Sei sulla pagina 1di 16



5.1

&

'

"

CONCRETE MATERIALS AND MIXES


5.1.2 Materials
5.1.2.1 Portland Cement
Add the following to item 1:
1a.
The chloride content shall not exceed 0.1% when tested in accordance with Clause
4 of BS EN 196-2.
1b.
The heat of hydration shall not exceed 290 kJ/kg at 7 days when tested in
accordance with BS EN 196.
1c.
The acid soluble alkali level measured as (Na2O+0.658 K2O) shall not exceed 0.6%
by weight determined in accordance with BS EN1962.
1d.
For any type of cement, the following physical & mechanical test shall also be
included:

Consistency in accordance with BS EN 196-3

Setting time in accordance with BS EN 196-3

Soundness in accordance with BS EN 196-3

Compressive Strength BS EN 196-1

1e.
The compressive strength of the cement when tested at 28 days according to BS EN
196 shall be at least 42.5 MPa.
The test results shall meet the following mechanical and physical requirements given as
characteristic values:
Strength
Class
32.5 N
32.5 R
42.5 N
42.5 R
52.5 N
52.5 R

Compressive Strength MPa


Early Strength
Standard Strength
2 days
7 days
28 days
16.0
32.5
52.5
10.0
10.0
42.5
62.5
20.0
20.0
52.5
30.0
-

Initial Setting
Time
minutes

Soundness
(expansion)
mm

75
60

10

45

Add the following after item 4:


5.
Any consignment not used within two (2) months from the date of manufacture will
not be allowed to be used in the works.
6.
Approval of cement does not relieve the Contractor of the responsibility to produce
concrete of the specified strength.

&

'

"

5.1.2.2 Silica Fume


Delete item 2 and replace with the following:
2.
Microsilica from each furnace and type of base metal shall be type tested to the
requirements of ASTM C 1240 including its optional requirements. Type testing shall be conducted
at least once every three years.
2a.
In addition the material delivered to the project site shall be tested at the frequency
stipulated in ASTM C1240. The test results shall conform to the requirements of ASTM C1240 as
well as the following:
Properties
SiO2
Free Carbon
Bulk density
Chloride
Other metals
2b.

Value
Min. 85%
Max. 3%
Max. 600 kgs/m3
Max. 0.2 %
Report as assayed

Batch test certificates shall be provided for each consignment delivered to the site.

5.1.2.5 Aggregates
Add the following after item 1:
1a.
Except as may be modified hereunder the aggregate (fine and coarse) for all types of
concrete shall comply in all respects with BS 882 "Concrete aggregates from natural
sources".
Add the following after item 2:
2a.
Before any material from a particular source is used, the Contractor shall obtain
representative samples of fine and coarse aggregates and carry out the necessary tests and
analyses to show that the samples comply with the Specification. During the progress of the
works, the grading and chemical characteristics may be checked at frequent intervals.

&

'

"

Add the following to Table 5.1.2.1 and Table 5.1.2.2


Table -5.1.2.1a : Limits for Physical, Chemical And Mechanical
Properties of Aggregates for Concrete
S No.

Test

1.

Light weight pieces

2.

Water absorption

3.

Specific Gravity (Apparent)

4.

Partially crushed faces of


coarse aggregate with at least
one crushed face.

Test Methods

ASTM C123
ASTM C128
ASTM C127
ASTM C128
ASTM C127
Hand Picking
and Visual
Inspection
Method

Permissible Limits

Fine
max.0.5%

Coarse
max.0.5%

max.2.3%

max.2.0%

min.2.60

min.2.60

100%.

Acid soluble Chlorides, Cl


For reinforced concrete made
with SRPC cements

max.0.03%

max.0.01%

max.0.03%

max.0.02%

max.0.03%

max.0.02%

OPC & MSRPC cements

max.0.03%

max.0.04%

For prestressed concrete &


steam cured structural
concrete

max.0.03%

max.0.01%

min100KN

max.30%

OPC & MSRPC cements


5.

For mass concrete made with


SRPC cements

Mechanical strength
10% fines value
6.
Impact value
7.

8.

