Sei sulla pagina 1di 29

7.

INFRASTRUCTURE AND UTILITIES


7.1 INTRODUCTION
The development site, named the Villa Development , Umm Al Daman in Alain Road, Dubai, is to become a
low density residential community within Mirras land, south-west of the Al Ain Dubai Road opposite of Dubai
Outlet mall. The project site is comprised of an area of 122045 Sq.m / 3.45 Hectares), and is located within the
Al Ain Dubai Road,

7.2 BACKGROUND
The infrastructure assumptions have been built based on the information provided by the data collected from the
concerned authorities, our assumptions have been built.
The Infrastructure Master Plan for the Villa Project uses basic criteria and method of calculations that are used
in many other Dubai residential developments.
Infrastructure development is based primarily on the existing Dubai Municipality (DM), Dubai Electrical and
Water Authority, RTA, Civil Defines, Du & Etisalat and Dubai concerned Authorities Standards, Specifications
and Guidelines.
A dedicated services corridor for each infrastructure utility is provided, ensuring minimal conflict with other
services and easy facilitation for the utilities house connections. Location of the proposed tapping connections is
determined based on the approved option of the proposed Master Plan, all to the in compliance to the maximum
with DM & RTA Right Of Way (ROW) standard.

Road Classification and Design Speeds (DM)


Roadway Classification

Design Speed
(km/h)

Posted Speed
(km/h)

Collector

70

60

Local road

50

40

DESIGN BASIS AND PARAMETERS


Design Vehicle:

The design vehicle for collector roads is the AASHTO Bus Single 12.1 meters in length and for local roads is
the AASHTO Single Unit Truck 9.1 meter in length.
Sight Distance:

Stopping Sight Distance (SSD) is the distance required by the driver of a vehicle traveling at a given speed to
bring his vehicle to a complete stop after an object on the carriageway becomes visible.
Passing Sight Distance (PSD) is the minimum sight distance that must be available to enable the driver of one
vehicle to pass another vehicle safely and comfortably.

7.3 ROAD NETWORK

Values for SSD and PSD for a given Design speed are shown in following Table

The geometric design criteria govern the minimum parameters that are used in developing the detailed horizontal
and vertical design. Design speed is selected to match the roads hierarchy the higher the type of road, the
higher the design speed that needs to be maintained.

Stopping Sight Distance and Full Overtaking Sight Distance (Geometric Design Manual for Dubai Roads GDMDR)

Design speed is the main factor, affecting all other design parameters. The road alignment shall be designed so
as to ensure that standards of alignment, visibility and super-elevation are consistent with selected design speed.
Being a purely residential development speeds will be restricted and kept to minimum to maintain safety and
create a residential environment.

Design Speed
(km/h)

SSD
(m)

PSD
(m)

70

110

280

50

65

455

Horizontal Alignment:

The road classifications and design speeds proposed for this project are given in Table
Based on the design speed and limiting super-elevation rates of each category of roadway, the minimum radii
will be fixed. The minimum curve radius that will be adopted for each road classification depending on the
design speed is given below
1

Recommended Horizontal Curve Criteria (AASHTO 2011)

Road

Design Speed
(km/h)

Minimum Curve Radius


(m)

Collector

70

215

Local Access

50

100

Pavement Markings and Traffic Signs

Pavement marking and traffic signs are an essential provision which act as a means of communication between
the road and driver. The Pavement marking and traffic signs (Information, regulatory and warning signs)
will be provided at appropriate locations, as per the Dubai Traffic Control Device Manual.

Vertical Alignment:

Pavement Type:

Vertical alignment consists of a series of grades connected by parabolic vertical curves. It is used to establish
elevations for all roadway features. The criteria for the proposed design grades are in accordance with the DM
Geometric Design Manual and AASHTO. The proposed gradients for each roadway are as shown in the Table
below.

