1. Which of the following project would be the best for your company?
Project A is being done over a six-year period and has a NPV of $70,000.
Project B is being done over a three-year period and has a NPV of
$30,000. Project C is being done over a five-year period and has an NPV
of $40,000. Project D is being done over a one-year period and has an
NPV of $60,000.
Project A
Project B
Project C
Project D
2. During which of the following phases does, the project sponsors have the
greatest influence on the scope, quality, time, and cost of the project?
A.
B.
C.
D.
Concept Phase
Development Phase
Execution Phase
Close Down Phase
3. The communication between the project manager and the project team
members is a vital factor in project accomplishment. Which of the following
is the best process?
A.
B.
C.
D.
Status Reports
Approved Documented Forms
Written and Oral Communication
Formal Chain of Command.
4. Which of the following would be the BEST project amongst projects A,B,C
and D? Project A has an IRR of 12%. Project B has an IRR of 17%.
Project C has an IRR of 31%. Project D has an IRR of 21%.
A.
B.
C.
D.
Project A
Project B
Project C
Project D
B. Project B
C. Project C
D. Project D
6. Which of the following type of person(s) is/are authorized to determine the
requirements of a new project?
A.
B.
C.
D.
Project manager
Senior management
Customer
Stakeholders
Identification of risks
Task estimates
Detailed resource estimates
The business need for the project
Third party
Seller
Buyer
None
Candidate A
Candidate B
Candidate C
Candidate D
Initiation
Planning
Execution
Control
15. The project manager should obtain support for the project throughout the
performing organization. How does he accomplish this?
A. By ensuring that there is a communication plan.
B. By correlating the need for the project to the organization's
strategic plan.
C. By connecting the project to the personal objectives of the sponsor.
D. By ensuring that the management plan includes the management
of team members.
16. When is the project manager assigned to a project?
A.
B.
C.
D.
17. A market demand, a business need and a legal need what do these
words mean as far as a project is concerned?
A.
B.
C.
D.
Planning
1. The process of creating a work breakdown structure results in which of the
following?
A.
B.
C.
D.
A project schedule.
Team buy-in.
A project completion date.
A list of risks.
Cost.
Scope.
Resources.
The schedule.
A.
B.
C.
D.
Formal reporting
Communications management plan
Stakeholder management
Earned value
14. Which of the following is not a factor in the assessment of project risk?
A.
B.
C.
D.
Risk event
Insurance premiums
Risk probability
Amount at stake
B. CPM
C. Monte Carlo
D. GERT
16. A project manager asks the team members about the time estimates for
their tasks. Then he develops agreement on the calendar date for each
task. In this situation, he is said to be involved in which of the following
activities?
A.
B.
C.
D.
Initiation
Activity sequencing
Scope definition
Schedule development
17. The calculated duration for a project is 28.166. The standard deviation is
5.5. The project manager is computing the probability of completing the
project on a specific day. Which of the following would be the most helpful
for him in this situation?
A.
B.
C.
D.
PERT formula
Monte Carlo simulation
Variance analysis
Probability analysis
18. The budget estimate of a project should be at what range of the actual
cost?
A.
B.
C.
D.
-5% to +10%
-75% to +25%
+10% to -25%
-10% to +25%
Source selection
Solicitation
Solicitation planning
Procurement planning
20. A contractor suddenly turns down in the middle of the project. A new team
has been replaced the vacancy. The project manager is going to address
the new team. He should tell the team to emphasize on which of the
following activities?
A. Identify team roles and responsibilities
22. Some organizations are now using 6-sigma. But generally, which method
of quality control is used in an organization?
A.
B.
C.
D.
1-sigma
2-sigma
3-sigma
5-sigma
23. A project manager identifies a risk that a fire could occur in the building
during the testing. What should he do?
A.
B.
C.
D.
24. A project manager takes over an existing project. He finds that there are
no quality standards. This situation relates to which of the following quality
process?
A.