Drying Shrinkage
Potential reactivity,
Note 2
Of Aggregates, Chemical
Method Of
Cement-Aggregate
Combination

BS 812 Part
117,
Appendix C

BS 812 Part
111
BS 812 Part
112
BS 812 Part
120
ASTM C289

ASTM C227

max.0.05%
Innocuous

Innocuous

6 month expansion 0.10 %


maximum

&

'

"

Delete item 5 (i) and replace with the following:


Table- 5.1.2.2a Frequency of Routine Tests on Aggregates
S No.
1.
2.
3.
4.
5.
6.
7.
8.

Tests
Grading - BS EN 933-1
Material finer than 0.075 mm BS EN 933-1 or ASTM C117
Clay lumps and Friable Particles
- ASTM C 142
Organic impurities ASTM C 40
Water absorption - ASTM C128/C127
Specific Gravity - ASTM C128 /C127
Shell content - BS EN 933-7
Particle shape BS 812 Section 105 Part
105.1.& Section 105 Part 105.2
Acid soluble chlorides, Cl
Qualitative-BS 812 Part 117
Appendices A/B

9.
Quantitative-BS 812 Part 117
Appendix C

10.

11.

12.

13.

Acid soluble sulphates,


SO3 - BS EN 1744-1

Soundness, Mg SO4 (5 cycles)


ASTM C88
Mechanical Strength
10% Fines or impact value
- BS 812 Parts 111, 112
Los Angeles abrasion - ASTM C 131/C 535
Moisture variation in sand - by
Oven dried method

Frequency
Per 1,000m3 Concrete
- do Per 4,000m3 Concrete
Per 20,000m3 Concrete
- do - do - do - do Per 10,000m3 Concrete
Each 12 concrete days if result
is more than 75% of the limit
and each month if result is less
than 75% of the limit.
Per 10,000 m3 or each 24
concrete days if result is more
than 75% of the limit & each 2
months if result is less than
75% of the limit which ever is
less.
Each 48 concrete days or
20,000 m3 whichever is less
Each 30 concrete days or
10,000 m3 whichever is less
- do Twice daily

14.

Drying Shrinkage
BS 812 Part 120

At the start of the project


and whenever there is a
change in the source of
supply

15.

Potential Reactivity:
of aggregates (ASTM C 295, C 289)
of Carbonate (ASTM C 586)
of Cement aggregate combination (ASTM C
227)

At the start of the project


and whenever there is a
change in the source of
Supply

16

Light weight pieces test (ASTM C 123)

Per 20,000 m3


&

'

"

Add the following after item 8:


9.
The results of these tests shall be submitted to the Engineer and his approval shall
be obtained before any of the material is used in the works. Part of each sample will be
required for concrete trial mixes and part shall be retained for comparison with subsequent
deliveries.
10.
Sampling for testing and analysis shall be carried out, where applicable, in
accordance with BS 812 Part 102
11.
The maximum size of the aggregate shall not be larger than 1/5 of the narrowest
dimension between sides of the member for which the concrete is to be used and not larger
than 3/4 of the maximum clear distance between reinforcing bars.
12.
Beach sand shall not be permitted for use in concrete mixes.
13.
Unless otherwise authorized by the Engineer coarse aggregate shall be delivered to
site in separate sizes according to the maximum specified aggregate size for each grade of
concrete.
14.
Aggregate shall be tested for petrographic analysis. The petrographic analysis report
shall include the recommendation on the possibility of using aggregate in the production of
concrete.
15.
Fine Aggregate shall be clean sharp natural and/or crushed sand complying to the
grading requirements of BS 882 Zone C or M. The Contractor shall mechanically wash
aggregate to remove salts and other impurities in order to meet the requirement specified.
16.
Coarse aggregate shall be prepared as single sized aggregate and blended to
produce normal size grading. The combined grading shall be within the appropriate grading
limits given in BS 882. However, in no case shall materials passing the 0.075mm, sieve
exceed three (3) percent by weight of the combined aggregate.
17.
Aggregates that are deleteriously reactive with the alkalis in the cement in an amount
sufficient to cause excessive expansion of concrete shall not be used.
17.1: Aggregates may initially be assessed for its reactivity in accordance with ASTM C289
and if potential reactivity is indicated, then mortar bar tests in accordance with ASTM C227
shall be carried out.
17.2: If the Petrography report determines the aggregate as silicate type, the aggregate shall
be tested for alkali silica reactivity. If the aggregate is defined as carbonate type, the test
shall be conducted for alkali carbonate reactivity. The test results shall show that the
aggregate is not deleterious for use in concrete.
5.1.2.6 Water
Add the following item after item 1:
1a.
The mixing water should be clear, apparently clean and free from matter harmful to
concrete in its fresh or hardened state. Potable water can be used. Water shall be tested for
physical and chemical properties and meet the requirements of BS EN 1008.
1b.
Water for curing concrete shall meet the requirements of BS EN 1008 and not
contain impurities in sufficient amounts to cause discoloration of the concrete. Sources of
Water shall be maintained at such depth and the water shall be withdrawn in such a manner
as to exclude silt, mud, grass and other foreign matter.
The frequency of testing for the materials shall be as follows:

