Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
If your project is fairly complex, you may consider using earned-value management (EVM) to help control
performance. By providing cost and schedule performance assessments of both the total project and its major
parts, EVM allows you to identify the likely problem areas so you can take the most effective corrective actions.
The following example presents a realistic illustration of how EVM can support insightful analysis of your projects
performance.
Suppose the Acme Company has awarded a contract for the production of two specialized and complex
corporate brochures to Copies R Us. The contract calls for Copies R Us to produce 500 copies of Brochure A
and 1,000 copies of Brochure B. It further states that Copies R Us will produce Brochure A at the rate of 100 per
month and Brochure B at the rate of 250 per month. Production of Brochure A is to start on January 1, and
production of Brochure B is to start on February 1.
Here's the project plan:
Start
End
Elapsed
Time
Number of
Copies
Brochure
A
Jan 1
May
31
5 months
500
100,000
Brochure
B
Feb
1
May
31
4 months
1,000
100,000
Total
Total
Cost
200,000
A quick glance reveals that you budgeted 200 a copy for Brochure A (100,000 / 500 copies) and 100 a copy
for Brochure B (100,000 / 1,000 copies).
Suppose its the end of March, and youre three months into the project. Heres what has happened as of March
31:
Start
Elapsed
Time
Number of Copies
Produced
Brochure
A
Jan 1
3 months
150
45,000
Brochure
B
Feb
1
2 months
600
30,000
Total
Total
Cost
75,000
Your job is to figure out your schedule and cost performances to date and to update your forecast of the total
amount youll spend for both brochures. Follow these steps:
1.
Determine the planned value (PV), earned value (EV), and actual cost (AC) for Brochure A
through March 31 as follows:
PV = 200 per brochure 100 brochures per month 3 months = 60,000
Determine the schedule variance (SV), cost variance (CV), schedule performance index (SPI),
and cost performance index (CPI) for the production of Brochure A through March 31 as follows:
SV = EV PV = 30,000 60,000 = 30,000
CV = EV AC = 30,000 45,000 = 15,000
SPI = EV / PV = 30,000 / 60,000 = 0.50
CPI = EV / AC = 30,000 / 45,000 = 0.67
Your analysis reveals that you produced only half of the copies of Brochure A you thought you would and
that each brochure cost you 1.5 times the amount you had planned to spend (1 / CPI = 1 / 0.67 = 1.5; also,
actual cost per brochure / planned cost per brochure = [45,000 expended / 150 brochures produced] /
200 per brochure = 300 / 200 = 1.5).
3.
Determine the planned value (PV), earned value (EV), and actual cost (AC) for Brochure B
through March 31 as follows:
PV = 100 per brochure 250 brochures per month 2 months = 50,000
EV = 100 per brochure 600 brochures = 60,000
AC = 30,000
4.
Determine the schedule variance (SV), cost variance (CV), schedule performance index (SPI),
and cost performance index (CPI) for the production of Brochure B through March 31 as follows:
SV = EV PV = 60,000 50,000 = 10,000
CV = EV AC = 60,000 30,000 = 30,000
SPI = EV / PV = 60,000 / 50,000 = 1.20
CPI = EV /AC = 60,000 / 30,000 = 2.00
Your analysis reveals that production of Brochure B is 20 percent ahead of schedule and 50 percent under
budget (1 / CPI = 1 / 2 = 0.5; also, [30,000 expended / 600 brochures produced] / 100 per brochure = 50 /
100 = 0.5).
5.
6.
7.
Determine the overall status of your project by adding together the schedule variances (SV), the
cost variances (CV), and the updated estimates at completion (EAC) for Brochures A and B.
Project SV = 30,000 + 10,000 = 20,000
Project CV = 15,000 + 30,000 = 15,000
Assume the remaining work is performed at the originally budgeted rate.
EAC = 115,000 + 70,000 = 185,000
If project production rates and costs remain the same until all the required brochures are produced youll finish on
budget five months late.