The pavement structure will be designed following the AASHTO GUIDE FOR DESIGN OF PAVEMENT
STRUCTURES and in accordance with the RTA Design Standards. The design of the flexible pavement
structure shall recognize the following factors:

Road

Design Speed
(km/h)

Max. Grade
(%)

Collector

70

Local Access

50

10

AASHTO and GDMDR provide guidance on minimum grade and 0.3% as practical minimum where the road is
kerbed.

Traffic Volumes
Materials of Construction
Drainage
Reliability
Performance

The pavement type for all the roads will be asphalt however parking will be interlock tiles for easy
maintenance of utilities underneath.
Design Standards/Codes:

Vertical curves shall be parabolic and provided at changes in gradient greater than or equal to 0.5%. To ensure
adequate visibility at crest and sag curve locations, vertical curves shall be provided based on the requirements
provided in the DM Geometric Design Manual and AASHTO.
K values GDMDR

Design Speed
(km/h)

Crest Curves

Sag Curves

70

30

25

50

Cross Slope

The cross slope of carriageway is 2.0%, Parking lane is 2.0%. For local roads, one sided cross slope is provided
to lessen the number of gullies and manholes
Parking Arrangement:
Parallel parking spaces are to be provided on all the local roads to allow for visitors of the development to have
a proper and safe parking. Parking will be delineated with drop curb to give the look and feel of separation
between parking and the carriageway.
2

RTA Geometric Design Manual (GDM)


Dubai Traffic Calming Manual
American Association of State Highway and Transportation Officials (AASHTO)
AASHTO Guide for Design of Pavement Structures
American Interlocking Concrete Pavement Institute (ICPI Tech Spec 4)

Road Hierarchy:
The road network consists of mainly 2 type of roads based on ROW
Type 1 : 36.6 m ROW Collector Road
Type 2: 15.25m ROW Local Road

7.3.1 ROAD HIERARCHY

7.3.2 ROAD CROSS SECTION MARKER LAYOUT

7.3.3 ROAD TYPICAL CROSS SECTION

7.4 POTABLE WATER NETWORK


Total Population

Water Demand

Average
Daily
Demand

INTRODUCTION

Existing 900 mm portable water pipeline located along the Al Ain road on the southern side of the development
will be the main DEWA tie-in point.

LAND
USE

Residents

Workers

DESIGN PARAMETER:

Visitors/
Students

Residents

Workers

Visitors/
Students

Water Demand
Nos.

m3/day

The Potable Water network design will be based on the fully developed project. The Dubais typical
design standards as supplied by DEWA will be used as the primary basis for the design for this project.

Residential
Mosque

60

0.12

2.4

Water Consumption rate for various facilities in this project will be assumed as follows for the
purpose of calculating the water demand:

Commercial
Total

40

0.35

1.6

100

0.47

823

DEWA Demand Range


(Liter/capita/day)
Category
Residential

Residents

Workers

250 - 350

Residents

Workers

Visitors

350

Retail

60 - 80

70

Exhibition /
Recreation

100

100

Community
Facility

60-80

14 40

70

30

Mosque

10 - 60

10 60

60

40

Utilities

10 - 60

40

2,340

819.00

819

819

Peak Factor:

Consumption Rates Used


(Liter/capita/day)
Visitors

2,340

40

A peak factor of 1.25 shall be adopted for seasonal daily water demand fluctuation in accordance
with DEWA design guidelines (a peak factor; in the range between 1.25 and 1.5). Higher peak factor is
not anticipated as any hourly fluctuation in the water demand will be covered by the available 24 hours
storage within each building.
Hours of Supply

The water supply system was designed considering an average daily demand supply for 24 hours.
Storage Tanks

Due to DEWA requirements, one day average daily demand to be stored at each individual plot is required
to provide a storage tank to pressure to all levels within each villa/ building should be used while
designing for the network in order to accommodate the daily variation in demand.
Hydraulic Design:

Hydraulic design will be based on the Hazen- Williams formula:


Q= 0.278CD2.63 S0.54
Where:
Q
C
D
S

= Flow rate (m3/s)


