Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DESIGN GUIDELINES
The following items represent the preferences of FSG-Utilities-Mechanical Distribution for basic
materials and systems. It is assumed that manufacturers’ recommendations are followed in all
cases, unless specifically directed otherwise. This document is not intended to cover all
aspects of good engineering specifications and is not intended to be a substitute for competent
engineering design. This is a living document and will be changed as new technology becomes
available or old technology is brought to our attention. Any advice on changes will be welcomed
and evaluated. Please note dates on all pages and contact FSG-Utilities-Mechanical
Distribution for verification that you have the most current copy.
System Description:
1. Steam is distributed throughout the campus via looped high and low pressure
distribution systems. Radial feeds also exist to some locations on campus. For
reliability and maintainability, looped systems are preferred wherever possible.
Low pressure use is preferred wherever possible for economic and safety
reasons.
2. The high pressure system is operated at 155 psig, 410° F (40°F superheat). The
low pressure system is operated at 20 psig, 300° F (40°F superheat). The
pressures and temperatures indicated above are nominal at the Power Plant.
The actual pressures and temperatures fluctuate based on Power Plant
operation and location in the system. NOTE: Because the 20 psig system is
connected to the 155 psig system through pressure reducing valves (PRVs) in
numerous places, the same anchoring and expansion standards are used for the
20 psig system and the 155 psig system, with any exceptions noted.
3. The Oakdale Campus is served through a 125 psig steam distribution system.
The 125 psig system is operated at saturation temperature of 353° F. The same
design standards are used on the Oakdale 125 psig steam distribution system as
those required for the Main Campus 155 psig steam distribution system.
5. For applications where it is anticipated that the 20 psig distribution system has
adequate or near adequate capacity for the majority of the year, but not adequate
during peak load periods, a pressure reducing valve booster station shall be
connected from the 155 psig distribution system to maintain a minimum line
pressure of 15 psig.
1. Pressure reducing valves (PRVs) shall be eccentric plug control valves sized and
installed to manufacturer's specifications. Manufacturer: Cashco Ranger.
(Valves may be provided by FSG out of the project budget if requested.)
2. Valve bodies shall be steel or ductile iron. Cast iron will not be accepted.
3. Valves are to be air operated. Pilot operated valves may be allowed under
special circumstances. Consult with FSG-Utilities-Mechanical Distribution.
4. PRVs from the high pressure system will always be fail-close. Valves on the low
pressure system may be fail open, at the discretion of FSG-Utilities-Mechanical
Distribution and the maintenance staff of the affected building.
6. Valves shall have flangeless bodies designed to fit between two raised face
flanges. The bodies shall fit between ANSI 300# flanges.
9. Where the PRV is smaller than line size, the isolation valves shall be at least one
standard pipe size larger than the control valve (up to line size.)
12. The pilot pressure sensing line shall be tied into the main pipe at least 20 pipe
diameters downstream of the pressure reducing valve. There shall be a pressure
gauge on the pilot line.
13. Installation of a bypass valve shall be determined during the design phase in
consultation with FSG-UTILITIES-MECHANICAL DISTRIBUTION based on the
use of the system. Systems using steam mainly for heating shall generally have
a bypass. Systems using steam mainly for process use shall generally not have
a bypass.
2. Steam traps are to be modular stainless steel inverted bucket traps. Traps shall
have orifices appropriate to the pressure of the steam line.
3. Each trap will have an upstream block valve, test valve, and strainer, a
downstream swing check valve, a test valve, and a block valve, as shown in
Figure SD-2.3. There shall be no trap bypasses.
4. Traps shall be piped off of drip legs. Drip leg diameter shall be equal to the pipe
size for pipes up to 4" and at least one-half the pipe diameter for pipes over 4".
Length of the drip legs should be 1-1/2 times the diameter of the pipe, with a
minimum of 12".
5. Drip legs shall be equipped with blowdown valves on the bottom of the drip leg
equal to the smaller of line size or 2". Where 2” valve will not fit, 1-1/2” valve may
be substituted with FSG-UTILITIES-MECHANICAL DISTRIBUTION approval.
Blowdown valves shall be piped from the bottom of the drip leg cap wherever
possible.
