UNIT 4
POWERHOUSE
INTRODUCTIONS
JASON MCLAUCHLIN
PROJECT ENGINEER
DANNY ROBERTS
FIELD ENGINEER
PROJECT TEAM
THE PROJECT
32 MW Francis Turbine/Gen
1000 Steel Lined Power Tunnel
Subterranean Concrete Structure
and Tailrace: 7,949CY placed
Mechanical and Electrical Building
Systems
Integrated Facility Controls of
Units 3 and 4
Upgraded Unit 3 controls and
Governor
Synchronous Bypass
PROJECT GOALS
Manage In-stream
Flows of the Baker and
Skagit Rivers
Restore Facility
Generating Capacity
Lost in 1960s landslide
Maintain Water Supply
to Lower Baker Adult
Fish Trap
PROJECT STRATEGY
Design-Build Delivery
Collaborative Team Approach
Focus on achieving PSEs
performance requirements
Phased Design and
Construction
CONSTRUCTION
PHASE I - EXCAVATION
PHASE 1 EXCAVATION
PHASE 1 EXCAVATION
PHASE 1 EXCAVATION
PHASE 1 EXCAVATION
PHASE II TUNNELING
PHASE II - TUNNELING
PHASE II - TUNNELING
Unit 4 Tie-In
Bottom of 270
Surge Shaft
50LF in 22day
shutdown
Laser Scanned
PHASE II - TUNNELING
PHASE II - TUNNELING
PHASE II - TUNNELING
PHASE IV TAILRACE
PHASE IV - TAILRACE
PHASE IV - TAILRACE
PHASE IV - TAILRACE
FINISHED PRODUCT
SUCCESSFUL PROJECT
Tunneling Operation Extremely Accurate
Achieved all Tolerances in Stacking Unit
Digital Upgrade of Unit 3 Control Room and
hydraulic system
Commercially Operational 100 days ahead of
schedule
Successful Overall Design Coordination with
Owner provided Unit
No interruptions to ongoing Unit 3 generation
LOWER BAKER
UNIT 4
POWERHOUSE
QUESTIONS?