METHOD STATEMENT
Re-Routing of FA Cable

Hotel

TABLE OF CONTENTS

SL.NO

DESCRIPTION

1.0

OBJECTIVE

2.0

SCOPE

3.0

REFERENCES

4.0

RESOURCE PLANNING

5.0

WORK METHODOLOGY

6.0

TESTING / COMMISSIONING SEQUENCE

7.0

SAFETY EQUIPMENT

8.0

SAFETY CHECKS

9.0

ATTACHMENTS

Transco
Subtstation
Muroor Road
Near Dusit Thani

METHOD STATEMENT
Re-Routing of FA Cable

Hotel

1.0

OBJECTIVE
1.1

2.0

The purpose of this method statement is to ensure that correct materials and
procedure are implemented during execution of work.

SCOPE
2.1

3.0

This Method Statement defines the sequence and methodology to be followed for
Fire alarm Re-Routing, Testing & Commissioning.

REFERENCES
a)
b)
c)
d)
e)

Local Authorities Having Jurisdiction


Project Quality Plan
Project Safety & Health Manual
Approved Shop Drawings
Contractor Specifications

4.0

RESOURCE PLANNING

4.1

Material
Item
1

4.2

Description
FA Cable

Machinery / Tools / Equipment

Item

Description

General Tool Box

Electrical multi-meter

Ladder/ scaffoldings

Tester

Transco
Subtstation
Muroor Road
Near Dusit Thani

METHOD STATEMENT
Re-Routing of FA Cable

Hotel

Manpower

4.3
Item

5.0

Description

Commissioning Engineer

Project Engineers

Skilled Technicians

General Worker

WORK METHODOLOGY
5.1

General Requirements
a)

b)
c)
d)
e)

6.0

TESTING / COMMISSIONING SEQUENCE


6.1

HOLD POINTS

1)

Ensure all continuity test reports for cables installed are available and signed by the
concerned parties.
Approved drawings available
Power available.
All interfaces are connected and confirmed.
All third party system tested and ready for fire alarm testing.
All areas where the detectors installed are clean and free from dust or any works that emits
smoke and heat.

2)
3)
4)
5)
6)

6.2

Ensure that all materials to be used and equipment to be installed should be


checked by the Project Engineer / Supervisor against equipment data sheet
and approved drawings.
The latest revision of the Approved shop Drawing should be available at the
installation area.
Project Engineer / Supervisor will ensure that safety requirements have been
complied with and are in place.
Project Engineer / Supervisor will orient and familiarize all the workers and
assistants involved in the installation regarding relevant approved drawings,
Test the fire protection systems in accordance with manufacturers
recommendations. Locate where accessible for servicing and replacement.

COMMISSIONING
FA Panel Loop wiring and network wiring Pre-Commissioning:

Transco
Subtstation
Muroor Road
Near Dusit Thani

METHOD STATEMENT
Re-Routing of FA Cable

Hotel

Loop & Network continuity will be completed along with contractor


engineers and readings will be noted in the format supplied by them.

FA Panel Assembly & Programming:

All incoming and outgoing loops will be identified and noted with tags.
Start up the FACP
Connect the PC to the FACP
After charging the FACP batteries will be connected and Software will be
down loaded to the master controller and other FACP in the network.
Start up loop recogonization & Device recogonization
After loop recogonization is cleared, and all the address are assigned by the
FACP to the field devices, start labelling of devices according to the
location of the devices.
Start assigning the equation of related devices
Upload the data to FACP.
FA System Commissioning

Device Testing

As each loop is completed and terminated into the control panel the
following tests will be carried out: - Activate random device by smoke
tester, blower or break glass key. As each device is operated the address at
the local FACP and in terminal unit will be checked and labelled on the test
sheets as correct. Where a combined detector /sounders are located the
operation of the sounder will happen when the device is tested.

3rd party interfaces will be tested by triggering the IFU from the panel and
checking that the contacts have changed state with a multimeter.

The results will be recorded on the test sheets


Cause & Effect Testing
Each Device will be tested and the type of activation will be at the
discretion of the witnessing parties.

A full set of Documentation will be provided along with as built with all loop devices shown
including their unique reference number designated panel/loop/device number.

Transco
Subtstation
Muroor Road
Near Dusit Thani

METHOD STATEMENT
Re-Routing of FA Cable

Hotel

Process Chart
Start

Loop Cables
tested & all
detector bases
fixed& Signed
off by Engineer

Ensure the all


termination on
all the FACPs

CO2 System
Text Address &
Technical
Submittal
Approved

Power on at all
panels.

Panel Assembly &


Programming.

System Software loading.

Testing.

Cause & Effect Testing

Implement Cause & Effect, test commission and witness to


Consultant.

Stop

Transco
Subtstation
Muroor Road
Near Dusit Thani

METHOD STATEMENT
Re-Routing of FA Cable

Hotel

7.0

SAFETY EQUIPMENT
All necessary PPE and safety gear shall be worn at all times during the execution of work,
in full compliance with safety requirements.
1
2
3
4

8.0

Helmets
Safety Shoes
Hand gloves
Safety signs

SAFETY CHECKS
Safety checks will be made prior to commencement of work in order to ensure that materials
and equipments are in safe working order in accordance with project and site regulations.