WP 5115A Prefabricated bathrooms Phase I & II

Method Statement for Application of "PCI" Waterproofing

VENETIAN MACAU
HOTEL FIT OUT

ELECTRICAL INSTALLATIONS WAI FAT CO., LTD.

Version 3
22.03.2006
-1-

1.

Scope of Work
1.1 Specification Reference
Architectural Specification Section 07140 rev.3, Clause 2.01 B-D
1.2

2.

Third Party Interfaces


Concrete substrate in interior wet areas;
Drywall Substrate
Floor Drains
Pipe works
All other finishing works

Work Methodology
2.1 Time
8:30am ~ 6:00pm
2.2

Duration
According master program for this task duration
Refer to Item 2.3 Sequence for application duration

2.3

Sequence
2.3.1 The substrate must be solid, dry, clean, smooth (steel-Trowelled finish, no
pocket, gaping cracks and ridges) and free from oil, grease and other residues
which should be removed by sand-blasting, brushing or shot-blasting if
necessary.
2.3.2 Absorptive mineral substrates are to be primed with PCI Gisogrund, diluted 1:1
with water.
2.3.3 Wait the primer to dry (at least 3 hours).
2.3.4 Apply PCI LASTOGUM Liquid Applied Waterproofing Membrane
A. Manufacturer recommended applying at least two coats (thickness of wet film
each wet film coat : 0.5mm).
B. The first coat should be applied with PCI Lastogum red. Evaporation time
after first coat is minimum 3 hours at +23C and 50% relative humidity. Higher
temperatures reduce and lower temperatures increase these times. The air flow
will affect the evaporation time as well.
C. Sealing the corner and wall/ floor and wall/ wall joints
Press PCI Pecitape Objekt sealing tape onto the fresh first coat at corners, wall
/floor and wall / wall joints. Cut the tape to fit at corners.
D. Sealing the pipe penetrations
-2-

Using the fingers, stretch a PCI Pecitape 10 x 10 / PCI Pecitape 35 x 35 sealing


gasket to give a tight fit over the pipe. Place it in position, bedding it onto the
fresh first coat.
E. Sealing a floor drain
Cut a PCI Pecitape 35 x 35 sealing gasket to suit the drain system to be used.
Place it in position, bedding it onto the fresh first coat. Contact PCI for
specific guidance if necessary. Insert loose flange of the floor outlet and screw
down.
F. Before the application of the second coat, ensure the first coat is dry (at least 6
hours) and has not been damaged.
G. For wall application, apply the second coat of PCI Lastogum grey which is a
one-component system. For floor application, apply the second coat of PCI
Lastogum grey which is a two-component system (Need to mix the two
components by slow speed drill fitted with a suitable paddle for at least 2
minutes before use).
H. Ensure the cured waterproofing membrane is dry and has not been damaged
before fixing tiles. If water flooding test is necessary, wait for at least 3 days
after the second coat has been completed, before carrying out the test.
I. Tiles can be fixed after the second coat has been completed for at least 24
hours at + 23C and 50% relative humidity.
2.4

Location
Bathroom Interior Wet Areas

3. Resource Required
3.1 Personnel
Site Supervisors
Trained Waterproofing Applicators
3.2

Plant
N/A

3.3

Materials
PCI Gisogrund Primer
PCI Lastogum Red
PCI Pecitape
PCI Lastogum Grey

3.4

Specialist Services
-3-

3.5

4.

5.

Flood water test after completion for floor


Water spray test for wall after completion

Supervision
Experience Site Supervisors
Foremen
Safety officer

Assessment of Significant Risks


4.1 Access / Egress
Blockage of the bathroom access during the waterproofing curing period.
4.2

Place of Work
According to the Scope of Works for Package 5115A

4.3

Others at Risk
Refer to the risk assessment sheet

4.4

Competence for 'Key' Activities


Water proofing test pass

4.5

"Dangerous Goods, Noise, Manual Handling, etc"


N/A

4.6

Environmental Impacts
Disposal
Waterproofing material mix with ground water

Control Measures to be used


5.1 Emergency Arrangements
Please refer to Material Safety Data Sheet.
Emergency Call : 1. Mr. Wong Peng Tong 6338673 / 339966
2. Mr. Andrew Ip 6557228 / 339966
5.2

Security
Provide by CM & Major Trade contractor.
Temporary fencing to block the access bathroom during applying the
waterproofing.
-4-

5.3

Third Party Liaison


MEP package
Drywall package

5.4

Work Instructions and Field Controls


On completion of the waterproofing, CM to be informed prior to tests. No material /
finishing shall be placed on the waterproofing prior to testing.
A.

Visual Inspection :
Visually inspect waterproofing system installation thoroughly in presence of
architect's representative. Bubbles formed in the waterproofing system will be
made good in accordance with the manufacturer's recommendation. Repair any
defects as recommended by manufacturer.

B.

Testing of Horizontal Installations:


Flood test to be carried out for checking the water tightness of the waterproofing
system. The surfaces shall be cleaned, checked for cracks and the flood test
carried out as follows:

After the waterproofing membrane is applied, allow minimum 72 hours for


the membrane to cure before conducting the water flooding test;
Temporarily block off all the water outlets by means of impermeable
materials;
Flood the waterproofed area with water to a depth of not less than 25mm;
Allow the water flooding to stand for 24 hours;
Make joint inspection with client's representative of the waterproofing
system to check any abnormal appearance (e.g. debonding, peeling off,
etc.);
Make joint inspection with client's representative of the underside of the
waterproofed area to check any water leakage;
Record the testing result on inspection forms, taking record photos where
necessary;
Remove all the block out at water outlets and allow the water to drain away,
or pumped the water out by vacuum pump.