&

'

"

Table5.1.2.3 Frequency of Routine Testing:


ITEM
a.
b.

Cement - as per BS
EN 196
Steel
Deformed Steel Bar
as per BS 4449
Strand as per
ASTM A416 if needed

Sampling
Method
BS EN 1967

Test
Method
BS EN196

BS 4449

BS 4449
ASTM
A370
Concrete

ASTM A416

c.
Air content, as per BS
EN 123501-7

BSEN
12350-1

BSEN
12350-7

Flexural strength of
Prism as per BS EN
12390-5

BSEN
12350-1

BSEN
12390-5

Bleeding as per
ASTM C232

BS EN
12350-1

C 232

Splitting Tensile
Strength of Concrete
Cylinder as per ASTM
C-496 & others
Depth of Water
Penetration (BS EN
12390 P-8)

Test Frequency Rate


Each 5000m3 of concrete
poured.
3 Specimens per each size
100 tons.
1 Specimen per each size 18
ton
Once at the time of mix design
of concrete or as directed by
the Engineer.
Once at the time of mix design
of concrete or as directed by
the Engineer.
One at the time of mix design
of concrete or as directed by
the Engineer.
One at the time of mix design
of concrete or as directed by
the Engineer.

BS EN
12350-1

C-496

BSEN
12350-1

BS EN
12390-8

ISAT as per BS 1881p-208

BS EN
12350-1

BS 1881 208:1996

Rapid chloride
permeability

BS EN
12350-1

ASTM C
1202

Each 200m3 of particular


grade of structural concrete or
as directed by the Engineer.
Each 500m3 of particular
grade of structural concrete or
as directed by the Engineer.
Each 200m3 of a particular
grade of structural concrete or
as directed by the Engineer.

Slump test - as per


BS EN 12350-2
Concrete Mix Design
(Mixing and Sampling
in the lab) as per BS
1881, Part 125 & In
Site (Sampling) as
per BS EN 12350-1

BS EN
12350-1

BS EN
12350-2

From each transit mixture load


arrived at site
All mixes are to be designed
once for verification and
approval.

Kerbs-as per BS
7263

BS EN 1339

BS EN
1339

e.

Water

BS EN 1008

BS EN
1008

3 Samples to be taken from


each batch of up to 1000
kerbs in whole consignment
One Sample per every week
of production of concrete or as
agreed by the Engineer

&

5.1.3

"

'

CONCRETE MIXES

5.1.3.1 Design Mixes


Add the following after item 1:
1a.

Structural concrete shall have a service life of at least 100 years.

5.1.3.3 Reports
Add the following after item 1:
1a.
Approval for concrete mixes shall only be given after submissions and the results of
the site trial are found to be satisfactory. Approval will not be given on the strength of
documentary submissions only.
1b.
Each mix of concrete must be given a unique identification number which shall be
cross referenced in all documents concerning the mix.
1c.
Submissions for each mix of concrete must be made during the mobilization period.
The submission shall comparatively outline the properties required by the specification and
either the actual mean properties of the mix proposed obtained statistically from previous
production batches or the target values assigned for production. The submission must
contain the total chlorides and sulphates based on cementitious content, total aggregate
grading together with a graphical illustration, the aggregate cement ratio by volume, the
hydrated cement % by volume, the fineness modulus, the nominal aggregate size distribution
by weight percentage, the total % passing 75 m, wet mixing time, distance from plant to site
and estimated delivery time. A sample copy of the approved batching plant computer printout
shall be enclosed.
1d.
The specification stipulates limits for properties in the form of minima-maxima. These
limits must not be construed as targets to achieve. The designer must aim for a target mean
for each property to attain the quality of concrete required.
1e.
A site trial mix in the form of a dummy placement must be conducted in accordance
with Appendix 2.1 of these Specifications to determine the properties of the fresh and cured
concrete proposed. In addition the site trial will enable assessment of The Contractors ability
to perform formwork and rebar construction, quality checks, placement and curing tasks.
Site Trial
Various Parameters and abilities need to be assessed during the site trial and shall include
the following but not limited to:
Slump reduction over time.

