Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
RETAINING STRUCTURES
5.1 Introductory notions. Classification
Retaining structures are construction works for which the main load is
represented by the earth pressure. The aim of a retaining structure is to
support the side of an excavation or a fill or, in the case of cofferdams, to
support the pressure of the water.
According to their destination, retaining structures can be grouped in
temporary works and permanent works.
Temporary works serve to support the sides of excavation in which a
foundation or an underground structure is built or, in the case of cofferdams,
to create an area in which work below water level can be carried out in dry.
Based on the construction system, the temporary retaining works can be
classified as:
- works with recoverable elements (timbering, sheet piling)
- works with non-recoverable elements (diaphragm walls)
Permanent works can be retaining structures above the ground level
(retaining walls, quays etc.) or underground structures (basement walls,
subway lines and stations etc.).
5.2 Timbering
Timbering implies the support of the sides of excavation by timber boards, the
stability being maintained by means of horizontal struts or, in the case of large
excavations, by raking struts or shores.
There are three main variants of timbering:
- timbering with horizontal boards,
- timbering with vertical boards or runners,
- timbering with soldier piles and horizontal laggings.
5.2.1 Timbering with horizontal boards
The use of this kind of temporary support is restricted to soil having a
cohesion large enough to enable the side of the excavation to stand
unsupported for a certain length of time until the elements of the timbering are
put in place. In this category enter firm to stiff cohesive soils.
105
There are three main elements which form this kind of timbering:
horizontal boards,
walings, placed vertically,
struts.
The fig. 5.1 shows the phases of the construction of a timbering using
horizontal boards:
- I: the untimbered excavation is performed, on a depth depending on
the cohesion of the soil;
- II: boards, walings and struts corresponding to the first step of
excavation are put in place; the struts are tightened by cutting them
slightly too long and then driving one end with the other held in
position, until they are at right angles to the waling;
- III: a new untimbered excavation is performed, followed by the
installation of boards, walings and struts.
106
1 vertical pile
Fig. 5.2
Another solution, which has the advantage of improving the working space, is
to use raking struts (fig. 5.3).
1 raking struts
Fig. 5.3
5.2.2 Timbering with vertical boards or runners
This kind of support is used in non-cohesive soils (sands, gravels) and in soft
clays and silts. Unlike the case when horizontal boards are used, in these
ground conditions the timbering is placed in position ahead of the excavation.
Fig. 5.4 shows the phases of the construction of a support using vertical
boards.
- I: On the ground surface a first row of frames is placed, consisting on
guide walings and struts. Timber runners are pitched behind the
walings. The usual dimensions of these boards are 175 mm by 38
mm or 175 mm by 50 mm in lengths up to 4.8m. After driving the
runners at the depth of the first step, wedges are placed between
them and the walings.
107
Fig. 5.5
Another procedure suitable for deep excavation is the one using poling
boards, known also as the marciavante procedure. Construction phases
using marciavante method are shown in fig. 5.6.
- I the first set of bracing frames is put in place, on whose contour
poling boards of 1.5-2 m in length are driven; between them and the
walings of the bracing frames are put wedges;
- II excavation is performed up to a level of 0.3-0.4 m above the tip of
the poling boards; the second set of bracing frames is installed;
between the poling boards and the second set of bracing frames are
placed guiding wedges which will insure the required inclination of
the second set of boards;
- III poling boards of the second set are driven; between them and the
second set of bracing frames are placed wedges; then, phases II
and III are repeated until the final level of excavation is reached.
109
112
Fig. 5.11
Sheet piles are inserted into ground by driving. In order to ease the
penetration and insure the closing of joints, timber sheet piles are sharpened
at the lower end on the groove side (fig. 5.12).
Fig. 5.12
Sheet piles are driven with the tongue in front and the groove sliding in the
tongue of the previously installed sheet piles. Otherwise, the groove could be
stucked with soil grains obstructing the penetration of the sheet pile and
causing the opening of the joint.
To make better use of the driving capacity of the available equipment, in
some situations 2 or 3 timber sheet piles are driven simultaneously, after
joining them by means of clamps (fig. 5.13).
113
1 tongue; 2 groove
Fig. 5.13
In order to avoid the opening of the joints between the sheet piles in case
obstacles are met in the ground, the driving is not done for the entire depth
for each sheet pile but in ladder, observing to keep the difference in level of
the tips of two consecutive sheet piles (or bunches of 2-3 sheet piles) less
than 11.5 m.
Timber sheet piles are manufactured of green wood, because the dry wood in
contact with water would expand, deforming the wall.
The advantages of the timber sheet piles are: easiness in manufacturing;
reduced weight; easy to be installed; low cost. The disadvantages are: limited
length (max. 68 m, from which 3...4 m the embedment; complete
recovering is practically not possible; cannot be driven deeply into dense
granular soils or stiff clays without risk of splitting.
5.3.2 Steel sheet piles
Steel sheet piles are used when deep penetration or penetration in hard soils
are required. There are many types of rolled steel sections available for sheet
piles, which differ among them by the shape and by their interlocking
sections. The most common types are:
U type of steel sheet piles, at which joints are placed along the wall
axis at each intersection of the axis with the profile (fig. 9.16a);
S type of steel sheet piles, at which joints are also along the wall axis
but at every second intersection with the profile (fig. 9.16b);
Z type of steel sheet piles, at which joints are placed outside the wall
axis, alternating from one side to the other (fig. 9.16c).