= Hazen- Williams coefficient
= Internal pipe diameter (m)
= Slope of energy grade line (m/m)

Minimum Pressure:

A pressure of 1 bar shall be accepted as a minimum delivery pressure at the boundary of the individual
property to ensure water supply to the ground level or underground storage tanks for each property. The
criterion of minimum pressure of 1 bar in the distribution system at highest point of the water supply
scheme is recommended by DEWA.
Maximum Velocity:

The maximum velocity of water in the distribution pipelines shall not exceed 1m/s and in Transmission
pipe line shall not exceed 1.5m/s as per DEWA standard and specifications
Pipe Materials:

Glass fiber Reinforced Epoxy (GRE) pipes shall be used for the distribution mains for the water
supply network in compliance with latest DEWA (WD) Technical Specifications and approve
Valves:
Isolation valves shall be installed at different strategic points to ensure uninterrupted supply of
water and to provide flexible operation and easy maintenance.
Gate valves shall be in accordance with BS Cods and will be provided at all branch lines for the
purpose of isolation and easy maintenance.
Air release valves- shall be installed at summit points in the pipelines.
Blow- off (wash- out) valves shall be provided at low points (sag) in the pipelines.
Thrust Blocks

Thrust blocks must be provided at all pipes tees, bends, junction, reducers, end caps and valves.
Water Meters:

The secondary system shall be provided with appropriately sized water meters. All service
connections shall be metered based on DEWA-W regulation and procedure.

4.2 EXISTING POTABLE WATER NETWORK

7.4.3 PROPOSED POTABLE WATER NETWORK

PIPE MATERIAL:

7.5 IRRIGATION WATER SYSTEM

Pipe materials will be as follows:

INTRODUCTION

The landscape design is expected to comprise of various ornamental plant species as grass, ground cover, hedges,
shrubs, trees and palm. The irrigation network will be designed to convey the required TSE demand of all landscape
areas within the project.
DESIGN STRATEGY

The network is a separate system that serves only the irrigation activities within Villa Development project. The
Irrigation network is designed to serve all the green areas within the development, open space areas and soft cape
areas within ROW. Irrigation Water Tank of a capacity of two day demand will be allocated within the project
along with pumping station. The irrigation tank will be supplied via 160mm diameter uPVC pipeline from the TSE
network on the north side of the project. TSE will be pumped from the tank to the internal and shallow irrigation
networks. will connect to the Proposed TSE tank, if the irrigation water demand is more than the TSE generating
from the proposed Package Sewerage Treatment Plant (STP). The design will consider to connect from the existing
DM irrigation line from the southern side of the development
DESIGN CRITERIA

The irrigation network will design based on the water requirement for the plantation shall be as follows:

Palm trees ......................


Ornamental trees ............
Grass................................
Shrubs & hedges..............
Ground covers, Flowers & creepers

227 lit/day
100-120 lit/day
15 lit/m2/day
25 lit/day
15 lit/m2/day

HYDRAULIC DESIGN:

The hydraulic design of the irrigation network is based on Hazen Williams formula:
Q= 0.278C D^ 2.63 S^ 0.54
Where:

10

= Flow rate (m3/s)

C
D

= Hazen- Williams coefficient


= Internal pipe diameter (m)

= Slope of energy grade line (m/m)

For sizes up to 6 uPVC pipes with pressure ratings not less than 15 bar shall be used.
All uPVC pipes passing through ducts shall be solvent weld joints.
For sizes 8 and above; GRP pipes with 15 bar pressure ratings shall be used

7.5.1 ESTIMATED IRRIGATION DEMAND

11

7.5.1 EXISTING IRRIGATION NETWORK

12

7.5.2 PROPOSED IRRIGATION NETWORK

13

7.6 FIRE FIGHTING SYSTEM


INTRODUCTION

As per Dubai Civil Defense requirements the fire network within v i l l a Development A l A i n r o a d p r o j e c t
assumed to be design and operated based on a separate network with separate fire tank and pump room as
per Civil Defense regulations and specifications UAE Fire & Life Safety Code of Practice -2011 Edition.
DESIGN STRATEGY

