Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
~
1
:;:::
~-------
r'
..
...
-------
:
l
.
_ .._,--------- ,_..,--_.
-_. --
SAFETY
--'~~~-.-- ~~~A~$PEC T SO F--.. . . . . -~.
MAINTENANCE
I:
_ ...
__ ..
,;
;~
,
J
;
~.-
"
,I .
L,
,I'
L
r
!
,
i
,!
i
SffETY ASPECTS OF NAINTENANCE
by
.-.~
.. _-- -._--.
!
Dr. H. Farabi
Depdrtment of Chemical Engineering
The! University of the West Indies
st. Augustine
- ---._-
"--'-
r
the. maintenance act illi i,es may .bea,. hazard foCtile personnel
~
illvo I vecC::-'=:"'--:'-:- -
in them.
It is necessary,~therefore, to exercise careful control of
maintenance work in order to eliminate hazards to the plant and to
j
the personnel.
,
.r
i
I
- 2 -
,.
mOi-e
positive policy
----~~-
I.
~-
-~-
-- - - --.
r---
I,
- 3 -
- 4 .-
waste disposal
equipment removal
excavation
.-
---.-------~~--
.'-'-"'-.-"--~"--
----------
-----
----------------
- - - - - - - - - --------- _.-
Equipment worked on
electrical equipment
sprinkler system
Area classification
flammable area
Special hazards
fire
corrosive substances
toxic substances
Equipment used
.-mobile crane
--Time of day
after hours work
-=f:
Contents of permit
A typical permit-to-work, in this case a clearance certificate,
is shown in Figure 1.
Some important features of a permit and its use are as follows.
The section of plcint and the item of equipment on which work is to
done should be specified. The equipment may be idehtified by an
identification tag and this should be cross-referenced on the permit.
The nature of the work to be done should be clearly described. There
should be a certificate that it is safe to proceed- with the work.
This certification means that the possible hazards have been considered.
The precautions already taken, such as isolation of pipes and of moving
machinery, should be stated and so should those still to be taken,
such as use of breathing apparatus. The period of validity of the
<.
- 5 -
- G ~.--.---
.. - - - - - - - -
system.
It is a principal object of such a system to: define the
responsibilities of all conce~ned. The exact division of responsibility
--r
I
~.
while the job is being done. An example is a change from work on pump
bearings which does not involve breaking into the process lines to
other work which does. If such a change of intention occurs, a separate
permit should be issued.
The area affected by the
Work at a particular plant may
plants. It may be appropriate
the supervisor on such a plant
r-
[
l.
/
,.
"
//.t' . .
'1~
I
------~.
-----
------------- -
- 7 -
---- --
MAINTENANCE ACTIVITIES
Emptying, purging and cleaning
Much maintenance , work requires the prior removal of process
materials from vessels and pipes. Frequently these materials are
corrosive, toxic and/or flamrnable.
The normal procedure for emptying a vessel or pipe_ is to isolate
it, to vent to release the pressure and then to draw off tile contents.
It is then-frequently necessary to remove-t~aces of process rnaterial
from the inside of the vessel or pipe. This may be done to render
tile equipment safe for'welding or to allow people to work inside.
When welding has to be done, the removal of process material
should be rather thoro~gh .. Some materials form residues wllich are
very difficult to shift and which can adhere to the sides and. roofs
- 11 -
as well as the bottoms of tanks. These residues can give off flammable
vapours at the high temperatures used in welding.
There are various methods which may be used to remove traces
of process materials from equipment. These include steaming out,
mechanical washing and hand cleaning.
Washing with cold water or purging with air are not effective
methods of removing oil. Reliance on these method~ has been the cause
of many accidents.
The problems of preparing equipment for maint,enance work have
already been -considered in relation to vessel entr~ and are considered
further below in connection with line breaking and demolition.
f
[
/-:
I,,:.-.
rb
--'.-
..
-- .-:~----------;--
- 9 -
---
- -,.
-'
-- -
------_.
