FORWARD
Design And Development Forum (DDF) is a professionally managed autonomous
organization. The main functions of DDF are to provide research and consultancy
services in the areas, which have bearing on the creation of infrastructure and built
environment. These include, among others, Design and Development of Human
Settlements, Regional and Urban Planning, Transportation Planning and Engineering,
Environmental Planning and Architectural and Engineering Design. Important area
where DDF has excelled is in the field of feasibility and impact assessment studies.
Key personnel of DDF have worked in India and abroad and have won competitions
and awards for outstanding work.
Haryana Infrastructure Development Board has appointed DDF to prepare the City
Development Plan of eighteen towns of five districts of Haryana State. The three
towns of Jhajjar districts are Jhajjar, Bahadurgarh and Beri. The district headquarter
of Jhajjar is an important NCR town.
This CDP presents a comprehensive perspective of Jhajjar Town, its spatial
characteristics, infrastructure and industrial profile, socio-economic characteristics,
strengths and weaknesses. The proposals made in the Development Plan of Jhajjar for
the year 2021 have been discussed in this report. Inferences have been drawn through
analysis of various existing infrastructure facilities like water supply, sewerage, solid
waste management etc. Major findings and proposals for integrated development of
Jhajjar Town in short-term and long-term perspective are discussed in the report.
Financial implications are also worked out.
The report is the outcome of hard work put in by multidisciplinary team, consisting
of, among others, Regional and Urban Planners, Engineers, Social Scientists and
economists. DDF appreciates the support provided by DC office, Municipal
Committee Jhajjar, PHED, RTO, DIC, TPO, DSO in data collection and
understanding the problem at grass root level.
New Delhi
Amit Bose
Development Planner
ii
LIST OF CONTENTS
Contents
List of Tables
List of Figures
List of Photographs
List of Maps
Abbreviations & Units
1
Introduction....................................................................................................1
1.2
1.3
Scope of CDP.................................................................................................2
1.4
2.2
Introduction....................................................................................................6
2.3
History............................................................................................................6
2.4
2.5
Physiographic Features..................................................................................7
2.6
Climatic Conditions.......................................................................................7
DEMOGRAPHIC PROFILE.................................................................................9
3.1
Introduction....................................................................................................9
3.2
Growth Trend.................................................................................................9
3.3
3.4
3.5
Literacy........................................................................................................10
3.6
3.7
Occupational Pattern....................................................................................11
3.7
3.8
Introduction..................................................................................................14
4.1
4.2
iii
4.3.1
4.3.2
4.3.3
Zoning Regulations..............................................................................18
4.3.4
4.3.5
4.3.6
4.3.6.1
4.3.6.2
Strategy Options...................................................................................20
4.3.7
Policies.................................................................................................20
4.3.7.1
Introduction..................................................................................................23
5.2
5.2.1
5.2.2
Industries..............................................................................................24
5.2.3
Agricultural Sector...............................................................................24
5.2.4
Informal Economy...............................................................................25
5.3
5.4
5.4.1
5.4.2
5.4.3
5.4.4
5.4.5
5.4.6
5.4.7
Strategy Options...................................................................................27
Background..................................................................................................28
6.2
6.3
Heritage Sites...............................................................................................29
6.2.1
Shaheedi Park.......................................................................................29
6.2.2
Clock Tower.........................................................................................29
iv
6.2.3
6.2.4
6.2.5
6.4
Water Bodies................................................................................................30
6.5
6.6
6.1.1
Strategies..............................................................................................31
6.1.2
Financial Implications..........................................................................34
WATER SUPPLY.................................................................................................35
7.1
Introduction..................................................................................................35
7.2
Existing Status..............................................................................................35
7.2.1
7.2.2
Coverage..............................................................................................35
7.3
7.4
7.5
7.5.1
Vision...................................................................................................37
7.5.2
Strategies..............................................................................................44
7.5.2.1
7.5.2.2
7.6
8
Financial Implications..................................................................................45
SEWERAGE........................................................................................................47
8.1
Introduction..................................................................................................47
8.2
Existing Scenario.........................................................................................47
8.3
8.4
8.4.1
8.4.2
8.4.3
8.4.4
8.4.5
Increasing complaints...........................................................................49
8.5
8.4.6
8.4.8
Strategies..............................................................................................56
8.4.8.1
Short-Term Strategy.............................................................................56
8.4.8.2
8.4.8.3
8.6
9
Financial Implications..................................................................................57
DRAINAGE.........................................................................................................58
9.1
Introduction..................................................................................................59
9.2
Existing Status..............................................................................................59
9.3
9.4
9.4.1
Vision...................................................................................................60
9.4.2
Strategies..............................................................................................60
Financial Implications..................................................................................62
SOLID WASTE MANAGEMENT..................................................................63
10.1
Introduction..................................................................................................63
10.2
Existing Status..............................................................................................63
10.2.1
10.2.2
10.2.3
10.2.4
10.2.5
Street Cleaning.....................................................................................65
10.2.6
Transportation of Waste.......................................................................65
10.2.7
Disposal of Waste.................................................................................66
10.2.8
10.3
10.4
10.5
10.5.1
Vision...................................................................................................67
10.5.2
Strategies..............................................................................................72
10.5.2.1
10.5.2.2
vi
Financial implications..................................................................................73
ELECTRICITY................................................................................................74
11.1
Introduction..................................................................................................74
11.2
Existing Status..............................................................................................74
11.1.1
Electricity Consumption.......................................................................74
11.1.2
Demand-Supply gap.............................................................................75
11.1.3
Tariff Structure.....................................................................................75
11.3
11.4
11.4.1
Vision...................................................................................................76
11.4.2
Strategies..............................................................................................77
11.4.3
11.5
12
Financial Implications..................................................................................77
TRAFFIC AND TRANSPORT........................................................................78
12.1
Introduction.................................................................................................78
12.2
Existing status..............................................................................................78
12.2.1
12.2.2
Transport Facilities...............................................................................78
12.2.3
12.3
12.4
12.4.1
Vision...................................................................................................81
12.4.2
Strategies..............................................................................................81
12.4.2.1
12.4.2.2
12.4.2.3
12.4.3
12.5
13
Freight Expressway..............................................................................88
Financial Implications..................................................................................88
SOCIAL INFRASTRUCTURE.......................................................................89
13.1
Introduction..................................................................................................89
13.2
Existing Status..............................................................................................89
13.2.1
Education..............................................................................................89
vii
Health...................................................................................................89
13.2.3
13.2.4
13.3
13.4
14
14.1
Introduction..................................................................................................94
14.2
Existing Status..............................................................................................94
14.2.1
14.2.2
14.2.3
14.2.4
14.2.5
14.2.5.1
Drainage..........................................................................................96
14.2.5.2
Pavements/Roads.............................................................................96
14.2.5.3
14.2.5.4
Street Lighting..................................................................................97
14.2.5.5
Water Supply.....................................................................................97
14.2.6
14.2.7
14.3
14.3.1
14.4
14.4.1
Vision...................................................................................................99
14.4.2
Strategies............................................................................................102
14.5
15
Financial Implications................................................................................103
MUNICIPAL FINANCE................................................................................104
15.1
Introduction................................................................................................104
15.2
15.2.1
15.2.2
Municipal Income..............................................................................105
15.2.3
Municipal Expenditure.......................................................................107
15.3
viii
15.4.1
Vision..................................................................................................110
15.4.2
Strategies............................................................................................110
15.4.2.1
Accounting System:........................................................................110
15.4.2.2
E-Governance System:..................................................................110
15.4.2.3
House Tax:.....................................................................................110
15.4.2.4
Land as a resource..........................................................................111
15.4.2.5
User charges...................................................................................112
15.4.2.6
15.4.2.7
Capacity Building...........................................................................112
15.4.2.8
Municipal Bonds.............................................................................113
15.4.2.9
Right Sizing..................................................................................113
15.4.2.10
16
URBAN ENVIRONMENT............................................................................115
16.1
Introduction................................................................................................115
16.2
Problematic Areas:.....................................................................................115
16.2.1
16.2.2
Water Pollution:.................................................................................116
16.2.3
16.2.4
Land Pollution:...................................................................................117
16.2.5
Recommendations:.............................................................................118
16.3
17
Conclusion..................................................................................................119
DISASTER MANAGEMENT.......................................................................120
17.1
Introduction................................................................................................120
17.2
Earthquake..................................................................................................120
17.3
Fire Hazard.................................................................................................121
17.4
Floods.........................................................................................................122
17.5
Proposals:...................................................................................................122
18
VISION..124
18.1
Background................................................................................................124
18.2
Introduction................................................................................................124
18.3
SWOT Analysis..........................................................................................125
18.4
Investment Plan..........................................................................................127
ix
19.1
Background................................................................................................128
19.2
Monitoring Unit.........................................................................................129
19.3
Plan Review...............................................................................................129
19.4
LIST OF TABLE
Table 3.1:
Table 3.2:
Table 3.3:
Table 3.4:
Table 3.5:
Table 3.6:
Table 4.1:
Table 4.2:
Table 5.1:
Table 7.1:
Table 7.2:
Table 7.3:
Table 7.4:
Table 7.5:
Table 7.6:
Table 8.1:
Table 8.2:
Table 8.3;
Table 8.4:
Table 8.5:
Table 8.6:
Table 8.7:
Table 8.8:
Table 9.1:
Table 9.2:
Table 9.3
Table 10.1:
Table 10.2
Table 10.3:
Table 10.4:
Table 10.5:
Table 10.6:
Table 10.7:
Table 11.1:
Table 11.2:
Table 11.3:
Table 11.4:
Table 11.5:
Table 12.1:
Table 12.2:
Table 12.3:
Table 13.1:
Table 13.2:
Table 14.1:
Table 14.2:
Table 14.3:
Table 14.4:
Table 15.1:
Table 15.2:
Table 17.1:
Table 18.1:
10
11
11
12
12
13
15
19
24
36
37
38
38
39
43
47
49
50
51
51
52
53
55
60
60
61
64
66
67
68
69
70
71
74
75
76
76
77
78
81
82
90
92
95
100
101
102
106
107
122
127
xi
LIST OF FIGURES
Figure 1.1:
Figure 3.1:
Figure.3.2
Figure 4.1:
Figure 4.2:
Figure 10.1:
Figure 12.1:
Figure 15.1:
Figure 15.2:
Figure 15.3:
Figure 18.1:
4
9
12
15
21
63
79
104
107
109
124
LIST OF PICTURES
Photo 4.1:
Photo 4.2:
Photo 5.1:
Photo 5.2:
Photo 6.1:
Photo 6.2:
Photo 6.3:
Photo 6.4:
Photo 6.5:
Photo 6.6:
Photo 6.7:
Photo 6.8:
Photo 6.9:
Photo 9.1:
Photo 9.2:
Photo 10.1:
Photo 10.2:
Photo 10.3:
Photo 10.4:
Photo 11.1:
Photo 12.1:
Photo 12.2:
Photo 12.3:
Photo 12.4
Photo 12.5:
Photo 12.6:
Photo 13.1:
Photo 13.2:
Photo 14.1:
Photo 14.2:
Town Area
Clock Tower
Mandi Near Mini secretariat
Commercial Establishments
Shaheedi Park
Clock Tower
Baba Gazi Kamal Pond
Kanak Champa and Toot
Jacaranda
Weeping Bottlebrush and Dhak
Amaltas
Kachnar and Pink Trumphet
Snapdragon, nasturtium and Periwinkle
Open surface drainage Network
blocked Rainwater causing nuisance
Solid waste lying along road
Solid waste Collection points
Transportation of solid waste
solid waste dumping site
Power House
Roundabout in Jhajjar
Congestion on Roads
Internal Roads
Bad condition of Roads
Katcha Road, Jhajjar
Encroachment by the informal sector
Shaheedi Park
Fire office, Jhajjar
Slums in Jhajjar
status of Infrastructure in slums
14
14
23
23
29
29
30
32
32
33
33
33
34
59
59
64
65
65
66
74
78
79
79
80
80
80
89
90
94
94
xii
LIST OF MAPS
Map 2.1:
Map 2.2:
Map 3.1
Map 6.1
Map 7.1
Map 8.1
Map 10.1
Map 12.1
Map 17.1:
5
7
9-10
29-30
35-36
47-48
63-64
78-79
120
LIST OF ABBREVIATIONS
ASI
AUWSP
BPL
CBOs
CDP
CEZ
CPHEEO
DIC
DMA
DUDA
GIS
GT
HSIDC
HUDA
IDSMT
IEBR
IHSDP
INTACH
IPT
IRBT
ITI
JNNURM
LCS
LRT
MCJ
MIS
MOU
NCR
NCRPB
NCT
NGO
NH
NOC
NSDP
PHE
xiii
LIST OF UNITS
Ha
KM
KV
lpcd
MCM
MGD
mld
MT
MW
sq km
Hectare
Kilometer
Kilo Volt
Liter Per Capita per Day
Million Cubic Meter
Million Gallon per Day
Million Litres per Day
Metric Tonnes
Mega Watt
Square Kilometer
xiv
1.1 Introduction
The Government of India has launched Jawaharlal Nehru National Urban Renewal
Mission (JNNURM) programme for promoting reforms and investments for selected
cities with focus on efficiency in urban infrastructure, community participation and
accountability of Urban Local Bodies (ULBs). The scheme requires states and ULBs /
parastatal organizations to undertake a set of reforms at each level. Parallel to this, Urban
Infrastructure Development Scheme for Small and Medium Towns (UIDSSMT) aims for
improvement in urban infrastructure in towns and cities in a planned manner but this
scheme applies to all cities/towns as per 2001 census, except in cities/towns covered
under Jawaharlal Nehru National Urban Renewal Mission (JNNURM). It has subsumed
the existing schemes of Integrated Development of Small and Medium Towns (IDSMT)
and Accelerated Urban Water Supply Programme (AUWSP). The duration of the scheme
is for seven years beginning from 2005-06.