B.
C.
D.
Quality analysis
Quality control
Quality planning
Quality assurance
26. The risk ranking of the project is an input to which of the following part of
the risk management process?
A.
B.
C.
D.
27. A project must be completed in three months using only four resources.
Which of the following would be helpful for a project manager at this
situation?
A.
B.
C.
D.
28. Suppose a project has the following risks: 20% probability of a 14 day
delay in the receipt of customer requirements; 10% probability of a 21 day
delay in the procurement process; 50% probability the integration will take
14 days longer. What is the expected value of these events?
A.
B.
C.
D.
49 days
35.8 days
11.9 days
7 days
29. A task has an early start of day three, a late start of day 13, an early finish
of day 9 and a late finish of day 19. What is the duration of this task?
A.
B.
C.
D.
6
3
10
7
Task 4 can start after Task 1 is completed and must be completed when
Task 3 is completed.
The estimate for Task 4 is ten.
What is the shortest estimated duration in which the project can be
completed?
A.
B.
C.
D.
11
10
18
9
32. As a project manager, you are involved with schedule development for the
project. You have analyzed the project, compressed the schedule and
completed a Monte Carlo analysis. Which of the following output will
result?
A.
B.
C.
D.
33. People who find themselves living and working in a different environment
are generally disorientated. What are they experienced by such
disorientation?
A.
B.
C.
D.
Culture shock
Sociocentrism
Temporal shock
Ethnocentrism
Risk qualification
Risk response planning
Risk control
Risk identification
35. Which of the following process means determining the physical resources,
their quantities, time of their use, etc.?
A.
B.
C.
D.
Resource planning.
Resource leveling.
Resource selection.
Resource materials.
36. As a project manager, you have finished the risk response planning
process. You are left with residual risks. How should you treat them?
A.
B.
C.
D.
37. While creating the final list of activities, a team member tells you that a
task has been forgotten in the WBS. What should you do?
A.
B.
C.
D.
38. A project manager has completed a WBS and cost estimates for each
work package. He wants to create a cost estimate from this data. What
should he do?
A.
B.
C.
D.
39. Which of the following is a basic rule or guideline for creating a work
breakdown structure?
A. The first row should describe the products of the project.
B. Each level of a work breakdown structure is a smaller segment
of the level above.
C. A work breakdown structure should be like a to-do list, listing every
task in chronological order that needs to be done to complete the
project.
D. Functional areas should organize a work breakdown structure.
40. You are the project manager of a new, large and complex project.
Because this project is business-critical and very visible, the executive
sponsor has told you to analyze the risks and prepare mitigation strategies
for them as soon as possible. The organization has risk management
procedures that are seldom used or followed. But the history of handling
risks is bad. The project's first milestone is in two weeks. In preparing the
risk management plan which of the following persons has/have a LEAST
important role?
A. Project team members
B. Executive sponsor
C. Individuals responsible for risk management policies and templates
D. Key stakeholders
41. The project information has been distributed among the stakeholders
according to the communications plan. Some project deliverables have
been changed according to the change control plan. All stakeholders
received the communication containing notification of the change. One of
them was surprised upon being informed of a previously published change
to a project deliverable. He communicated the same to the project
manager. What should the project manager do?
A. Determine why the stakeholder did not receive the information and
let him know when it was published
B. Review the communications plan to determine why the stakeholder
did not understand his responsibility
C. Review the communications plan and make revisions, if
necessary
D. Address the situation in the next steering committee meeting so
others do not miss published changes
42. As a project manager for large bank you are in charge of developing a
new certificate of deposit product. This needs information technology
systems development. Your internal information technology staff is not
responsive enough and does not have expertise in the technology needed
for this project. You do not have time or the information to develop a
detailed statement of work. In this situation, which of the following contract
would you prefer?
A.
B.
C.
D.