Increase of concrete temperature over time.

Transporting cubes from the site to an approved independent laboratory.

The correlation between strength and durability values of 28-day wet cured cubes
and 7-day wet cured structure.

The Contractors ability to construct leak free formwork.

The Contractors ability to provide shaded and suitable areas for sampling and cube
making.

&

'

"

The Contractors ability to place, compact and cure the concrete.

The Contractors ability to perform quality control.

1f.
Each class of concrete (shown on the drawings) is denoted by its 28 days
characteristic cube strength and the maximum size of aggregate. Preliminary laboratory tests
shall be carried out to determine mixes that satisfy the specification with the approved
materials.
1g.
The Contractor shall carry out as many trial mixes at his own cost, as may be
necessary to demonstrate that the mix design, site tasks and curing procedure adopted will
produce concrete of the specified properties.
1h.
When the mix has been approved, variations shall not be made in the proportions,
type or the source of the constituent ingredients, or in the size and grading classification of
the aggregate without the consent of the Engineer. A new submission shall be made by the
Contractor in the event any change in the approved parameters.
1i.
Samples shall be tested to determine the following properties of mixes proposed for
initial field tests:
I.

Bleeding in accordance with ASTM C232 (non-vibrating) shall not exceed 0.5% for
structural concrete.

II.

Drying shrinkage in accordance with BS EN 1367 shall not exceed 0.05 % for
structural concrete.

III.

Air content if applicable BS EN 12350

IV.

Workability to BS EN 12350

V.

Chloride permeability shall be less than 2,000 coulombs for structural concrete, when
tested in accordance with ASTM C-1202.

VI.

Water Permeability test results according to BS EN 12390-8 shall not exceed 10mm
for concrete contain microsilica and 25mm for concrete does not contain microsilica.

VII.

Fresh and hardened concrete densities to BS EN 12350 and BS EN 12390


respectively.

VIII.

Compressive strength to BS EN 12390

1j.
If the minimum maximum values are not complied with, the proposed mixes shall
be rejected.
1k.
All costs connected with the preparations of trial-mixes and the design of the
job-mixes shall be borne by the Contractor.
1l.
The average compressive strength of the trial mixes shall exceed the specified
characteristic strength by a margin of 1.64 times the standard deviation measured from the
validated production history of the specific mix from the concreting plant, except that no
standard deviation less than 3.5 N/mm2 shall be used as a basis for designing a mix.
1m.
The average ASTM C 1202 permeability shall be below the specified value by 500
coulombs.

"

&

'

"

1n.
Statistical data: Where there is no validated statistical data existing for the specific
mix design submitted for approval, The Engineer shall assign estimated mean strengths
based on the trial mix and to the following table:

No.

fck,cube or
fc,cube
[N/mm2]

Minimum
Margin
[N/mm2]

< 30

+9

30

+9

40

+10

50

+12

60

+15

Estimated Target Mean


[N/mm2]
Trial mix mean
less 4
Trial mix mean
less 4.5
Trial mix mean
less 5
Trial mix mean
less 6
Trial mix mean
less 7

Lower limit of range


[N/mm2]
Trial mix mean
less 8
Trial mix mean
less 9
Trial mix mean
less 10
Trial mix mean
less 12
Trial mix mean
less 14

1o.
The mean strength shall not be computed from a mixture of different mix designs.
1p.
The estimated mean strengths shall be replaced with the actual mean strength once
at least 40 results from 40 separate loads made over at least 30 days is available. The target
strength to aim for shall be the actual mean and not the minimum strength stipulated in the
specification. The producer must maintain a register of product data obtained from production
batch tests for each mix design as follows.