At equal mass and identical disposition of the material against the vertical
plane, sheet pile walls made of the three types of sections (profiles) have
different stiffnesses, as a result of the position of joints. Thus, at the U type
of walls, the principal axis x ' x ' of each element is parallel to the axis x-x of
the wall. Slight relative rotations of the sheet piles under the pressure normal
to the x-x axis are possible, hence the real stiffness, considering the
interlocking, should be diminished. When stresses in the wall are checked,
one should consider in this case w x 0.75 w x , where wx is the resistance
modulus against the x-x axis and w x is the reduced resistance modulus,
considering the joints. At the S-type of walls, the principal axes x ' x ' of each
element are parallel among them but inclined in respect to the axis x-x of the
wall. The possibilities of rotations are smaller than in the first case and
w x 0.85 w x . At the Z-type of walls, the principal axes x ' x ' of adjacent
sheet piles are normal one to the other, the rotation tendencies of the
adjacent sheet piles are cancelling; in this case w x 1.0 w x .
There is a great diversity of interlocking sections (fig. 5.17). The joints or
interlocking sections must be strong enough to support the tensile stresses
occurring in exploitation, must be watertight and must insure an easy
penetration and extraction of the sheet piles.
Steel sheet piles can reach lengths up to 30 m.
Fig. 5.17
5.3.3 Reinforced concrete sheet piles
Reinforced concrete sheet piles are precast elements, of square or
rectangular cross-section, with sides of max. 5060 cm and thicknesses of
1050 cm. Their length is limited to 1820 m, because of the large weight
which would make the driving very difficult or impossible.
The interlocking system can be similar to the one used at timber sheet piles.
In fig. 5.18 a is shown a reinforced concrete sheet pile having a tongue and
groove type of joint. In order to reduce the friction during the driving process,
the tongue is provided only in the lower third of the sheet pile, in the upper
116
part there are two grooves. The gap between grooves is filled with jute and
mortar (fig. 9.18b).
Fig. 5.18
9.4 Embedded walls
Embedded walls made of reinforced concrete are intensively used as
retaining structures for deep excavations, particularly in urban, congested
areas. Unlike sheet piles walls, embedded walls made of reinforced concrete
cannot be recovered and reused.
From the constructive point of view, embedded walls can be formed by bored
piles or by panels.
5.4.1 Embedded walls made of bored piles
There are two types of pile walls:
- secant pile walls
- contiguous pile walls
Secant pile walls are of two kinds:
- hard/hard secant pile walls
- hard/soft secant pile walls.
Hard/hard secant pile walls consist of overlapping concrete bored piles. The
secant pile wall is constructed in two stages (fig. 9.19). All piles constructed
during stage 1, defined as primary piles, are spaced at specified spacing. All
piles constructed during stage 2, defined as secondary piles, are positioned
between the primary piles and secant with the primary piles.
Fig. 5.19
117
Guide walls are placed at the ground surface to ensure the designed position
and the verticality of each pile.
Fig. 5.20
Usually, only the secondary piles are reinforced (fig. 9.20). However, primary
piles can also be reinforced with reinforcing cages of rectangular shape or
with steel sections (fig. 5.21a,b).
If proper construction is insured, hard/hard secant pile walls offer a high water
tightness.
Hard/soft secant pile walls (fig. 5.22) are constructed in a similar way as the
hard/hard secant pile walls. The difference is that primary piles are formed of
a low strength cement/bentonite mix, where bentonite is an active clay rich in
montmorillonite.
This kind of walls are used when the conditions for watertightness are less
severe.
Fig. 5.21
Fig. 5.22
Contiguous pile walls
118
When the wall is not required to retain water, contiguous bored piles are used
(fig. 5.23). The piles are constructed at centres equal to the pile diameter plus
an allowance for temporary casing width and tolerance which can vary
between 70 and 150 mm. Guide walls may be used at ground level to ensure
positional tolerance.
Fig. 5.23
5.4.2 Embedded walls made of panels
Embedded walls made of panels will be named in what follow as diaphragm
walls.
Panels are rectangular trenches with lengths depending on the excavation
equipment and on the position within the wall.
The common feature of all types of diaphragm walls is that the excavation of
the trench is made under the protection of a supporting fluid or slurry. This is
a clay suspension of 1.031.10 g/cm3 density, formed by mixing water with
bentonite. Additives are also used to improve the flow characteristics of the
fluid and the gelling or blocking action of the fluid. The clay suspension
infiltrates through the sides and the bottom of the trench, filling on a certain
distance the pores of the soil. Through this layer of soil with low permeability
only water can pass, while clay particles are accumulating at the face of the
layer forming a shield called cake. The layer of soil enriched in clay together
with the cake form a screen. The presence of this screen and of the pressure
exerted by the suspension on the sides of the trench ensure the stability of
the walls if the required properties of the suspension are met, such as the
density, viscosity, shear strength, pH, sand content etc.
The corresponding tests and compliance values are specified in various
codes.