6. Blowdown piping on drip legs and strainers shall face away from the blowdown
valve handwheel and shall not discharge onto electrical equipment.
C. Check Valves:
1. All check valves shall have either bronze or stainless steel seats and flappers.
2. Bodies shall be bronze, cast steel or forged steel. Cast iron bodies are not
acceptable.
D. Strainers:
1. All strainers shall have bronze, cast steel or forged steel bodies. Cast iron is not
acceptable.
3. The blowdown port of each strainer shall have a pipe nipple with a full port sized
gate valve with no cap.
4. Any strainer on 155 psig steam system shall be 300# class. Any strainer on
20 psig steam system shall be 150# class
E. Piping:
2. Piping shall be sloped 1/4" per 10' of pipe to a drip leg. Pipe shall be sloped
down in the direction of steam flow, where possible.
3. Trapping stations shall be located every 250 feet on all steam lines. Direct bury
systems will require steam vaults to access trapping stations.
4. All piping 2-1/2” and larger shall be butt welded, with no backing ring. Welds
shall be visually inspected by a qualified welding inspector.
5. All piping 2” and smaller shall be screwed piping. All flanges on screwed piping
shall be backwelded.
6. All piping 4” and larger on the low pressure or condensate systems, and all
piping over 2” on the high pressure system, shall be analyzed with an appropriate
stress analysis program by a qualified engineer to properly size and design
hangers and avoid excessive stress in any pipe sections.
8. Piping shall have high point vents to allow complete filling of pipe for the
hydrostatic test.
9. Provisions shall be made for blowdown of new steam piping to clean out debris.
Provisions are to be shown on design drawings. Blowdown plans are to be
developed in consultation with FSG-UTILITIES-MECHANICAL DISTRIBUTION.
10. Provisions for pipe expansion shall be made. Both high and low pressure
systems shall be designed for 500° F. Expansion joints (see Section “H”) are
the preferred method. If expansion loops must be used, please inform FSG-
UTILITIES-MECHANICAL DISTRIBUTION of the reasons.
F. Fittings:
2. Threaded systems shall use unions where appropriate. All unions shall be
Nicholson Uniflex Steel/Stainless Pipe Couplings. Pipe unions shall have
replaceable gaskets.
G. Gate Valves:
H. Expansion Joints:
1. Manufacturers: Adsco Model SO-391-RJ, Yarway Fig. No. 6239, Hyspan 6500
series and ATS Thermal Pac Series P2 Ball Joints. All expansion joints on a
project shall be by the same manufacturer and the same model.
2. All expansion joints shall be piston or ball type joints with steel bodies and
chromium plated steel slips.
3. Joints shall have internal and external guides integral with joint gland and body.
Joints shall be equipped with limit stop.
5. Joint shall allow the addition of new packing while joint is in service under full line
pressure. The packing ram shall be steel, with no shutoff valve.
I. Safety Valves:
1. Sized to State of Iowa Codes and ASME Section VIII Unfired Pressure Vessel
Code.
3. Small safety valves (2-1/2” outlet or smaller) shall be Kunkle Figure 6010 or
equal.
4. Large safety valves (3” outlet or larger) shall be Kunkle Figure 300 or equal.
5. Each safety valve shall have an individual vent pipe to outside. Consult with
FSG-UTILITIES-MECHANICAL DISTRIBUTION on vent pipe size and routing.
6. Safety valve generally not to be hard piped to vent line. All safety valves larger
than 2” shall have cast drip plates (Kunkle Figure 299 or equal) at the base of the
vent pipe, with drain holes piped to a suitable drain.
J. Condensate Pumps:
K. Gauges:
3. Range Selection: 20 psig system gauges shall be 0-30 (psig). Medium pressure
(20-90 psig) gauges shall be 0-100 (psig). 155 psig system gauges shall be 0-
200 (psig).
L. Steam Flow Meters: All buildings have their steam usage monitored by vortex shedding
steam meters.