FP (Fixed price)
CPPC (Cost plus percentage of costs)
CPIF (Cost plus incentive fee)
T&M (Time and materials)
45. A project manager and his team are working together to develop a work
breakdown structure. However, the team members are doing work that is
not included in the work breakdown structure. What exactly is the purpose
of a work breakdown structure?
A. Guide the cost estimate for a project, not how the work is done.
B. Provide senior management with a high level view of the project
scope.
C. Include the work required to create the products of the project.
D. Include the total project scope or all of the work that must be
done to complete the project.
46. A project manager is attending his first bidders' conference. He asks you
for advice on what to do during the session. What would you advise him?
A. You do not need to attend this session; the contract manager will
hold it.
B. Watch for sellers who ask too many questions in an attempt to
block out the other sellers.
C. Make sure you give all the sellers enough time to ask
questions. They may not want to ask questions while their
competitors are in the room.
D. Let the project sponsor handle the meeting so you can be the good
guy in the negotiation session.
47. A project team has members in five different locations with varying
information systems. The project manager works with the project team to
determine how the project information will be distributed. Which of the
following documents is having such type of activities?
A.
B.
C.
D.
Execution
1. Which of the following is not a part of the contract documents?
A.
B.
C.
D.
Scope of work
Proposal
Negotiation process
Terms and conditions
A.
B.
C.
D.
4. Which of the following project reports meant that they are in their pure
state?
A.
B.
C.
D.
plan communications.
manage resources.
distribute information.
report performance.
5. One of the important role of the project manager during project planning
is:
A. Creating a Gantt chart and getting management to approve it
B. Following the plan set by management
C. Coordinating the creation of a document that can be used to
guide the project
D. Making a list of tasks the team members are required to perform
6. Which of the following would be the first step of a project manager when a
system development project is nearing closure and an unplanned risk is
identified, that could potentially affect the project's overall ability to deliver?
A. Mitigate this risk by developing a risk response plan
B. Alert the project sponsor of potential impacts to cost, scope or
schedule
C. Qualify the risk
D. Develop a workaround
7. What is the result of using the compromise to resolve a conflict between
two parties?
A.
B.
C.
D.
Lose-lose
Win-lose
Win-win
Lose-win
8. The scope statement is checked against the work results to ensure the
conformance of the customer requirements. For which of the following are
the results are documented and used?
A.
B.
C.
D.
Schedule development.
Integrated change control.
Project plan execution.
Project plan development.
10. Which of the following would be followed after a project is ending one of its
phases?
A.
B.
C.
D.
Management meeting
Team meeting
Scope management
Scope verification
A.
B.
C.
D.
misleading.
hard to automate.
complex.
closed and inaccurate.
13. Which of the following is the most appropriate contract type in a particular
situation during the project when you realize you need a consultant
immediately to begin working on a project?
A.
B.
C.
D.
15. Which of the following project elements is not included in the effective
stakeholder management?
A.
B.
C.
D.
17. Which of the following will be your First action if the seller on your project
abruptly goes out of business?
A.
B.
C.
D.
21. Which of the following activities is performed during the scope verification?
A.
B.
C.
D.
Commitment
Expense
Cash out-flow
Capital investment
23. Which of the following tools are frequently used in Procurement planning?
A. Make or buy analysis, expert judgment, and contract type
selection
B. Contract type selection, bidders conferences, and expert judgment
C. Expert judgment, audits, and bidders conferences
D. Make or buy analysis, contract type selection, and weighting
system
24. A contractors deliverable has been delayed for certain days. You want to
determine the effect of this event on the project schedule. Which of the
following method is used for this purpose?
A.
B.
C.
D.
Risk Identification
Risk Mitigation
Risk Simulation
Risk Assessment
27. The Management of a company has defined some quality standards for a
project. They want to be sure that the project is following such standards.
Which of the following statement would be the most helpful for them?
A.
B.
C.
D.
Quality audit
WBS
Risk management plan
Statement of work
28. What is the role of a project manager during execution of the project?
A.
B.