Based on the criterion of the material met in a vertical section and of the role
played by the wall, embedded walls made of panels (diaphragm walls) can be
divided into two categories:
- homogeneous walls
119
- composite walls
Homogenous walls are diaphragm walls at which both the material used and
the role played are unchanged along the same vertical.
In function of the material, homogeneous walls are classified in:
- cast in situ concrete diaphragm walls
- precast concrete diaphragm walls
Composite walls are diaphragm walls at which the functions of strength and
water tightness are separated on the vertical.
Cast in situ concrete diaphragm walls
The basic sequences of the construction of a panel are:
I. construction of guide-walls
II. excavation, with a bentonite suspension
III. placing the reinforcement
IV. concreting
V. trimming
A distinct phase is represented by forming the joints. Its position between
the above specified basic sequences depends on the type of installation used
for excavating the trench.
I.
120
Fig. 5.24
II.
Excavation of panels
- Excavation with the Kelly-type installations. The characteristic
feature of these installations, which are attached to an existing
equipment (such as a crane or excavator) is the presence of a heavy
rod named kelly having at its end a hydraulically operated grab. In
fig. 5.25 is shown a kelly-type installation, equipped with a
hydraulic grab made in Romania. The grab has two jaws which are
opened and closed by means of hydraulic jacks. The lifting and the
lowering of the kelly is done by cables. For the excavation, the grab
with open jaws is brought above the guide-walls and is inserted
slowly in the trench to avoid waves of the slurry which could affect
the walls. Under its own weight and the weight of the kelly, the grab
is let to fall from a height of 13 m above the bottom and penetrates
in the soil. Loaded with soil, the grab is then lifted above the guidewall and, after a rotation of the excavator (or crane), is discharged in
a truck. During the excavation, the level of the supporting fluid is kept
permanently 0.51.0 m below the ground level, but at least 1.0 m
above the groundwater table. Samples are taken periodically from
the slurry and tested in the laboratory at the construction site to
determine the properties of the suspension, which are checked
against the required ones, to ensure that the suspension does not
become excessively diluted or contaminated by soil particles.
for doing so is the following: during the excavation, the stability of the
installation, whose center of gravity is high due to the very long kelly, is
ensured by the reaction opposed by the soil encountered by the jaw of the
grab; if this reaction is not uniform, there is a risk for the installation to rotate
and overturn; if the shafts would have been excavated in sequence, one of
the jaw would rest on the ground while the other would enter in the shaft
previously excavated and filled with slurry, situation which should be avoided.
Fig. 5.26
122
Panels are reinforced with reinforcement cages which include vertical and
horizontal bars, forming two parallel nets linked with stirrups and inclined bars
(fig. 5.29). Each cage is provided also with suspension and lifting bars,
124
bracing bars to improve the stiffness for the handling operations and spacers,
usually made of rollers, to ensure that the correct concrete cover is
maintained. On the vertical, the cage can be made of one piece or of several
pieces assembled by welding as the cage is lowered in the trench. When two
cages are installed in horizontal direction, the minimum distance between
them shall be 200 mm.
Concreting
When starting concerting, the supporting fluid and the concrete in the
concreting pipe shall be kept separate by a plug of material of by other
suitable means. To start concreting, the concreting pipe shall be lowered to
the bottom of the trench and then raised approximately 1 m. After concreting
has started, the concreting pipe shall always remain immersed in the fresh
concrete. The minimum immersion should be 2 m.
Since the top of the cast concrete is contaminated because of the contact
with the slurry and may not be of the required quality, sufficient concrete shall
be placed in the panel to ensure that the concrete below the cut-off level pass
the specified properties. This is achieved by providing an additional height of
concrete above the cut-off level.
Fig. 5.30 shows the operations of placing of the reinforcement cages in the
trench and of the concreting of a panel.
Trimming
The steel stop ends are steel tubes with a diameter equal to the width of the
trench which are introduced in vertical position at the ends of a panel,
penetrating 0.51.0 m below the bottom of the trench in order to have
ensured the stability. The tubes are lowered into the trench with cranes and
extracted by use of hydraulic jacks. In the case of stop ends which are
extracted vertically, it is essential to define the optimum time for starting this
operation. If the tube is extracted too soon, the fresh concrete behind the tube
will flow in the space left by the tube. If, on the contrary, the extraction is done
too late, the tube can be sticked to the concrete and the recovering becomes
impossible. In order to avoid sticking, small rotations should be applied to the
tube before commencing the extraction and then the extraction should be
made gradually during the setting of the concrete. Usually, the extraction
starts 46 hours after the concreting is finished. A method to prevent the
contact between the concrete and the tube is to provide at the extremity of
the reinforcement cage a shield made of thin steel plate, on the entire depth
of the trench. In the case of tubes which are extracted laterally, the extraction
shall be made upon the completion of the excavation of the adjacent panel.
Instead of recoverable steel tubes, non-recoverable precast elements can be
used as stop ends (fig. 5.31).
Fig. 5.31
In the case of using E.L.S.E. installations for the excavation of the trench, the
joints are formed by cutting into the concrete of the previously cast adjacent
panel. Cutting is done by the teeth of the excavating tool (fig. 9.32).
In special cases, water stops can be incorporated into the joints.
