METHOD STATEMENT
Re-Routing of FA Cable
Hotel
TABLE OF CONTENTS
SL.NO
DESCRIPTION
1.0
OBJECTIVE
2.0
SCOPE
3.0
REFERENCES
4.0
RESOURCE PLANNING
5.0
WORK METHODOLOGY
6.0
7.0
SAFETY EQUIPMENT
8.0
SAFETY CHECKS
9.0
ATTACHMENTS
Transco
Subtstation
Muroor Road
Near Dusit Thani
METHOD STATEMENT
Re-Routing of FA Cable
Hotel
1.0
OBJECTIVE
1.1
2.0
The purpose of this method statement is to ensure that correct materials and
procedure are implemented during execution of work.
SCOPE
2.1
3.0
This Method Statement defines the sequence and methodology to be followed for
Fire alarm Re-Routing, Testing & Commissioning.
REFERENCES
a)
b)
c)
d)
e)
4.0
RESOURCE PLANNING
4.1
Material
Item
1
4.2
Description
FA Cable
Item
Description
Electrical multi-meter
Ladder/ scaffoldings
Tester
Transco
Subtstation
Muroor Road
Near Dusit Thani
METHOD STATEMENT
Re-Routing of FA Cable
Hotel
Manpower
4.3
Item
5.0
Description
Commissioning Engineer
Project Engineers
Skilled Technicians
General Worker
WORK METHODOLOGY
5.1
General Requirements
a)
b)
c)
d)
e)
6.0
HOLD POINTS
1)
Ensure all continuity test reports for cables installed are available and signed by the
concerned parties.
Approved drawings available
Power available.
All interfaces are connected and confirmed.
All third party system tested and ready for fire alarm testing.
All areas where the detectors installed are clean and free from dust or any works that emits
smoke and heat.
2)
3)
4)
5)
6)
6.2
COMMISSIONING
FA Panel Loop wiring and network wiring Pre-Commissioning:
Transco
Subtstation
Muroor Road
Near Dusit Thani
METHOD STATEMENT
Re-Routing of FA Cable
Hotel
All incoming and outgoing loops will be identified and noted with tags.
Start up the FACP
Connect the PC to the FACP
After charging the FACP batteries will be connected and Software will be
down loaded to the master controller and other FACP in the network.
Start up loop recogonization & Device recogonization
After loop recogonization is cleared, and all the address are assigned by the
FACP to the field devices, start labelling of devices according to the
location of the devices.
Start assigning the equation of related devices
Upload the data to FACP.
FA System Commissioning
Device Testing
As each loop is completed and terminated into the control panel the
following tests will be carried out: - Activate random device by smoke
tester, blower or break glass key. As each device is operated the address at
the local FACP and in terminal unit will be checked and labelled on the test
sheets as correct. Where a combined detector /sounders are located the
operation of the sounder will happen when the device is tested.
3rd party interfaces will be tested by triggering the IFU from the panel and
checking that the contacts have changed state with a multimeter.
A full set of Documentation will be provided along with as built with all loop devices shown
including their unique reference number designated panel/loop/device number.
Transco
Subtstation
Muroor Road
Near Dusit Thani
METHOD STATEMENT
Re-Routing of FA Cable
Hotel
Process Chart
Start
Loop Cables
tested & all
detector bases
fixed& Signed
off by Engineer
CO2 System
Text Address &
Technical
Submittal
Approved
Power on at all
panels.
Testing.
Stop
Transco
Subtstation
Muroor Road
Near Dusit Thani
METHOD STATEMENT
Re-Routing of FA Cable
Hotel
7.0
SAFETY EQUIPMENT
All necessary PPE and safety gear shall be worn at all times during the execution of work,
in full compliance with safety requirements.
1
2
3
4
8.0
Helmets
Safety Shoes
Hand gloves
Safety signs
SAFETY CHECKS
Safety checks will be made prior to commencement of work in order to ensure that materials
and equipments are in safe working order in accordance with project and site regulations.