2. Steam meters shall to be installed in long straight runs of pipe to ensure even
flow.
a. Meters shall be installed with 20 pipe diameters of straight, unobstructed
pipe upstream of the meter, and 10 pipe diameters of straight,
unobstructed pipe downstream of the meter.
b. If the total of 30 pipe diameters absolutely cannot be accommodated,
straightening vanes might be approved by FSG-UTILITIES-
MECHANICAL DISTRIBUTION. When straightening vanes are used,
80% of the available straight pipe shall be upstream of the meter and
20% of the available straight pipe shall be downstream of the meter.
3. The steam meter shall be aligned with the direction of the flow.
4. Meters and associated piping shall be sized to provide steam flow rates of
between 5 and 100 fps. Meters may go upstream or downstream of pressure
reducing valve, depending on pressures and flows. Consult with FSG-
UTILITIES-MECHANICAL DISTRIBUTION if questions arise.
5. The steam meters used are of three different styles, based on the size of the pipe
the meters are used on. Steam metering stations may be installed in 2", 3", 4",
and all larger sized pipe.
a. 2" and 3" steam meters are flanged. Mating flanges to be used are ANSI
Class 300. Flange bolts shall extend through both meter flanges. See
Figure 15251.12.6.1 for installation details.
b. 4" steam meters are a flangeless design. The meter shall be sandwiched
between two ANSI Class 300 flanges. See Figure 15251.12.6.1 for
installation details.
c. Meters to be installed in lines larger than 4" are an insertion type meter.
The pipe shall be prepared with a 2" Thread-O-Let, with a pipe tap of
1-7/8" minimum. There shall be a minimum of 48" head clearance above
the tap to allow for installation and removal of the meter. See Figure
12521.12.6.3 for installation details.
7. All meters shall have isolation and bypass valves as shown on the installation
drawings.
M. Pressure Transmitters:
2. Pressure transmitters shall be installed with a shut-off valve, pigtail, and pressure
gauge as indicated under Section “L.7”.
N. Temperature Transmitters:
O. Burial Selection:
1. Main Services - Walk Tunnels: Steam lines designated as a main campus steam
service by FSG-UTILITIES-MECHANICAL DISTRIBUTION shall be installed only
in walk tunnels for reliability, maintainability and potential to be upgraded. The
main service tunnels shall have room enough to transport any required
replacement parts between the pipe supports, with clearance space for fingers,
heads, and carrying of devices.
a. Tunnel floors shall be positively sloped towards a drain or sump.
b. Tunnels shall be ventilated with supply fans controlled by a thermostat
with an On/Off/Auto switch.
c. Tunnel entrances shall be hinged, spring assisted Bilco doors or
equivalent. Tunnel entrances shall not be placed under roads. Doors
shall be key lockable. Dead bolt locks are not acceptable. No key shall
be required to open door from inside, and exit lever shall be easily
accessible.
d. At tunnel locations where serviceable items are located, tunnel chambers
shall be installed with surface access.
e. Surface access shall allow hands-free upright entrance wherever
possible.
f. All tunnels shall have lights and outlets for the length of the tunnel on
separate circuits.
g. No plastic expansion anchors shall be used in the tunnel, even for
conduit.
h. Emergency lighting is not required. All tunnels entrants are required to
have flashlights.
i. All tunnel entrances shall have aluminum OSHA notice signs stating
“Entry into Utility Tunnels requires approval! Daytime 335-5156/
335-6103; Nights/Weekends 335-5022 (page Mechanical Distribution on-
call person)” mounted just inside the entrance.
Following are our preferences for each type of system. We may be willing to look
at alternate systems that are not discussed below, but would be reluctant to
approve downgraded versions of those discussed. Please note that while all of
these options have their uses, they are not all interchangeable or proper for all
locations or designs. Consult with FSG-UTILITIES-MECHANICAL
DISTRIBUTION for selection of appropriate system.
a. Pre-Insulated Piping: Pre-insulated piping generally consists of a steel
carrier pipe, insulation and an outer casing pipe. The system is pre-
designed by the manufacturer and fabricated off-site. It is assembled in
the field like a jigsaw puzzle. Installation is tolerant of contractor error.
High difficulty of field modification. Usually has a lead time of 8 weeks
after receipt of order.
1) Preferred System: Permapipe Multi-Therm 500 or equal.
Minimum System: Permapipe Escon-A or equal.
2) Acceptable Manufacturers: Permapipe/Ricwil, Rovanco,
Thermacore.