Phases of the construction of a cast in situ diaphragm wall made of panels
The wall is made by a number of panels. The panels disposition, their
dimensions in plane, the construction sequence, are established in the
design, taking into account the peculiarities of the job, the excavating
installations etc.
127
129
130
Fig. 5.37
The phases of the construction of a diaphragm wall made of precast concrete
are:
- I - excavation of the trench; this is usually done under a bentonite
suspension but, with a carefully prepared slurry, can be done also directly
under a self-hardening slurry;
- I bis - when excavation is made under bentonite suspension, after
completing the excavation the bentonite suspension is replaced by the selfhardening slurry using the tremie pipes, as in the case of concreting;
- II - lowering into the self-hardening slurry of the precast elements.
When the excavation under the protection of the wall is performed, the
hardened slurry on the exposed face of the wall is trimmed.
The characteristic feature of the diaphragm walls made of precast concrete is
the use of self-hardening slurries.
A self-hardening slurry is a bentonite suspension in which a certain amount of
cement and additives are added. The self-hardening slurry is setting and then
hardening, like a plastic mortar, in the excavated trench, producing a firm
binding between the precast element and the surrounding soil and closing the
joints between the elements.
The receipt of the self-hardening slurry is established by laboratory tests.
Requirements are different in the case when the slurry is used also as a
supporting fluid in the excavation phase, as compared to the slurry which is
replacing a bentonite suspension.
The retarder additive should ensure the starting of the setting after the
lowering of the precast elements into the slurry. After that, the hardening
process should be quick enough, in order to ensure a good binding between
the precast elements and the soil.
Composite walls
The self-hardening slurry is widely used in the case of composite walls.
Indeed, in the lower part of a wall for which only the water tightness is
131
132
Fig. 5.39
Fig. 5.39 shows the main stages for the construction of an underground
structure (for instance a subway gallery):
- construction of the embedded walls;
- first excavation phase of excavation;
- placement of the first row of struts;
- second phase of excavation;
- placement of the second row of struts;
- third phase of excavation;
- placement of the third row of struts;
- concreting the base of the gallery;
- after the hardening of the concrete in the base of the gallery,
dismantling the lower row of struts;
- concreting the walls and the slab of the gallery;
- after the hardening of the concrete in the gallery, dismantling the
intermediate row of struts;
- gradual filling of the space above the gallery, including the
dismantling of the upper row of struts.
Embedded walls for underground structures constructed with the top - down
method
This method is sometimes called Milanese method, since it was first applied
at the construction of the Milano subway. It consists in construction from the
beginning, near the ground surface, a reinforced concrete slab connected to
the embedded walls, in which holes are left for the access of people and
equipments and evacuation of the excavated soil. The excavation takes place
under this roof. The advantage of the method is the possibility to resume
activities at the ground surface (car traffic etc.) before completing the
133
underground structure. When the span between the embedded walls is large,
intermediate supports for the slab can be built, represented by steel columns
founded on barrettes, which are cast in situ reinforced concrete blocks,
constructed with the same technique as the cast in situ diaphragm walls.
Fig. 5.41
135
b
Fig. 5.42
Fig. 5.43
136
The analysis of the vertical boards is done as for simply supported beams of
span l1, the distance between two consecutive walings or the vertical distance
between struts. For a width b of the board, the load per unit length on the
board is:
q p aH b 0,65 H tan 2 ( 45
)b
2
(5.1)
The bending moment in the board is:
M
q l12
8
(5.2)
8 all
W bd2
6
(5.3)
where all is the allowable strength for the material in the board and d is the
thickness of the board, which will result from the relation (5.3).
The analysis of the walings is done as for simply supported beams of span l 2,
the horizontal distance between struts. The waling takes the reaction from
boards pertinent to a field l1. The load per unit length of the waling is:
q1 p aH l1
(5.4)
(5.5)
M1
M1
all
W1 ef 2
6
(5.6)
From the relation (5.6) is determined f.
137
(5.7)
To check the struts in compression the relation (5.8) is used:
II
N
w all II
A
(5.8)
where
timber
all
N
all
A
(5.9)
Usually, timbering are using fir or pine, for which the following values of the
allowable strengths can be used:
- for bending all = 120 daN/cm2
- for compression along the fibres ac II = 120 daN/cm2
- for compression normal to the fibres ac = 18 daN/cm2
If instead timber, steel elements are used, in the design relations previously
given, appropriate values for all and w should be introduced.
5.5.3 Analysis of sheet pile walls and embedded walls
Sheet pile walls and embedded walls can be grouped, based on the criterion
of the statical system, in two categories:
- walls forming statically determined systems (cantilever walls;
anchored or propped walls with one level of anchor or prop in the
upper part and free earth support at the bottom);
- walls forming statically undetermined systems (walls with one level of
anchor or prop in the upper part and fixed earth support at the
138
bottom; walls with two or more levels of anchor or prop in the upper
part and free or fixed earth support at the bottom).
The analysis of the sheet pile walls and embedded walls has two objectives:
- to determine the depth of penetration of the wall in the soil, taking
into consideration various failure modes;
- to determine the structural design of the wall to resist bending
moments, shear forces and prop or anchor forces derived from
equilibrium calculations.
In fig. 5.44 are shown various kinds of failure for these walls.
