PROJECT MANAGEMENT - IV
Time left: 0:19:54
Question 1 of 30
If a project needs one earth mover six months from now in order to
complete one activity, and the organization has four such machines, there is no
equipment resource constraint.
True
False
Question 2 of 30
Nancy tells her supervisor that as of right now, $1.05 worth of work has
been accomplished for each $1 worth of scheduled work. Nancy got this
information from viewing the
CPI
TCPI
SV
PCIB
SPI
Question 3 of 30
Risk management is a reactive approach that is designed to ensure that
surprises are reduced and that negative consequences associated with
undesirable events are minimized.
True
False
Question 4 of 30
Scheduling projects classified as resource-constrained focuses on
completing the project as soon as possible under the given resource
constraints.
True
False
Question 5 of 30
Regina's boss has told her that her project is very important. If the
critical path is delayed, she will be given whatever she needs to get it back
on schedule. Her project is classified as ________ constrained.
Performance
Quality
Time
Resource
Cost
Next
Save and finish later
ClassMarker Home
About ClassMarker
Terms and Conditions
Privacy
Site map
Contact Us
Copyright 2006 - 2015 ClassMarker Pty Ltd. All rights reserved.
Home
Group tests
My groups
My details
o
o
o
Hi KUMAR
Log out
Test
PROJECT MANAGEMENT - IV
Time left: 0:18:49
Question 6 of 30
A project monitoring system involves all of the following EXCEPT
Question 7 of 30
Adopting proven technology instead of experimental technology is an
example of mitigating a risk.
True
False
Question 8 of 30
A risk profile is a list of questions that have been developed and
refined from previous, similar projects.
True
False
Question 9 of 30
Gene is trying to order the concrete needed to continue his project.
However, the supplier will not be able to deliver it until next week. This is
an example of what kind of resource constraint?
Information
Materials
Equipment
People
Working capital
Question 10 of 30
Risks that can result in a system or process that will not work are
known as
A) Technical risks.
B) Funding risks.
C) Schedule risks.
D) Cost risks.
E) Unnecessary risks.
Next
Save and finish later
ClassMarker Home
About ClassMarker
Terms and Conditions
Privacy
Site map
Contact Us
Copyright 2006 - 2015 ClassMarker Pty Ltd. All rights reserved.
Home
Group tests
My groups
My details
o
o
o
Hi KUMAR
Log out
Test
PROJECT MANAGEMENT - IV
Time left: 0:17:56
Question 11 of 30
In monitoring project time (schedule) performance, actual performance should
be compared to
Question 12 of 30
The only accurate method for determining the true time progress of the
project is to compare the project network schedule against the actual network schedule to
measure if the project is on time.
True
False
Question 13 of 30
In some cases, conditions or scope can change, which, in turn, will
require a change in the baseline plan to recognize new information.
True
False
Question 14 of 30
Percent of the original budget that has been earned by actual work.
Question 15 of 30
The baseline is derived from merging information from the work packages
with the project network.
True
False
Next
Save and finish later
ClassMarker Home
About ClassMarker
Terms and Conditions
Privacy
Site map
Contact Us
Copyright 2006 - 2015 ClassMarker Pty Ltd. All rights reserved.
Home
Group tests
My groups
My details
o
o
o
Hi KUMAR
Log out
Test
PROJECT MANAGEMENT - IV
Time left: 0:16:50
Question 16 of 30
The inability to fit more than two earth movers on a construction site
at the same time when more are needed to complete the activity on time is an example of a
physical constraint.
True
False
Question 17 of 30
Responses to all identifiable risks should be a top priority for the
project manager.
True
False
Question 18 of 30
Physical
Scheduling
Resource
Technical
Time
Question 19 of 30
To determine if a project is time-constrained or resource-constrained
you would consult the project priority matrix.
True
False
Question 20 of 30
Purchasing an accident insurance policy would be an example of
responding to a risk by _____________ it.
A) Mitigating
B) Retaining
C) Ignoring
D) Transferring
E) Avoiding
Next
Save and finish later
ClassMarker Home
About ClassMarker
Terms and Conditions
Privacy
Site map
Contact Us
Copyright 2006 - 2015 ClassMarker Pty Ltd. All rights reserved.
Home
Group tests
My groups
My details
o
o
o
Hi KUMAR
Log out
Test
PROJECT MANAGEMENT - IV
Time left: 0:15:54
Question 21 of 30
The schedule variance for a project is calculated by:
EV - PV
PV - EV
EV - AC
CV - EV
AC - SV
Question 22 of 30
When resource constraints are added to technical constraints the
original project network may change as well as the completion date.
True
False
Question 23 of 30
The level of resources each activity will need to be completed in the
given amount of time has been estimated; therefore, there are no resource
constraints.
True
False
Question 24 of 30
Risk events that occur in the early stages of a project will have a
greater cost impact than those that occur in later stages.
True
False
Question 25 of 30
The attempt to recognize and manage potential and unforeseen trouble
spots that may occur when a project is implemented is known as
A) Risk forecasting
B) Risk management
C) Contingency planning
D) Scenario analysis
E) Disaster protection.
Next
Save and finish later
ClassMarker Home
About ClassMarker
Terms and Conditions
Privacy
Site map
Contact Us
Copyright 2006 - 2015 ClassMarker Pty Ltd. All rights reserved.
Home
Group tests
My groups
My details
o
o
o
Hi KUMAR
Log out
Test
PROJECT MANAGEMENT - IV
Time left: 0:13:52
Question 26 of 30
When considering the sequence and timing of activities, which of the
following is NOT one of the types of project network constraints?
Technical
Resource
Physical
All of these are types of constraints that could impact structure of the
project network
Time
Question 27 of 30
When considering risk value, the lower the value, the higher the level
of risk.
True
False
Question 28 of 30
Splitting is a scheduling technique used to get a better schedule or
better resource utilization and should be used without hesitation.
True
False
Question 29 of 30
One common mistake that is made early on in the risk identification
process is to focus on consequences and not on the events that could produce
consequences.
True
False
Question 30 of 30
If resources are not adequate to meet peak demands, the resulting
reschedule is termed
A) Resource-constrained scheduling.
B) Time-constrained scheduling.
C) Mandatory leveling.
E) Allocation.