C.
D.
Leader.
Coordinator.
Director.
Integrator.
Smoothing
Problem solving
Compromise
Forcing
30. Other than confronting, smoothing and forcing, which of the following
conflict resolution techniques is used on a project?
A.
B.
C.
D.
Directing.
Withdrawing.
Controlling.
Organizing.
Project manager
Team
Management
Stakeholders
Quality control
Quality management
Quality planning
Quality assurance
33. You are accommodating a new project in your department. You want to
move resources from one project to another. Your department is currently
working at capacity. By doing so, it will inevitably delay the project. Out of
the following, you can move resources from which project?
37. Your project is in execution phase. The project has a very tight time line for
review of the seller's submittals and for completing the project. You discover
that your specifications are incomplete. You are not sure of the extent of the
problem. What should you do FIRST?
A. Hold a meeting with the stakeholders to determine what areas are
incomplete
B. Tell the seller to stop work until further instructed
C. Begin comparing your requirements to the specifications and
at the same time you hold a meeting with the stakeholders to
determine what areas are incomplete
D. Have the seller stop work on the parts of the project that are
completely defined
38. Which of the following risk events MOST likely interfere with attaining the
objectives of a project schedule?
A.
B.
C.
D.
39. You are working in a matrix organization. A team member comes to you
and admits that he is uncertain of how to perform a part of the task. He
suggests a training class available next week. Where should the cost of the
training come from?
A.
B.
C.
D.
Evaluating risks
Confirming submittals have been sent
Confirming that changes to the contract are made
Answering questions of potential sellers
41. Under which of the following conditions a seller is required the seller
agreement, a formal and a written correspondence?
A. A change to the project is issued.
B. A meeting with the seller's management is held.
C. The seller is asked for supporting information.
C. Stop all work and request that the customer contact you when they
have fulfilled their responsibilities.
D. Continue working according to your contract. Remind the
customer both verbally and in writing of the customer's
responsibilities. Provide the customer with an estimate of the
impact if they do not meet their responsibilities.
47. You are the new project manager in a functional organization. The project
is a large one involving activities that the organization has never done
before. Your predecessor has left the firm. Basically in such type of firms,
different units are often rather hostile to each other. You get adequate
documentation, including an agreed-to project charter, project plan, WBS,
etc. The project is on schedule and within budget. However, the
atmosphere in meetings with the project members often seems tense. You
find offhand comments made by participants. It indicates a high level of
dissatisfaction with the project. You review all of the major project
documents with the key stakeholders and get agreement they are still
accurate. You think this is not enough to solve the problem. Which of the
following is the best comment for this situation?
A. Stakeholders have very different expectations about what the
project is supposed to accomplish.
B. The organizational structure and dynamics prevent people from
working together effectively.
C. There are personality conflicts among the project team members
that you need to uncover and resolve.
D. The project does not have an effective executive sponsor and thus
is not viewed as a high priority.
Controlling
1. Through which of the following does the generally accepted method to
confirm accuracy of tasks progress?
A.
B.
C.
D.
Earned value
Probability vs. outcome
Maximum ceiling
Work breakdown structure
cost control.
cost management.
cost budgeting.
cost estimating.
4. Which of the following will not assist in determining the impact of a scope
change?
A.
B.
C.
D.
Project charter
Baseline
Performance measurement
Milestones
5. With which of the following does the scope change control will not
integrate?
A.
B.
C.
D.
Schedule
Cost
Procurement
Quality
11. All of the following can be used as a quality control tool EXCEPT:
A.
B.
C.
D.
Life-cycle costing
Pareto diagram
Work breakdown structure
Sampling
13. Which of the following is not relevant for analyzing a cost overrun?
A.
B.
C.
D.
communication plan.
lag.
labor rates.
resources used.
Stakeholder management.
Communications management.
Quality management.
Risk management and reporting.
15. Which of the following measures is used for the cost Performance Index?
A.
B.
C.