Arithmetic mean

Minimum

Maximum

Standard Deviation

Count

&

'

"

5.1.3.4 Concrete Classes


Delete Table 5.1.3.1 and replace with the following:

Concrete
Class

Maximum
Aggregate
Size (mm)

Range of
Cement
Content
(kg/m3)

Microsilica
(Percentage
of Cement
Weight) -%

Maximum
Free
Water/Cement
Ratio

Characteristic
28-Days
Cylinder
Strength
CCS (N/mm2)

Characteristic
28-Days Cube
Strength
CCS (N/mm2)

50/20 MS 7
20
370 - 400
7
0.40
50
40
45/20 MS 7
20
350 - 380
7
0.40
45
36.5
40/20 MS 7
20
345 - 370
7
0.40
40
32
50/20
20
425-500
0.45
50
40
45/20
20
425-475
0.45
45
36.5
40/20
20
350-450
0.45
40
32
37/20
20
330 - 350
0.42
37
30
35/20
20
320 - 330
0.42
35
29
30/20
20
300 - 400
0.5
30
24
25/20
20
250 - 275
0.5
25
20
16/20
20
230 - 250
0.5
15
13
Note: Concrete Classes are defined based on the Characteristic 28 Days Cube Strength CCS (N/mm2)
5.1.3.7 Water Cementitious Materials Ratio
Delete item 1 and replace with the following:
1.
The water cementitious ratio shall be determined in accordance with BS EN 206.
1a.
The water cementitious ratio of structural concrete shall not exceed 0.4
1b.
The water cementitious ratio of blinding concrete shall not exceed 0.5
5.1.3.8 Slump Limits
Add the following after item 1:
1a.
The slump of the concrete with microsilica shall be at least 100mm and for normal
concrete shall be at least 75mm. The maximum slump for normal concrete is 120mm. There
is no upper limit for the slump of concrete with microsilica. However, the concrete shall not
show any sign of segregation during placement. The slump for piling concrete shall be
180mm minimum.
1b.
Workability shall be assessed by the following tests the requirements for which shall
be as specified elsewhere in the documents.

Slump test shall be performed according to BS EN 12350-2

Compaction factor shall be performed according to BS EN 12350-4

Vebe time shall be performed according to BS EN 12350-3

Flow test shall be performed according to BS EN 12350-5

&

'

"

5.1.3.13 Adjustments to Concrete Mixes


Add the following after item 1:
1a.
If the maximum aggregate size is 10mm, the maximum cementitious content
stipulated for each class of concrete may be increased by up to 20kg/m3. For 40 mm
aggregates the cement content may be decreased by 30 kg/m3.
1.
The Contractor shall use Microsilica for structural concrete in any environment with a
requirement for concrete permeability of a maximum of 2000 coulombs (ASTM C 1202).
5.1.3.15 Permeability Tests
Add the following after item 2:
2a.
In view of the large variation of permeability values obtained with the ASTM C 1202
test, the target for the value at a trial mix shall be the maximum of [2000 minus 500]
Coulombs unless validated production data exists for the population statistic for a specific
mix design which shows it to be different. The population shall consist of at least 40
specimens from different batches with data for the range of values, the standard deviation,
the population mean and a graphical frequency distribution.
The water permeability when tested in accordance with BS EN 12390-8 shall not exceed
10mm for structural concrete.
5.1.4

Construction Requirements

5.1.4.4 Quality Control and Testing


Add the following to item 1:
1a.
The testing shall be either performed by the approved independent agency or at the
site laboratory in the presence of the Engineer or his representative.
5.1.4.5 Quality Control Testing on Fresh Concrete
Add the following after item 1 (v)
1(vi). The testing of fresh concrete and the making of cubes must be performed by
qualified technicians. Cubes made on site shall be prepared on a level, hard surface in a
mobile or fixed shaded hut complying to BS EN 12390. The molds shall be checked to
conform to BS EN 12390. The Cubes shall be protected from evaporation losses immediately
after making by encasing each cube with Hessian and a plastic bag. The cube in its mold
shall be transported to the vicinity of the curing tank not earlier than 12 hours but not later
than 36 hours from its making and de-molded. The de-molded cubes shall be instantly
immersed in a temperature controlled curing tank. The cube shall be protected from damage
and drying out during transportation.
1(vii). The producer is prohibited from handling the cubes or transporting them to the
laboratory once they have been made. The Consultant shall be the custodian of the cubes till
they have been tested. Cubes must be tested in an approved independent laboratory or at
the site laboratory where the tests are supervised and witnessed by the Engineers
representative. They shall not be tested in the producers laboratory.
1(viii). A sample for test cubes shall mean two sets, each of three cubes taken from a spot
sample.
1(ix). A sample of concrete shall be taken at random on eight separate occasions during
the first five days of using a mix at least one sample being taken each day. The standard