Observation shall be made to the ceiling areas below and adjacent rooms three
times daily. Any watermark or leakage shall be recorded on inspection form.
A copy of duly signed inspection form to be submitted to the Architect upon
completion of the flood test.
-5-

Any leakage or defect observed to be made good and have the area to be retested
until a satisfactory result is being obtained.
C.

Testing of Vertical Installation


Carry out joint inspection with client's representative for water spray test to
waterproofing system applied on wall (exceeding 300mm high only) with the
following procedures.

After the waterproofing membrane is applied, allow minimum 72 hours


for the membrane to cure before conducting the water spray test;
Apply water using a common domestic telephone type shower head fitted to
a 13mm diameter supply pipe delivering water pressure of not less than
0.2N/mm2 (30 psi). Locate the pressure gauge at a distance not exceeding
1500mm from the shower head;
Move shower head to and from or as directed by client's representative
along the waterproofing wall surface to be tested (at the level at approx.
100mm below the highest level of the waterproofing membrane ), at a
perpendicular distance between 300mm to 600mm for 2 minutes;
Carefully make inspection of the other side of the waterproofed wall surface
to check any water seepage;
Record the testing result on inspection form, taking record photos where
necessary;

Observation shall be made to the wall of adjacent rooms three times daily. Any
watermark or leakage shall be recorded on inspection form.
A copy of duly signed inspection form to be submitted to the Architect upon
completion of the water spray test.
Any leakage or defect observed to be made good and have the area to be retested
until a satisfactory result is being obtained.
5.5

Permits
About 1m height working platform

5.6

Personnel Protective Equipment


Helmet
Reflective wear
Safety shoe
-6-

5.7

6.

7.

8.

Glove

Specialist Training
Subject by manufacturer.

Provision of Information
6.1 Changes to Information
All the update information will be submitted to GBCML as soon as any update
information for the supplier/applicator.
6.2

Confirmation of Emergency Arrangements / Drills


According to GBCMLs emergency arrangements / drills, such as fire drill.

6.3

Employee and Third Party Briefings


WRC training/Briefing
Tool box talk
Submit above record to GBCML

Verification Records
7.1

Initial Records Requirements


Setting out of floor leveling.
Substrate

7.2

Records to be taken during Construction


Inspection form with photos for completion of the water spray test / flood test.

7.3

Completion Certification Package


Warranty issued by Manufacturer

7.4

Filing Arrangements
Full set of records will be submitted to GBCML

Appendixes
Demarcation for the height of wall waterproofing
Hazard identification sheet
Risk Assessment Sheet
PCI Material Safety Data Sheet
-7-

Works Related Projects: Package 5115A - Prefabricated Bathrooms Phase I & II


Type of Activity Operation : Application of Waterproofing

Date : 20/03/2006

Hazard Identification Sheet


Job Task
Application of
waterproofing
material

Hazard

People Affected

Cause of Hazard

Worst Harm due to


Hazard
Eye irritation

Eye contact with the


waterproofing material

Installer

Workers did not


wear and use safety
equipment

Inhalation with the


volatile element

Installer

Skin contact with the


waterproofing material

Installer

Workers stayed in Dizziness


the closed area for
a long time
Workers did not
Skin irritation
wear and use safety
equipment

Fall of Person

Installer

Worker use
unsafety platform
or ladder

Muscular stress/sprain

Installer

Uncorrect manual Body injury


handling operation

Body injury

1 2

Existing Control
Remark
Measures
Wear safety goggles when working above
eye level or if there
is danger of
splashing.
Supply fresh air by
ventilator.

Wear safety gloves. After application,


installer should wipe
off substance and
clean with soap and
water.
Sufficient working space should be
provided such as
work platform
Warm up / use
correct tools

Date : 20/03/2006

Works Related Projects: Package 5115A - Prefabricated


Type of Activity Operation: Application of Waterproofing

Risk Assessment Sheet


Risk

Control Measeure

Rating of Harm
Probability
2

Eye contact with the Wear safety goggles


waterproofing
when working above eye
material
level or if there is danger
of splashing.
Inhalation with the Supply fresh air by
volatile element
ventilator .
Skin contact with the Wear safety gloves. After
waterproofing
application, installer
material
should wipe off substance
and clean with soap and
water.
Fall of Person
Sufficient working space 2
should be provided such
as work platform
Muscular
Warm up / use correct
2
stress/sprain
tools

Note :

Risk Level

Consequences
3

Recommended
Action

Remark

(Green)

Safety Goggles
required

Supply fresh air by


ventilator
Safety Gloves
required

(Green)

(Green)

(Green)

Use safety
workplatform

(Green)

Warm up / use
correct tools

Probability or Likelihood Rati Almost Certain (5), Probable (4), Possible (3), Remote (2), Impossible (1)
Consequence Rating: Very High (5), High (4), Medium (3), Low (2), Very
Risk Level: (Red), (Orange), (Yellow), (Green)

2 2