Vodafone Netherlands

Terminal NL Wave 3
Detailed Test Plan

Author
Surajit Bagchi
Project Manager- Vodafone
Henk.de-Keijzer@vodafone.com

Status
Initial Draft
Status Date
22-Dec-2014

Date Printed:
Save Date:

CONFIDENTIAL

Page 1

DOCUMENT CONTROL
Modification History
Version
0.1

Author(s)

Date Released

Surajit Bagchi

22 Dec 2014

Notes
Initial draft

Review History
Version Reviewed

Reviewer

Date Reviewed

0.1

Henk.de-Keijzer@vodafone.com

Notes

Approval History
Version Approved

Approver

Date Approved

Notes

Additional Distribution List


Recipient

Date received

Asim K Chatterjee

Page 2
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

CONTENT
Document Control.........................................................................................................2
Modification History........................................................................................................................... 2
Review History................................................................................................................................... 2
Approval History................................................................................................................................. 2
Additional Distribution List.................................................................................................................. 2

Content.........................................................................................................................3
1 Introduction.............................................................................................................5
1.1
1.2
1.3
1.4

Background.............................................................................................................6
2.1

3
4

High Level Data Model:........................................................................................................... 6

Test Objectives.......................................................................................................7
Test Scope:.............................................................................................................8
4.1

5
6

Overview................................................................................................................................. 5
Identification............................................................................................................................ 5
References.............................................................................................................................. 5
Notations and Abbreviations:................................................................................................... 5

Out of scope............................................................................................................................ 8

Assumptions...........................................................................................................9
Test Strategy.........................................................................................................10
6.1
High Level overview of system test approach.......................................................................10
6.2
Test Goals:............................................................................................................................. 11
6.3
Types of Testing..................................................................................................................... 11
6.4
Test Approach System Testing............................................................................................ 11
6.5
Risk Assessment................................................................................................................... 12
6.6
Entry / Exit Criteria................................................................................................................ 12
6.6.1
System Testing............................................................................................................... 12

Test Plan...............................................................................................................13
7.1
7.2
7.3

Test Environment Build Strategy..........................................................................15


8.1
8.2
8.3
8.4

Test Planning Workshops...................................................................................................... 13


Roles and responsibilities...................................................................................................... 13
Test Schedule........................................................................................................................ 14
Test Environment.................................................................................................................. 15
Test Data Strategy................................................................................................................. 15
Test Tools............................................................................................................................... 15
Configuration Management................................................................................................... 15

Test Management & Reporting Procedures.........................................................16


9.1
Test Management.................................................................................................................. 16
9.1.1
Defect Tracking/Management Procedures.....................................................................16
9.1.2
Change Management Procedures.................................................................................18
9.1.3
Progress Tracking Procedures.......................................................................................18
9.2
Reporting............................................................................................................................... 18
9.2.1
Test Progress Reporting................................................................................................. 18

10 Test Deliverables:.................................................................................................19
10.1
10.2
10.3
10.4
10.5

System Test Cases............................................................................................................ 19


Traceability Matrix:............................................................................................................ 19
Test Result Report:............................................................................................................ 19
QA Summary Report:........................................................................................................ 19
System Test End Report:................................................................................................... 19

Page 3
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

1 INTRODUCTION
1.1 Overview
For Local Integration layer (LIL/ ODS), existing Article Master Stock interface IF0161 from 3TM to LIL will
be enhanced due to Business process changes/ decision to use EAN # as additional article numbers,
Thuiskopijheffing (Copy Right levy) and technical issues experienced in the current interface flows (e.g.
not being able to correctly identify deactivated articles). And some pass through interfaces between 3TM
and AXY-RS/ Dynafix via LIL.

1.2 Identification
The purpose of the document is to create a complete and consistent detail test plan that provides high
level testing guidance and insight in the following levels of tests:
System Testing/SIT Verify the correctness of the new functionalities implemented and check
whether the system as a whole with all modules is working as expected with available test data.
Vodafone BICC UAT Support: Support will be provided during UAT as per the scope mentioned
in UAT test strategy provided by BICC.