At the same time, Integrated Housing & Slum Development Programme (IHSDP) aims at
combining the existing schemes of Valmiki Ambedkar Awas Yojana (VAMBAY) and
National Slum Development Programme (NSDP) under the new IHSDP Scheme for
having an integrated approach in ameliorating the conditions of the urban slum dwellers
who do not possess adequate shelter and reside in dilapidated conditions. Like UIDSSMT
Scheme, IHSDP is also applicable to all cities/towns as per 2001 census, except in
cities/towns covered under Jawaharlal Nehru National Urban Renewal Mission
(JNNURM).
Jhajjar town is not among the sixty-three cities identified under the JNNURM. However,
the aim of planned and integrated development of Jhajjar town can be served by the
UIDSSMT and IHSDP schemes. Considering this, the Government of Haryana has
initiated steps for preparation of City Development Plan (CDP) to promote planned and
integrated development of selected towns and cites of Haryana and Jhajjar is among those
selected towns.
Urban Infrastructure
Financial Management
Defining the growth directions and the need for up-gradation of services in the
town
Defining existing water bodies like ponds, lakes etc. in the town and assess the
technical and financial resources needed to revitalize them.
Defining specific capital investment needs for rehabilitation and additional capital
investment needs in both the core city and in urban poor areas.
Assessing the gap in financial resources for meeting the investment needs
STAGE I
Literature Review
NCR Plan
State Plan
District Annual Plan
Master/Development
Plan
Project Plan
Chapterisation
STAGE II
Data Collection
Secondary Survey
Location and Regional
settings
Physiographic
Features
Socio-economic
Profile
Traffic and Transport
Infrastructure
Municipal finances
Site Inspection
Visual and
Photography
STAGE III
Data Analysis
Existing status
Demographic Profile
Economic Base
Land Use Pattern
Infrastructure:
Physical and Social
Heritage and
Environment
Traffic and Transport
Municipal finances
Proposals
STAGE IV
Issues Identification
Identification of
issues for each
aspects
Constraints
Aspirations
STAGE V
Recommendations
Conclusions
Recommendation
Financial Implications
DEVELOPMENT PLAN
Plan PrposalsState/NCR/District
Population Projection
Infrastructure
Demand and Supply
The key stakeholders viz., Municipal Committee of Jhajjar (MCJ), Department of Public
Health, District Industrial Centre (DIC) Jhajjar, Haryana State Industrial Development
Corporation (HSIDC), Haryana Urban Development Authority (HUDA), Haryana Vidyut
Prasaran Nigam, District Planning Office, District Statistical Office, Regional Transport
Office etc. have been approached for dissemination of information on subject under their
control. The CDP has been conceptualized considering the status acquired by Jhajjar as a
strategic destination for various activities and initiatives planned by Haryana State
Government.
Jhajjar
2.2 Introduction
Jhajjar is one of the growing urban centers in the state of Haryana and the government of
Haryana, recognized the importance of Jhajjar town and declared it as district
headquarters on July 15, 1997.
2.3 History
Jhajjar has a rich historical heritage. The history of town dates back to medieval age and
according to the legend, the town found 1300 years ago. The town is believed to be found
by Chajju, in whose name, the name of the Jhajjar town has been derived as Jhajju and
thereafter Jhajjar. The places of antiquity in the town include the tomb and tank of Shah
Ghazni Kamal and a group of seven large tombs of local celebrities. There is Gurukul at
Jhajjar, found in 1915 AD which has a rich collection of ancient coins, moulds, seals,
inscriptions, which throw a light on the past life of the people inhibiting the region in
general and town in particular.
DEMOGRAPHIC PROFILE
3.1 Introduction
The demographic characteristic, a major component in the formulation of a CDP, is
analyzed in terms of the pattern of population growth and its spatial spread within the
city. The analysis reflects its population growth as excessive by natural increase, inmigration and jurisdictional increase. The social composition of the towns population has
been analyzed through indicator like persons below poverty line, scheduled caste and
scheduled tribe persons, age and sex structure and labour force.
The town had a declining growth rate in all the decades from 1951-1991, where as it
registered the highest growth rate of 40.8% during the last decade due to recognition of
the Jhajjar town as the district headquarters during 1997,resulting very high rural-urban
migration from surrounding areas for jobs. Shifting of district level offices and
construction of mini secretariat added attraction to the town.
Considering the high growth rate in the previous decade, planning for induced economic
activities the population projections for the year 2011 and 2021 are done on an average
growth rate of 60%. As per development plan of Jhajjar town, 2021.
Population
24247
27693
39004
Gross density(ppsqkm,)
4041
4616
6500
As shown in Table 3.1 the gross density has been steadily increasing from 4041 persons
per sq km in 1981 to person per sqkm in 2001. Density of 65 persons per hectare is low
when compared with the standard, UDPFI guidelines recommends density of a small
town (Population less than 50,000) to be 75-125 ppha. This indicates scope for re
densification of the existing town area.
3.5 Literacy
Literacy rate of the town was 80.1% as per 2001 census, which is higher when compared
to the district average of 72.4%. Female literacy was 70.5% which is much higher than
the district average of 59.5%.
10
Male
Female
Population
20976
18026
SC Population
3858
3369
Source: District statistical Handbook, Jhajjar
Total
160735
7227
Categories
of No. of Workers
Employment
Cultivators
1306
Agricultural
579
labourers
Household
732
Industries
Other than H/H 10725
industries
Total Workers
13342
(Source:
Census of India 2001)
Figure 3.2
Workers in Jhajjar in
%
age
workers
9.8
4.3
of
Total
5.5
80.4
34.2
Distribution of
2001
11
Overall
Worker
Cultivators
Male
Female
Total
Household
workers
307
Other
workers
8335
Total
809
Agriculture
workers
305
497
1306
274
579
425
732
2390
10275
3586
13342
9756
Eighty Two percent of total workers are from the segment of other activities while only
Eighteen% of total workers are engaged in agriculture, cultivation and household
activities. (Refer Table 3.4 and figure 3.2) The household workers constitute more of
females which clearly shows the tendency of the females to work from home. This should
be kept in mind while developing any kind of infrastructure for females. .(refer table 3.5)
Table 3.5 Work Participation in Jhajjar 2001
Category of
Worker 2001
Workers
Main Workers
Marginal Workers
Total Workers
Non Workers
Percentage to
Total Population
Total
10960
2382
13342
25660
Male
8655
1101
9756
11220
Female
2305
1281
3586
14440
28.1
6.1
34.2
65.8
In 2001, 82% of the total workers are the main workers while only 18% constitutes to
marginal workers. The main workers constitutes more male population while the marginal
workers constitute more of female population. While more number of females than males
are not working at all.
12
Year
1951
1961
1971
1981
1991
2001
2011*
2021*
Population
10514
14234
18947
24247
27693
39004
62407
99851(100000)
Percentage
Growth (%)
35.4
33.1
28.0
14.2
40.8
60.0
60.0
13
4.1 Introduction
Land and its use form the base of any development. Land is the most crucial economic
tool for planned development of the urban areas and achievement of social objectives
through its judicious allocation for future use.
The Town has been planned keeping in view the present trend, physical constraints, and
future possibilities of growth for a population of 100000 in 2021 AD. Most of the vacant
areas around the existing town have been found sufficient to accommodate the population
of 100000 in 2021. The whole town has been divided into 17 wards. The major land uses
characteristics have been given in table 4.1and figure 4.1.
Design and Development Forum
14
Area(in hectare)
Residential
Commercial
Industrial
Institutional
Roads/Transport
Parks/open area
Total area
525
60
110
190
170
120
1125
38
5
8
13
12
8
100
4.3.2
Keeping in view the above facts and consideration various land uses have been proposed
with town planning principles for a population of 1 lakh by 2021 A.D.
Residential
Jhajjar town has been proposed to be developed for projected population of 1 lakh
persons by 2021 AD. The existing town would accommodate about 20,000 persons in the
long run. The rest of the population would be accommodated in new residential sectors
with average net residential density of 225 persons per hectare. The sector adjoining to
industrial sector has been proposed to be developed at higher residential density of 250
persons per hectare whereas other sectors have been proposed to be developed with
residential density of 200 persons per hectare. The sectors proposed for residential
purpose are 2, 5, 6, 7, 8, 9, 11, 12, 12A and 13 sectors.
Commercial
An area of 60 hectare has been proposed to be developed for commercial use in sector-1.
This sector would also function as a city centre. The above commercial area also includes,
15
Public Utilities
An area of about 95 hectare has been proposed for the development of public utility
services like provision of water supply, electric grid sub-station and disposal work etc. In
addition to the existing 132 KV. Sub-Station located on Jhajjar Gurgaon Road, another
sub station has been proposed on Jhajjar-Bahadurgarh Road asper requirement of the
electricity department. The capacity of existing Jhajjar out fall drain is to be enhanced to
carry sewerage and storm water of the town for its ultimate fall in Drain No. 8. also an
area of 36 hectare is proposed for water works and electric sub- station on Bahadurgarh
and Gurgaon roads respectively. For solid waste, disposal, an area of about 10 hectares
16
17
4.3.3
Zoning Regulations
The legal sanctity to the proposals regarding land use is being given to the effect by a set
of zoning regulations which from a part of this development plan. These regulations will
govern the change of land use and standards of development. They also will elaborately
detail out allied and ancillary uses which will be permitted in the various major land uses
and stipulate that all change of land use and development shall be in accordance with the
details shown in the sector plan thereby ensuring the preparation of detailed sector plans
for each sector to guide the development and enforce proper control
4.3.4
There are three government owned vacant sites available in the city. One of these is
having bus stand. This land can be developed to locate underground parking, and
Informal sector activities on first floor. Beside they may be permitted to roam around in
the city for four hours a day i.e. from 8a.m. to 10a.m. and 5p.m. to 7p.m in designated
localities. The rest of the time they can do their business by standing in this allotted
spaceon nominal charges. They can park their rehdis in the parking space in the basement
The second floor will have Institutional (office) use. Initially the above suggested plan
can be followed but in later stages the bus terminal which is located in the heart of the
city must be shifted in outer areas of the town
The second site located in ward No.11 had a depression which has been filled up and now
the area is proposed to have a commercial complex and parking space.
The municipality office is proposed to be shifted from the existing fire office building to
the clock tower which will also house the library. Once this office is shifted, the shops
abutting the entrance on the clock tower have to be relocated. These shops can be shifted
to the vacant land near Police station and above city bus stand.
Beside, public toilets i.e. eco toilets should be constructed at all above specified location
as well as in Shaheedi park and in newly developed bus stand in HUDA area.
18
The projected population for 2021, of Jhajjar, will be 100000. The total municipal area is
6 sqkm while the proposed planning area is 11.25 sqkm. The percentage of the area
supposed to be allocated to different land uses according to the UDPFI guidelines is given
below in the table 4.2
Table 4.2: Land Use for 2021 according to UDPFI Guidelines
S. No.
Land Use
1
Residential
2
Commercial
3
Industrial
4
Transport & Communication
5
Public and Semi-Public Uses
6
Green Belts and Open Spaces
Total
Source: UDPFI Guidelines
% of Total
45
4
10
14
12
15
100
Area (hectares)
506.25
45.0
112.50
157.50
135.0
168.75
1125
In the above table the land uses are taken on the basis of the vision which is developed
looking at the current trend of growth of the area and near by towns surrounding it like
Bahadurgarh a Industrial centre and proposal of SEZ and construction of Kundli, Palwal
and Manesar Expressway; more residential facilities are required for the town to
accommodate the projected population.
4.3.6
4.3.6.1
Although Jhajjar town has a potential to develop as an Industrial town but to strengthen
the industries and economy of a town, there is a need to have a good infrastructure base.
As specified in UDPFI guidelines the industrial use for this kind of town should be
between 8%-10% of total land use. But in case of Jhajjar, land under industrial uses is
17%. Which established that Jhajjar town will be induced to develop as an industrial town
of Haryana state. For the Industrial development existing infrastructure in terms of
quantity and quality is inadequate in Jhajjar. Which need to develop to sustain industrial
activities.