&

'

"

deviation shall be calculated from at least 40 individual cube results each representing
separate batches of each concrete mix produced by the same plant under the same
conditions of mixing. Thereafter one sample shall be taken at random for each class of
concrete in accordance with the Clause on Quality Control of these Specifications. The
sampling rate for the ASTM 1202 and BS EN 12390-8 permeability tests shall be 1 sample
every 200m3 for each test.
1(x). In addition to the above requirements, at least one sample shall be taken from each
individual structural unit even the quantity is less than 200 m3, or part of a unit, when the
latter is the product of a single placement.
1(xi). From each sample three cubes shall be made for testing at 28 days and three for
testing at 7 days.
1(xii). The frequency of sampling may be required to be varied if directed by the Engineer.
1(xiii). The procedures shall be repeated when materials or design mixes are changed.
1(xiv). A test result for a sample shall mean the mean of three cubes forming the sample
set. Each individual result in the sample set shall be within 15% of the mean result. In the
event that any individual result fails to comply with the closeness requirements, the non
complying result shall be discarded from the mean calculation and the mean shall be derived
from the remaining results from the two cubes. The number of total accumulated results
below the specified characteristic compressive strength should not be more than one and no
result should fall below the characteristic strength minus 3 N/mm3. The average compressive
strength test result of the cubes in a sample set when tested at 28 days shall not be less than
the design characteristic 28 day cube compressive strength.
1(xv). If the above criteria are not satisfied, the unit represented by the sample is
questionable and the following actions may be instructed as appropriate:

Cutting and testing cores from placed concrete

Load-testing relevant structural units

Cutting out and replacing defective concrete

1(xvi). If the range of individual cube strengths made from the same sample exceeds 15%
of the mean, then the method of making, curing and testing cubes shall be checked. In the
event of a sample having a range exceeding 20%, then the result shall be unacceptable and
the Engineer may order any of the following actions:

Improving quality control

Cutting and testing cores from placed concrete

1(xvii). Structural Concrete shall be tested for durability properties by conducting


permeability tests as specified herein and when directed by the Engineer.
1(xviii). Permeability tests in accordance with BS EN 12390-8 shall be carried out. The
maximum acceptable penetration at 28 days shall be 10mm for concrete using microsilica as
ingredient and 25mm for concrete produced without using microsilica.
1(xix). 100 mm cores shall be tested to ASTM C 1202 Chloride permeability. The maximum
acceptable value shall be 2000 Coulombs.

&

'

"

5.1.4.6 Quality Control Testing on Hardened Concrete


Add the following after item 1:
1a.
In the event core testing is required, the Contractor shall cut cores from locations
identified by the Engineer and test them to BS EN 12350 and 12390.
1b.
In the event the test specimens for durability tests (water permeability test and
RCPT) fail to meet the specification, three cores from the structure shall be tested and the
test results shall meet the Contract specification requirements.
1c.
The cost of cutting and testing cores and any resultant delay shall be borne by the
Contractor regardless of whether the permeability of the deposited concrete proves to be
satisfactory or not.
1d.
Where the permeability test results found by testing the three cores taken from the
structure is confirmed as not complying with the permeability requirements, then the Engineer
may instruct that further cores be cut and tested in order to determine the full extent of the
defective concrete and further investigations to be carried out.
1e.
Defective concrete shall be cut out and replaced or alternative remedial action shall
be taken, as directed by the Engineer. The cost of such work and any resultant delay shall be
borne by the Contractor.
Add the following after item 7:
8.
When instructed by the Engineer concrete shall be tested for drying shrinkage and
wetting expansion, for which 75x75mm prisms shall be prepared and tested in accordance
with BS EN 12350 and 12390 or BS6073 Part 1 Appendix D. The maximum acceptable
limits shall be:
Drying Shrinkage:

0.05%

Wetting Expansion:
0.03%
9.
Cubes may be required and trials carried out to determine stripping times for
formwork, the duration of curing and to check testing and sampling errors.
10.
The air content of air-entrained concrete shall be determined (ASTM C231) for every
200m3 each batch produced until consistency has been achieved, when required by the
Engineer. The maximum value shall not exceed 2%.
11.
Tolerances in Proportioning Materials per load (not per batch) shall be as follow:

Cement: Measurement for proportioning all cement shall be accurate to within one
(1) percent throughout the range of use. In the case of bagged cement only full bags,
undamaged or unbroken will be permitted.