This document will focus majorly on system testing details- e.g. approach, strategy etc.

1.3 References
This document is based on and refers to the following documents:
Sr. No.
1
2

Title
VF_NL HLD Terminal NL Wave 3 ver.1.0.doc
VF_NL_BI
Detailed
Design
Terminal_NL_Wave_3_V1.10.doc

Version
-

1.0

Date
21-Nov-2014

1.10

114-Dec-2014

1.4 Notations and Abbreviations:


Please refer the below table for notations and abbreviations used in this document:
Abbreviation/Notation
HLD
LLD
MM
LIL

Description
High Level Design
Low Level Design
Material Master
Local Integration Layer

Page 4
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

2 BACKGROUND
2.1 High Level Data Model:
Below is the charcoal diagram for the project:

Page 5
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

3 TEST OBJECTIVES
Testing is the systematic search for defects in all project deliverables. It is the process of examining an
output of a process under consideration, comparing the results against a set of pre-determined
expectations, and dealing with the variances.
The main test objectives are:

Identify and publish the scope and substance of the testing effort
Identify and publish risks to the successful completion of the project
Verify functional correctness from a design point of view
Verify functional correctness from system behaviour
Test product robustness and stability
Report on the status of the product regarding the tests and measures

Page 6
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

4 TEST SCOPE:
The scope of this document concerns with testing of source data processing coming from different
source systems. This comprises:

System Test/SIT: Verify the test goals mentioned in this document.


VF BICC UAT Support: Support will be provided during UAT based on the scope of IBM-BI.
Scope of UAT support will be as defined in UAT strategy document provided by VF BICC.

Test Deliverables for System Test:


Sr.
No.

Deliverable Name

Detail test plan

System test cases

System Test Result

QA Summary Report

Remark
This document will contain test scope, test approach and all detail on
different test activity
Will contain functionality covered, steps to follow, expected output, input
test data
Will contain execution status of each test case.
Will contain daily execution status report along with defect details. At the
end of each level of testing IBM will provide the overall project health
along with Go, No-Go suggestion for the next level.

4.1 Out of scope


The out of scope items for testing are mentioned below:

Article (Item) Interfaces from LIL to ATLAS are out of scope.


Interface from LIL to Downstream Systems containing the Article Stock information is out of
scope.
Any test goal that is not mentioned in this document.
Infrastructure support/system administration is out of scope. Vodafone Contracting Company and
Supplier Contracting Company will jointly initiate and ensure in time systems access.
Test Data Creation IBM will not create any test data manually. IBM will receive all required test
data from source systems as mentioned in detailed design document prior to system testing to
cover all possible test scenarios.
Performance & Automation Testing
Verification/validation of any functionality not mentioned in detailed design document
Non functional testing

Page 7
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

5 ASSUMPTIONS
The assumptions for performing the test activities are mentioned below:
No.

Assumption

IBM will receive test data from stock interface IF0161 (from
3TM) to LIL prior to system test starts

Connectivity should be established between 3TM and LIL

3
4

Comment

During SIT/VF BICC UAT phase IBM-BI will provide support


from 9 AM to 6 PM IST.
Test environment will be ready with test data prior to system
test starts.

Page 8
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

6 TEST STRATEGY
This section describes the approach and methodologies to plan, organize and manage the testing.
The test strategy is business driven and aims at:
-finding major defects as early as possible
-making the critical path of the testing phase as short as possible

Detail Test Plan


Describes the test approach, procedure and planning for test activities.
Specifies all the test activities to be performed for verifying the functionalities.

Test Designing
Test Case Identification:

Test goals need to be identified based on detailed design document.

Test cases need to be created based on test goals.

Requirements traceability matrix will be created to trace the test coverage between test
goals and test cases.

Test Environment Requirement:


Environment details (Unix box name, database name) for each test level will be provided in QA
Summary Report document.

