Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
-In combination with classic energy resources it increases plant energy efficiency.
2. PRESENT TECHNOLOGICAL PROCESS AND CONNECTION OF NEW
EQUIPMENT WITH THE EXISTING PLANT
Heating plant Cerak is an integral part of PUC Beogradske Elektrane and it produces and
delivers heat energy for heating and domestic hot water to customers in Belgrade municipalities of
Cukarica and Rakovica. Basic fuel currently used in the plant is natural gas or fuel oil. Total boiler
installed capacity is 244.3MW, the consume capacity for heating and hot water is 230MW, while
the estimated installed capacity of 16,3 MW produces hot water. The designed level for summer
operation mode (15 June-15 October) is 65/22C, with the flux of 120 m3/h for sanitary hot water
production. The present summer operation mode is set up at 62/45C for the capacity of 6MW with
flux of 300 m3/h of hot water. It is expected that in the upcoming period modernisation and new
operation mode of district heating substations would be set up at 250 m3/h flux and temperature
mode of 60/40C.
Clean area possible for solar collectors placing is approximately15,000 m2. The covering of
two parking areas is included. The present route of gasoline and main district heating pipeline has
been considered at location selection (calculated 5 m from the gas line route). In consideration of
future enlargement of the main plant structure, location spot for accompanying structure with the
area of 8x8m for equipment storage (pumps, equipment for measuring and regulation, plate heat
exchangers, expansion vessel) was chosen, as well as location of heat accumulator with capacity of
1.000 m3.
Due to differences in pressure between main pipelines and solar collectors and different fluids
used in circulation (during heating plant winter operation mode, working fluid of solar plant would
be the mixture of liquid of water and propylene-glycol, while the main pipeline would use
chemically adjusted hot water), it would require installing plate heat exchanger. During design
phase, it would be proper to calculate plate heat exchanger area extension for 30% due to the
presence of propylene glycol in the working fluid. Figure 1 presents technological process of
connection between new equipment with the existing plant.
2.1. Required heat energy for sanitary water heating obtained by gas combustion
All three mentioned operation modes are specified in accordance with 6 MW of heat consumption,
meaning that approximately same volume of heat has to be delivered to customer regardless of
operation mode in question.
Case 1: Present operation mode of 62/45C with hot water flux of 300m3/h:
Required amount of heat energy on one-hour basis necessary for water warming to specified
temperature is (constants taken from TRNSYS16 software):
.
m3
kg
kJ
MJ
Q = m c p t = 300
999 3 4.19
17 K = 21347.6
(1)
h
m
kgK
h
where:
.
Q required amount of heat energy, m - mass of water flux, - water density (= 999
p=1bar, i t=20C), cp- specific heat of water, c p = 4.19
kg
; at
m3
kJ
, t - difference of temperatures for
kgK
MJ
MJ
= 94271138.5
day
year
(2)
Amount of heat injected with fuel into boiler (chemical gas energy) is:
Q=
94271138,5
MJ
kJ
= 105922627.52
= 10.592 1010
0.89
year
year
(3)
In which:
=0.89 boiler efficiency coefficient
Net caloric value of gas is Hd = 34 MJ/m3, or Hd = 45.5 MJ/kg, and required volume of gas for
one year is:
m= 3115371.4 m3/year
Similarly to the calculation method for required amount of heat for water warming for present
operating mode, calculation of designed summer operation mode and new operating mode for heat
energy production is performed.
Case 2: Designed operation mode of 65/22C with hot water flux of 120m3/h:
Q = 518 370.7
MJ
MJ
184 = 95 380 208.8
dan
god.
(4)
Amount of heat injected with fuel into boiler (chemical gas energy) is:
Q=
95 380 208.8
MJ
kJ
=107 168 773.9
= 10.717 1010
0.89
god.
god.
(5)
Case 3: New operation mode of 60/40C with hot water flux of 250m3/h
Q = 502 297.2
MJ
MJ
184 = 92 422 684.8
day
year
(6)
Amount of heat injected with fuel into boiler (chemical gas energy) is:
Q=
(7)
According to Srbijagas records [1], gas price for business consumers is Cg= 24.7 RSD/m3, i.e.
Cg=0.009 EUR/MJ, respectively. In accordance with Eurostat data [2] on gas prices variation during
1991-2006, it is accepted that gas price annual increase would be 6%. Figure 2 presents data for
projected gas prices. Also, total gas costs of 38,125,212.22 EUR, from 2008 to 2028 and for plant
summer operation mode is calculated. The analysis is made for 21-year period in order to calculate
estimated savings during solar collector lifetime (collector life time is currently estimated to 20-25
years). Simultaneously, that would be adequate period for savings assessment due to CO2 emission
reduction.
0.0289
0.0257
0.0229
0.0203
0.0181
0.0161
0.0143
0.0128
0.0114
0.009
0.0101
08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Year (-)
2.2. Heat energy for sanitary water heating obtained from combined system for heat energy
production (gas combustion in the boiler and solar thermal system)
Two collector types are chosen for heat energy production through utilization of solar energy:
evacuated and flat-plate, i.e. three types: Apricus, NAU and GJ. [3-5]. The calculation is made for
total collector surface of 5,000 m2.
4
The heat quantity obtained from the selected collector and from the boiler in the combined
system for heat energy production is given by simulation in the programme TRNSYS16, [6].