D.
16. A project becomes more complex. How does it affect the level of
uncertainty in the scope of the project?
A.
B.
C.
D.
Decreases.
Increases.
Remains the same.
Decreases and then increases.
+ACQ-1,000
+ACQ-2,000
0.938
1.034
18. Determine the CV of the project, if EV is +AD0- 350, AC is +AD0- 400, and
PV is +AD0- 325.
A.
B.
C.
D.
Negative 50
450
Negative 55
500
20. Which of the following is correct if two events cannot occur in a single
trial?
A.
B.
C.
D.
21. Generally, which of the following is better illustrated by a bar chart than a
network diagram?
A.
B.
C.
D.
Resource trade-off
Progress or status
Logical relationships
Critical paths
22. There is a major delay on a non-critical path activity. Which of the following
action must not be taken in this situation?
A.
B.
C.
D.
23. Which of the following compares actual dates with planned dates?
A.
B.
C.
D.
PERT
Schedule definition
Variance analysis
Resource leveling
Risk quantification
Risk identification
Risk monitoring and control
Risk response planning
Lessons learned
Scope verification
Corrective action
Scope planning
26. You have been assigned as project manager for a construction project.
You discover that a deliverable will be late. It will cause the project to be
delayed by four weeks. Your analysis shows that the item can be
purchased from another seller at a higher price without affecting the
schedule. What is the BEST thing to do?
A. Evaluate the impact of the decision
B. Discuss the impact with the customer and ask for a decision
C. Crash or fast track the project
D. Change the project plan to reflect the new due date
27. During the planning phase, Task G is on critical path. It was estimated to
complete in five days. But, on day two, it became clear that Task G would
take 15 days, which will impact the imposed project end date. The project
team meets to perform root cause analysis to identify the cause of the
variance and to plan schedule recovery with activities performed later in
the schedule. What is the output of this meeting called?
A.
B.
C.
D.
Corrective action
WBS updates
Activity list updates
Schedule updates
29. A project manager analyzes the status of the project. He determines that
the project is two weeks behind schedule. He wants to recover the
original schedule. There is plenty of remaining budget in the current plan.
What is the BEST option for him in this situation?
A. Crash the schedule
B. Inform the team that overtime will be required for a short time to
recover the schedule
C. Reduce the scope of work with a change request
D. Compress the testing and quality management portion of the
project
30. A project manager wants to assess quality of the project. To do so, he
needs to measure the height of each table produced. But that would be
too expensive. In this case, which of the following tools will be more
useful?
A.
B.
C.
D.
benchmarking.
a sample.
a control chart.
a Pareto diagram.
Notify management
Hold a team meeting
Look for alternative ways to meet the quality level
Ask management to come up with options
34. During the first half of the project, five team members left for other projects
without being replaced. Two team members went on vacation without
informing you. Others expressed uncertainty about the work they were to
complete. In this situation, which of the following must be created for the
second half of the project?
A.
B.
C.
D.
35. The networking vendor informs the project manager that the recent
earthquake will impact the delivery of critical components. The project
Configuration management
Work authorization analysis
Status review meeting
Integrated change control
37. After a big effort, the project team finally determines the specifications for
a major scope change. What should the project manager do next?
A.
B.
C.
D.
38. The project progress is tracked according to plan. The project manager
discovers that final deliverables will not be completed to meet deliverable
dates imposed by management. What should the he do now?
A. Renegotiate scope with stakeholders using some combination
of scaling back final deliverables or extending the project
timeline
B. Remember not to agree with unreasonable timelines imposed by
management
C. Drive the project team to work faster to make up for lost time
D. Recalculate the project schedule and distribute according to the
communications plan
39. A team member notifies you that he has added extra functionality to the
project. There was no impact on the cost or schedule. What should be
done as a result of this change?
