Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CIGRE 2012
SUMMARY
Recently, for the purpose of power grid expansion, old equipment upgrade/updating and substation
refurbishment/extension project are increasing in the world. Even though, the portion of GIS
substation is increasing up to now, still conventional type AIS substation are main type substation in
the world due to issue of GIS maintenance time, spare component compatibility and project cost.
Therefore, many AIS substations are being maintained through refurbishment, upgrade and extension
of existing substation using AIS equipment. However for sites where land is scarce GIS is becoming
more and more popular for complete renewals of substations. Using GIS can make the renewable work
much easier thanks to the very small footprint of GIS. In addition the outage can be kept to a minimum
if the new GIS can be built, while keeping the old station in service. The only necessary outage would
then be when changing over the objects to the new GIS.
End of 2010, asset owner National Grid Corporation of Philippines (NGCP) issued the substation
refurbishment/extension project and Hyosung are now working with the construction. This paper
describes some issues considered during design of this project, such as transformer power capacity
growth, main equipment dismantling and new secondary system integration into existing system.
It can be expected that these kinds of projects will increase more and more in the world to achieve
the grid expansion as well as system maintenance. So careful consideration shall be given to minimize
the design error, and this contribution will be helpful to approach future similar projects. Furthermore,
more issues and experience during engineering design and execution will be shared for future project.
KEYWORDS
Substation, Air Insulated Switchgear, Turnkey Project
gabbamin@hyosung.com
1. Introduction
The demand of electric power is increasing due to rapid growth of economy in the world. Even
though there are issues about Euro zone economic crisis and political issues in the Middle East, it is
expected that the electric power demand will increase more than the increase of installed capacity.
The increase of electric power demand has influenced the generation, transmission and distribution
market, and the importance of substation part is increasing. Actually the numbers of new substation
projects are increasing with refurbishment, replacement and extension project of existing substation
due to the electric power demand growth and aged facility. AIS (Air Insulated Switchgear) is still the
main type of substation design, even though GIS (Gas Insulated Switchgear) was applied to the
substation about 40 years ago. The reason for this is limited GIS capability, compatibility problem of
spare part and long maintenance time. So, it can be expected that the number of AIS substations will
increase and it is emerging issue of engineering design considering interface with existing control,
protection system and limited shutdown schedule in the refurbishment / extension project.
From this back ground, the turn-key base contracts, where one contractor is responsible for
equipment procurement, design, engineering, transportation, erection to test & commissioning is
increasing in the Middle East region. The first major success factor of turn-key projects is low cost,
customizing and engineering to propose system interface. The second one is procurement ability
through partner-ship with skilled manufacturers. And the third one is risk management ability, within
the limited project budget and contract period, learned from various project experiences in the world.
Hyosung have delivered high voltage equipment to several hundred of substations in the world as a
manufacturer and executed AIS / GIS turn-key projects at the 15 countries.
In this paper, the following issues will be discussed, which are dealt with during project execution
like transformer power capacity growth, check point during main high voltage equipment dismantling,
transportation, test and system integration of existing secondary system into new system applying IEC
61850 protocol.
2. Project Outline
The following Luzon, San Esteban & Laoag and Bohol projects are turn-key contracts for substation
refurbishment, and extension including electrical, civil, structural, architectural and mechanical
portion task at the 9 sites in the Philippine Luzon and Visaya grid. Especially existing high voltage
equipment is planned to be dismantled from existing M substation located in Luzon grid and will be
transported to each site to execute the reinstallation, test & commissioning work together with new
delivered equipment. This means that, the design and engineering of the substations was done after
careful study of existing equipment and system.
Luzon expansion project: Substation refurbishment and extension project for 7 sites in the
Luzon Grid
San Esteban Laoag project: Substation refurbishment and extension project for 3 sites in the
Luzon grid.
Bohol Backbone project: One new substation project and one extension project in the Visaya
grid.
Nominal Voltage
230kV
69kV
1850mm
800mm
3200mm
900mm
4000mm
2000mm
Figure 3. Section view of Transformer (A Phase) Figure 4. Section view of transformer (B Phase)
ITEM
Gantry Structure
Material
SS400
Tensile Strength
48 Kgf/
Conductor
AL Alloy
THAL 660
14.8 Kgf/
28 Kgf/
String Set
Steel
24kgf/
40Kgf/
First of all, to prove the re-use of existing gantry tower and beam, the structure was modeled as
below Fig.5 and value of displacement and stress was checked.
Location
Gantry Tower
Gantry Beam
String Set
Displacement
2.08mm
0.411mm
-
2. Circuit Breaker
3. Disconnect switch
1) Testing of insulation resistance (2.5kV DC for
1 minute)
2) Tests of insulation resistance of motor
operation and auxiliary device control wiring
3) Measurements of contact resistance
4) Checking of operating mechanism
5) Anti condensation function
Check List
1.
1.1
1.2
1.3
1.4
2.
2.1
2.2
2.3
Remark
Result
Remark
3.1
3.2
3.3
3.4
3.5
4.1
4.2
4.3
4.4
4.5
No.
Result
1.
2.
3.
4.
5.
Condition
Proposal
Radiator
Fan
Bushing
LCP Cable
Oil leaks due to bushing Replacement of all bushings to recover the insulation
crack
level
Corrosion of Cable
Replacement of Cable to avoid short circuits
Main Body
Apart from above transformer, overall appearance and oil condition was good to re-use, but it was
decided to need the oil re-filling and gasket replacement.
3.3. System upgrades to IEC 61850 protocol
The IEC 61850 protocol is being applied to NGCP system for the new substation automation
control system. The existing IED using IEC 60870-103 protocol is required to be integrated to the
automation system using IEC 61850 protocol system supplied through this project. So, overall system
was designed as below using protocol converter and separate gateway.
-
In addition to substation automation system, the protection management system (PMS) slave unit
was delivered under this project. It was connected PMS grid which NGCP is gradually establishing.
PMS is a separate system with substation automation system and fault/event recorder, but function is
similar. It will conduct the similar function as redundant concept, but the advantages are as below.
Collecting all the information from protection relay and fault/event recorder including event,
logical-linker, alarm, setting data, fault waveform files from relay & fault recorder. The substation
automation system and fault/event recorder can only collect part of above information, and they can
analyze certain part of information, while the PMS can get all the information and provide full data for
further analysis and advanced application.
It is possible to tele-control all the function of protection relay and fault recorder including remotely
modify the setting value, switch setting zone, logical-linker and generate the new waveform files of
fault recorder.
In the master unit, PMS could implement many advanced application in grid level including remote
centralized setting management, alarming when setting value changed, etc.
4. Conclusion
End of 2010, asset owner National Grid Corporation of the Philippines(NGCP) issued the substation
refurbishment / extension project and Hyosung are now in the construction phase. During the
engineering design and execution of these projects, some technical issues, such as transformer power
capacity growth, main equipment dismantling and new secondary system integration into existing
system, was considered and approved for the submitted report using analysis and calculation tools. We
also described the results of integration of substation existing and new automation system.
Now, NGCP is operating these systems in Philippines and Hyosung is executing another project
including 500kV substation.
BIBLIOGRAPHY
[1]
[2]
[3]