Infrastructure firefighting network is designed to serve fire hydrant pillars installed within the ROWS's.
Buildings firefighting system is a separate system and will not feed from a proposed infrastructure
firefighting tank and pump room. The firefighting is designed as a ring / loop system. The external
firefighting system for theVilla Development in Al Ain Road project will be designed in accordance with the
requirements of Civil Defense and NFPA relevant standards,( NFPA standards were used as general guidelines
system). Control valves are properly located throughout the network of Ductile Iron piping network in order
to secure convenience during maintenance, operation and shutdowns.. Air release valves are installed at all high
points and washout valves at all low points for line flushing. Pillar type fire hydrants are adequately spaced in
accordance with occupancy classification and Civil Defense requirements.
HYDRAULIC DESIGN:

The fire water tank shall be designed as per Civil Defense regulation and in accordance with
NFPA 22 in all respects.
Fire water tank shall be constructed in two equal compartments or in two interconnected tanks to
allow periodic cleaning and maintenance works of each component.
The volume of total effective fire water storage shall be enough to cater the pumping demand of not
less than 60 minutes of fire pump set capacity and will be not less than 460 m3.
The fire water tank shall be provided with filling connection directly from DEWA line with a float
operated valve for automatic refilling. The tanks shall be provided with drain arrangement, overflow
connection, level indicators low level switch, and other necessary accessories.
The firefighting Tank and pump room will be accommodated in the allocated utilities hub in plot 1,
as shown in the attached master plan.
PIPE MATERIALS:

Pipe material shall be approved by civil defense and shall confirm to manufacturing standards as per
Table 2.1 and Table 2.2 UAE Fire & Life Safety Code of Practice -2011 Edition.
Pipes shall be HDPE as per Dubai Civil Defense requirements to suit the water used for fire
protection.
Thrust blocks must be provided at all pipes tees , bends, junction, reducers, end caps and valves.
VALVES:

The hydraulic design of the irrigation network is based on Hazen Williams formula: Q=
0.278C D^ 2.63 S^ 0.54

Gate valves will provide at all branch lines for the purpose of isolation and easy maintenance.

Where:
Q
C
S

Air release valves- shall be installed at summit points in the pipelines.


= Flow rate (m3/s)
= Hazen- Williams coefficient D
= Internal pipe diameter (m)
= Slope of energy grade line (m/m)

Hazen-Williams pipe roughness confident is considered as 130 for Ductile Iron pipes and 140 for
Polyethylene pipes.
The pipelines will be designed on velocity of water not exceeding 1.0 m/s.
Min. flow rate for any public fire hydrant shall be 500 gallons per Minute (1900 LPM ) ( 250
GPM/outlet,950LPM/outlet).
Two numbers of public fire hydrants shall be considered for hydraulic demand calculation, thus
reaching the total flow requirement to 1000 Gallons per Minute (3800LPM).
Minimum Pressure required at most remote hydrant shall be 6.9 bars.
FIRE WATER TANK AND PUMP ROOM:
14

Isolation valves shall be installed at different strategic points to retain the flexibility of the
operation and maintenance.

Blow- off (wash- out) valves shall be provided at low points (sag) in the pipelines.
ABOVE GROUND FIRE HYDRANT:-

Pillar Type Fire Hydrant shall confirm to AWWA C502 and shall be UL listed, and approved by Civil
Defense. The hydrant upper baler above grade shall be provided with two (2) 2.5 inch size valve
outlets conforming to BS 336, instantaneous, female with cap & chain and one (1) pumper connection
4 inch size, round, male thread, conforming to BS 336 with Cap & chain. The lower barrel below grade
shall be provided with a valve and a stem extending to the top of the pillar hydrant with an operating
nut screw. The barrel shall be provided with a breakable flange.
Hydrant shall be approved type and have not less than a 6 in diameter connection with the mains.
Max. Spacing between public hydrants along public roads shall be not more than 100 m.
Number, location and spacing of hydrants will be approved by Civil Defense Departments.
Hydrants shall be located not less than 40 ft (12.2 m) from the buildings to be protected