Test execution.
Initiation of the test execution will be based on the fulfillment of entry criteria mentioned in this
document.
All identified System test cases will be executed as part of system test.
Success or failure of any test function/feature will be determined based on difference between
expected result and actual observation. Defects will be logged for failed test cases.

Test Reporting:
It is the process of reporting the progress of testing activities in each test level such as new identified
test cases, deviations from the baseline (test design).Furthermore the progress of execution, results
of the tests including issues found, root cause identification, known issues. A daily progress report
will be sent during system test execution.

6.1 High Level overview of system test approach

Connectivity establishment:

Connectivity verification from 3TM (interface IF0161) to LIL

Source file Validation:

Verification of source file IF0161_O_<YYYYMMDDHHMMSS>.txt


Verification of mapping at LIL/ODS as mentioned in detailed design document

Page 9
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

Data Loading:

Verify data loading as mentioned in detailed design document


Data validation once data loading completed- randomly selected data will be validated

Mapping:

Validate attribute level mapping between source and target data as per the mapping sheet mentioned in detailed
design document

6.2 Test Goals:


The following are the test goals based on business functionality:

Vodafone NL
Vodafone NL
Terminal Wave - Test Terminal
Goals_v0Wave
1.xls - Detail test plan_v 0.3.xls

6.3 Types of Testing


This section defines the types of testing, which relate to business functions (Functional Types) or to
structural functions (Non-functional Types). These test types will be mapped to the various test types
which will prove system compliance.
Functional Types of Test
The following is a list of all functional types of tests which will be performed for the project:
System Test/SIT
VF BICC UAT
Support

Test goals mentioned in section# 6.2


Support will be provided during UAT phase. Details of support will be defined in
BICC UAT plan document.

Non-functional Types of Test


NA

6.4 Test Approach System Testing


Sl#

Test Area

Approach Details
Verify whether source data is coming from 3TM
to LIL in the landing directory as mentioned in
detailed design document

Connectivity Test

Interface Test

Validation of each source data based on latest


detailed design document.

Data Loading

Verify all details related to data loading as


mentioned in detailed design document

Mapping Validation

Attribute level validation from source to target


based on the mapping sheet mentioned in the
detailed design document

Dependency
Connectivity should be
set between 3TM
interface to LIL
Source data should be
available prior to system
test.
Source data should be
available prior to system
test

Comment

Updated mapping sheet


should be available

Page 10
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

6.5 Risk Assessment


This section comprises a detailed risk assessment of the test strategy, driven by the business decisions,
business requirements and technical requirements of the solution under development.
Sr.
No.
1

Description of Risk & Impact

Rank
(H/M/L)

Test data will not available prior to system test

Mitigation Strategy & Status

Communicate VF test manager and source system in case


test data not received in time.

6.6 Entry / Exit Criteria


This section defines the entry and exit criteria for the System Test

6.6.1 System Testing


Entry Criteria

Coding and unit testing completed successfully

Unit test result and all open issues are documented and available

All test hardware platforms are identified, installed, configured and verified- ready for testing. E.g
identify LIL test server, Teradata server.

All applicable standard software tools including testing tools must have been successfully installed.

All required accesses are granted for each team member.- E.g. Teradata access for testing team.

All documentation and design of the architecture must be made available.

Test cases and test plans are reviewed and signed off by VF test manager

A separate test environment must be available.

Required test data is available in test environment.

Exit Criteria

All System Test Cases are executed and execution status is recorded
At least 95% of test cases executed are passed- out of which all critical and high priority test cases
are passed. Go ahead with failed test cases will be decided based on mutual agreement with IBM
Test Manager and VF Test Manager.
All open defects are reviewed and agreed by Vodafone for go-ahead in next test level
IBM has delivered a final and signed-off ST End Report (or QA report) to Vodafone- ensuring no
blocking defect is open and maximum of 5 severe defect can be in open status.

Page 11
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

7 TEST PLAN
7.1 Test Planning Workshops
After the initial version of this document is distributed and made available to all stakeholders, review will
be done on this document. Once review feedback is received by all stakeholders, document will be
modified and send again for review. This process will be completed based on the defined milestone date
once all stakeholders are agreed to test planning mentioned in this document.

