
Page No.
7.2
7.3
Waste Audit
To review the site management, the project-based waste baseline audit will be
conducted quarterly. Project shall be audited by a committee though site visit. A waste
baseline audit scorecard was developed to quantify site waste management efforts,
shown as Appendix A. By identifying the measures of waste reduction, the facilities
support on site and etc, the scoring of baseline audit would reflect the implementation
of waste management.
8.
Rev. No. :
Effective Date :
Page No.
10
recycling of C&D materials at regular intervals. The record of the toolbox talk training
record will be presented in the monthly environmental report.
Environmental Promotion and Incentive (such as the supermarket coupon) to
encourage good waste management performance on site. Waste Management Key
Performance Index (WMKPI) was introduced to rank subcontractors on performance
indicators tracked across implementation of waste management, Appendix B.
Figure 1
APPENDIX (
Waste Recycling Companies /
Charities
Waste
Paper
Contacts
3R Hong Kong International Eco-Action
Limited
Mr. Thomas Ng
Phone: 8203 8508
Email: hk8880888@gmail.com
Website: www.3r.com.hk
Fook Woo Waste Paper Company Limited
Ms. Sandy Fung
Phone: 2676 8800
Plastic
(a) Each job / location to submit application form to Yan Oi Tong to open account.
(b) Yan Oi Tong will provide suitable bin / metal cage for plastic waste collection free of
charge subject to its availability and approval by Yan Oi Tong.
(c) Transport: self-transport plastic waste to Yan Oi Tong.
(d) Frequency: need to contact Yan Oi Tong 2 days in advance to arrange staffing
logistics.
(e) Fee: HK$27 weight bridge charge waived for Gammon accounts.
(f) Record: can provide monthly report upon request.
Condition of materials:
Minor concrete or grouting on materials is accepted
separated each type of plastic
Broken
concretes, rock,
boulders,
rubbles, bricks,
glass
Waste Timber
Furniture
Electrical Item
etc
Crossroads Foundation
Website: http://www.crossroads.org.hk/ourneeds/donate-goods#what-do-we-receive
APPENDIX )
Detailed Waste Reduction Measures
Construction stage
Tendering
stage
and
Activities involved
Type of Landfilled
Waste Generated
Site setup
a. Site office
c. Demolition
a. Protection
1. Temp wood
b. Grouting
Substructure Stage
RC Structure
a. Pile Cap
1. Wasted Timber (hard & 1. Use of metal formwork to reduce the timber waste
softwood) from formwork 2. Reuse timber as many as possible
3. Remove the nails before reycycle
3. Provision of waste sorting containers for timber waste
4. Reserve task force to carry out the collection and sorting of waste
5. Provision of recycler to collect
1.) Packaging waste for 1. Provision of waste sorting bins for packaging waste
welding
2. Reserve task force to carry out the collection and sorting of waste
3. Provision of recycler to collect
4. Selection of bulk quantities per pack to reduce packing materails.
4. Soil / Marine mud
1. reduce and/or recycle marine mud for backfilling and/or mud bricks
Transporation cost
c. Excavation
1. Furniture
c. Excavation
b. ELS
1. Plan to provide sufficient waste sorting facilities for different type of waste
2. Reserve task force to carry out the collection and sorting of waste
3. To determine the recycler for collection
4. To plan the logistic for the waste collection and recycling from different floor, e.g. Refuse
chute,jump lift or hoist
5. Modular design for design and build project
6. Use of BIM to reduce abortive work
7. Use of LCC/LCA estimation model
8. Use of prefabricated elements
b. Site hoarding
Foundation stage
1. reduce and/or recycle marine mud for backfilling and/or mud bricks
a. Recycling container for timber formwork
b. Cost per worker x no of workers
c. Transporation cost ($600/truck)
d. Use of metal formwork
a. Utilities
Cable, plastic, cable drum 1. Provision of waste sorting bins for cable waste
from cable laying works
2. Reserve task force to carry out the collection and sorting of waste
3. Provision of recycler to collect
4. Precise order of utilites
b. Drainage works (manhole Concrete / metallic pipe & 1. Provision of waste sorting bins for timber waste
& pipe)
timber waste
2. Reserve task force to carry out the collection and sorting of waste
3. Provision of recycler to collect
4. Precise order of drainage materials (pipe, concrete and timber)
c. Excavation
4. Soil / Marine mud
1. reduce and/or recycle marine mud for backfilling and/or mud bricks
a. Formwork
1. Waste
formwork
a. Recycling bins
b. cost per worker x no of workers
c. Transporation and handling free for recycling
d. Use of Metal formwork
b. Concreting
2. Waste concrete
3. timber packaging
d. Scaffolding
4. Bamboo
timber
Page 1 of 2
a. Recycling bins
b. cost per worker x no of workers
c. Transporation and handling free for recycling
d. Use of Metal frame
Construction stage
Activities involved
Type of Landfilled
Waste Generated
5. Metal Scaffolding
1. Ensure materials are handled and stored in good condition to prevent deterioration and wastage
2. Restricted the s/c to collect for reuse
3. Provision of waste sorting bins for metal recyling
4. Reserve task force to carry out the collection and sorting of waste from others
6. Dust screen
Plastering
E&M installation
Fitting Out
Mis
4. Plastic (barrier)
5. Domestic waste
1. Provision of waste sorting bins for domestic waste, 3 color recycling bins & general refuse bin
2. Workers having lunch in restricted areas
Page 2 of 2
APPENDIX *
Building Waste Baseline Audit
Scorecard
__________________________
Date:
__________________________
For those question rated as Yes, please score from 1 to 3. (1 Unacceptable, 2 General, 3
Excellent,). For those question rated as No, please score 0.