The current population is largely concentrated in the core city area, resulting in
enormous stress on the infrastructure concentration in core city area and
deteriorating quality of life, apart from increasing disaster vulnerability.
The primary barriers to the urban sprawl are the inadequate coverage of
infrastructure throughout the city.
19
Strategy Options
State Government and the Municipal Committee should make a conscious efforts in
controlling the city sprawl in a phased and planned manner, adopting best practices in
urban development and planning norms. There is an opportunity in the form of
availability of large developed tracts of land in around the town where development can
be planned and regulated in a phased manner. The growth management strategy should
thus focus on:
Controlling and guiding urban sprawl in a phased manner applying modern
principles of physical planning and growth management.
Planning and providing for infrastructure, including connectivity in the line with
the intended growth plan, rather than attempting to only service already congested
areas the focus should be dispersing growth more evenly across the city.
Applying innovative methods of using land as a resource to finance development,
like TDR, FSI banks and land pooling mechanism like the TP scheme, etc.
Formation of a Special Planning Authority covering Jhajjar municipal area and
urban fringe areas, to arrest indiscriminate sprawl and ensure equitable and
sustainable urban development.
4.3.7
4.3.7.1
Policies
Alternate Development Strategies
Sustainable Urban Development in Jhajjar District:
Jhajjar
Design and Development Forum
20
Infrastructure
Spinal Cord
Intermediate Towns
Delhi
Figure 4.2 Corridor Development
The available infrastructure and its potential must be exploited to the maximum extent.
Corridors with the high growth potential can be identified and developed for future
urbanization. A typical corridor of about 65 km connecting Jhajjar with Delhi would be
ideal for the pilot scheme which can be extended further. The corridor consisting of
railway, highway, pipeline, H.T.power line and communication lines would form the
infrastructure spine. (refer figure 4.2)
There is a need to arrest the migration from the rural areas and small towns to large cities
and encourage reverse migration to rural areas through creation of job, improving the
quality of life, providing basic amenities and improved access to the city. This will lead to
insitu urbanization of select rural locations. This calls for providing urban amenities in
rural areas besides providing employment and income generation avenues.
Commercialization
Infrastructure and habitat development would involve seed capital and recurring
investments in operation and maintenance. This would be possible through introduction
of commercial principles in recovering the cost from the beneficiaries through a host of
user pay instruments. The principle of user pay, abuser pay and polluter pay needs
to be utilized to ensure cost recovery.
Privatization
21
Every mega project needs resettlement and provides potential and new opportunities.
New mega industrial projects, SEZs and Food processing industries provide basic jobs
and create multiplier effect for other related employment opportunities.
The industrial houses from these anchor industries have to be attracted in the planning
stage itself. The local resources should be appropriately identified and used in supporting
the industrial requirements while planning, implementing development of the town.
22
5.1 Introduction
The economic base refers to the key sectors that drive the citys economy. The analysis
has been focused for identifying the lead sectors of the towns economy, and examining if
the growth within the lead sectors likely to be maintained in a medium-term framework.
The workers population indicate an increasing pattern from last three decades, being the
commercial activity, predominate the scene. The town of Jhajjar is traditionally the
agricultural market center for the hinterland. It acts a commercial center to retail activities
dealing in consumer goods located near bus stand, etc. There was a new Anaj mandi
(Grain Market or Agricultural Produce market) located within the town with shops and
platforms to auction various agricultural commodities. A market committee was
managing the market. In addition there were several private shops and municipal markets.
There were about 3122 shops/ establishments located in the town. There was a persistent
demand for the commercial spaces in the town despite the presence of the above
establishments due to vibrant trade and commerce activities. Ward wise distribution of
shops etc are shown in Table 5.1.
Photo 5.2 Mandi
PhotoNear
5.2 Mini
Commercial
Secretariat
Establishments
23
Establishments/shops
Office
Hotels/
817
182
32
20
118
138
63
215
187
157
65
252
252
405
219
3122
Complexes
564
159
25
119
28
42
88
42
9
17
10
41
38
136
469
1787
Restaurants
1
1
1
3
Total
1382
341
57
139
146
180
152
257
196
174
75
293
291
541
689
4913
It is quite evident from the table 5.1 that ward no. 1, 15, 14, 2, 12, 13 and 8 are highly
commercialized areas, having more than 200 commercial establishments.
5.2.2
Industries
The town was observed to be less industrialized as main industries are located in the near
by town of the district. However some small scale industries were located in the town like
katha manufacturing, rubber, wooden furniture, agricultural machinery, marketing of
agricultural machinery etc. It was serving as mandi cum service town dealing with
marketing of agriculture produces and allied products as well an administrative centre.
5.2.3
Agricultural Sector
In the agriculture sector the town has been supplying locally manufactured conventional,
as well as modern tools and implements. Educational and training programmes are being
run by the agriculture Departments for the welfare of the farmers.
5.2.4
Informal Economy
There is a sizeable presence of informal sector activities and enterprises in Jhajjar town,
which produce comparatively inexpensive goods and services while providing abundant
opportunities for self-employment to a large section of population. This unorganized
sector has to be recognized as an important segment of urban human activity, which is
making positive contributions to the growth, and economic development of the town.
24
5.4.1
The state will take effective measures to promote entrepreneurship for rapid
industrialization of the state. EDP need to be organized with special purpose on rural
youth and women. Non Government organization and industrial association will be fully
involved in finalizing the curriculum for the training programmes and for organizing
EDPs.
5.4.2
25
i)
Mega project with investment of Rs. 100 crore and above or any project
employing more than 500 persons irrespective of investment to be set up in the
backward areas would be extended the facility of financial assistance at 50%
of the tax paid on the sale of goods produced by such industrial units, under
the Haryana value added tax act, 2003 for the period of 7 years from the date
of start of commercial production.
ii)
Exemption from local area development tax (LADT) for a period of 5 years.
5.4.4
New SSI units in the backward areas would be extended the facility of financial
assistance in the shape of interest free loan to be quantified at 50% of the tax paid on the
sale of goods produced in such industrial units, under the Haryana value added tax act,
2003 for a period of 5 years from the date of start of commercial production to be
repayable after a period of 5 years.
5.4.5
In order to boost the exports and enhance competitiveness of exporting units, subsidy
upto 1% of the FOB value of exports subject to maximum of Rs. 10 lacs per annum shall
be given.
5.4.6
Various incentives such a market fee exemption, interest fee loan at 75% of the tax paid
on the sales of goods produced in such industrial units shall be given HVAT Act 2003 for
a period of 5 years from the date of start of commercial production. This would be
repayable after a period of 5 years. Charges for change of land use exempted upto 50%
special priority for release of electric connection etc. shall be applicable to the units
coming in commercial production after the commencement of new policy. No market fee
shall be levied on agricultural and horticulture.
26
Strategy Options
Jhajjar has unique inherent economic drivers that could be nurtured and promoted in a
systematic manner to generate high overall economic growth. The key inherent economic
drivers for the town lie in the services sector, including education, health and trade &
commerce. There is potential for industrial development in the region, as well given the
availability of water, land and strategic regional setting by way of proximity to
Chandigarh in the north and Hisar in the south.
Some of the strategy options include:
Promote industrial and overall economic development by capitalizing on inherent
strengths like abundance of water and proximity to regional centers like
Bahadurgarh, Ambala and Chandigarh.
Improving and strengthening regional connectivity
Developing infrastructure and leisure facilities in Jhajjar aimed at providing a
good quality of life to attract and retain good quality manpower in the areas of
hospitality, education, health care services industry managers and skilled
workforce.
Develop leisure/entertainment facilities in the immediate short term including
beautification of towns landscape.
Branding and marketing of Jhajjar in national international context.
Develop local skill of shoe making in the international context.
Develop riverfront including heritage walkway, bathing ghats and sanitation
facility.
27
6.1 Background
Heritage is what we receive from the past. It shapes our present identity and provides
insight for our future. It includes a range of activities such as stewardship, preservation,
research, education and engagement. It encourages sensitivity to the indigenous natural
environment, to the impact of human activity on the natural environment, as well as to
differing perspectives regarding objectives, ideas, places and traditions.
Water bodies as resource give a character to the town. Water bodies act as recharge zones
and can be developed as a recreational center with various allied activities. Similarly, the
heritage sites/buildings give an identity to the town. However, these sites/buildings are
not conserved properly.
28
Shaheedi Park
This area is dominated by the existence of artistically designed group of seven large
tombs of local celebrities including a tank of Shah Ghazni Kamal and a large ghat of 17
steps flanked by two octagonal towers made in 1626AD.
6.2.2
Clock Tower
The Samadhi is situated in the western part of Jhajjar in a beautiful Vatika and temple
where a Bhandra is held every year on 1st January.
6.2.4
This beautiful temple is situated in ward No.5 on approx.400 sq.yds. of land. This temple
is presently running an free Eye Treatment centre in its campus. This temple is run by a
trust.
6.2.5
Kakra wala Peer situated at Gwalison road approximately 1.5 Km from the city on
4 acres of land.
29
Pancholi wala Peer again situated at Rohtak road approximately 1.5 km from the
city.
30
Strategies
The Clock tower and Johad/pond which are present in the town need to be
developed as recreational sites. The Johad/pond has water in all season. Therefore
for development as a recreational site we have to develop different recreational
activities like, boating etc. This will help in recharging water table, development
of town level park at pond side and throughout the year activities on this secluded
stretch of land. Private partner may be involved to participate in the development
water front or recreational site. The sites even if outside the municipal limit but in
the near vicinity of the town can be developed and integrated with the the heritage
sites in the town. Old clock tower can be conserved as a historic site of the town
which shows the history of the town. Some part of open spaces can be developed
as an amusement park so that tourist attraction increases in the town and play an
important role in Jhajjar economy.
Private partner may be involved to participate in the development of recreational site. For
the convenience of general public, one guide map should be provided at each of the major
entry to residential areas of the town. Thus, there may be three to four guide maps per
sector/ ward/ mohalla. One guide map of sector/ ward/Mohall may also be provided in the
shopping area. One guide map indicating development plan/ master plan of the residential
areas of the town may be provided at each major entry of the town. The advertisement
right at the bottom of the Guide Map may be given to the professional agencies on PPP
basis against which the agency shall provide and maintain the said Guide Map for a
minimum period of three years.
Besides this city as a whole can be beautified by planting of more trees and plants, which
give city a different and soothing looks. Following species can be planted in roundabouts
or in parks or at a specified location:
1. Semal ( Bombax Ceiba):
Identifying characters: A towering tree. Flowers are large, deep red, coral or yellow
with five waxy petals. The bark is ashen and smooth.
Flowers: In March
Fruits: Ripen and split open in May releasing microfibres in air.
31
5. Weeping Bottlebrush
Identifying characters: A willow tree with bright scarlet spiky flowers on long sta
mens. The fruits are small, woody and cup shaped.
Flowers: In February- March
32
33
6.1.2
Financial Implications
Rs. 6 Crore
34
WATER SUPPLY
7.1 Introduction
The infrastructure profile refers to the status of infrastructure and utility systems in the
town. Its analysis has been indicated the adequacy or inadequacy of infrastructural
services in terms of coverage, quantity, and quality. The gap between demand and supply
of different infrastructural services has been measured. The cost of delivering services
and recoveries made from them has been also reviewed.
Urban growth both spatially and population wise puts pressure on infrastructure,
particularly water supply, sewerage, solid waste, drainage, electricity, traffic and
transportation etc. Unless infrastructure is improved to the required level, quality of life
suffers. Most importantly, it influences economic development of the city and investment
climate.
The Haryana Public Health Engineering Department provides and maintains water supply
and sewerage facilities in Jhajjar. This department is responsible for planning, design,
construction, implementation, maintenance, operation & management.
The present water supply of the town is depends mainly upon canal system. Jhajjar Town
is having population 39004 persons as per 2001 census. The main source of water supply
is Yamuna canal. Subsoil water is brackish and unfit for drinking purpose.
The total supply hour is 8 hours i.e. 6 am to 8 am in the morning, 4 pm to 6 pm in the
evening.
Presently NCR has given 10.97 crore to improve the water supply network of Jhajjar
town and to achieve the 135 lpcd target. The balance 3.8 crores is also there with public
health to augment the present water supply network. The ongoing scheme still have 2
years for its completion.
7.2.2 Coverage
The existing water generation capacity is 4.5 mld, As per PHEDs claim 74% of the total
population and 74% of the Municipal area is covered under potable water supply scheme.
At present 110 lpcd water is supplied to the town. 52 kilometer of distribution line is
spread over 80% of the town area.
35
Canal/TW
4.5
110
2
2
2
52km
74%
74%
5052
36
Vision
The vision is to enhance the coverage and access to piped water supply in Municipal
area to 100% and 24 hours a day to create a system for continuous quality water in an
equitable, efficient and sustainable manner.
Table 7.2: Goals and service Outcomes- water Supply
S.No.