-----_._- _.
~-.---
.. -.
- ..
------
<
- 10 --------
r
i
l .
- 11 -
- 12 -
r'-j
i :
r'
f
l
L
- 13 -
process plant. For a given crane there- is a maximum safe load and
maximum safe jib radius. There is normally a safe load indicator,
but nothing to indicate the safe jib radius. If this latter is exceeded,
the jib itself constitutes the main load and a small additional load
may be enough to topp 1e the crane.
It is important for crane drivers to be well trained in the
operation and limitations of their cranes and in the special hazards
of process plants.
A rather less obvious hazard in cranes hired from outside
contractors is the use of cab heaters which are not sui~able for flammable
areas. A heater is needed, but it should be of an appropriate type.
Forklift trucks
- It-i s-conven i en-t--to-note-here the- Iliizards ass-o-clatedwj th:TorkJjJ~t_._-~~~_
trucks. IncidEnts _ar.e numerous in which for~li_ft trucks are driven
into and damage buildings and plant, including process plant. Pipework
is particularly at risk.
It is desirable, therefore, to review the routes which are used
by forklift trucks and to consider whether there is a need for special
protection of vulnerable features such as pipebridges and for special
training for drivers.
SOME MAINTENANCE PROBLEMS
Materials identification
Misidentification of materials is a significant problem. Materials
errors may occur in maintenance ~Iork. Situations in which they are
particularly likely are those where the materials look alike; e.g.
low alloy steel and mild steel or stainless steel and aluminium painted
mild steel.
It is necessary, therefore, to exercise careful control of
- 14
~--
~---~---------
t::-"
l:.
items.
External corrosion
External corrosion beneath lagging is a considerable problem
on process plant. It is important that the maintenance system should
check on external corrosion.
L-.l
-.
- 15 -
--
~-.
- 16 -
t .'
,.
,I
~-~~---I:
(1)
(2)
(3)
r'!
design modifications;
commissioning modifications;
operating modifications.
II:-: l
temporary modifications;
permanent modifications.
non-sanction modifications;
sanction modifications.
-1,
I
..
.
-~;----
- 17 -
~ '''f
- 18 -
k:.
i~
,.
,.
. I
if i..Y'P
a change
plant throughput me,) rp-n
. -,-
....
;
t, -,
- 19 -
---------
. __ .. _--
.--.~-------~--"-
.. - - - - - - - - -
CONTROL OF MODIFICArIONS
The elements of a system for control of plant modification are
. (1) procedures, (2) assessment, (3) inspection, (4) documef1tation,
and (5) training.
There shou.ld be a formal procedure which requires all modifications
to be author,ized by competent persons and a standard method of making
the safety assessment; there should be a system of inspection of
modifications by a competent person to make sure the work h~~ been
done as intended and is complete; there should be a system of documentation to record the change; and there should be adequ~te training
so that all personnel concerned understand the system of control.
Authority for modification
Systems for the control of modifications and the levels at which
particular types of modification can be authorized vary somewhat, but
the basic principles are quite clear. There should be a well defined
and understood system of authorization.
<
- 20 -
---------------- r
There is a problem area here. Many plants are designed and built
by outside contractors, who initially have the greatest expertise about
the plant but also eventually lose touch with it. -
[
L
Identification of modifications
- 21 -
~---
Critique of modifications
Modifications proposed are not always necessary. Sometimes the
proposal is a symptom of a problem which is better dealt with in some
other way.
It is appropriate, therefore, tllat a proposed modification should
be considered critically. Questions which may be asked concerning
it are: Is it necessary? Is it economic? Is there a better alternative?
Procedure for modifications
Before authorizing a modification particular attention should
be paid to ensuring that
'(1) The number and size of relief valves required are not changed
(or any necessary changes are specified).
(2) The electrical area classification is not changed (or any
<
- 22 -
,r-
nr--
I
r
f'
I
~", :.;,
g:~
r
r-'
!