In what follows, several types of walls pertaining to the two categories will be
considered.
Fig. 5.44
a. Cantilever walls
These walls are free at the upper part and derive their equilibrium from the
lower, embedded part of wall. Two situations can occur:
- wall acted upon by a horizontal force H;
- wall retaining soil of a height h.
In the first case, the load can be, for instance, the resultant of the pressure
exerted by water on the free upper part of the wall (fig. 9.45 a). Subjected to
the force H, piles bends and rotates. If the deformations by bending are
disregarded, the wall can be treated as an infinitely stiff plate rotating around
a point O (fig. 9.45 b). On the front face of the wall, above the point O, the
139
K p tan 2 (45 o );
2
K a tan 2 ( 45 o )
2
Fig. 5.45
Fig. 5.46
By computing along the embedment t the difference between the passive and
active earth pressure, a resultant diagram is obtained (fig. 5.46 a), with
ordinates limited on both faces by two lines of (K p K a ) inclination.
The diagram thus obtained is physically not possible, since there are two
pressures in the same point O. In reality, the transition from the left to the
right part of the pressure diagram cannot be done by a jump like in the fig.
9.45.a, but gradually, along a curve passing through the point O (fig. 5.46 b)
and which can be approximated by a line (fig. 5.46 c).
140
The stability of the wall is insured by the couple of forces E p and E 'p ,
representing the resultants of passive pressures developed on the two sides
of the wall is in equilibrium with the overturning moment produced by the
force H.
In order to find the embedment t required for insuring the stability, two
methods can be used:
- in the first method, the final diagram in fig. 5.45 c is used, involving
three unknowns: t, d and e, for which only two equilibrium equations
are available, the horizontal forces equation and the moment
equation. A trial and error approach is then used.
- an embedment depth t is proposed;
- the two equilibrium equations are written:
X0
(5.10 a)
Mc 0
(5.10 b)
Equation (5.10 a) represents the horizontal projections of horizontal forces,
while equation (5.10 b) expresses that the moment about point C is zero.
- the system of equations is solved, to find the unknowns d and e;
- the computation is repeated for a new value of t, until the following
condition is fulfilled:
e
f
FS
(5.11)
t
1
( K p K a ) t o2 o 0
2
3
(5.12)
Equation (5.12) leads to the following equation:
t3
o 6
H
H
to 6
h 0
(K p K a )
(K p K a )
(5.13)
141
The solution of eq (9.13) is obtained by trials in order to obtain t o. For the first
trial, values of the ratio to/h in function of given in the table 9.1 can be
used.
Table 5.1
to/h
20
1.6
25
1.2
30
0.9
35
0.7
40
0.5
(5.13)
In order to find the maximum bending moment, the pressure diagram used for
the computation of t is taken (fig. 5.45 c or fig. 5.46 a) and the depth zo at
which the shear force is zero, corresponding to M max, is found. For instance,
when the diagram in fig. (5.47 a) is applied:
H
zo
1 2
z o (K p K a ) 0
2
(5.14)
2H
(K p K a )
M max H ( h z o )
(5.15)
1
( K p K a ) z o2
2
(5.16)
Fig. 5.47
In the case of the cantilever wall retaining a soil of height h, the approach is
similar as in the previous case, with the difference that the horizontal action is
produced by the active earth pressure (fig. 5.48). The corresponding
diagrams are given in fig. 5.49 a, fig. 5.49 b and fig. 5.49 c. The bending
moment diagram is shown in fig. 5.50.
142
Fig. 5.48
Fig. 5.49
Fig. 5.50
b. Walls with one level of anchor or prop in the upper part and free earth
support at the bottom
When the cantilever wall cannot take the loads or when the ground conditions
do not allow to obtain the embedment required by the fixed-end condition, an
additional support is provided in the upper part of the wall by means of an
anchor (fig. 5.51 a) or prop (fig. 5.51 b). The second support is represented
by the embedment depth t, as a free earth support.
143
Fig. 5.51
Fig. 5.52
It is assumed that by the elastic displacement of the prop or anchor and by
the rotation of the wall around the base, conditions for development of
passive earth pressure in front of the wall are met. The two pressure
diagrams can be drawn (fig. 5.52). The problem is statically determined, there
are two unknowns (the embedment depth and the load in the strut or anchor
RA) and two available equilibrium equations ( X 0, M A 0) . A factor of
safety FS of 1.52 can be introduced by dividing the passive pressure force
to FS.
144
Fig. 5.53
Field measurements have shown that the real active earth pressure diagram
is different from the diagram with linear distribution resulting from the
Rankines theory. As a result of the bending of the wall and of an arching
effect, a redistribution of the pressures is occurring, leading to a overloading
of the supports and to a discharge of the field (fig. 5.53). To take into account
this effect, a coefficient of reduction of the maximum bending moment
corresponding to the triangular diagram is introduced. The German Code
EAU 77 recommends to take 0.67 Mmax.
c. Walls with one level of support in the upper part and fixed earth
support at the bottom
Unlike the previous case, the point of rotation is located above the base, the
wall changes in curvature within the embedment depth, leading to the
development of passive resistance on both sides of the penetration depth (fig.