1
Goal
Network cover for General
2011
100%
2016
100%
2021
100%
household
Network cover for Slum
100%
100%
100%
3
4
5
6
7
households
Per Capita Supply
24/7 Water supply
Quality of water
Non Revenue Water
Cost recovery (percent of
135 lpcd
50%
Safe & Good
25%
100%
135 lpcd
80%
Safe & good
15%
100%
135 lpcd
100%
Safe & Good
15%
100%
O&M)
Goals and service outcomes of water supply to be achieved till 2021 are given in table
7.2. .Supply of 135 lpcd of safe drinking water should be accomplished till 2011. Plan
should have 24 hrs water supply may not be the priority at that time but is a goal for 2021.
Description
Estimated
Water Demand
Availability
Surplus/Deficit
population
In No.
(MLD)
@ 135 lpcd
MLD
MLD
37
50704
6.85
4.5
2.35
The present status of water supply is given in table 7.3 according to which water
generated is very less for 2006 population. There should be planning to fulfill the current
demand and there should be planning to provide 100% water supply connection in all the
sectors (domestic, commercial, industrial). Strategies and time frame are given in table
7.4 and design criteria in table 7.5.
Table 7.4: Strategies and Time Frame Water Supply
S.No.
1
Strategy
Asset
2007 2008
2009
2010
2011
2012
2013
Management
2
Plan
Leak
3
4
plan
Mapping & GIS
Piloting
24/7
water supply
Source
Augmentation
Network
detection
Coverage
for
General
7
Households
Network
Coverage
for
Slum Households
Table 7.5: Design Criteria and Target Service Level
Description
Population
Per capita
Collection
Demand
Treatment
Demand
Total Demand
Unit
In number
Lpcd
System Percent of Road Length
Capacity Percent of Generation
MLD
Based on Norms
2021
100000
135
90
100
58.5
38
System Pattern
For general convenience of distribution, a grid pattern where the different mains are
interconnected keeping dead ends to a mini mum is recommended. The system facilitates
any one point being fed at least from two different directions. For small water supplies,
the tree system with smaller mains branching off from a single trunk main may be
adequate.
Zoning
Zoning in the distribution system ensures the equalization of the supply of water
throughout the area. The zoning depends upon (a) density of population (b) type of
locality (c) topography and (d) facility for isolating for assessment of waste and leak
detection. If there is an average elevation difference of 15 to 25m between zones, then
each zone should be served by a separate system. The neighbouring zones may be inturn
connected to provide emergency supplies. The valves between the zones, however, should
normally be kept closed and not partially opened. The layout should be such that the
difference in pressure between different of the same zone or same system does not exceed
3 to 5m.In case of Jhajjar town, the general topography of the town is fairly flat and has
gentle slope towards south west.
Location of Service Reservoirs
The location of service reservoirs is of importance for regulation of pressures in the
distribution system as well as for coping up with fluctuating demands. In a distribution
system fed by a single reservoir, ideal location is a central place in the distribution system
which affects a maximum economy on pipe sizes. If topography permits, ground level
reservoirs may be located taking full advantage of differences in elevation. it may be
desirable to have tail end reservoirs for the more distant districts. These tail end reservoirs
may be fed by direct supply during lean hours or booster facilities may be provided.
General Design Guide Lines
Unit Consumption
Based on the CPHEEO Guidelines, the unit consumption most appropriate for the project
area appear to be as follows :
i)
Domestic
135 lpcd
ii)
Non-Domestic
20 % of domestic supply
39
Fire Demand
ii)
CPHEEO guidelines suggest storage provision for 24 hours water requirement of the
command area at the reservoir site. Commensurate with this norm and as the reservoir is
being fed by a number of tube wells; one day storage capacity is suggested. This will
ensure uninterrupted supply during the repair of tube well/rising main/ pumping
machinery. As indicated earlier, storage volume as worked out by projected water demand
of the command area in 2021 will be suggested with provision for future augmentation.
The town and its surrounding areas will be divided into several water supply zones
depending upon existing natural barriers, population. Proximity of supplying GSR,
natural ground elevation, distance to be covered to supply furthest consumers, etc. Each
water supply zone will be demarcated with the existing GSR located preferably at a
central, elevated position depending on the existing situation. This reservoir will act as
service reservoir, which will distribute water to the consumers by gravity through well-nit
distribution network. New GSRz will be proposed to be located strategically in the
proximity of its command area.
The reservoir will be of Reinforced cement concrete (RCC) construction having more
than one compartment (as suitable) to facilitate future maintenance. The tank shall have
retaining wall around periphery and RCC base slab and roof slab. It will be provided with
proper roof protection works and necessary inlet, outlet, overflow and washout piping
arrangement. The tank shall be designed for un-cracked section with Grade 40 concrete as
per Indian Standards. The reservoir premises will be provided with necessary utility
services, disinfections arrangement, guard house and boundary wall.
Boosting
For distant localities, booster may be provided instead of increasing the size of mains or
height of the reservoir unduly for maintaining the required pressure.
Location of Mains
For roads wider than 25 meters, the distribution pipes should be provided on both sides of
the road, by running rider mains suitably linked with trunk mains.
Design and Development Forum
40
Irrespective of the methods used, the hydraulic analysis of pipe network is based on
fundamental laws, viz., Q = 0 at a junction, H a o around a loop or a circuit and h = k Q
which is the exponential friction flow equation relating the head loss to the flow in pipe.
Hydraulic Design of Pipelines
Two universally accepted formulae for hydraulic design of flow through a circular
conduit are Hazen-Williams formula and Darcy-Weisbach formula. Hazen Williams
Formula is an empirical formula. Hazen-Williams coefficient C defines the pipe
roughness characteristics. C values for various commercially available pipes in the area
have been provided in CPHEEO Guidelines.
Darcy- Weisbach formula is a dimensionally consistent formula. Here the friction factor
f defines the roughness characteristics. A number of implicit relationship are available
to determine f out of which Colebrook-White equation is widely used which yields
sufficiently accurate results.
Consultants propose to use DarcyWeisbach formula for hydraulic design of water supply
distribution network. The formula is:
Hf
f(L/D) (V2/2g)
Hf
Length of pipeline in m
Where:
The values of equivalent wall roughness coefficient (e) adopted in all hydraulic
calculation are as below:
Ductile Iron pipe
0.10 mm
HDPE pipe
0.05 mm
41
The transmission main from boosting station to service will be sized to cater for the
ultimate stage flow as per the projected water demand. Material of the transmission line
will be Casts Iron of Class LA.
Valves, fittings and equipment to be installed on transmission line will be of Cast Iron PN
25 pressure rating to keep provision for future augmentation in capacity of the pipeline
and pumping machinery, too. The pressure pipeline will be proposed to be laid inside the
service corridor of main roads. It will be provided /with necessary air, washout and
isolation valve at suitable locations for future maintenance.
Distribution Main
The design of the distribution network for the entire project area will be done based on
the values of contour lines and spot levels as available in the base maps and development
plans.
The new areas in project town and other areas to be provided with reticulated supply
system, being of urban in nature will be provided with hydrants to meet firefighting
needs. Considering the nature of development / land use and material of construction of
the buildings/ structures, the probability of occurrence of fire fighting system for the
town:
Head of 7mwc; fire tenders will collect water from these hydrants and boost to the
required pressure.
The average spacing between two fire hydrants may be kept as 120m; there are examples
where the spacing is even more; the hydrants need to be located on major roads on
distribution main so as to assure the supply of the required quantity of water.
Material and Size of Pipe Work
For distribution network also C.I. pipes of suitable dia as per CPHEEO guidelines need to
be used.
Disinfection of water
Due to long haulage of water (whenever envisaged), the residual chlorine in treated water
may be completely/ partially lost. This is not desirable as it may allow microorganisms to
grow and will ultimately cause health hazards among the consumers. Hence, disinfection
of water should be done at selected boosting / GSR locations. However, if such provision
42
1.
2.
3.
4.
5.
6.
7.5.2
Anion exchanger.
Strategies
Areas with very good ground water prospects especially areas along Yamuna Canal, etc.
need to be protected. Artificial recharge through rainwater harvesting and riverbeds
should be undertaken. The surplus canal water during monsoon period for recharging
depleted aquifers to be used and lastly roof-top rain-water harvesting should be made
mandatory in building bye laws especially in the over-exploited blocks.
All new development areas should have two distribution lines, one for drinking water and
other for non-drinking water/recycled treated wastewater to reuse the treated wastewater.
At least 50% of the treated wastewater should be recycled for these purposes and
emphasis should be laid towards waste minimization, which can also help in improving
the overall environment. Government may also provide liberal tax rebates for
institutions/industries adopting recycled wastewater to compensate for the cost involved
in treating wastewater for recycling.
43
7.5.2.2
The bulk supply system can be done in new areas on neighbourhood pattern
Public Private Partnership
The public health department should adopt rationalized approach for revenue generation.
Public private partnership need to be introduced for operation and maintenance of the
water supply scheme.
44
7.6
Financial Implications
17.4 km
Rs.4.35crores
25% of 49.5 km
12.4 km
12400m
Rs.3.10 crores
Rs.7.45 crores
20% of 7.45
Rs.1.49 crores
Rs.8.94 crores
9 X Rs.1 crore
Rs. 9 crores
= 3.1 + 4.35
10% of 9 crores
Rs.11.88 crores
iii)
= 9 + 0.9
= 9.90 + 1.98=
Total cost
2.38 crores
i + ii + iii =
23.20 crores
45
2.32 crores
23.20 + 2.32
25.52crores
46
SEWERAGE
8.1 Introduction
Sewerage, the core element of physical infrastructure, determines the environmental
status of any settlement. Development of appropriate sewerage carriage system with
efficient treatment acts as a prerequisite for facilitating balanced and harmonized
development. Augmentation of existing systems/treatment facilities as well as adoption of
new technologies of waste treatment now being focused by every city/town, which
aspires to cover its total population under sewerage network system.
Sewerage system:
Coverage:
Separate
50% of Total Area
49% of Total Population
Number of STP
Zero
Number of Disposal:
One
Quantity generated
3 MLD
Quantity intercepted for treatment: Nil
Length of Sewer line (in km)
20 km
Source: PHED Jhajjar
Presently the sewage system is partly laid and for the rest of the city already a estimate of
3.9 crores has been prepared. The amount has been sanctioned but the work still has to
47
i)
ii)
Analysis from the sewerage sector reveals that sewerage network coverage
needs to be enhanced in the town area.
iii)
The poor and slum dwellers lack safe sanitation facilities and hence are prone
to health related diseases.
iv)
v)
vi)
vii)
8.4.2
The emphasis has not been given on waste minimization, which helps in improving the
environment as a whole. The concept of recycled wastewater for non-drinking purposes
has not promoted so far.
48
Due to non existence of storm water sewerage system in Jhajjar town, whole of the
silty/muddy surface water passes through the sanitary sewers, as the sewer lines are
designed only for sanitary purpose. Due to this, during rainy season sanitary sewers
overflows & take time to discharge surface water, which creates inconvenience to the
public.
8.4.4
Most of habitants keeps cows & buffalos etc in the residential colonies & they discharge
cow dung etc. in the sewer lines resulting into frequent blocking of sewer lines& also
creates unhygienic gasses in the sewer lines which causes accidents while cleaning the
sewer lines.
8.4.5
Increasing complaints
After the rainy season, due to entering muddy water /Garbage / polythins etc. the sewer
lines generally chokes & number of complaints regarding overflow and blockage
increases. To remove blockages, desilting is immediately requires but due to shortage of
staff. i.e. sewermans with the department extra (skilled) labour is required but as per govt.
instruction department can not engage daily wagers on muster rolls & also there is no
contractor enlisted by the cooperative Labour & construction societies through which the
labour could be arranged.
Vision
S.No.
1
2
3
4
5
Goal
Network cover for general household
Network cover for Slum household
Treatment and Disposal
Recycling and Reuse
Cost Recovery(Percent of O&M)
2011
90%
60%
100%
15%
85%
2016
100%
100%
100%
40%
100%
2021
100%
100%
!00%
60%
100%
49
Description
Estimated
Sewage Generation
Population
In No.
50706
62407
81204
100000
(MLD)*
@ 108 lpcd
5.48
6.74
8.77
10.8
Degree of Treatment
The degree of treatment sill mostly be decided by the regulatory agencies and the extent
to which the final product so treatment are to be utilized. These regulatory bodies may be
the local body or a State Pollution Control Board. The method of treatment adopted
should not only meet the requirements of these regulatory agencies but also result in the
maximum use of end products consistent with economy.
Design Period
The treatment plant, like the sewerage system is normally designed to meet the
requirements over a 30 years period after its completion. The time lag between the design
and the completion should not ordinarily exceed 2 to 3 years and even in exceptional
circumstances 5 years.
Population Equivalent
The industrial wastewater may be discharged into public sewers if the industrial effluents
meet the tolerance limits as prescribed by IS:3306-1974. If wastewater are to be
discharged into inland surface waters, tolerance limits set by IS:2490-1963 are to be
satisfied. For industrial effluents to be discharged on land for irrigation purposes, BIS
code IS:3307-1965 should be followed.