A. Implement change control processes to track the change
B. Understand what functionality was added, to determine course
of action
C. Notify the functional manager that scope changes are not approved
D. Make sure marketing is aware of the change
40. A project manager has access to a tremendous amount of historical
information on projects. He wants to use this information to mathematically
forecast the future outcome of projects. Which of the following would he
MOST likely use?
A.
B.
C.
D.
Benchmarking
Trend analysis
Variance analysis
Decision trees
41. A functional manager wants to make a change to the time associated with
a task. There is not enough reserve to accommodate the change. Who
will order this kind of changes?
A.
B.
C.
D.
Senior management
The functional manager
The project manager
The team member performing the work
42. You have just been assigned as the project manager. The project is in the
middle of the execution phase. You are determining how you will control
the project. Which of the following would be the BEST way?
A. Use a combination of communication methods.
B. Hold status meetings because they have worked best for you in the
past.
C. Refer to the Gantt chart weekly.
D. Meet with management regularly.
43. A project team has invited many of the project stakeholders to help them
inspect quality on the project. Which of the following would NOT be an
output of this activity?
A.
B.
C.
D.
44. During project execution, a team member identifies a risk that is not in the
risk management plan. What should the project manager do?
A. Analyze the risk
B. Get further information on how the team member identified the risk,
because you already performed a detailed analysis and did not
identify this risk
C. Disregard the risk, because risks were identified during planning
D. Inform the customer about the risk
45. +ACI- is an uncommon state of nature, characterized by the absence of
any information related to a desired outcome. Which of the following
states the other definition of +ACI-?
A.
B.
C.
D.
It is an act of God.
It is an amount at stake.
Uncertainty.
Risk aversion.
Quality planning.
Quality assurance.
Quality work results.
Quality control.
Closing
1. In which of the following order does the processes are performed in the
Closing process group?
A.
B.
C.
D.
2. When was the contract is considered closed From the seller's point of
view?
A.
B.
C.
D.
Contract documentation
Procurement audits
Scope change control
Formal acceptance
Formal acceptance
Statement of work
Payment schedule
Change control procedure
Network diagrams
Project plans
Status reports
Lessons learned
B. Management
C. Project manager
D. Client
10. Which of the following documents does the project manager refer during
closure of the project?
A.
B.
C.
D.
Trend analyses
Documents that describe the project status
Documents that describe the product of the project
Change requests
12. You are the project manager for a large international bank. The project
team has just implemented an electronic funds project. It involves four
large vendors. You are struggled through every phase of the procurement
process since the bank had a weak internal contracts department. You
want to ensure that the problems are resolved for future projects. What
would be the MOST appropriate thing to do?
A. Document all of the issues in a memo and schedule a meeting with
the head of the contract office
B. Include an agenda item in the project closedown to discuss these
issues in a non-threatening manner
C. Address this through contract change control
D. Conduct a procurement audit
13. The scope of work is completed on a project. However, the customer is
not happy because they want additional work to be completed. In light of
this, what should be done?
A. Begin closure on the contract and sign a new one for the
additional work
B. Change to a cost reimbursable contract
C. Tell the customer it is too late to make a change
D. Add to scope of work and proceed with additional work after
obtaining management's agreement
14. Part of the project objectives for your company was to acquire additional
expertise completing a large scale project. The project is mostly
Professional Responsibility
1. Which of the following step is to be taken when your company puts a new
product into the market place without any reports of problems, but later on
your internal research indicated that there is a possibility of two serious
injuries per year and would cost $21,000,000 to fix?
A.
B.
C.
D.
3. What would be the best thing done by a new project manager if at the
beginning of creating the project's scope of work one stakeholder wants to
add many items and another wants to describe the functional
requirements and though the project is important for the company but a
seller will do the work?
A. The scope of work should be general to allow the seller to make
its own decisions.
B. The scope of work should be general to allow clarification later.
C. The scope of work should be detailed to allow clarification later.
D. The scope of work should be as detailed as necessary for the
type of project.