5.54). The pressure diagram is constructed as in the case of the cantilever
wall (fig. 5.43 c). The theoretical diagram can be replaced by the design
diagram in fig. 9.55 and the embedment depth t by the reduced depth to.
Fig. 5.54
145
Fig. 5.55
An approximate method which can be used in this case is named the
method of replacing beam. It is considered known the depth y of the inflexion
point of the deformed shape of the wall. Thus, for 20 o , y = 0.25 h and for
30 o , y = 0.08 h, where h is the height above the excavation level. Taking
the inflexion point as a hinge, the wall is divided into two simply supported
beams: BC and CD. The equilibrium equation for the upper beam BC leads to
the reaction at the level of the strut or anchor R A and the reaction in the
support C, RC. To obtain the value of to, the condition of moment O in the point
D is written for the lower beam CD. Then, t is taken as: (1.201.25)to.
5.5.4 Solutions for the support in the upper part of embedded walls
From the point of view of the support in the upper part, embedded walls can
be classified in two categories:
propped walls, where the support is provided by struts (fig. 5.51 b)
anchored walls, where the support is provided by several means,
such as:
- tendons or tie rods transferring the load to a steel or reinforced
concrete plate or to a concrete block called deadman (fig. 5.51 a);
- tendons or ties transferring the load to a group of raking piles, from
which one pile works in tension T, the other in compression C (fig.
5.56 a);
- anchor piles (fig. 5.56 b);
- ground anchors (fig. 5.56 c).
The deadman may be formed of isolated elements (fig. 9.57a) or by a
continuous plate (fig. 9.57b).
Fig. 5.56
146
Fig. 5.57
The stability of the deadman is insured by the passive resistance of the soil in
front of the plate or block (fig. 9.58). The stability condition is:
R A Pa
Pp
FS
(5.17)
where Pa and Pp are the active and passive forces and F S a factor of safety
which can be taken 1.5.
Pa
1
1
d 2 l K a e d l K a d l K a ( d e);
2
2
Pp
1
1
d 2 l K p e d l K p d l K p ( d e);
2
2
(5.18)
(5.19)
where l is the distance between tendons;
d height of the deadman;
e distance from the upper edge of the deadman to the ground level.
Relations (5.18) and (5.19) are used in the case of continuous plates and in
the case of isolated plates of width b, when l 2 b , and for e 4 d .
As for the position of the deadman, the following procedure is used (fig. 9.58):
from the bottom of the wall (in the case of free earth support) or from the point
of inflexion at the depth y (in the case of fixed earth support) the failure plane
should not interfere with the active soil zone behind the retaining wall.
Fig. 5.58
5.6 Ground anchors
A ground anchor is an installation capable of transmitting an applied tensile
load to a load bearing stratum.
Ground anchors can be permanent, when required to ensure the stability and
satisfactory service performance of the permanent structure or excavation
being supported or temporary, when used during the construction phase of a
project to whitstand forces for a known short period of time, usually less than
2 years.
Fig. 5.59 shows several examples of permanent structures using ground
anchors: a retaining wall (fig. 5.59 a), a high rise building with a multiple-level
basement, founded below the water table and subjected to uplift forces of the
water (fig. 5.59 b), a tower for an electrical line (fig. 5.59 c).
148
Fig. 5.59
Examples of temporary ground anchors are given in the fig. 5.60.
Fig. 5.60
A ground anchor consists basically of an anchor head, free anchor length and
fixed anchor.
Fig. 5.61 shows a typical ground anchor.
Fig. 5.61
The main phases in the construction of a ground anchor are:
1 boring of a borehole
Special equipments are used, able to bore holes at any inclination; the kind of
boring (cased or uncased; under a slurry etc.) as well as the boring tool are
adapted in function of the ground conditions.
2 introduction in the borehole of a tendon
149
Tendons usually consist of steel bar, strand or wire, either singly or in groups.
3 grouting
The most common grouts used for ground anchors are cemetious grouts
which usually are water/cement mixes, with a ratio lying in the range of 0.35
to 0.60. Admixtures to improve the properties of the grout, such as the
workability or durability, or to increase the rate of strength development are
sometimes used.
The main functions of the groutings are:
- to form the fixed anchor length (L fixed), which is the designed length of
the anchorage over which the tensile load is capable of being
transmitted to the surrounding ground;
- to reinforce the ground in the close vicinity of the fixed length, in
order to increase the capacity of the anchor;
- to increase the watertightness of the ground in the close vicinity of
the fixed length in order to reduce the losses of the grout.
Grouting is usually made through a grouting tube; the separation between the
fixed anchor length and the free anchor length is made by using a device
called packer, which is an expandable rubber ring surrounding the grouting
tube.
4 stressing
Stressing is required to fulfill the following two functions:
- to ascertain and record the load carrying behavior of the anchor;
- to tension the tendon and to anchor it at its lock-off load.
Stressing equipment is similar to the one used for prestressed concrete
elements.
Stressing should not be carried out until a sufficient hardening of the grout in
the fixed length has been achieved, which normally requires seven days.
The component of the ground anchor which transmits the tensile load from
tendon to bearing plate or structure is called anchor head.
A special problem is the corrosion protection.