Effluent Disposal and Utilization
50
Process
SS
1.
2.
3.
Percentage Reduction
BOD
Total
45-60
60-80
30-45
45-65
Coliform
40-60
60-90
75-85
70-90
80-90
75-85
90-95
85-90
80-90
75-80
90-95
85-95
90-95
80-90
90-60
90-96
90-95
90-95
95-97
95-98
Component
Recommended
Clarification
Design Period
in years
30
Sewer Network
2
Works)
3.
Pumping Machinery
15
4.
Sewage
30
years
The Construction may be in a phased
Treatment
Plant
51
30
utilisation
Sewage Treatment
Table 8.6: Sewage Treatment Plant Operation
S. No.
Type of
1.
Treatment
Preliminary
Operation
Units Employed
Screen
of
different
designs
Skimming Tanks
Grit chamber
Primary
3.
Secondary
solids
Removal
of fine
biological
flocculation
Final
52
S.No.
1
Strategy
Asset
2007
2008
2009
2010
2011
2012
2013
Management
2
Plan
Rehabilitation
of
Old
Network
3
System
UGD for the
unsewered
4
5
areas
Maping & GIS
Network
Converge
for
Slum
6
Household
Recycle
&
Reuse
Strategies and time frame till 2013 are given in table 8.7. The first and foremost step
should be develop the asset management plan for minimal expenditure to be incurred.
8.4.7
53
54
Parameter
Units
TF
ASP
AL+MP
OD
Single Cell
UASP+MP
WSP
Detention Time
1 Day
4 to 6 hr
3 to 5 hr
1 Day
20 to 30 Days
6 to 10 Days
2 to 4 Days
0.3
0.25
0.5
0.3
2 to 3
1 to 2
0.6 to 1
Method of Oxygen
Atmosp
Mechani
Mechanical
Mechanical
Biological
Biological ( Algae)
Not
Supply
Power Required
heric
180
cal
250
300
400
(Algae)
Nil
Nil
Required
120
East of Operation
Simple
Difficult
Simple
Simple
Very Simple
Very Simple
Simple
High
High
Moderate
Moderate
Low
Low
Moderate
30.0
35.0
20.0
20.0
6.0
8.0
20.0
Annual O&M
Medium High
High
Medium
Very Low
Very Low
Low
Reliability
FC Removal
Good
90-96%
Good
95-98%
Good
95-98%
Very Good
98-99%
Very Good
98-99%
Good
95-99%
Land required
Capital Cost
Ha/MLD
Kw/MLD
Rs. Lakh/MLD
Least
90-96%
Note: TF Trickling Filter, ASP Activated Sludge Process, AL aerated Lagoon, OD Oxidation Ditch, WSP Stabilization Pond,
UASP Up flow Anaerobic Sludge Blanket, MP Maturation Pond.
55
Strategies
Short-Term Strategy
All households accessible to the existing sewer lines must be connected and now
shall be given to legalize unauthorized connections on priority.
Community toilets to be constructed especially for slum clusters at places where
sewer connection is available.
Cleaning of sewer should be undertaken through modern suction machines. The
operation will be quick and without damage to the skin of the sewer lines.
Proper storm water sewerage system of the town should be laid
Measures may be taken to shift the cattles from town area to other place r they
should be charged licence fee for keeping cattle into separate drain system.
Municipal Committee may be advised to raise the low laying area as such surface
water may flow by gravity.
For chocked sewer lines/ desilting, special permission may be granted to engaged
the sewer helpers through muster rolls as per requirement and advance
arrangement of LOC for making payment to labour immediately on completion of
job be made.
The labour contractor may be got enlisted through the cooperative L&C Society.
So that on requirement labour could be arranged through the contractor.
For getting the unauthorized 80% sewer connections regularized, the procedure
may be simplified.
8.4.8.2
8.4.8.3
56
33.45km X 1.51crores
101.02 crores
Cost for MPS, IPS and rising main @0.35crores = 33.45kmX0.35 crores
= 11.70 crores
Cost of Sewerage system =
101.02 + 11.70
57
112.72 crores
58
DRAINAGE
9.1 Introduction
Drainage is an important element of physical infrastructure and constitutes removal and
disposal of surplus rainwater from the land and to some extent protect flooring the area.
Since urban expansion is inevitable, increase run-off would require remodeling of the
existing drains as well as provision of new/supplementary drains. Provision of
appropriate drainage in marginal settlements consisting of slum clusters,
informal/unauthorized colonies etc require due attention.
9.3
59
Vision
The vision for Jhajjar is to align, develop and manage the existing drainage
network and to cover the entire town integrating with Drain No.8.
Table 9.1 : Goals and Service Outcomes Storm water Drains and water Bodies
S.No.
1
Goal
Storm Water Drain Coverage
2011
70%
2017
100%
2021
100%
(% of road length)
Rehabilitation of
Existing
100%
100%
100%
50%
70%
100%
According to table 9.2 is 134 km length of drainage requires up gradation and four water
bodies are to be conserved and rejuvinated in the town.
Description
Storm Water Drainage Water
New Formation Pucca open Drains
Primary Drains De-silting and Strengthening
Tanks regeneration and Nala Strengthening
Water Bodies Conservation
Unit
Gaps Up to 2011
Kms
Kms
66.90
134
Nos.
9.4.2 Strategies
The town drainage system need to be designed for maximum rainfall of five year
frequency storm for internal as well as peripheral drains and ten years frequency storm for
the main drains. Usually the system is designed for a maximum rainfall of one-hour
duration. The co-efficient of run-off need to be calculated for areas with composite land
use pattern on the basis of anticipated land use in the new areas and existing land use
pattern for the areas already developed. For Jhajjar town, the run-off coefficient should
not be less than 0.6.
Water logging areas are low lying areas in the city and agricultural fields are to be
immediately relieved of the problem by undertaking a drainage rehabilitation program.
The construction of new drains and connecting links would be taken up as a priority,
along with strengthening of the existing drains with lining and sidewalls. In addition,
60
S.N Strategy
o.
1
Primary
Rehabilitation
2007
2008
2009
2010
2011
2012
2013
Drain
and
improvement
2
Programme
Improvement Works
and Construction of
Territory Drains
Rejuvenation
and
Rehabilitation works
61
62
10.1 Introduction
Solid waste management, an obligatory function of Urban Local Bodies (ULBs) is poorly
performed resulting in problems of health, sanitation and environmental degradation in
most of the towns. Unless concerted efforts are made to improve the flow of resources to
solid waste management and build up systems that incorporate the basic requirements of a
proper waste management practice, the problem will keep aggravating.
63
establishments
Vegetable and fruit market
Industrial
Construction and demolition waste
Hospitals and Clinics
Floating Population
0.86
0.36
0.75
0.19
0.26
14.10
% of total
56.78
25.98
6.12
2.58
3.52
1.38
1.84
100.00
64
65
Population range
Average
per
value(grams/capita/day)
210
210
capita
In Jhajjar, the municipal area with projected population of 1.0 lakhs is estimated to
generate around 21 MT of solid waste per day at 210 gm / cap / day, by the year 2021.
Such a high volume of waste generation demands a strategic approach for disposal in
66
S.No.
1
2
3
4
5
6
Goal
Door to Door Collection
Source Segregation
Mechanized Handling of Waste
Scientific Disposal
Waste to Energy Generation
Cost Recovery (percent of O&M)
2011
80%
80%
100%
100%
40%
5%
2016
100%
100%
100%
100%
70%
15%
2021
100%
100%
100%
100%
100%
40%
Solid waste /management plan should be prepared keeping in mind the goals and service
outcome stated in table 10.3 and the design criteria given in table 10.4.
Table 10.4: Design Criteria and Target Service Level
67
Unit
Based
on
CPHEEO
Norms
2021
Population
Per capita Waste Generation
Collection Type
In Lakh
Grams/day
-
100000
210
Door-to-Door
Collection
Source
Percent of Generation 100
Percent of Rated 100
Treatment Type
Capacity
-
Sanitary Landfill
Treatment Demand
Percent of Generation 100
Total Solid Waste Generation MT
21
Collection and treatment of whole of 21MT of waste generated in the near future should
be targeted and achieved. (refer table 10.4)
68
S.No.
Source
10-15
Households
2
3
4
5
Institutions
Market Stalls
Function Halls
Hospitals,
homes
Construction/Demolition
degradable waste
-
waste
Garden Waste
Municipal Vehicle
Deposit in large community bin or to the
municipal vehicle
69
Mode of Collection
Door to Door
Area of Collection
Primary Collection Vehicle
Secondary Storage
1. Residential colonies of Multi-bin cart/tricycle-with2 Bio-degradable in Skips/wheel containers 2.NonHigh and Middle income bins for Biodegradable waste biodegradable-Sell or hand over to waste Collector
group
2.Hotels/Restaurants
&
Biodegradable
Vegetable Carrying bins to Transfer Point
Markets/Transfer
Stations
Small Community Bin Slums/urban
System
Colonies
The mode of collection and storage should be area based like door to door collection could be done for residential colonies and in hotels while
the large community bins should be placed in fruit and vegetable markets. Similarly, small community bins should be placed in slums. (refer
table 10.6)
70
S. No.
1
2
Strategy
2006
Door to Door Collection
Introduction of Twin Bin System
3
4
5
6
7
at Storage
Source Segregation
Mechanization of Transportation
Fleet Management System
Development of Compost Plant
Development
of
Scientific
Landfill Site
IEC Activities
2007
2008
2009
2010
2011
2012
2013
Door to door collection and segregation should be taken up on war footing while the development of Compost plant and sanitary land filling
site can be taken up in later stages. (refer table 10.7)
71
Vermiculture: .
Vermiculture may be adopted for biodegradable waste. It will help to make the
system self sustaining.
10.5.2.2
Long term Strategies
Solid Waste Management Plan need to be prepared and implemented.
72
Safe and separate storage as well as door step collection of bio medical waste,
hotel and industrial yard waste etc on full cost recovery basis.
Building byelaws need to be notified to ensure provision of refuge collection.
10.5.2.3
Public Private Partnership:
Private organizations need to be involved for collection, segregation, storage and
disposal and they may be permitted to use waste material for recycling or
otherwise for commercial purposes.
Dustbin should be located at suitable place in the residential areas/ manholes
/bazaars keeping in view the public convenience. While deciding the location it
may be ensured that the dustbin is not placed in front of a residential plot/ shop.
The design of the dustbin/ garbage bins should be such that the garbage does not
spillover the bins and an unhygienic condition is not created around the same. The
advertisement right on dustbins / garbage bin may be given to the professional
agencies on PPP basis against which the agency shall provide and maintain the
said dustbins/ garbage bins for a minimum period of three years.
73
ELECTRICITY
11.1 Introduction
Electricity is an important aspect of the physical
infrastructure that requires planning, development and
management for improved quality, productivity and
economic activities. It has become one of the life line of
modern day life. Town becomes handicap without proper
and uninterrupted supply of electricity.
Photo 11.1 Power House
S. No.
1
2
3
4
5
6
7
8
9
Total
Uses
Domestic
NDS
Industrial
Tube Wells
W/W
Banks
Street Light
Irrigation
Others
No. Of Connections
26303
3009
280
1480
70
3
4
1
2
31152
74
2000-01
2006-07
2011-12
2016-17
2020-21
45.94
1.16
10.55
7.4
93.24
1.66
13.29
15.53
161.4
1.57
11.83
26.33
249.07
1.43
10.74
40.61
(Actual)
36
1.5
12.2
6.5
75
S.No.
1
Goal
2011
Saving 100%
Energy
Mechanisms
Adequate lighting 100%
2017
100%
2021
100%
100%
100%
in Non-lit areas
To achieve the above said vision it is a necessity to have energy saving systems and adequate
lighting in black areas or non lit areas of the town. .(refer table 11.3)
Table 11.4: Strategies and Time Frame Street Lighting
S.
Strategy
2007
No.
1
Conversion
Existing
2008
2009
2010
2011
2012
2013
of
tube
Lights to Retro
2
fits
Power
saver
power lamps
Provision of new
lighting
system
for
Non-lit
the
areas
and
emerging areas
11.4.2 Strategies
In order to meet the additional demand, there is need to have new power plants in the subregion. Site has been identified for 3X500 MW power plant at Jhajjar district and at Jhajjar.
Modern techniques for load management must be adopted to flatten the load curve and
76
2006-2012
2012-2017
2017-2021
Total
Additional
Capacity Required
in MW
4.11
15.42
29.18
48.71
Cost
of
Power
Generation
(@ Rs. 4 crores/MW)
16.44
61.68
116.72
194.84
Cost of Transmission/
Distribution
(@2.5 Crores/ MW)
10.28
38.55
72.95
121.78
Total Cost
26.72
100.23
189.67
316.62
Financial implications for the block years 2006-2012, 2012-2017 and 2017-2021 estimated
to the tune of Rs. 26.72crores, 100.23crores and 189.67crores respectively. (Refer Table
11.5)
77
12.1 Introduction
Transport infrastructure forms the backbone of any
economy and plays an important role in the development
of a town/city. The objectives of studying transport sector
are to understand and analyze the present scenario of the
city and to understand existing potentials and scope of
development.