7.6.1 PROPOSED FIRE FIGHTING NETWORK

15

7.7 FOUL WATER AND SEWERAGE SYSTEM


Wastewater Generation
INTRODUCTION

Total Population

Plot

There is no existing sewage network in the vicinity of the project. Therefore, there is a need for a temporary
Sewage Treatment Plant (STP) on-site to cater for sewage treatment. This STP shall be temporary and is designed
for the ultimate flow with no spare capacity.
FOUL WATER SYSTEM STRATEGY

The design strategy adopted for this project is to provide gravity sewers system that has manholes of 6 meters
maximum depth, in order to avoid lifting stations as much as possible. Our proposal i s to provide shallow
connection point for each plot, as most of the plots are villas, and then connect to the main network. Our utility
corridor however, has been structured in a way that can cater any new requirements by the concerned different
authorities.

Area no.

Residents

Workers

Sewage Generated

Visitors/
Students

Residents

Workers

Nos.

Residential

Average
Sewage

Visitors/
Students

Generation

m3/day

2,340

702.00

702

Mosque

60

0.10

1.80

Commercial

40

0.25

1.20

100

0.35

3.00

705

Total

2,340

702

VELOCITY:
Self-Cleansing Velocity

GENERATED SEWAGE EFFLUENT

Population : The population of the development is 2340 residents, 7 workers and 100
visitors.

Peaking Factor: The peaking factor used in municipal projects in Dubai is a variation of the
commonly used
Babbitt formula:

To provide a self-cleansing regime within gravity sewers, the minimum velocity shall be above 0.75 m/s at
peak flow.
Non-Scouring Velocity

The maximum mean velocity shall not exceed 3 m/s at the design depth of flow.
DEPTH OF FLOW

PF = 4.25 x P -1/6
Where P is the population equivalent in thousands
WASTEWATER GENERATION RATES

The waste water generation rates used and t he sewage flow generated based on DM Design
guidelines are shown below.
Wastewater Generation Rate
Consumer
Residents
Commercial/Retail staff
Visitors
Worker
Recreation Facility Users
School

16

As per Dubai Municipality Design Criteria, the depth of flow will be as per the below table
Maximum pipe percentage full in sewer pipes.

Description
Trunk sewer lines
Main and lateral sewer lines

Average Daily Generation in liters/


Capita
300
50
30
50
95
50

Maximum d/D
0.75

Minimum d/D
0.50

0.85

0.50

d/D is the ratio of flow depth to (d) to nominal pipe diameter (D).
a.
Minimum flow shall be considered to avoid sedimentation.
b.
Maximum flow shall be clear sedimentation

HYDRAULIC DESIGN EQUATION

Design of Sewer shall be based on equations such as Colebrook-White: V = (


2gDS)^0.5 log [Ks/3.7D + 2.51v /D ( 2gDS)^0.5 ]
Where
V
G
D
S
Ks
V

= velocity ( m/sec
= gravitational acceleration (m/s2) = 9.81 m/s2
= pipe diameter ( m)
= hydraulic gradient (m/m)
= Linear measure of effective roughness = 0.6 mm
= Kinematics viscosity of fluid (m /s) = 1 m /s

PIPE MATERIAL

The pipe material will be UPVC for the pipe up to 300 mm diameter and GRP for the pipes greater than 300
mm Diameter.
DESIGN OF MANHOLES

The Design of manholes is as per the standards of:


DM. specifications and guidelines.
TYPES

Refer to standard drawings which will be as per DM standards


SEWAGE TREATMENT PLANT (STP)

STP is temporary till the tie-in connection provided by DM is constructed. The capacity of the STP shall be
determined during detailed design stage. No spare capacity shall be considered. For future the network shall be
connected to the DMs main network, which shall make the STP obsolete. An Odor control system shall be
provided to ensure that obnoxious gases and odors are in concentration lower than the detection level. DM design
criteria shall be used for design of STP. Treated Sewage Effluent (TSE) shall be used for Irrigation purpose.
The proposed STP is located at the South East of the site. The general layout for the proposed sewerage network
and the STP is presented in the below drawing..

