Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
exe
=====================================================
Default Project..................................................FRD IND
EPENDENTA-1 - B1-4
Projects:
FRD INDEPENDENTA-1 - B1-4.......................................
.INDEPENDENTA PHASE - 24.02.2015
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Progres
s Override
Calculate start-to-start lag from ...............................Early S
tart
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................237
# Not Started....................................................188
# In Progress....................................................17
# Completed......................................................32
# Relationships..................................................348
# Activities with Constraint.....................................12
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A1020 Kick-off Meeting
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2660 Start procurement instruction from Beneficiary
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3160 Process engineering P6
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3180 Electric engineering P6
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3190 Mechanical & PP engineering P6
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3200 Safety engineering P6
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3210 General & surveying engineering P6
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3370
A4780
A4800
A4810
A4820
- B1-4
Activity:
- B1-4
Activity:
- B1-4
Activity:
- B1-4
Activity:
Errors:
------Warnings:
--------Activities without predecessors..................................4
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A1020 Kick-off Meeting
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2660 Start procurement instruction from Beneficiary
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A4780 PCI 001
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A5210 PCI 002
A1040
A1050
A1060
A1070
A1080
A1090
A1100
om
A4850
Project:
P12 Test pump
Project:
HAZID/HAZOP/SIL study
Project:
Final land arrangement
Project:
Mechanical engineering
A3300
Out-of-sequence activities.......................................1
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
HAZID/HAZOP/SIL study
A2930
A3300
A4650
Activity:
Activity:
Activity:
Activity:
# Activities Scheduled/Leveled...................................205
# Relationships with other projects..............................0
Data Date........................................................19-Feb15 00:00
Earliest Early Start Date........................................19-Feb15 08:00
Latest Early Finish Date.........................................08-Aug15 16:00
Exceptions:
----------Critical Activities..............................................15
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A1100 M7 - 10% Punch list closed/Final as-built documentation accepted by Petr
om
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2330 P12 Automation/electrical skid installation
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2370 P12 Power electrical system
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2380 P12 Automation system
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2560 P12 Precommissioning
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2570 P12 Commissioning
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2660 Start procurement instruction from Beneficiary
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2850 P6 Electrical panel & control panel installation
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2950 P12 Electrical panel & control panel installation
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A2960 P12 A & E skid assembly
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A3070 P12 Complet punch-list item and obtain Petrom acceptance
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A4130 PO placed
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A4140 Materials delivered & accepted
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A4150 PO placed
Project:
FRD INDEPENDENTA-1 - B1-4
Activity:
A4160 Materials delivered & accepted
A3370