Photo12.1 Roundabout in Jhajjar
Jhajjar town is located on the national Highway no. 71 and is very well linked with
surrounding region through a network of state highways and district roads. This town is not
linked with the railway network.
12.2.2 Transport Facilities
Table 12.3 Various Types of Roads in Jhajjar, 2003-04
Type of Road
Bituminous Top Roads
Cement Concrete Roads
Brick Paved Roads
Kutcha Roads
Total
Length of Road(Km)
19.80
19.20
5.00
22.90
66.90
The total length of all kinds of roads in Jhajjar town is 66.90 kilometer. 29.60% of the total
road length falls under bituminous category and 28.70 % the concrete category. The total
length of brick paved road length of 7.47 km while Kutcha roads amount to 34.23 Km, as
shown in Table 12.1 and Figure 12.1
78
Source
:District Statistical Handbook, Jhajjar , 2003-04
For rapid growth of Jhajjar town, transportation issues have assumed critical importance.
Since the proportionate growth of road length in the Jhajjar area has been almost static,
traffic congestion has increased leading to endless transportation gridlocks. (Refer Map 12.1)
79
12.3
80
S.No.
1
Goal
Percentage
reduction
2
3
2011
25%
2017
30%
2021
30%
60%
80%
100%
100%
100%
100%
in
Travel Time
Riding Comfort
Transport Safety
For achieving the 100% development there is some goal and their service outcome which
shows the year wise development of Traffic Management ending by 2021. Up to 2021 all
goal should be achieved for the whole town development.(refer table 12.2)
12.4.2 Strategies
The major problem in transportation network is the encroachment on right of way on major
road that is on railway station road, which has effectively reduced the carriageway and
subsequently its capacity. In Jhajjar there is very big Mandi. Due to this Mandi it has heavy
traffic flow of tractors and loading unloading also takes place. Narrow roads and sharp turns
make the situation worse. Roads are not properly equipped with signage, road marking, street
names and street furniture, further the situation is aggravated in slum areas where roads are
not paved, lanes are narrow with potholes and without street light.
The strategies are towards to ensure quality of transport network and its compatibility with
land uses. To provide reliable and efficient transport network by 2021 and improving the road
conditions to withstand the traffic to be generated by that time short-term as well as long
term measures need to be taken.
81
S.
Strategy
2007
2008
2009
2010
2011
2012
2013
No
.
1
Upgradation
Roads
Formation of New
Roads
Pedestrianization
& Signages
Parking
Management
Junction
Improvement
Widening
and
Strengthening
Bridges
of
Flyover/Elevated
8
Highway
ROB/RUB
&Pedestrian
subway
Integration
&
82
Network with NH
Provision of Bus
Shelter
12.4.2.1
83
Design Criteria. Strategy shall focus to have 100% coverage of surfaced roads
including up-gradation of roads.
It is proposed to improve the condition of existing roads through up gradation,
widening and strengthening.
Asset Rehabilitation. Up gradation shall be undertaken to extend, refurbish and
enhance the roads. Plans would be phased so as to optimize cost and surface
condition and shall include upgrading earthen roads to Bituminous Topped roads.
This phased up-gradation would considerably reduce the costs on new formations.
Widening and Strengthening of road Structure. With due consideration to the
growing traffic intensity it has been proposed to upgrade all the major roads with
specific focus on the State and National Highways and some major roads. It is
proposed to widen and strengthen, existing network along the ULB periphery and
develop it is a Internal Ring Road. It is proposed to develop the roads as two lane
divided carriage way facility, with flyovers and ROBs at major junctions and railway
crossing respectively.
Parking. Parking spaces must be provided at appropriate locations, on-street/off
street, with proper management, and use of ITS. Appropriate parking fees should be
levied to manage the demand and reflect the cost of the urban land used up for the
purpose.
Traffic Management Plan. These shall focus of junction improvements, traffic
management within core areas of the town, regional level proposals, parking and
pedestrian facilities. It has been observed that, in most of the major roads in the town
pedestrians are forced to use the carriageway due to the absence or poorly maintained
footpaths. Footpaths of 1.5m wide are proposed along the major roads where heavy
pedestrian movements are observed. For traffic safety and convenience, appropriate
signs, marking lighting, guideposts are required to be provided on curves,
intersections, public utility places, etc. Proposals for road furniture are made
Design and Development Forum
84
12.4.2.2
Master plan for transport network of Jhajjar town should be prepared to dovetail land
uses with transport network.
Institutional integration must be set in motion merging responsibilities for transport
management and land development at the town level.
Reliable and unified vehicle registration database for future demand management
needs to be initiated.
The physical, institutional and socio-economic environment, in which bicycle and
cycle-rickshaws are operating, needs to be documented and understood. This can help
in creating policies, design guidelines and infrastructure, where bicycle and cycle
rickshaw can co-exist with rapid motorization and continue to provide environment
friendly mobility option to Jhajjar residents.
There is a need of a state level transport regulator with branches at city level in the
public transport domain. The transport regulator can ensure fair prices to transport
operator while maintaining quality of services. The presence of a regulator will also
encourage the private corporate sector to invest in this area. This is important, as
small individual operators do not have the required technical, financial or managerial
competence. Large towns region can have more then one private sector company to
run bus services, and this will result in more competition and better services. It will
also free up resources for the government.
As economic activities especially Mandi activities in cities expand and city
population grows, a substantial amount of freight traffic would be generated. The
timely and smooth movement of such freight is crucial to the well being of the people
and the viability of the economic activities they undertake. However, with limited
85
86
87
SOCIAL INFRASTRUCTURE
13.1 Introduction
Social infrastructure has been recognized as a growth-stimulating and sustaining route in
planning. The effectiveness of social infrastructure in achieving the objective of city
development plan would depend upon its capacity to contribute to improvement in the
quality of life, enhanced self-dependency and towns sustainability, creation of livable town
through reducing the sense of alienation among the residents with less dependence on other
settlements for basic infrastructure. The analysis is based on facilities available through
Design and Development Forum
88
89
Schools
Public libraries
Higher education
Professional institutions
Recreational
Others
Facility
Hospitals
Beds
Doctors
Nurses
Primary health centers
Dispensaries
Maternity and Child Centre
Primary, Nursery
Secondary and Higher Secondary
No
1
36
12
12
4
0
1
6
2
Degree Colleges
0
1
Gardens/open parks
Cinema
Clubs
Community Centre
Police stations
Fire Stations
Post offices
2
1
0
0
0
1
1
3
90
91
Facilities
Additional Requirement
2006-12 (0.23lakh)
Number Cost
2012-17 (0.19lakh)
Number Cost
Total Requirements
2017-21 (0.19 lakh)
Number Cost
Education
1
Primary School
10
1.12
15
1.68
17
1.90
20
2.20
2.11
10
3.02
12
3.62
14
4.20
62
43
6.90
12.95
45,000 pop
Integrated School with Hostel
0.11
0.11
4.
facility
Integrated School without Hostel
0.40
0.40
0.11
0.22
0.11
0.11
5. facility
Sub-Total
3.34
4.92
5.61
7.02
0.55
20.89
Health
6
Poly clinic
Nursing home, child welfare and
0.19
0.19
maternity centre
0.19
0.38
0.57
0.19
0.36
0.60
0.84
0.48
7
19
1.33
2.28
7 Dispensary
Sub-Total
0.55
0.98
1.41
0.86
3.80
Recreation
8 Community Hall
9 Recreational club
10 Music, dance and drama centre
11 Meditation and spritual centre
Sub-Total
0.29
0.58
0.19
0.36
0.19
0.06
0.10
0.29
0.58
0.19
15
1
1
1
0.71
1.42
0.19
0.06
0.10
1.77
Others
12 Police station
13 Fire station
Sub-Total
1.1
1.1
1
1
1.1
1.1
2.2
2.2
4.18
6.48
7.21
10.79
28.66
92
The cost of development of town Level Park in the town comes out to Rs 5 crores excluding the cost of land.
So, the net finances required for development of social infrastructure in the town would be Rs. (28.66+ 5) 33.66 crores.
93
14.1 Introduction
When a rural migrant comes in a city, they discover that the housing, jobs, amenities that
had pulled them to the city are not available or inaccessible or beyond their affordable
limit. As a result in Jhajjar, 23% population lives in slum settlements making a living with
minimal informal resources that is available to them.
Slums are essentially the products of urban poverty. Population living in slums lacks
access to basic services like safe water supply, sanitation, solid waste disposal, drainage,
access roads, street lights, and neighbourhood amenities like safe play area for children
and community facilities, and electricity connection, health and education facilities
94
Sl. No.
1.
2.
3.
4.
5.
6.
7.
8.
Name of Slum
Mata Gate
Sita Ram Gate
Goshiyan Mohalla
Beri Gate
Silani Gate
Chawani
Arya Nagar
Adarsh Nagar
Total
Population
727
1154
673
1963
1236
1763
960
580
9056
In the Municipal area, there are 8 slums with an approximate population of Nine thousand
and fifty six, which are spread over the whole town, which is a cause for concern and
requires appropriate strategies. Another concern is that several of them are non-notified
making it difficult for the provision of infrastructure and other services on sustainable
basis. Some of the slums in the MUNICIPAL COMMITTEE, JHAJJAR area are very old
established more than two decades ago and continue to suffer deprivations.
U
95
Congested Roads
No sewerage connection
Drainage
This important amenity is needed to carry the wastewater of the town to a point from
where it is possible to dispose it off finally. Proper drainage, open or covered is
essentially required for the purpose. A general survey of the town indicates that major part
of the city does not have adequate drainage and in some part, the existing drainage needs
immediate overhauling. This is otherwise desirable as roads cannot be maintained unless
and until proper drainage network cover the whole town. The drainage project initially
should cover the major part of the old town and newly grown up colonies by
identification of sites, which are in dire necessity of modifying/constructing new drains.
Drains are chocked in some slum areas resulting in overflow of the drains and
environmental degradation.
96
Pavements/Roads
Several colonies need pavements for the newly developed areas as the inhabitants find it
difficult even to reach their houses during rains. Surface drains are also proposed for these
areas. Provision of C.C. pavements/premixing in the city area required to strengthen the
old damaged existing pavements, to give proper access to the public and to provide
smooth flow of the traffic in the city area.
14.2.5.3
It is the one of the most important basic services. In slum areas, it is the primary amenity,
which is to be provided by the local body. Municipal Committee has deputed Safai
Karamcharis to clean these areas. Some of the slums in Jhajjar have a very poor sanitary
conditions, one of the major reasons for this being open drains and lack of drains in those
areas. Similarly, there is no provision for dumping solid waste generated by the residents
and it is dumped at any open space available, usually in open drains or on a vacant plot,
corners of the street etc.
14.2.5.4
Street Lighting
Newly developing colonies require street light facility. Existing light points are also to be
replaced in slum clusters. Besides sodium and mercury lights are to be provided on major
roads and junctions from where slum pockets started. In the absence of parks in the slum
areas, children of slum cluster usually play on the road are easy pray for accidents.
14.2.5.5
Water Supply
Provision of safe drinking water in the slums areas is essential because prevailing sanitary
condition in these areas are not satisfactory and have every possibility of water borne
disease like Cholera, E-Hepatitis, and Gastroenteritis. Presently slum dwellers are
dependent for their need of drinking water and for other purpose on the hand pump
installed in the area and water supply provided through stand posts.
97
98
The sector derives its importance due to the scale and nature of operations;
The activities are concentrated around the old town areas, along the important
road network in the town. They occupy the road margins, footpaths etc. and are
spread all over the MUNICIPAL COMMITTEE, JHAJJAR area.
The people involved in the informal sector constitute a major portion of urban
poor as these units have a low labour income though the entire family might be
involved.
99
S.No.
1
Network
Goal
Coverage
Slum
2011
90%
2017
100%
2021
100%
households
UGD
Coverage
Slum
90%
100%
100%
3
4
5
Households
Adequately Lit Slum
Adequate Road Link for the Slum
Pucca houses for all Slum
100%
100%
80%
100%
100%
100%
100%
100%
100%
6
7
Households
Education for all in Slums
Best Quality in Slums
100%
80%
100%
100%
100%
100%
for
for
By the end of this project that is by the end of 2021 all facilities like network coverage,
lighting, proper road connectivity, pucca houses and education to all is to fully provided.
(refer table 14.2)
100
Description
Unit
Population
Households
Housing Demand
Distribution Network Demand
Sewer Network Demand
In No.
Nos.
Percent to hhs
Percent of Road Length
Percent of Road Length
Persons
Persons
Persons
Gms per Day
Cu.m
m
75
30
50
210
030
300
m
m
0.25
0.51
101
S.No.