Table 1 shows data of different parameters for the selected collectors such as: collector area,
absorber area, total absorber area, absorber unit price and total expenses for each collector type.
Table 1. Data on different collector parameters
No Manufacturer Country
1.
Apricus
2.
NAU
3.
GJ
Type
Australia/
Vacuum
China
Germany Flat plate
Denmark/
Flat plate
Vietnam
Total
Total costs, Tk
Unit price
absorber
(colector area
of abs.,CA
area, PUA
5000 m2)
2
2
2
2
(m /pcs.) (m / pcs.)
(m )
(EUR/ m )
(EUR)
Collector Absorb.
area Pk area, PA
4.35
2.4
2,760.0
154
425,000
2.14
1.9
4,440.3
193
857,000
13.5
12.56
4,659.8
137
639,000
Table 2. Amount of heat from the boiler and coll. and the amount of heat entering the boiler
Collector area
5000 m
Collector
a) Apricus
b) NAU
c) GJ
Table 2 contains data related to the estimated gas costs burning in combined system boiler, in
cases when the part of produced heat energy in the combined system is obtained from the solar
thermal system with a) Apricus type of collectors, b) NAU type of collectors and c) GJ type of
collectors.
In case of present production of heat energy (operating mode 62/45OC and flow of 300 m3/h
of hot water, total collector area of 5,000 m2), the achieved savings results show that the most
profitable one would be the combined system with solar thermal system and Apricus collector type,
whose total investment cost would pay out in 6.29 years. Likewise, the results have shown that the
total investment costs for the solar thermal system with NAU collector type would pay out in 8.77
years, while with GJ collector type that period would be 7.50 years, Table 3.
The anticipated gas price increase of 6% per year has a favourable effect on pay out period
reduction. The biggest savings are expected at the end of operation life.
Table 3. Investments pay out period for the operating mode of 62/45OC and flow of 300 m3/h
Collector
a) Apricus
b) NAU
c) GJ
Collector area
5000 m2
Collector
a) Apricus
b) NAU
c) GJ
In the case of designed operating mode for heating energy production (operating mode
65/22C and flow 120 m3/h of hot water), obtained savings have given better results comparing to
present operation mode (Table 5). Certain better pay out can be noticed than in the case of present
6
operating mode. That can be explained by better efficiency in collectors operation, when return
temperature is lower (22C compared to 45C).
Table 5. Investments pay out period for operating mode of 65/22C and flow of 120 m3/h
Collector
a) Apricus
b) NAU
c) GJ
Collector area
5000 m2
Collector
a) Apricus
b) NAU
v) GJ
In the case of future operating mode of heating energy production (operating mode 60/40C
and flow of 250 m3/h of hot water), results of obtained savings are similar as in two previous cases,
as shown in the Table 7, i.e. they are some where between present operating mode and designed
operating mode .
Table 7. Investments pay out period for operating mode of 60/40C and flow of 250 m3/h
Collector
a) Apricus
b) NAU
c) GJ
Table 8. Reduction of CO2 emissions for mode of operation of 62/45C, 300 m3/h
Table 13. Reduction of CO2 emissions for operating mode of 60/40C, 250 m3/h
combined system for DHW production for collector area of 5,000 m during summer operating
mode of Heating Plant Cerak. Three possible operating modes of combine system is analyzed for
o
the specified heat capacity of 6 MW: present of 62/45 C with flow of 300 m /h of hot water,
o
designed of 65/22 C with flow of 120 m /h and future of 60/40 C with flow of 250 m /h, that will
be achieved after planned reconstruction and modernization of entire system of HP CERAK.
In accordance with type of collector and its operating mode, gas savings are ranging from
7.58% to 11.54%. Investment can be paid out in period between 5.6 and 8.77 years depending on
collector type and operating mode of combined system. The study uses annual increase in gas price
3
with growth rate of 6% (present gas price is 0.3 EUR/m in 2008 year) and increase in gas price that
favorably influences pay out period, and the best saving is forecasted for the end of operation life of
solar collectors.
Installation of solar collectors would reduce hazardous gases emission, especially CO2 that
has significant effects on environment and contributes to the people health. Additionally, the CO2
emission reduction has in EU, and in accordance with Kyoto protocol, its market value and opens
2
the possibility of applying for CDM project. For areas of 5,000 m , savings for 21 years are approx.
7% of total investment costs, and by increasing collector areas the savings additionally increase due
to fixed costs for equipment and monitoring of CDM project.
AKNOWLEDGMENT
This research has been financed by Ministry of Science and Technological
Development
of
Republic
of
Serbia,
in
the
frame
of
National
Energy
Efficiency Program. Research has also been supported by PUC Beogradske
elektrane, Belgrade.
REFERENCES
[1] www.srbijagas.com
[2] http://epp.eurostat.ec.europa.eu/
[3] www.apricus.com
[4] www.nau.gmbh.de
9
[5] www.arcon.dk
[6] TRNSYS16, A Transient System Simulation Program, Solar Energy Laboratory, University of
Wisconsin, Madison, USA and Transsolar, Stuttgart, Germany.
[7] D. Pahud, Central Solar Heating Plants with Seasonal Duct Storage and Short-term Water
Storage: Design Guidelines Obtained by Dynamic System Simulations, Solar Energy Vol. 69,
No. 6, pp. 495509, 2000.
[8] www.naturalgas.org/environment/naturalgas.asp
10