Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Abstract
The benefits of a properly executed Underbalance
Operation (UBO) can result in a well of higher quality
and value than that of a conventional well, if proper
planning and execution is achieved. This paper discusses
the importance of detailed planning when undertaking a
UBO and the consequences when conducted improperly.
UBO has demonstrated numerous times that:
Higher penetration rates (>2X) can be realized
Higher productivity (>2X) can be achieved
Higher reserves recovery are achieved
UBO has proven to reduce development costs, on multiwell projects. The timing for this cost reduction depends
largely upon:
the well construction staff in charge of the
operation
the rate of knowledge transfer from the
experienced personnel (service technicians) to
the operator
the utilization of the information by the
operator.
The current knowledge base of UBO is miniscule
compared to conventional Overbalance Operation
(OBO) knowledge. Access to this knowledge base and
implementing the value of the knowledge are critical to
expansion of the technology and the establishment of
credible operating practices. Global industry
organizations such as the International Association of
Drilling Contractors (IADC), Society of Petroleum
Engineers (SPE), and Gas Technology Institute (GTI)
have dedicated significant time and resources to
promote the exchange of knowledge and develop safe
Introduction
Globally, thousands of oil and gas wells are drilled
annually. Many of these wells have little to no detailed
planning conducted prior to spud of the well and many
of these wells are drilled under an IADC Footage
Contract, with little or no direct Operator Supervision.
This method generally results in a successful effort
relative to drilling cost and predicted productivity
outcome. As the well plan becomes more complex, the
more detail in planning is required (Figure 1). Drilling a
well with Underbalance Technology requires a
significantly higher level of planning detail be conducted
and reviewed by experienced staff (1) prior to final
acceptance and implementation, since the well could
produce hydrocarbons to surface. The typical UBO
process involves not only producing live hydrocarbons,
but also storing of volatile hydrocarbon liquid and
flaring of hydrocarbon gas. This physical difference to
OBO drilling requires greater attention relative to well
control and safety.
A UBO is one where the hydrostatic head (circulating
pressure) in the wellbore is less than the reservoir
pressure for every operation. Industry experience has
shown that employing conventional drilling practices
and 'conventional wisdom' is not always applicable to an
Underbalance Operation (2).
In many instances, UBO is employed to achieve
enhanced drilling performance only. The rationale for
using Underbalance Drilling (UBD) is to achieve a
higher rate of penetration to reduce drilling costs. This
Phase 1 Planning
Reservoir Screening
Planning begins with the screening and candidate
selection process. An underbalance operation is not a
panacea for improving productivity and increasing
reserves. It is critical for success to concurrently plan the
well with the Drilling and Geology Groups. Before the
UBO commences, the operator must determine what
achievement is required from the operation. Several
questions must be answered before continuing to the
next phase of planning.
What drilling problems will be minimized, or
eliminated?
IADC/SPE 81627
HSE Compliance
HSE Compliance is crucial in todays environment and
is required for all systems used on a drilling operation.
Since UBO may produce live hydrocarbons or other
dangerous gases, during the drilling process, the operator
must review accepted HS&E policies to ensure
compliance to corporate and regulatory procedures. The
drilling contractor equipment must be fitted with specific
safety equipment, the personnel must have adequate
PPE, and safety procedures should be outlined and
adhered to during any operation. Conventional drilling
operations pose numerous situations that require safety
measures being implemented. However, UBO require
additional safety measures.
Due to the release of pressured gases near the rig floor,
all personnel should be equipped with adequate hearing
protection. Caution should be used when rigging up the
UB equipment, taking advantage of prevailing wind
direction to carry flammable gases away from the rig (4).
Safely securing all equipment used in the release of
pressured gases.
Because the UBO may require handling of live
hydrocarbon,
while
drilling,
a
definitive
HAZOP/HAZID should be conducted. This function
should also include a review of personnel training levels
and skill sets to determine whether the appropriate
training or skills are available. If the training or skills are
not appropriate to the plan, time and cost should be
provided to obtain the necessary training. Supervisory
personnel skill sets should match the level and type of
operation. The oil and gas industry lacks qualified
Operational Consultants, skilled in UBO. This lack of
skilled UBO personnel drives operators to procure
supervision from the abundant pool of consultants
skilled in OBO method. Figure 2 illustrates the relative
size of available personnel as compared to well type
experience. There is no managed database from which to
access the appropriate consultant. When Underbalance
Operations become more commonplace, an organized
network may enable the operator to select the most
appropriate consultant for the area, project, reservoir,
etc. However, until this time comes, the planning group
will have to determine the skill sets necessary, then
shake many hands and see many faces to obtain the
IADC/SPE 81627
Phase 2 - Execution
Rig Selection Crew Training HSE
In an ideal world, rig selection would be based in-part on
the rig crews knowledge and experience with UB
operations. However, in the real world, abundant UB
experience is limited to a few regions. The majority of
the wells drilled today use conventional methods and
thus crew training is required when selecting a rig with
no UB experience.
Proper crew orientation to UBO is imperative for safe
operations. The crew should receive supplemental
training of well control measures, roles and
responsibilities, chemicals handling and PPE, HAZOP,
and other suitable topics as necessary for the particular
well plan, as per IADC UBO Classification (5,10).
IADC/SPE 81627
Case Histories
Several Case Histories are presented which demonstrate
the planning effort and detail involved and the outcome
of the operation. Three of the four case histories will not
IADC/SPE 81627
IADC/SPE 81627
drill pipe and BHA. The operation was trip intensive and
trip time was 40% slower than with a drilling rig (Figure
4, 5). This slow trip rate resulted in very costly trip
times, when considering the high daily spread cost.
