Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
VENETIAN MACAU
HOTEL FIT OUT
Version 3
22.03.2006
-1-
1.
Scope of Work
1.1 Specification Reference
Architectural Specification Section 07140 rev.3, Clause 2.01 B-D
1.2
2.
Work Methodology
2.1 Time
8:30am ~ 6:00pm
2.2
Duration
According master program for this task duration
Refer to Item 2.3 Sequence for application duration
2.3
Sequence
2.3.1 The substrate must be solid, dry, clean, smooth (steel-Trowelled finish, no
pocket, gaping cracks and ridges) and free from oil, grease and other residues
which should be removed by sand-blasting, brushing or shot-blasting if
necessary.
2.3.2 Absorptive mineral substrates are to be primed with PCI Gisogrund, diluted 1:1
with water.
2.3.3 Wait the primer to dry (at least 3 hours).
2.3.4 Apply PCI LASTOGUM Liquid Applied Waterproofing Membrane
A. Manufacturer recommended applying at least two coats (thickness of wet film
each wet film coat : 0.5mm).
B. The first coat should be applied with PCI Lastogum red. Evaporation time
after first coat is minimum 3 hours at +23C and 50% relative humidity. Higher
temperatures reduce and lower temperatures increase these times. The air flow
will affect the evaporation time as well.
C. Sealing the corner and wall/ floor and wall/ wall joints
Press PCI Pecitape Objekt sealing tape onto the fresh first coat at corners, wall
/floor and wall / wall joints. Cut the tape to fit at corners.
D. Sealing the pipe penetrations
-2-
Location
Bathroom Interior Wet Areas
3. Resource Required
3.1 Personnel
Site Supervisors
Trained Waterproofing Applicators
3.2
Plant
N/A
3.3
Materials
PCI Gisogrund Primer
PCI Lastogum Red
PCI Pecitape
PCI Lastogum Grey
3.4
Specialist Services
-3-
3.5
4.
5.
Supervision
Experience Site Supervisors
Foremen
Safety officer
Place of Work
According to the Scope of Works for Package 5115A
4.3
Others at Risk
Refer to the risk assessment sheet
4.4
4.5
4.6
Environmental Impacts
Disposal
Waterproofing material mix with ground water
Security
Provide by CM & Major Trade contractor.
Temporary fencing to block the access bathroom during applying the
waterproofing.
-4-
5.3
5.4
Visual Inspection :
Visually inspect waterproofing system installation thoroughly in presence of
architect's representative. Bubbles formed in the waterproofing system will be
made good in accordance with the manufacturer's recommendation. Repair any
defects as recommended by manufacturer.
B.
Observation shall be made to the ceiling areas below and adjacent rooms three
times daily. Any watermark or leakage shall be recorded on inspection form.
A copy of duly signed inspection form to be submitted to the Architect upon
completion of the flood test.
-5-
Any leakage or defect observed to be made good and have the area to be retested
until a satisfactory result is being obtained.
C.
Observation shall be made to the wall of adjacent rooms three times daily. Any
watermark or leakage shall be recorded on inspection form.
A copy of duly signed inspection form to be submitted to the Architect upon
completion of the water spray test.
Any leakage or defect observed to be made good and have the area to be retested
until a satisfactory result is being obtained.
5.5
Permits
About 1m height working platform
5.6
5.7
6.
7.
8.
Glove
Specialist Training
Subject by manufacturer.
Provision of Information
6.1 Changes to Information
All the update information will be submitted to GBCML as soon as any update
information for the supplier/applicator.
6.2
6.3
Verification Records
7.1
7.2
7.3
7.4
Filing Arrangements
Full set of records will be submitted to GBCML
Appendixes
Demarcation for the height of wall waterproofing
Hazard identification sheet
Risk Assessment Sheet
PCI Material Safety Data Sheet
-7-
Date : 20/03/2006
Hazard
People Affected
Cause of Hazard
Installer
Installer
Installer
Fall of Person
Installer
Worker use
unsafety platform
or ladder
Muscular stress/sprain
Installer
Body injury
1 2
Existing Control
Remark
Measures
Wear safety goggles when working above
eye level or if there
is danger of
splashing.
Supply fresh air by
ventilator.
Date : 20/03/2006
Control Measeure
Rating of Harm
Probability
2
Note :
Risk Level
Consequences
3
Recommended
Action
Remark
(Green)
Safety Goggles
required
(Green)
(Green)
(Green)
Use safety
workplatform
(Green)
Warm up / use
correct tools
Probability or Likelihood Rati Almost Certain (5), Probable (4), Possible (3), Remote (2), Impossible (1)
Consequence Rating: Very High (5), High (4), Medium (3), Low (2), Very
Risk Level: (Red), (Orange), (Yellow), (Green)
2 2