All steel components which are stressed (tendon bond length, tendon free
length, anchor head) shall be protected against corrosion for their design life
(less than two years for temporary ground anchors, more than two years for
permanent ground anchors).
150
151
Fig. 5.62
As a rule, the passive force Pp, whose development requires, as shown in the
chapter 8, large displacements, is disregarded.
In the fig. 5.62 are also given recommendations for a preliminary selection of
the dimensions of the wall.
In fig. 5.63 are shown other forms of mass concrete walls.
Fig. 5.63
A filter of coarse permeable material is desirable behind a retaining wall to
prevent the development of high pore water pressures within the backfill. To
allow the water to percolating into the filter to drain out, weep-holes are
provided in the wall (fig. 5.64).
152
Fig. 5.64
The design of the wall has three aspects:
- structural design
Normally mass concrete walls should be designed on a no-tension basis
under the design earth pressure. At least two sections should be checked (fig.
9.62):
p max
min
N M N
M
N
6e
(1 )
A W B 1 1 B 2 B
B
6
(5.20)
where N is the total normal force on the base and e =
M
N
N = Pav + G
(5.21)
p med p all
(5.22)
(5.23)
p min 0
(5.24)
Relation (9.24) expresses the condition that the resultant of forces P a and W
is located within the middle third of the base ( e B 6 ).
- stability checks
Stability against sliding
The friction force S on the base (the component along the base of the
reaction R) is compared with the horizontal component P ah of the active earth
thrust. The friction force S is equal to the normal force N multiplied by the
friction coefficient between the base and the ground.
Pah m l N
(5.25)
where ml is a factor of safety equal to 0.8.
When values for obtained by field tests are lacking, values given in tab. 5.2
can be used, at least for a preliminary design.
Clays:
- Ic< 0.75
0.25
- Ic 0.75
0.30
Sandy clays and clayey
0.30
sands
Fine, silty sands
0.40
Coarse sand, gravels
0.50
Rocks
0.60
154
(5.26)
(5.27)
a being the arm of the force Pa in respect to the toe of the wall D
MS is the stability moment
MS = G d
(5.28)
Fig. 5.65
5.7.1.2 Gabions
Gabions are large cages or baskets usually of steel wire or square welded
mesh, rectangular in shape, filled with stone and used as gravity retaining
walls or anti-erosion works (fig. 5.66).
155
The permeability and flexibility of gabions make them suitable where the
retained material is likely to be saturated and the bearing quality of the soil is
poor.
Fig. 5.66
Gabion walls are designed on the same principle as a gravity mass wall. In
fig. 5.67 are given examples of gabion retaining walls. The density of the
stone fill can be taken as 60% of the solid material.
Fig. 5.67
5.7.1.3 Crib walls
Crib walls are built of individual units assembled to create a series of box-like
structures containing granular free draining fill, to form a gravity retaining wall.
156
The units should be so spaced, that the fill material contained within the crib
is not affected by climatic changes and acts in conjunction with the crib work
to support the retained earth.
The individual units can be made of timber or of precast concrete.
In fig. 5.68 is shown an example of assembling the individual units. In fig.
5.69 is given a vertical section on a crib wall.
Fig. 5.68
Fig. 5.69
This kind of gravity walls is indicated for use on compressible soils having the
ability to adapt to differential settlements.
5.7.2 Reinforced concrete walls
5.7.2.1 Cantilever walls
157
Fig. 5.70
The advantage of this wall is the use of the weight of the retained material,
resting on the base slab, together with the weight of the wall, in order to
ensure the stability against sliding and against overturning. Various structural
elements such as the slabs AB, BC and DE, working as cantilevers, are
designed to resist bending.
For the stability checks of a cantilever wall, the active earth pressure should
be defined. There are two approaches to compute the earth pressure:
- on the polygonal surface AFCD, in which FC represents the failure
surface with an angle
-
45 o
158
Fig. 5.71
5.8 Reinforced earth
The idea of using the soil itself for structures aimed to resist to the active
earth pressure, appeared in the construction of crib walls, gabions, cantilever
or counterfort walls, is best expressed by the reinforced earth, a system
patented by the French engineer Henri Vidal and introduced in practice in the
years 60s of the 20th century.
A compacted soil mass is stabilized as a result of frictional forces developed
between the soil and the tensile reinforcing elements, usually in the form of
horizontal strips made preferably of galvanized steel, but also of aluminium
alloys, plastic or geotextiles. The stresses within the soil mass are transferred
to the elements which are thereby placed in tension. The soil used as the fill
material should be predominately coarse-grained and be adequately drained
to prevent it from becoming saturated.
A reinforced earth retaining structure should be made in such a way that
several basic conditions are fulfilled: the facing should resist to the earth
pressure and be sufficiently flexible to withstand any deformation of the fill;
the length L of the strips should be long enough in order to ensure, by the
friction developed on the top and bottom surface of each strip in contact with
the soil, the stability of the structure; reinforcing elements should be able to
carry out the tensile stresses.
The facing is attached to the reinforcing elements to prevent the soil from
spilling out and to satisfy aesthetic requirements. Two of the most used
solutions are the facing consisting of precast concrete units (fig. 9.72 a) or of
pliant U shaped steel sections arranged horizontally (fig. 9.72 b).