3) Steam and condensate shall be installed in separate casing pipes.
4) Trapping vaults on the system shall be no more than 250 feet
apart. See Section “P” for vault details. Vaults are more than just
locations for traps and expansion joints. They also allow places in
the system for future tie-ins and allow adequate troubleshooting of
system leaks.
5) Provision for pipe expansion shall be made. Expansion joints
(Section “H”) in a vault are the preferred method. If expansion
loops must be used, inform FSG-UTILITIES-MECHANICAL
DISTRIBUTION of the reasons. Expansion loops take up more
ground space, save no money, provide a likely place to start
leaks, and prevent new pipe from being slid into the old casing
without excavation.
6) All wall penetrations shall be sealed with Thunderline Linkseals or
equivalent.
7) Casing pipe shall be air pressure tested.
b. Direct Buried FoamGlas: This consists of a steel carrier pipe with field
applied FoamGlas insulation and a heat sealed protective jacket. Must
be fully designed by project engineer. This system is all field fabricated.
This system is not tolerant of contractor error. This system may also not
be as watertight at wall penetrations.
1) Steam and condensate pipe shall be insulated separately with
adequate thickness Foamglas insulation.
2) Insulation shall be held onto pipe with wire. Outer jacket shall not
be used to hold insulation in place.
3) Outer jacket shall be heat sealed Pittwrap. Standard bituthene or
self-sealing wrap shall not be used. Install jacket per
manufacturer’s instructions.
4) Wall penetrations shall have outer jacket extended through wall
penetration. Urethane foam shall be used to seal between the
jacket and the concrete.
5) Trapping vaults on the system shall be no more than 250 feet
apart. See Section “P” for vault details. Vaults are more than just
locations for traps and expansion joints. They also allow places in
P. Vault Design:
1. All vaults shall be designed with enough room to do the work required.
3. All vaults shall have positive ventilation controlled by a thermostat with On-Off-
Auto option switch..
4. All vaults shall have either a drain to a storm sewer (preferred) or a permanently
installed sump pump and discharge piping.
5. All vaults shall have spring-assisted access doors (Bilco or equal). Manhole
covers are not acceptable. Doors shall be lockable with a key. In vaults, dead
bolts are acceptable.
9. All vault doors shall be sized to allow largest equipment in and out.
11. Power:
a. All vaults shall have at least one outlet and one switched light. Outlet
shall be sized to operate pump and saw-z-all.
12. Drainage:
a. All vaults shall have a gravity drain wherever possible.
b. All vaults shall have a sump hole at low point, ideally near the entrance.
Sump hole shall be 24” in diameter and 24” deep.
13. Ventilation:
a. Cold Hole (a hole in which no high temperature lines are present):
1) A cold hole shall have power and small airflow for humidity control
with freezestat.
b. Hot Hole (a hole in which high temperature lines are present):
1) A hot hole shall have large power flow with a freezestat.
14. All vaults may require two separate openings, or one opening and grate in
Q-door.
16. All wall piping penetrations shall be sealed with link seals.
17. All outside walls shall be waterproofed. Match existing building waterproofing.
19. All vault supports for process piping and equipment shall be stainless steel.
20. All vault supports for maintainable items shall be galvanized or painted.
21. All vault surface drainage shall be routed away from all openings.
23. Power:
a. All vaults shall have a single speed fan with thermostat control fan to
have On-Off-Auto switch in vault.
24. All vault ventilation shall be either in vault or remote louvered penthouses.
25. All vault air ducts to louvered penthouses shall be ductile iron (push joint).
Q. Pipe Support:
1. All portions of pipe stanchions within 12" of concrete shall be 304L stainless
steel.
R. Insulation:
2. Insulation shall not be installed on steam traps and condensate return pumps.
3. At any point in the tunnel where there is an entrance to the tunnel, fan discharge
onto the insulation, or grating openings, there shall be a 0.019 inch stainless
steel jacket installed around all insulated pipes. All seams in the jackets shall be
placed facing downward.