7.2 Roles and responsibilities


The following table summarizes the testing responsibilities.
Roles
IBM Project Manager

Responsibilities

Review, Provide updates and maintain the detail test plan


Manage test plan execution
1st point of contact for issue resolution during all testing phases

Support Project Manager/Test Manager in the following areas:


IBM Test Lead

Testers

Prepare/modify detailed test plans


Define/identify test scope
Manage and Maintain test cases/scripts
Manage test execution and monitor defects
Manage and monitor test progress during all testing phases
Reporting test progress to VFNL test manager and IBM PM.

Identification and understanding of test requirements.


Test Case/Test Script Preparation and review
Preparation/Identification of Test data
Verify test environment
Test Execution
Logging defects and verify fixes once available
Providing traceability of test cases to Requirements to ensure proper test
coverage
Reporting test case/script creation/execution status to Test Lead/Test Manager
Prepare Test Result Report

VF Test Manager

Review and approve test deliverables


Co-ordinate with other teams along with IBM Test Manager/Test Lead to complete
all levels of testing
1st level of contact point for issue resolution raised by IBM (as far as not IBM
internal)

Page 12
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

VF BICC Team

Create UAT test plan with required support from each vendor.
Discuss and agree with IBM regarding support required for UAT environment
setup, test data identification/creation, test execution etc.
Share UAT test scenarios of IBM scope.

7.3 Test Schedule


Attached is the major testing milestones for this project. Any change in the timeline will result in
modification of test milestones below.
Sl#
1
2
3
4
5
6
7

Milestone
Detailed Test Plan Creation
System Test Case Creation
System Test/SIT execution
UAT Support
IBM Stability Test
Roll Out & Go live phase
Babysit/Stabilisation Period

Planned Start
Date
8-Dec-2014
10-Dec-2014
29-Dec-2014
12-Jan-2015
03-Feb-2015
09-Mar-2015
14-Mar-2015

Planned End
Date
22-Dec-2014
24-Dec-2014
9-Jan-2015
30-Jan-2015
06-Mar-2015
13-Mar-2015
10-Apr-2015

Comment

Page 13
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

8 TEST ENVIRONMENT BUILD STRATEGY


8.1 Test Environment
This section defines test environment requirements so that the necessary hardware, software, tools and
other infrastructure components can be assembled to create the test environment.

System Test/SIT will be performed in stand alone system test environment connected to
FileExpress server to receive source data from different source systems.

VF BICC UAT support will be provided in UAT environment created and maintained by IBM (will
be done based on UAT plan provided by VF BICC).

8.2 Test Data Strategy


Test data will be received from 3TM source system as menbtioned in detailed design document.

8.3 Test Tools


Activities
Test Management
Defect Tracking
Telnet
DBMS tools

Tool
Microsoft Excel
Microsoft Excel
Putty, Winscp
sql scripts

Version
Excel-2003
Excel-2003
Putty v 0.60
NA

8.4 Configuration Management

The build management process must be followed at all times. Promotion of code from the
development environment to the test environment will not be automatic. A process, which includes
the use of configuration management, will be created to manage code promotions. Email notification
will be sent to the test leads before code can be promoted to the test environment.

During System Test, the configuration management team will be restricted from promoting any
changes or defect correction to the test environment without approval from the test manager.

Builds will be delivered with unique names or numbers. Release notes defining the defect fixes
included in the build will be delivered to the test team prior to the installation of each build in to the
test environment.

Environment changes will not be accepted. If there is a need for any of these changes it will need to
be handled via the Project Change control process. Environment changes include changes to the
version of the OS, User access control or network control devices which may impact the interface
testing.

No separate configuration management tool will be used for version controlling of test assets.

Page 14
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

9 TEST MANAGEMENT & REPORTING


PROCEDURES
9.1 Test Management
Each phase of testing will be coordinated by team lead for the phases responsible group.
VF test manager will be the escalation point for IBM-BI. Also VF test manager will track and monitor the
progress of testing and all issues related to testing.

