unevenly torqued stud bolts in high pressure gas lift and gas compression piping;
loose body plugs found in gas compression system Shut Down Valve (SDV);
cracked stainless steel tubing in a high pressure gas system transmitter due to
poor construction quality and practices;
other failures due to a combination of over tightening, vibration fatigue and the
tubing material not conforming to the specification.
shipping line stops left in the small bore fuel gas piping connected to the high
pressure flare header. This caused excessive stress loading in the piping which
eventually caused the pipe to fail;
numerous spring supports left un-commissioned in the turret piping downstream
of the swivel stacks. These were discovered after a period of production.
System punch listing is a compilation of system deficiencies and / or incomplete work to be addressed by a
project team or an operation team. Punch lists are generated based on site verification at project handover.
Page 1 of 3
SAFETY ALERT 21
NATIONAL OFFSHORE PETROLEUM SAFETY AUTHORITY
the required specifications and engineering standards were not established for
equipment packages and equipment items;
the quality control and commissioning checks were not effective. This process
should have identified any defects before the handover. Examples of this
included:
-
as-built piping system line walks were not checked against the piping design
intent using both piping isometric and stress isometric drawings;
the commissioning checks did not reveal some system defects. These
included defects in the mechanical completions, the presence of faulty parts,
incorrectly made up flange joints and the presence of shipping restraints;
the handover process between the project management and operations was
inadequate regarding the keeping of records, the documentation of the
management of change and the documentation of repairs carried out during
the project.
Key Lessons
While there are lessons specific to each of the incidents that occurred, the following key
lessons were common to all of the incidents:
the project specifications must be established and approved at the start of the
project in order to define the system requirements in sufficient detail;
every field change or repair made during the construction, installation and
commissioning phases of the project must be traceable and executed as an
approved change or as an authorised work pack;
commissioning and start-up activities should include, but not limited to, a
thorough process of control-loop tuning and optimization of operational
parameters that, if not addressed, may lead to loss of containment from flanges,
mechanical seals and small-bore fittings;
Page 2 of 3