4. If the pipe is held in place with a spider guide that does not have sufficient
clearance to allow at least 3/4” clearance between the insulation and the outer
ring, the following procedures shall be used:
3. The non-asbestos containing insulation shall meet or exceed the standards of the
following brands:
a. Johns Manville - Kaylo T-12
b. Pabco-Cal Temp
c. Manson-Cal-Max
d. Temperlite 1200
e. Owens-Corning Pink
1. All expansion joints shall have removable/reusable insulation covers that cover
the expansion joint from weld to weld. The expansion joint covers are required to
meet or exceed the following:
a. The outer jacket shall be Steamguard 1-Teflon coated Nomex cloth
7 oz./sq. yard x 0.010" thick.
b. The gusset shall be Steamguard 1-Teflon coated Nomex cloth 7 oz./sq.
yard x 0.010" thick.
c. The inter jacket shall be stainless steal crimped mesh.
d. The insulation shall be 2" thick, minimum of 6# density, ceramic wool.
e. The sewing thread shall be 3-ply 304 stainless steel and pure Nomex
thread.
f. The seam fasteners shall be stainless steel lacing hooks.
g. ID tags shall be 304 stainless steel, embossed lettering.
h. All the rest of the hardware shall be 304 stainless steel.
i. Hog ring construction shall not be used.
j. Provisions shall be made for the packing cylinders to ensure snug fit
along the entire expansion joint.
1. All lines in preinsulated piping systems shall have one of the following types of
insulation, based on the manufacturer’s standard.
a. 850 Certainteed fiberglass insulation (or approved equal), mineral wool,
calcium silicate, or Foam-Glas.
b. High Pressure Steam: 3-1/2" thick.
c. Low Pressure Steam: 2-1/2" thick .
d. Condensate: 1” thick.
e. The different insulating values do not affect the thickness of insulation
desired.
System Description:
The Water Plant currently produces soft water and distributes it to the campus through a large
network of piping. The majority of the system is looped, but there are some radial feeds.
Looped systems are preferred for reliability and maintainability. There are also several
connections to the City of Iowa City water lines, used to feed or be fed in emergencies.
Whenever additional water loads are to be applied to the water distribution systems, an
evaluation of the load design requirements and available water distribution facilities and
operational needs of the Water Plant and water distribution systems must be made. It is
requested that the Designer consult with FSG-Utilities-Mechanical Distribution.
A. Water Pipe:
1. Ductile iron piping shall be class 350 restrained joint piping for 18” and smaller.
For 20” and larger pipe, class shall be determined based on pipe laying
conditions.
3. Acceptable Manufacturers: Griffin - Snap Lok, U.S. Pipe – TR Flex, Clow - Super
Lock, or American Pipe.
5. All field cut joints shall be mechanical joint with Megalug series 1100 restraint.
Manufacturer’s field kit shall not be used.
7. Valves 14” and smaller shall be Clow F-6100 resilient wedge gate valve or
approved equal.
9. All pipe shall be laid in a sand bed and shall have at least a 12” sand envelope.
System Description:
Currently, the chilled water distribution system uses the same specifications as the domestic
water system except as noted below:
System Description:
The campus sanitary system collects sanitary sewage from all campus buildings from
connections at manholes. The campus sewers then discharge into the City’s sewer lines at
several places for the final journey to the City sewage plant.
The campus storm sewer system collects storm water and some cooling tower blowdown from
all over campus and directs it to many locations to drain into the Iowa River.
Whenever additional sewage loads are to be added to the sewer collection system, an
evaluation of the load design requirements and available sewer collection facilities must be
made. It is requested that the Designer consult with FSG-Utilities-Mechanical Distribution.
A. Sewer Pipe: Select the appropriate pipe from the choices below. FSG-Utilities-
Mechanical Distribution’s preference is for push joint PVC sewer pipe, but there are
locations where this is not an appropriate choice. Cement sewer pipe shall be used only
where absolutely necessary.
3. Ductile iron pipe with restrained joints. See Section on water piping.
Electronics:
The sensors in the meter station consist of a pressure transmitter, a temperature transmitter,
and a steam flow meter, all provided by FSG-Utilities. The sensors require conduit and wiring to
a central location which will be an existing PLC or a new PLC. The wiring destination and PLC
components that the project needs to cover must be coordinated with FSG-Utilities on a per
case basis. A separate specification covers the wiring and PLC required.