17

7.7.3 PROPOSED SEWERAGE NETWORK

18

7.8 STORM WATER DRAINAGE SYSTEM

STORM WATER DRAINAGE SYSTEM STRATEGY

Since the project is located in an undeveloped area, there is no existing DM. drainage network within the vicinity
of the project.
The proposed drainage catchment considers all the post development area to be
drained/discharged to the proposed drainage system that will be local drainage system as temporary till the DM
construct the main drainage.
The local drainage system is designed in such a way as to provide for significant volumes of water retention as
well as discharge through infiltration cells/soakaways.

V=-2[(2gDS)log{ks/3.7D+2.51v/D(2gDS)1/2}]1/2
Where:
V
G
D
S
Ks
V

velocity in m/s
gravitational acceleration in m/s2
pipe internal diameter in m
hydraulic gradient in m/m
roughness coefficient in m
kinematic viscosity of fluid in m2/s

Run Off Coefficient C:

Asphalt Brick- Tile Roof


Sandy soil - Clay soil soft cape

SYSTEM DESIGN:

On examining the topography of the land, the directions of the discharge of the runoff have been
assessed. A conceptual layout of the storm main is presented below.

0.75
0.2

Clear Times

As per DM regulation and recommendation the clear time is 4 hours.

Rainfall Intensity:

Max. & Min. velocity:

As per DM criteria, rainfall intensity is 36.69mm in 90 minutes (24.46 mm/hr.) for return period of 10 years
and 30 mm in 90 minutes (20 mm/hr.), for return period of 5 years. The 5 years storm return period is used for all
local drainage facilities in all local projects in Dubai.

Maximum and Minimum velocities in Drainage Pipes

Clearance Time:

As per DM design criteria, system clear time refers to an amount of time after a storm event ends which is
required to remove storm water volume from catchments area. This time has been set to minimize commercial
impacts and to protect the public. This clear time philosophy is used to size the pipe only.

Pipe Description

Minimum (m/s)

Maximum (m/s)

Gravity line

0.75

2.5

Pressure line

1.0

3.0

PIPE MATERIALS:

Peak Runoff Flow:

As per DM regulations, Drainage pipes should be uPVC. The minimum pipe size permissible on
drainage projects is 250 mm

Peak flow is estimated by using the Rational Method Formula:

GULLY TYPES:

Q=2.78CIA

Kerb inlet gullies will be used in the drainage system to intercept runoff.

peak runoff rate in l/sec.


runoff coefficient
rainfall intensity in mm/hr
catchments area in ha.

MANHOLES:

Where
Q
C
I
A
Hydraulic Design:

This is based on the Colebrook- White Formula as follows:


19

Manholes in the drainage system will be installed in accordance with the following design criteria:
Maximum spacing:
Minimum manhole lower shaft diameter:
Maximum manhole lower shaft diameter:

100 m
1200 mm
2400 mm

Drainage Storage Facilities

This Drainage Storage Facilities is provided under the green areas so that the generated volume will dissipate
through the proposed cells.
The storage facilities for all catchments will consider the generated volume from 1 in 50 year Storm
as recognized by the Dubai Municipality .These facilities will occupy the green area and will be placed near the
sidewalks with a max. of 6m width and depth of max. 3.1m, the infiltration rate will be considered to ensure that
all the generated volume from 1 in 5 years Storm will dissipate for the duration of 24 hours.