In what follows, a simplified method of analysis is presented.
159
b
Fig. 5.72
(5.29)
where K is the appropriate earth pressure coefficient at depth z.
The frictional resistance available on the surfaces of the element is given by:
F 2 L B Y z tan
(5.30)
where L is the length of the element, b is the width of the element, the
angle of friction between soil and element.
In order to obtain the minimum length of the element, L min, which is the length
of the element beyond the failure surface AC (fig. 9.72), P should be
multiplied by a factor of safety FS which should not be less than 2.
FS P F
FS K z d H 2 L min B z tan
F K d H
L min S
2 b tan
(5.31)
From the relation (9.31) results that Lmin is constant and independent of z.
160
The thickness of the element is obtained knowing the tensile force P and the
width b, from the condition of tensile resistance of the material. The thickness
of the facing is determined in function of P, H , d and the strength
characteristics of the material used for facing.
The anchoring length Lmin should be ensured outside the failure surface AC,
where the shear stresses on the surfaces of the element are acting in wards
(fig. 9.73). Sometimes, in order to facilitate the construction process, instead
of a linear variation with depth of the length, a step-wise variation can be
adopted (fig. 9.73 b).
Fig. 5.73
When the fill is made of granular material, displacements of the wall are
sufficient to develop the active limit state condition and K in relations (5.29)
and (5.31) can be taken as Ka.
For a preliminary design, the following values can be used: d = 0.7 m; H =
0.250.30 m; b = 75 mm.
In the design of the earth reinforced earth structure, the external stability must
also be considered.
Although behaving as a relatively flexible structure, a reinforced earth
structure should be designed, from the point of view of external stability, as if
it were a gravity wall. The back of the wall should be taken as the vertical
plane through the inner end of the lowest reinforcing element. The total active
thrust on this plane is calculated by the Rankine theory. The factor of safety
against sliding between the reinforced fill and the foundation soil should not
be less than 2. The pressure distribution on the base must be wholly
compressive and fulfill conditions (5.225.24) as for a gravity wall.
161
Fig. 5.74
The soil for the construction of the earth dike should fulfill some requirements:
to ensure watertightness, to be compactable, to avoid being easily eroded by
the water flow. Clayey sands with about 25% clay fraction meet these
requirements. But even dikes made of sand could be a reliable solution,
counting on a watertightness reached in short time, as a result of the filling of
the voids by the fine particles carried by the water. When the dike is
constructed on the land or in dry in periods of low waters, clay can be also
162
used, if excavated in dry form, spread and compacted in thin layers. The clay
fill should not be used for the construction of dikes by discharge under water,
since the soil is softening and forming an unstable fill.
At flow rates larger than 0.1 m/s, slopes of the dikes should be protected to
prevent erosion.
5.9.1.2 Rock fill dikes
Rock fill dikes, made of large blocks of stone, have the advantage of steeper
slopes in comparison with the earth dikes and of resisting better to erosion
forces caused by the water flow. Instead, they are permeable and require
special measures to ensure watertightness, such as concrete cores (fig. 5.75
a) or clay cores (fig. 5.75 b), when the construction of the dike is made in dry,
or sheet pile walls (fig. 5.75 c), when dike is built in water. In all cases, the
watertight element should penetrate into an impervious layer of soil.
Fig. 5.75
5.9.2 Sheet piles cofferdams
5.9.2.1 Single skin cofferdams
These are formed by one-line timber or steel piles, working as cantilever walls
(fig. 5.76 a) or as walls with free earth support and raking struts (fig. 5.76 b),
when ground conditions do not allow to drive the sheet piles to a depth
required in a fixed-end support.
Fig. 5.76
163
Other means to ensure the stability of the single skin cofferdams are
represented by earth fills placed in front of the wall (fig. 5.77 a) or on both
sides of the wall (fig. 5.77 b).
Fig. 5.77
5.9.2.2 Earth-filled double-wall cofferdams
Double-wall cofferdams consist of two parallel lines of steel piling connected
together by a system of steel walings and tie rods. The space between the
lines of piling is filled with coarse cohesionless materials such as sand, gravel
or broken rock.
The width b of the cofferdam should be not less than 0.8 of the retained
height h of water (fig. 5.78). The penetration of the piling into the soil below
the bottom of the river should be sufficient to develop the necessary passive
resistance and prevent horizontal sliding of the cofferdam as a gravity
structure.
Fig. 5.78
A major disadvantage of double-wall cofferdams is that if failure takes place in
a certain point, it will propagate on a relatively large distance along the wall.
5.9.2.3 Cellular cofferdams
164
Fig. 5.79
In fig. 5.79a is shown one of the most utilized type of cellular cofferdam, with
circular diaphragm cells. The main advantage of this type is that each cell is a
self-supporting unit, which means that the loss of stability of one cell does not
imply the progressive failure of the entire wall. Also, each cell can be filled
independently of adjacent cells. Circular diaphragm cells can be constructed
in rough and flowing water of maximum velocity about 1.3 m/s, and at large
depths of water, reaching 2025 m.
A good example of the use in Romania of this kind of cellular cofferdam is
represented by the works at the navigation and hydro energetic system at the
Iron Gates, on the Danube (fig. 5.80).
165
Fig. 5.80
166