Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
DATE:
LOCATION:______________
RESPONSIBLE SUPERVISOR:_____
PLANT/EQUIPMENT:
July, 08 ,2002
____M.#36 ___________ __________
Eng. ABD EL AZIZ MOH.
COP. # 6
DESCRIPTION OF WORK: REMOVE THE UNIVERSAL JOINT FOR REPAIR & REINSTALL
___________________________________________________________________
SAFETY PRECAUTIONS
Lock out Tag out procedures must be applied before commencing work
Cold work permit should be issued and signed daily.
Safety meeting will be held on location daily, with all personnel involved in the task
Keep all walkways, stairs and access doors clear of obstructions.
Clean up any spillage of oil/chemicals immediately.
All tools must be in good condition, and the correct tools for the work
Use only correctly color coded lifting equipment (blue) universal weight 60kg
All workers must wear correct PPE at all times
Inspect All Lifting Tools And Check For Color Coded
ICC should be issued
A copy of procedure should be on work site
Gas free check should be applied before starting the job
Remove any source of ignition at work place
Fire extinguisher and trained person should be valid during the work
Good communication between performing authority OIM before and during the job to ensure every body
understand the written proced. And risk assis. For the job
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Isolation Procedures :1. Close main Fuel valve install spade out fuel line & Open the vent valve of the fuel filter to
ensure the fuel pressure become zero
LOTO
( MM )
2.
3.
4.
Close suction & discharge valve of the pump & Open drain valve LOTO
(Prod.)
5. Isert spade on suction & discharge valves of the pump to comply with recommended standard
isolation ( SVI + Spade )
( Prod. )
6. Make sure by monitoring the pressure gauge on suction and discharge line of the pump that
the reading of the gauges are zero and there is no pressure build up in the system (if there is
leak from the valves causing pressure build up dont resume the job)
(MM)
(MM)
(MM)
(MM)
Date
Mech. Maint,
Asst.Gen. mgr.
Gen.Maint.
Gen.mgr.
Production
Gen.mgr
HSE
Gen.mgr.