9.1.1 Defect Tracking/Management Procedures


Defects will be logged and tracked through Microsoft Excel tool.
Purpose:
Effectively manage the monitoring and resolution of defects found in deliverables during the project
lifecycle.
Ensure that all defects are resolved with minimum impact to the project.
Ensure that audit trails of defects are maintained and analyzed.
Capture the information needed in order to perform root cause analysis at the project level, to
identify opportunities for improving the quality of both the work product and the process with which it
was created.
Definition of Defect:
It is an aspect of a work product or a deliverable that does not meet its intended purpose. In contrast to
nonconformity, a defect can be viewed as an inadequacy with respect to needs or general expectations.
All defects that are found during work product inspections and testing will be logged in defect tracker.

Defect Workflow:
Page 15
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

Log Defect in defect tracker

Defect Verified by Dev Team

No

Defect
Accepted?

Yes

Close Defect

Assign Priority

No
Need to fix?

Yes
Defect is deferred
Assign Developer to fix

Defect is fixed and sent for


verification
Yes
Assign tester to verify

Verification
failed?

No
Close Defect

This procedure ends when:


Defects have been closed and any analysis of trends and root cause has been completed.

Page 16
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

Overview of the definitions of defect severity:


Defect Severity
Blocking

Severe
Minor
Informational

Severity Definition
Catastrophic defect with complete loss of a service. Work cannot reasonably continue,
the operation is mission critical to the business and there is no work around. In general,
a blocking defect would prevent the product from being released or would involve high
cost. E.g. Defect that cause system to crash.
Defect results in severely loss of a service. A work around may exist but its use is
unsatisfactory on the long term.
Defect causes failure of non-critical aspects of the system. There is a reasonably
satisfactory work around.
Defect of minor significance. A work around exists or, if not, the impairment is slight.
E.g. A button is slightly off centre on a data screen.

9.1.2 Change Management Procedures


Change management process will be followed as per current IBM process.

9.1.3 Progress Tracking Procedures


The purpose of the procedure is to keep test progress consistent with the plan and raise a flag if there is
any risk of deviation. Test progress and risks are tracked against the plan. Then decisions must are made
to ensure progress stays within the plan or to update the plan

9.2 Reporting
9.2.1 Test Progress Reporting
The relevant process reports for this test project are:
Test Result Report - This report will describe the status of each system test case with its steps as pass
or failed along with associated defects. This report will be sent to VF within a week of system test
completion. This is applicable only for system testing.
QA Summary Report: This report will contain the summary of test case execution status, % of test
cases executed vs pass/fail, defect summary report, risks and mitigation plan, overall project status. This
will be sent to VF with regular interval of each test phases.
System Test End Report Includes summary of test execution report, summary of test result report,
summary of open defects and is signed off by the IBM project manager stating that IBM is confident (or
not) to proceed to the SIT. The report is delivered to the VF Test Manager before the start of the SIT. This
is the same document QA Summary Report.
.

Page 17
Information Security Level 2 - Sensitive
Proprietary and Confidential Information of Vodafone and IBM

10 TEST DELIVERABLES:
10.1

System Test Cases

System test cases will be documented and tracked through excel. Test cases will be maintained as a
separate document.

10.2

Traceability Matrix:

Traceability matrix is to map the test cases with test goals and vice versa. Traceability matrix will be
maintained in QA Summary Report along with test coverage.

10.3

Test Result Report:

Test result report will be created for system testing only. This report contains a detailed execution status
of each test case along with associated defects. Test result report will be maintained as a separate
document.

10.4

QA Summary Report:

QA Summary Report will contain day to day execution status in each test level. This report includes:

10.5

Test case execution summary report


% of test cases pass/fail report
Defect summary report
Risk and mitigation plan
Overall project health based on the status of above reports

System Test End Report:

This is similar to QA Summary Report which will be captured at the end of system test. This report will contain all
the details as mentioned in QA Summary Report along with IBM advice to go/no-go for the next level of testing.