,
- 23 -
Inspection of modifications
is the responsibility of the person authorizing a modification
to carry out a pre-commissioning inspection of that modific.ation _and __
to satisfy himself that it is in accordance with the design intent,that the standards for design, construction and testing have been followed,
that the _provisions of the safety assessment~ave been met and that
the work is complete.
It
Documentation on modifications
It is essential that plant documentation be kept up to date and
therefore that any modification be recorded. This requirement may
be met by the use of a formal register of modifications.
-If the modification requires-alterations to operatingor-inspe~tion---pract ices ;-i-j;--=i-s-necessari-that- the -appr':-opriate--ha-ng-es -be-made-in
-------tile documentation covering these asp_ects.
Training on modification systems
A system for the control of modifications can only work if-all
the personnel involved are aware of and have an -understanding of the
system through training.
The process operator who may turn off an agitator the maintenance
fitter 11ho may blank off a vent, the instrument artificer who may al ter
a trip setting, need to be a\1are of the hazards which these types of
modification may involve and of the system of control of modifications.
The plant managers and engineers who authorize modifications
need to have the theoretical knowledge, general 'practical experience
and experience of the particular process and plant to recognize potential
hazards, and also to appreciate situations where they should call in
expert assistance.
./
<
-'"
- 24 -
Commissioning modifications
The commissioning stage tends to involve numerous modifications
at a time when the plant manager and plant edgineer are heavily loaded .
.It may be appropriate, therefore, to appoint special personnel to check
these modifications. People who have been involved in hazard
identification during the design stage may well be suitable for this
task.
It is also advisable to conduct a post-commissioning check of
the pressure relief and blowdown arrangements about a year after startup.
'
ii
F'
-----!
.;
'
- 25 -
---~
.. -
...
The check on sewers and drains should cover not only the capacity
- nf-the underground sewers, but also that of the surface drainage so
as to ensure disposal of fire water.
A major extension also involves more Extensive changes of plant
configuration. It is particularly important, therefore, to check not
only tha~ there are suitable trip systems on the extension itself,
but that those on the existing plant are also still appropriate.
r.
--~
['
f
Safe-working procedures
A major extension usually means that there are on the site a
large number of contractors' personnel and also additional company
construction and maintenance personnel. This situation is a particularly
severe test of the safe-working procedures and the normal procedures
should be reviewed to check that they are adequate.
L..,
- 27 -
- .
_.
a~reed
"-_.
__.-
code.
- 28 -
I
!
._-----
The principal data required are those for failure, repair and
availability. The data are more valuable if they are of good quality.
Failure data should preferably give times to failure in each failure
mod~rather than overall failure rates.
Availability data should give
. ......
-----._- ---=--a:-fhtoUghj5lit~dehsit}'~Fath-erthan-a single downtime figure. --
!.
l.,
L
I
- 29 -
Maintenance policies
The policies which are followed in a process plant have a marked
influence on the level of failures experienced.
There is, however, no universally applicable policy. The policy
appropriate in a given case depends on the failure situation. In some
cases breakdown maintenance is sufficient, in others preventive:
maintenance is preferable.
Maintenance of protective devices
Maintenance of the protective devices on the plant is particularly
important and should be covered by a formal system with full documentation.
Some of the principal protective devices are
-(1). pressure relief- valves;
(2 )
(3)
(4)
(5)
(6 )
(7)
(8)
(9)
(10)
(11)
- ------
bursting discs;
tank vents and filters;
other pressure relief devices;
non-return valves;
mechanical trips and governors;
instrument trips;
other instrumentation;
alal-m systems;
sprinkler systems;
fire water systems.
This list includes not only the more obvious protective devices,
such as pressure relief valves, but also some other critical items
which are not always thought of as protective devices, such as tank
vents.
The maintenance of instrument trip systems is very important.
The de~tgn of such systems is based on the assumption of proof testing
at fixed intervals and is invalidated if this is not correctly-donee
- 30 -
L-.-
r
-
L..