Explanation: Sometimes the scope of work on a project can be described
in great detail. However, sometimes the seller has the expertise and the
5. Defining which of the following is the key factor for achieving customer
satisfaction?
A.
B.
C.
D.
7. You along with one of your team member from research and development,
after he tells you that his work is too creative to provide you with a fixed
single estimate for the task, decide to use the average time the task has
taken for past projects to predict the future. This is an example of:
A.
B.
C.
D.
Parametric estimating
PERT
CPM
Monte Carlo
Sunk cost
Fixed cost
Direct Cost
Variable cost
10. This is your first Project, and you are asked to plan a new project. Which
of the following is BEST in this situation to rely on - during planning to
improve your chance of success.
A.
B.
C.
D.
11. You have been asked to help senior management when your organization
is having a difficult time managing all of its projects. Which of the following
types of reports would help provide summary information?
A.
B.
C.
D.
Gantt charts
Project plans
Milestone reports
Detailed cost estimates
12. It is not known whether your company will be awarded a business. You
approach the official who will decide on this matter. You offer a payment to
him for any decision made or encouraged to your favor. What is this
payment called?
A.
B.
C.
D.
Token money.
A progress fee.
A sunk cost.
A bribe.
13. You are the project manager of a new product development project. It has
four levels in the work breakdown structure that are sequenced using the
arrow diagram technique. You received the activity duration estimates for
the project. As per the time management, what is done after activity
duration estimating?
A. Create an activity list
B. Update the work breakdown structure
C. Collect historical records
D. Duration compression
14. A project manager wants to establish a baseline for measuring project
performance. In this effort, he allocates overall cost estimates to
individual activities or work packages. What is this activity called?
A.
B.
C.
D.
Cost management
Cost estimating
Cost budgeting
Cost control
15. The cultural and ethical differences should not impede success of multinational projects. Which of the following assures this among the team
members?
A.
B.
C.
D.
Co-locating
Training
Forming
Teaming
17. Your company is on the way of breaking a deal in another country. One of
your official begins negotiations with people from that country. They want
to know which business practices are allowed and which are not. Which of
the following gives a proper guidance in this respect?
A.
B.
C.
D.
18. Which of the following includes activities like adhere to legal requirements,
satisfy competing needs, provide accurate and truthful representations
and disclose conflicts of interest?
A.
B.
C.
D.
19. During the execution of a project, the project manager wants a change in
the material purchased. Immediately, he calls a team meeting to plan in
this regard. Which of the following is reflecting in this situation?
A.
B.
C.
D.
Management by objectives.
Lack of a change control system.
Good team relations.
Lack of a clear work breakdown structure.
20. You are the project manager of a new software development project. You
are completed the construction phase. The next phase is testing and
implementation. The project is two weeks ahead of schedule. Before
moving onto the final phase, which of the following is a matter of concern
for you?
A.
B.
C.
D.
Scope verification
Quality control
Performance reports
Cost control
21. You are managing a fixed price contract. You think that a large customerrequested change might impact the schedule of the project. What should
you do?
A.
B.
C.
D.
Precedence diagramming
Arrow diagramming
Critical path
Conditional diagramming
24. Your team has just provided you with the activity duration estimates.
Before you start schedule development which of the following must you
refer?
A.
B.
C.
D.
25. A project is in planning phase. You have just been taking it over. Your
predecessor had made few processes for managing changes to the
schedule. You want to take a note on those plans. Which of the following
documents must you refer?
A.
B.
C.
D.
Communication plan.
Project plan.
Time management plan.
Schedule management plan.
Risk quantification
Risk monitoring and control
Risk identification
Risk response planning
27. You are the project manager for a large project under contract with the
government. The contract for this two year, multi-million dollar project was
signed six months ago. You were not involved in contract negotiations or
setting up procedures for managing changes, but now you are swamped
with changes form the sponsor and from people inside your organization.
Who is normally responsible for formally reviewing major changes to the
project/contract?
A.
B.
C.
D.