The second lateral was drilled under a similar plan as the
previous lateral. However, in an effort to reduce the
daily spread cost, the second lateral used nitrified water
as the drilling fluid. The earlier use of nitrified-diesel
provided considerable protection against corrosion. The
nitrified water required the addition of chemicals to
control the corrosion. While drilling, the corrosion
inhibitor was added through the injection system. Water
influx was observed very early in the second lateral and
this caused much difficulty with corrosion inhibition.
The rig and location layout did not permit the efficient
pre-treatment of injected water. Furthermore, the UBO
allowed greater water influx, which prevented
maintaining a consistent level of corrosion inhibitor in
the returned fluids. The ineffective corrosion inhibition
ultimately caused a total loss of the drill string, a cost of
$200K.
The cost of the well was in excess of $2MM against an
AFE of $700K. The cost could have been limited with
more detailed planning, complete with What if this
happens? What do we do then?. The plan execution was
pertinent for the planning level, but required costly
decisions at the well when managing a significantly high
spread cost operation. The do something/do anything
syndrome was apparent in view of the mounting costs of
the daily operation.
Greater detail to planning with contingency plans and a
more experienced wellsite supervisor would have
prevented many of the mistakes on this well.
Case History 3
Medium-size Independent Operator Underbalance
Drilling in Fractured Carbonate for Reservoir
enhancement Re-entry well Texas
The prospect, based on an offset well down-structure in
a fault intense horst-graben field and an analogous field
nearby, was planned for using underbalance operation to
prevent near wellbore damage and easily confirm the
presence of gas filled rock. The operator was aware of
underbalance benefits, but had little to no experience
with horizontal underbalance operations. A focused
planning effort was launched with the inclusion of
experienced personnel from an Underbalance Drilling
Services provider. The effort consumed several meetings
to define the objectives and goals of the well. Additional
planning meetings were held with the operator to focus
IADC/SPE 81627
IADC/SPE 81627
IADC/SPE 81627
10
IADC/SPE 81627
References:
1.
Expanding
Technology
Exploration
Enabling Technology
High Angle
(~90)
Vertical Wells
Footage Drilling
In fill Wells
Day Work
Drilling
Mature Asset/
Mature Technology
New Technology
Application
Many
Turnkey Drilling
Horizontal
Well OBO
Vertical Well
UBO
Experienced Personnel
Appraisal
(Air/Gas Drilling)
Directional Well
UBO
Horizontal
Well
UBO
Few
Underbalance
OBO
Day-work Drilling
Drilling Method
ERD
UBO
Directional
Conventional
11
Un-Conventional
Asset Value
IADC/SPE 81627
Complexity
Figure 1: Planning Detail Matrix
Case History 1
Drilling Progress
Case History 2
Days vs. Depth
0
5000
1000
5500
2000
Lateral 1
3000
Planned - Lateral 2
6000
Lateral 2
4000
5000
Actual Depth
6000
Depth, ft
Depth, ft
Plan - Lateral 1
6500
7000
7000
7" casing @
7367' M D
8000
9000
7500
8000
10000
0
20
40
Time, days
60
8500
0
10
20
30
40
Tim e. days
50
60
70
12
IADC/SPE 81627
Ca se History 2
Tota l Tim e Distribution
25%
Change BHA
Circulating
9%
3%
3%
Drilling
Fishing
6%
Other
1%
Reaming
4%
Rig Repair
Standby
8%
6%
Survey + Connection
35%
Trip
Case History 1
Surface Injection Pressure, ROP, Total Liquid Injection Rate vs. Tim e
SPP, p si
ROP, f p h*10 0
To t al Liq uid Inject io n Rat e, g p h
5000
4000
3000
2000
1000
0
1
10
Figure 6: Case History 1 - Surface Injection Pressure, Liquid Injection Rate, ROP
11
12
13
14
IADC/SPE 81627
13
Case History 3
Days v. Depth
Case History 4
Days v. Depth
2,000
2,000
Planned
Lateral 1
Unplanned Sidetrack
Unplanned Sidetrack 2
4,000
Depth, ft
Depth, ft
4,000
Planned
Lateral - 1
S/T 1 ( Redrill Lateral-1)
Lateral - 2
6,000
6,000
8,000
8,000
10,000
10,000
12,000
0.00
12,000
0
10
20
30
40
50
Time, days
60
70
10.00
20.00
30.00
40.00
Time, days
80
Case History 3
Planned vs. Actual Costs
Cost, USD
600,000
500,000
400,000
300,000
200,000
100,000
Pe
rm
its
D
ay
/L
w
oc
or
at
k+
io
M
n
ob
/
D
C
m
om
ob
pl
D
e
tio
ire
n
ct
R
io
ig
na
lS
er
vi
ce
C
em
B
it/
e
Sc
nt
in
ap
g
er
/R
M
ea
ud
m
er
/C
he
m
ic
M
al
ud
s
O
Lo
pe
gg
n
H
in
ol
g
e
R
Lo
en
gg
ta
in
lE
g
qu
Tr
ip
uc
m
en
ki
ng
t
/H
au
P&
lin
A
g
/P
lu
O
g
th
ba
er
ck
In
ta
n
To
gi
ta
bl
lT
e
an
gi
bl
es
Planned
Actual
50.00