Strategy
1
Better
2007
2008
2009
2010 2011
2012
2013
Access
2
Roads
Storm
Water
Drains
Sewer
Network
Sanitation
Facilities
Provision
of
Housings
As per National Slum Policy the objective to formulate strategy needs to be:
To integrate slum settlements and communities residing within them into the
urban areas as a whole by creating awareness amongst the public and in
Governance of underlying principles that guide process of slum development
and improvement and the options that are available for bringing about the
integration.
To strengthen the legal and policy framework to facilitate the process of slum
development and improvement on a sustainable basis and
To establish a framework for involving all stakeholders for the efficient and
smooth implementation of policy objectives (Annexure IV)
102
103
MUNICIPAL FINANCE
15.1 Introduction
The financial profile of the Municipal Committee of Jhajjar indicates the state of the
towns finances and the capacity of the Municipal Committee to manage its finances
and mobilizes resources for maintaining infrastructural services at prescribed norms
and standards.
104
105
I. Revenue Income
A
Tax
1 House Tax
2 Token Tax
3 Fire Tax
4 Trade Tax
Sub -Total
B
Non- Tax
5 Income from intrest
6 Retail income
7 Income from licence
8 Development charges
9 Rent from shops
10 Sale of land
11 Electricity
12 Tehbazari
13 Cattle fair share
14 Food licence
15 Sale of forms
16 Driving licence
17 Registration Fees
18 Sub -Total
II
Capital Income
19 Advances and Deposit
20 Stamp Duty
Sub -Total
TOTAL
2002-03
2003-04
2004-05
2005-06
Growth
1072969
66915
105766
45000
1290650
727077
75550
145919
28377
976923
1551011
0
111534
0
1662545
1192267
0
97608
0
1289875
+ve
-ve
-ve
-ve
-ve
30668
660512
2500
629833
842389
0
0
23420
600045
15732
3360
242015
0
3050474
10266
509841
2500
406610
482742
0
0
18440
0
9232
0
158992
0
1598623
25339
644244
17599
920054
888990
0
0
19730
595594
33670
0
211037
120673
3476930
28473
1051197
29651
3277822
861899
0
0
18800
637547
111892
46250
151978
122222
6337731
+ve
+ve
+ve
+ve
+ve
2391901
953280
3345181
975402
590570
1565972
1446954
1435376
2882330
1241379
1877428
3118807
7686305
4141518
-ve
+ve
+ve
+ve
-ve
+ve
+ve
+ve
-ve
+ve
+ve
8021805 10746413
106
Source:
Budget Municipal Committee, Jhajjar,
There is a positive trend in all the tax and non-tax revenue income from year 2004-05
and 2005-06 but after that, the income is some time decreasing and in some cases it
increases. This has clearly indicated that earlier the town did not have strong financial
positions to sustain and maintain the urban infrastructure but now due to proper
collection of taxes they are in a increasing manner in 2005-06.
EXPENDITURE
Office Salary
Return of Loan
Directors share
Law charges
Audit Fees
Expenditure on Election
Office Contigency
Miscleneous
Office repairing
Salary of house tax emp.
Contigency
Salary of rent tehbazari
Contigency of Tehbazari
Construction of Shops
Salary of garden and road
branch
2002-03
824735
0
0
0
10000
11787
100000
93609
0
103530
318
11631
0
0
2003-04
331705
0
0
17900
0
0
49429
29107
351
62180
0
16462
0
0
2004-05
654019
0
0
48750
0
9535
98481
72134
0
202707
13993
57186
0
0
2005-06
741125
0
0
22650
0
22964
120000
194640
0
180952
23130
48172
0
0
87226
106545
152250
215219
107
Contigency of Garden
Street Light
Reparing
of
Primary
10808
129825
10392
247006
2164
232516
0
111695
18
19
20
21
22
23
24
25
26
27
28
29
30
31
School
Library
Rent of Balwari
Expenditure on deseas
Salary of Sweeper
Contigency of Cleanliness
Un claimed Death Body
Salary of fire services
Contigency of fire
Burning & burial
Salary of Municipal Works
Contigency of Municipal
Construction of Drainage
Construction of pavements
Construction
of
C.C.
0
0
0
0
2279076
675037
5600
0
0
0
163139
5625
277040
47245
0
0
0
0
1826427
253129
4000
0
0
0
74112
0
0
0
0
798
0
0
3755269
266406
2400
571429
5924
0
268838
1841
0
0
0
908
0
0
4014448
293520
3200
728613
99649
0
245014
10050
0
70891
32
33
34
35
Roads
L.I.C. Loan
Advance Deposit
Purchase of Car
TOTAL
637990
0
2433214
0
7907435
84777
0
1044218
0
4157740
303462
0
1046583
0
7766685
170240
0
14085754
0
21402834
108
109
E-Governance System:
Municipal Committee Jhajjar has not computerized its basic information for Egovernance. Geographical Information System (GIS) is also proposed to keep the
current and accurate data related to physical aspects i.e. maps of ward boundary,
physical and social infrastructure houses and other establishments for proper planning
and financial return (house tax).
15.4.2.3
House Tax:
To achieve the target of 85% house tax collection municipality need revamp tax
collection methods. This system will help to provide employment as well as high
collection of house tax.
110
House tax collection is proposed through internet through credit card for the
convenience of the people and to save the time and manpower.
Use of GIS and three d (3d) model system to update the house/ properties data.
Provision of mobile van to pay the house tax and to identify locations of Easy
Billing System Network.
Provision of simplified unit area system, voluntary discloser and deposit
system.
Provision of penalty against the house tax offenders and incentives for
employees to collect maximum house tax.
Provision of drop boxes at convenient locations.
15.4.2.4
Land as a resource
Urban land is a highly valuable asset thats should be very judiciously used to raise
resources by the implementing agencies to fund the repayment of loans taken for
initial development and for funding future development programmes. Even the private
sector projects are likely to derive large benefits because of overall development of
Jhajjar and hence a considerable value would be added to there assets. It is therefore
desirable that a part of this net value addition should be recovered in the form of
development and betterment charges. The same should be used for funding further
development programmes in the town by loading it on to the land cost.
Optimal utilization of land through appropriate prices and distribution mechanism and
land use control measures can yield substantial surplus for the Municipality for
undertaking additional development works. Some of the methods through which land
could be used as a viable resource for financing various urban development
programmes in Jhajjar are as follows:
Creation of land banks by the Municipality and other agency for utilization for
future requirements
Permitting the private sector to develop the land and compulsorily recovering
a part of the value added because of such permitted development.
Granting of Transferable Development Rights(TDR),
Funding of infrastructure projects on innovative methods like
BOT,BOLT,BOOT etc by providing land as initial input.(Annexure 1)
Permitting commercial use of precious land by the private sector and deriving
returns in the form of social housing/development for the occupants of the
land
Recycling of land for facilitating the shifting/relocation of industrial units,
slum clusters located there on.
111
User charges
Among the non-tax resources, the user charges happen to be the most important
mechanism of cost recovery. Water supply, sewerage, solid waste management and
parks qualify for the imposition of user charge. The economic rationale of cost
recovery entails that the user charges have to be based on the unit cost of providing
service.
15.4.2.6
Reforms in institutional, fiscal and economic systems of the town will be necessary to
achieve the management efficiency and credit worthiness. It will help in sustaining a
long-term programme of infrastructure investments based on private finance while
ensuring the effective utilization of public funds. At the same time, systematic reforms
focused on critical services like water and sanitation is an equally important option.
Such systematic reforms in selected sectors would have to be centered on significant
private sector participation in the management, financing and delivery of services.
Without these reforms at the town level or specific sectoral level, it would not be
possible to ensure the inflow of private investment in urban infrastructure.
To ensure optimal utilization of linkages of Jhajjar with Haryana state for the
development of core economic activities such as agro-based industrial estate,
commercial complexes, residential complexes etc. Even the Municipal Committee
Jhajjar can have its own share in the joint venture.
Revision of house tax especially on rented house and rented commercial, institutional
and industrial buildings may be undertaken on priority.
15.4.2.7
Capacity Building
Since the problems associated with urban management are of relatively recent origin
in India. The ability to fully understand and deal with these problems is yet to fully
mature, especially at the State and city level. This calls for strengthening capabilities
to address these issues and under take the task of developing sustainable urban
management systems.
Capacity building will have to be addressed at two levels institutional and
individual. Institutional capacity would primarily involve creating a pool of
knowledge and a knowledge management center that would sustain and enhance
expertise as well as facilitate more informed planning. It would also sponsor regular
to help formulate the right mitigation strategies, without merely adopting what other
countries have tried.
112
Municipal Bonds
Resolutions of ULB to raise funds from the market through tax free Municipal
Bond.
Application to State Govt. for its share or grant/ guarantee cover.
Printing of Bonds.
15.4.2.9
Right Sizing
113
State governments and the municipal Committee should make a conscious effort at
controlling the city sprawl in a planned and unplanned manner, adopting best
practices in Urban development and planning norms. There is an opportunity in the
form of availability of large developed tracts of land in and around the town where the
development can be planned and replotted in a phased manner. The growth
management strategy should focus on:
114
URBAN ENVIRONMENT
16
16.1 Introduction
The basic meaning of environment is surroundings. The sum of social, biological and
physical or chemical factors composes the surroundings of man. Environment is
everything that surrounds man. The environment plays a crucial role in establishing
the paradigm of future development.
The general quality of environment of the Jhajjar town is good which can be
attributed to a number of factor like absence of industries, presence of reserved forest,
water bodies etc. However, there are some areas where the environment quality is
deteriorating due to the growing slums, low-lying areas, poor garbage disposal system
etc.
Air Pollution
Noise Pollution
Water Pollution
16.2.1 Noise and Air Pollution:
The database for Air Pollution is not available for the town. Air quality monitoring
stations are required to create data base so that appropriate remedial measures can be
suggested. Normally for Noise following standards are considered to maintain noise
ambience.
Figure 16.1 Norms for Noise Pollution
Day Time
Night Time
Limit in Db (A) Leq
A Industrial Area
75
70
B Commercial Area
65
55
C Residential Area
55
45
D Silence Zone
50
40
Note1. Day time is reckoned in between 6 a.m., and 9 p.m.
2. Night time is reckoned in between 9 p.m., and 6 a.m.
115
The air quality status is monitored since 1978 as Ambient Air Quality (AAQ) by
Central Pollution Control Board (CPCB) and Haryana State Pollution Control Board
but this town has no permanent station to monitor pollution level. Otherwise, the level
of air pollution is less in the town as no major industries in functioning the town.
There are some places viz. railway crossing point and crossing of state highway and
NH- 71 results in air and noise pollution.
1. Beside appropriate distinctions should be made between different environments in
terms of setting ambient noise standards, e.g. rural versus urban; educational and
medical establishments versus other areas, night-time versus daytime in residential
areas, areas in the vicinity of road, rail, airport infrastructure, and protected areas,
etc.
2. Noise emissions norms (e.g. loudspeaker, automobile horns, fireworks ratings)
appropriate to various activities need to ensure that exposure levels to third parties
who are not participants in the activity do not exceed prescribed ambient
standards.
116
117
118
16.3 Conclusion
The Jhajjar town being a border town is enriched with inherent potentials for
development, maintained properly and provided with good infrastructure and this will
result in one of the best environmentally rich places in Jhajjar District and Haryana
State. The general quality of the local environment is, at present, to some extent
normal. However, the time is not far when the same will deteriorate, if proper
attention is not given to environment related problems. It is further suggested that air
quality standard need to be maintained as per norms indicated by CPCB. (Refer
annexure no VI)
119
DISASTER MANAGEMENT
17.1 Introduction
Human settlements are frequently affected by natural disasters, which take heavy toll
on human lives, destroy buildings and infrastructure and have far-reaching economic
and social consequences for the community. Among all the natural disasters that
Jhajjar may face, earthquake and fire hazards are the most devastating ones.
17.2 Earthquake
The Vulnerability Atlas of India indicates that the Haryana Sub-Region of NCR falls
within High Damage Risk zone (MSK VIII)-with regard to earthquake. Accordingly,
town development/construction in the Jhajjar needs to be planned taking care of the
natural and man-made hazards. Jhajjar comes under High Damage Risk Zone.(refer
Map17.1)
Map 17.1 Haryana district map
Seismic Zone
Mewat
120
Type A-Houses constructed with stone, rural structures, un-burnt bricks, clay
etc may suffer destruction causing gaps in walls, collapse of parts of buildings,
loosening of cohesion of parts of buildings and collapse of inner walls.
Type-B-Buildings construction with ordinary bricks, large blocks, natural
stone and prefabricated type buildings may suffer heavy damage causing large
and deep cracks in walls.
Most building of type C i.e. RCC buildings may have small cracks in walls,
fall of large pieces of plaster, slipping of tiles, cracks/fall in chimneys etc.
Fright and panic is caused among people, breaking off of branches of trees etc
takes place.
Considering the areas affected during past earthquake of M 6.5, it can be expected
that such as earthquake could adversely affect the entire region with damaging
intensities and could affect more than 50% depending on the location of the epicentre. Therefore, in terms of probable damage scenario, Jhajjar is quite prone to
earthquake. The whole urban development must be checked for safety against an
intensity of VII probability of occurrence, and upgraded for required seismic
resistance in buildings and infrastructure as found necessary.