20

7.8.2 PROPOSED STORM NETWORK

21

7.9 TELECOMMUNICATION SYSTEM

DESIGN CRITERIA:
Telecommunications play a vital role in the profitable operation of todays business. The term
telecommunications encompasses all the services that a modern forward thinking communications service
provider will provide within the villas/ buildings.
The existing telecommunication system in vicinity of the project from du or Etisalat will be tapped as the main
carrier of telephone facilities in the development. Other telecommunication systems like satellite connections;
Ethernet etc. will also be considered and carefully studied.
Various systems can be considered such as voice, data and entertainment of the project. The preferred final
infrastructure solution will depend to some degree on those systems to be implemented.
Table (Entry Ducts as per Buildings Category)
Cross development transmission can be achieved using either separate transmission networks for each user
system, or combine all transmission into a single Ethernet network. For multiple transmission systems,
each system can use its own cable or be allocated fibers within a commonly used cable.
The recommended solution for the duct infrastructure is to provide ducting network to be used by all cable
systems, whichever cabling solution is adopted as du or Etisalat the primary lead provider has the ownership
of the ducts.

CABLE INFRASTRUCTURE:

The backbone of the network would be a fiber ring around the facility, with the nodes connected with
standard fiber cables. Fixed links would also be provided to distribution nodes. From the distribution nodes,
blown fiber tubing would be installed into each building, leaving the flexibility to install the required type
of fiber as services are required.

Requirement of providing GSM services within the facility or utilizing the service from the existing one in
proximity of the site will be examined in liaise with du and Etisalat.
Building Category

FOC Cable Calculation

INFRASTRUCTURE REQUIREMENTS:

For single network option, the duct infrastructure requirements are relatively simple. Every building that
may require some communication service needs to be provided with the entry ducts, giving access to the overall
development duct network.

Building

2 core FOC for every Villa

Retails / Commercial

2 core FOC & 6 pair CAT3


copper per 500 sqm

DUCT INFRASTRUCTURE:

This would allow the duct network to be designed in advance of the actual network design, after studying
and defining the cabling solution. A main duct backbone ring will be required around the development
(providing a level of diversity in the event of cable/ equipment failure), with each building within the facility
requiring any form of communications connected into the backbone. The table below will show the entry ducts
for building category as per DU and Etisalat design guidelines:

22

Table (FOC Cable Calculation)

7.9.1 ESTIMATED TELECOMMUNICATION DEMAND

23

7.9.2 PROPOSED TELECOMMUNICATION NETWORK

24

7.10 ELECTRICAL NETWORK

DESIGN CRITERIA AND PARAMETERS:


The Electrical network design will be based on the fully developed parcels for Villa Development Project.
The Dubais typical design standards as supplied by DEWA and other standard engineering practices in the Middle East will
be used as the primary basis for the design for this project.
Coordination with the local authorities will be conducted on a regular basis for them to provide the primary power connection
to the substation transformers provided and installed in the facility. For this purpose total connected load will be calculated
based on the different buildings (residential and commercial) and approval for the master plan load parcels and 11kv corridor
from DEWA will be taken, all based on DEWA (E) requirements for the LV and the 11 KV requirements for corridor and to
the basic compliance to RTA & DM typical standard for the road cross section and right of way.
POWER SOURCE:
An existing DEWA 132 KV substation on the northern side of Villa development project is proposed to serve the project area
subject to DEWA approval - with 11 KV cables network between the substations within parcels area and LV (415V) network
from substations to the individual villa components, final routing, size and material of these cables will be coordinated with
and fixed on approval from DEWA. The estimated load is 19.1 MW, approximately 23 No: of 1000 KVA transformers can
serve the demand for the project.
STAND BY GENERATOR:

Villa Development ,Umm Al Daman project is a social housing residential development ,hence a 150 KVA Standby
generator is proposed as backup for STP & Irrigation.

25

7.10.1 ESTIMATED ELECTRICAL LOAD

26

7.10.2 EXISTING ELECTRICAL NETWORK

27

7.10.3 PROPOSED HV AND LV CORRIDORS

28

7.11 PROPOSED UTILITY HUB

29

Potrebbero piacerti anche