% score = (Actual score / Total score) x 100%
Description
10
11
12
13
(Yes / No / NA)
Score
Sub-total
Description
(Yes / No / NA)
Score
Sub-total
Description
(Yes / No / NA)
Score
Sub-total
Description
Sub - contractors keep all the working areas clean and regularly deposit
rubbish in bins
Adequate and labeled waste bins are provided within close proximity of
all work fronts
8
9
(Yes / No / NA)
Sub-total
Score
APPENDIX +
Project-base Waste Management
Kick-off and Audit Schedule
Date:
Time:
Venue:
Present:
Item
1
1 March 2013
9:00a.m. to 11:00a.m.
Seymour Road Conference Room
Mr. Vincent YUEN
(VY)
(PC)
Mr. Percy CHAN
Mr. Sherman TANG
(ST)
Mr. Jason FUNG
(JF)
Ms. Selina CHIN
(SC)
Description
Data analysis
The landfill waste data of Seymour Rd project and Shiu Fai Terrace was
analyzed. The forthcoming activities were discussed to predict the types
and amount of waste generation.
Action
Note
PC
There is a concern about the trip ticket issue since it would involve different
projects.
Post-meeting note:
After clarified with EPD, centralized collection is only possible for those
project with contract sum below $1M (small scale - fitting out), for those
project / construction site with large than $1M, it is necessary to apply their
own billing account with using their own chit ticket and can not be shared
with other project and it is all required under Waste Disposal (charges for
Disposal of construction Waste) Regulation.
4
SC
Site Walk
Project Name
Start
End
Tentative Schedule
J3478
25 Feb 13
24 Apr 15
J3482
17 Jan 13
21 Apr 15
J3500
TBC
TBC
J3466
20 Jun 12
1 Dec 13
Week 1 of May 13
J3463
3 Jul 12
2 Aug 15
Week 2 of May 13
J3437
11 Jun 12
22 Dec 13
Week 3 of May 13
J3416
1 Jul 11
30 Jun 14
Week 4 of May 13
J3389
21 Jan 11
19 Jan 13
Week 5 of May 13
J3383
SS X301 Redevelopment of Kwun Tong Swimming Pool Complex and Kwun Tong 17 Dec 10
Recreation Ground Section 2
14 Sep 14
Week 1 of June 13
J3470
30 Jul 12
9 Jul 13
Week 2 of June 13
J3448
Main Contract Works for Proposed Redevelopment at 12 Shiu Fai Terrace Hong
Kong
9 Mar 12
1 Jul 13
Week 3 of June 13
J3456
18 Jan 12
13 Oct 14
Week 4 of June 13
J3409
J3408
Term Contract for Alteration and Addition Works at Happy Valley Racecourse of
the Hong Kong Jockey Club for Year 2011 - 2014
30 May 11
29 May 14
Week 1 of July 13
J3299
SS T333 - Redevelopment of Victoria Park Swimming Pool Complex Section 2-5 23 Nov 09
31 May 14
Week 2 of July 13
APPENDIX ,
Waste Management Key Performance
Index (WMKPI) Template
Project:
Month:_________
Subcontractors
A
Adequate?
(Y/N)
Total
Comment
B
Adequate?
(Y/N)
C
Adequate?
(Y/N)
D
Adequate?
(Y/N)
E
Adequate?
(Y/N)
F
Adequate?
(Y/N)
Year
G
Adequate?
(Y/N)