Encroachment, over crowded and haphazard growth affect the movement and
timely approachability of fire tenders in emergency.
Illegal and loose electric connections
121
Slums are constructed with highly flammable material and some constructed
with very toxic materials like plastics, polyethylene sheets, bamboo, soft wood
etc. without proper access for fire tenders.
Illegal storage and hazardous commercial activities
17.4 Floods
The river systems in Haryana causing floods are the Yamuna, the Ghaggar and other
rivers like Sahibi, Saraswati, Tangri and Markanda. A number of drains with
inadequate capacity also give rise to considerable inundation problems. Drainage
congestion due to surface and subsurface drainage problem, river spills and tendency
of rivers to change their course constitute the main flood problem in the state. (refer
Table 17.1)
Table 17.1 Multi-Hazard Prone District in Haryana*
Distt. Name
Ambala
Bhiwani
Faridabad
Gurgaon
Hissar
Jind
Kurukshetra
Rohtak
M.S.K.
IX or more
-
VIII
93.5
10.7
100
100
48.2
87.6
VII
6.5
64.3
73.6
100
51.8
12.4
Unprotected
11.7
2.1
15.8
6.2
32.6
37.2
21.3
9.1
Protected
44.7
27.1
9.9
7.8
28.5
25.2
17.5 Proposals:
1. Seismic micro-zonation on a scale of 1:1,00,000 to 1:1,50,000
should be prepared for Haryana state based on the already
available data/indicators. Seismic micro-zonation for selected
areas/towns like Jhajjar, having high growth rates should be taken
up on priority.
2. Comprehensive risk evaluation of Jhajjar needs to be undertaken on
priority in order to identify areas vulnerable to fires and database in
terms of available equipments and personnel should be compiled
and periodically updated. Part IV of National Building Code and
122
3.
4.
5.
6.
7.
123
VISION
18.1 Background
Jhajjar is a big town having population of 39004. After the analysis which was
entirely based upon the secondary information collected from the municipal
Committee office, PHED Haryana, town planning department, Jhajjar, and other
government agencies SWOT analysis is done which will help to build up the vision
for the town. (Refer figure 18.1)
Figure 18.1 SWOT Analysis
18.2 Introduction
A SWOT analysis is an instrumental framework in value based management and
strategy formulation to identify Strength, Weakness, Opportunity, and Threats
for a particular town.
Strength and Weakness are internal value creating (or destroying) factors such as
assets, skills or resources a city has at its disposal relatively to its competitors. They
can be measured using internal assessments or external benchmarking.
Opportunities and Threats are external value creating (or destroying) factors a city
cannot control, but emerge from either the competitive dynamics of its industry/
markets or from demographic, economic, political, technical social, legal or cultural
factors.
124
Jhajjar is a Mandi town for its hinterland which can be used as an strong
economic base for the future population.
It is in the close proximity to Delhi and Chandigarh and is directly connected
by the roadways and Railway.
Location and Geography.
One of the important town in the district and has very good economy.
Weaknesses:
Missing signages.
23% of the population is residing in slums which are scattered all over the
municipal area.
Lack of facility to recycle waste water.
12th schedule guidelines (73rd and 74th constitutional amendment) are yet to
be included in municipality functions.
Opportunities:
125
Developing market.
Threats:
Lowering of the water table and use of the underground water as a source.
Increasing traffics and with that increase in the encroachment on the streets.
Dumping of waste on the streets and open drain are adding the environmental
pollution.
Pollutants being directly flown into Agricultural Fields can cause severe water
contamination.
Water works is in very bad condition, it creates health problem for people of
the town.
No water or Sewage treatment plants.
126
2017
81204
2021
100000
S. No
2006-12
2012-17
2017-2021
Total
10.10
40.72
1.05
13.9
57.93
123.7
26.72
150.42
7.71
36.00
0.00
0.00
0.00
43.71
100.23
143.94
7.71
36.00
0.00
0.00
0.00
43.71
189.67
233.38
25.52
112.72
1.05
13.90
57.93
211.12
316.62
527.74
8.00
6.00
0.87
14.87
8.26
1.53
0.00
9.79
24.66
0.00
0.00
0.19
0.19
5.61
1.41
0.00
7.02
7.21
0.00
0.00
0.71
0.71
7.02
0.86
2.20
10.08
10.79
8.00
6.00
1.77
15.77
20.89
3.80
2.20
26.89
42.66
175.08
151.15
244.17
570.40
I. Physical Infrastructure
1
2
3
4
5
6
Total
Water Supply
Sewerage System
Solid Waste Management
Drainage
Traffic and Transportation
Sub-Total
Electricity
10
11
12
Total
Grand Total
19
127
19.1 Background
The master plan of the Jhajjar town should be convertible to 3-d model. Its zonal
plans should be prepared with the help of satellite imagery and geographic
information system inputs. It will be a very effective tool to check unauthorized
construction and efficient management of civic utilities.
Plan monitoring has two main objectives:
1. The socio-economic and functional efficiency of the performance of human
settlement has to be monitored and evaluated so that changes required to
improve the quality of life could be identified and put into action through the
appropriate measures.
2. The plan should be continuously made responsive to the emerging socioeconomic forces.
To achieve this object there should be monitoring system in the plan implementation
frame work. There is reasonable possibility of arresting the unintended developments
taking place in the city through effective monitoring. This is based on the following
proposition:
1. No long range urban development plan can be implemented as it is.
2. The plan should be responsive to the happenings and emerging Scio-economic
and other forces during the plan implementation period.
3. Time lags between the happenings and the emerging Socio-economic forces
and the plan responses create accentuating conditions of un-intended growth.
4. The responsive plan to check the unintended growth needs a scientific
monitoring frame.
Monitoring frame is required to evaluate the achievement of physical targets
prescribed in the plan and identification of physical and socio-economic change in the
city to review the plan policies.
There could be very large number of aspects in case of physical targets to judge the
performance of various sectors. For systematic and precise working, physical targets
for some selected aspects can be worked out in consultation with the local body. The
physical targets are to be monitored yearly, 5 yearly or in the midterm (2014). This
will provides a scale to assess the achievement in different sectors for the city
development
128
129
ANNEXURE-I
(Water And Sewerage Charges)
1) Water Charges
(A) Domestic
i) Un-metered supply
a) Flat rate for water connection having one tap
connection.
b) Flat rate for water connection having two tap
connection.
B) Industrial/ Commercial/ Institutional
i) Unmetered supply
a) Commercial/Institutional Water Supply
b) Industrial Water Supply
2) Sewerage
(A) Domestic
a) Sewage connection for Indian/European wcs
b) Sewage connection for urinals.
B) Commercial/Industrial/ Institutional
a) Sewage connection for Indian/European wcs
b) Sewage connection for urinals
c)Commercial/ Industrial/Institutional Sewage connections
at the rate of 1.25 Per Kilo Ltr. of waste water (the waste
water discharged in sewerage system will be taken as 70%
of the total water consumed by the consumer)
Rs. 80
Not Applicable
Rs. 5.00 Per Unit P.M
Rs. 1.80 Per Unit P.M
Rs. 6.25 Per Unit P.M
Rs. 1.85 Per Unit P.M
Other terms and conditions:1. Water connection fee shall be charged @ Rs. 300/2. No new connections of ferrule size above 10mm be sanctioned and that the
existing consumers with higher ferrule size be informed of the enhanced rates
alongwith an option to get the connections reduced to lower ferrule size of
10mm.
3. Electric pumps installed direct on supply line should in no case, be allowed to
continue and should be immediately removed and water supply disconnected
wherever the electric pumps installed direct on supply line are detected,
penalty at the rate of Rs. 1200/- by way of post misuse should be levied on the
beneficiary who should also be charged penal charges at the rate of Rs. 100/per month in addition to usual water charges till the pump is removed it should
be notified by P.W.D (Public Health) to all consumers through hand bills &
proclamation that direct on-line pumps will be confiscated and supply to the
defaulting consumer disconnected.
130
131
ANNEXURE-II
(Models of PublicPrivate Partnerships)
i) Build Operate Transfer (BOT)
Under this method of financing the public and the private sector join hands to
complete a project. A common method of financing urban transport works is the
Build-Operator-Transfer method.
This is a contractual arrangement whereby the project sponsor undertakes the
construction, including financing, of a given infrastructure facility, and the operation
and maintenance thereof. The project sponsor operates the facility over a fixed term
during which it is allowed to charge facility users appropriate tolls, fees, rentals, and
charges not exceeding those proposed in its bids or as negotiated and incorporated in
the contract to enable the project sponsor to recover its investment, and operating and
maintenance expenses in the project. The facility is transferred to the government
agency or local government unit concerned at the end of a predetermined term.
The main characteristic of such project is finance arrangement which sets its reliance
on the revenue generated from a project for the repayment of loans and investment.
An easily understood example is toll roads where the funds for the construction and
operation of the project are generated by the users.
A number of are involved in a BOT project. There is the entrepreneur who takes up
the work and is the driving force behind a project. The contractors construct and may
operate the asset. They may be a part of the operating group. The Government is a
party as it is the main client who wants the job done and a customer is the user of the
facility. A financier lends money and may be a bank or an international agency such as
the IFC and a facilitator does the initial assessment of a project and design it.
ii) Build-and-Transfer (BT)
A contractual arrangement whereby the project sponsor undertakes the financing and
construction of a given infrastructure or development facility. After the completion of
the project it is turned over to the government agency or local government unit
concerned, which pays the sponsor or an agreed schedule, its total investment
expended on the project, plus a reasonable rate of return thereon. This arrangement
may be employed in the construction of any infrastructure or development project,
including critical facility that, for security or strategic reasons, must be operated
directly by the Government.
132
133
134
ANNEXURE-III
(Special Economic Zones- Salient Features)
1. It is a specially delineated duty free enclave and shall be deemed to be foreign
territory for the purposes of trade operations and duties and tariffs.
2. Goods going to SEZ area from Domestic Tariff Area (DTA) shall be treated as
deemed exports and goods coming from the SEZ area into DTA shall be
treated as if the goods are being imported.
3. SEZ units may be set up for manufacture of goods and rendering of services,
production, processing, assembling, trading, repair, remaking, reconditioning,
and reengineering including making of gold / silver / platinum jewellery
articles thereof or in connection therewith.
4. SEZ units may export goods and services including agro products, partly
processed jewellery, sub-assemblies and component. It may also export by
products, rejects and waste scrap arising out of production process.
5. SEZ units may import without payment of duty all types of goods, including
capital goods, as defined in the policy, whether new or second hand, required
by it for its activities or in connection therewith, provided they are not
prohibited items of imports in the ITC (HS). The units shall also be permitted
to import goods required for the approved activity, including capital goods,
free of cost or on loan from clients.
6. SEZ units may procure goods required by it without payment of duty, from
bonded warehouses in the DTA set up under the Policy.
7. SEZ units may import, without payment of duty, all types of goods for
creating a central facility for software development can also be accessed by
units in the DTA for export of software.
8. Gems and Jewellery and Jewellery units may also source gold/ silver/
platinum through the nominated agencies.
9. SEZ units may also import/ procure from DTA specified goods without
payment of duty and subject to such conditions, as may be notified by the
Government, for setting up of units in the zone.
135
ANNEXURE-IV
(National Slum Policy- Salient Features)
Objectives:
To integrate slum settlements and the communities residing within them into
the urban area as a whole by creating awareness amongst the public and in
Government of the underlying principles that guide the process of slum
development and improvement and the options that are available for bringing
about the integration.
To strengthen the legal and policy framework to facilitate the process of slum
development and improvement on a sustainable basis.
To establish a framework for involving all stakeholders for the efficient and
smooth implementation of policy objectives.
Salient Features:
The policy primarily endorses and promotes an upgrading and improvement
approach to deal with slums and informal settlements as opposed to
resettlement. It proposes that all existing planning instruments such as master
plans, landuse plans etc. should be modified to ensure that slums and informal
settlements can be properly integrated into the wider urban area.
The policy states that all physical upgrading and improvement in informal
settlements should adopt a community based approach with the active
involvement of members of the community at every stage of design,
implementation, maintenance of services and assets. It sets forth specific
norms and guiding principles for physical infrastructure developments and the
desirability of collection of user charges.
The policy also emphasis improving access to social services- health,
education, child labour and child rights and public distribution system as their
effective delivery would also reduce social inequities and promote integration
of people residing in slums into the social and economic network of the city as
a whole.
The policy recognizes the importance of economic empowerment of slum
dweller and lays guidelines for provision of financial services for the poor and
economic support/ enterprise of development designed to address the
livelihood needs of the urban poor.
The policy proposes a sustainable financing mechanism for slum improvement
through Slum Development Fund at state level, while recognizing the role of
private sector funding and institutional finance.
136
137
ANNEXURE V
SCOPE & TOR FOR CDP
138
ANNEXURE VI
National Ambient Air Quality Standards
139