Water: The mixing water shall be measured by weight or by volume. In either case
the measurement shall be accurate to within one (1) percent throughout the range of use.

Aggregate:
The aggregates shall be measured by weight to accuracy within two
(2) percent through-out the range of use.

Admixtures: Admixtures shall be measured by volume if in liquid form and by weight


if solid. The measurement shall be accurate to within 3.0% throughout the range of use.
12.
The Contractor shall be responsible for the performance of all concrete mixes used
in the works. The mix proportions selected shall produce concrete that is sufficiently
workable and finishable for all uses intended and shall conform to the requirements of the
drawings and all other requirements of this Specification.

&

'

"

Add the following after item 5.1.4.6


5.1.4.7 Mixing Concrete
1.
Concrete shall be wet batched from a fully automatic computer controlled plant
whether it is ready-mixed or site-mixed. The plant shall have been audited and approved by
the Engineer for supply to the Works. Dry batching will only be allowed by the Engineer in
exceptional circumstances where the delivery of wet concrete is not feasible due to
transportation time.
The audit by the Engineer shall cover the following areas:

Quality system and control

Storage, handling and control of constituent ingredients

Fully computerized automatic plant and equipment

Calibration

Control of batching operations

Control in delivering concrete

Testing laboratory

Qualified experienced personnel

2.
All ingredients in the concrete must enter the system through the weigh scales or
volumetric devices. All weights must be automatically logged and printed by the plant
computer. Every ingredient must be weighed through the computer controlled automatic
weighing system and printed in the printout.
3.
Constituent ingredients shall not be added to the ready mixed wet concrete once the
agitator or truck has left the loading bay at the mixer.
4.
Delivery of the concrete load shall be accompanied by the approved batch plant
computer printouts. The printouts shall be for each individual batch as well as for the load.
The computer printouts shall have the details including but not limited to project name, client
name, consultant name, contractor name, location, structure details, mix id, grade of
concrete, weight of ingredients, variation between the mix design and actual quantity in
percentage, mixing time, time of mix started, time of mix finished, water cement ration, etc.
5.
The mixing time of concrete with microsilica shall be at least 60 seconds and that for
the normal concrete is 30 seconds.
6.
Mixers which have been out of use for more than 30 minutes shall be thoroughly
cleaned before any fresh concrete is mixed.
7.
The method of discharge from the mixer shall be such as to cause no segregation
whether partial or otherwise of the concrete materials.
8.
The aggregates shall be stored under shade on hard and leveled platforms. Storage
of aggregates and sand directly on the ground will not be allowed.
9.
The Contractor shall ensure that the constituent materials of the concrete are
sufficiently cool to prevent the concrete from stiffening in the interval between its discharge
from the mixer and compaction in its final position. Precautions shall include the shading of
aggregate stockpiles and the use of chilled water.

&

'

"

10.
The Concrete shall be carried in purpose-made agitators, operating continuously, or
truck mixers. The concrete shall be compacted and in its final position within 90 minutes of
the introduction of cement to water or damp or wet aggregates, unless a longer time is
agreed by the Engineer. The time of such introduction shall be recorded on the batch plant
printout note together with the weight of the constituents of each mix and other parameters
printed by the computer and as approved.
11.
When truck mixed concrete is used, water shall be added under the supervision,
either at the Site or at the central batching plant as agreed by the Engineer but in no
circumstances shall water be added in transit.
12.
Unless otherwise agreed by the Engineer, truck mixer units and their mixing and
discharge performance shall comply with the requirements of ASTM C 94.
13.
Re-mixing of concrete which has commenced to set shall not be allowed and in no
case shall such concrete be used in the Works.
14.
All nominal sized aggregates shall be kept in separate identified stockpiles from
which samples can be collected and tested as specified.
15.
The addition of water to wet batched concrete delivered to site from a concrete plant
shall not be permitted. Concrete delivery vehicles shall not be fitted with means of direct
delivery of water into the drum.
5.1.4.8 Minimum Test Requirements for Concrete
1.
Unless the Engineer otherwise directs, the testing program conforming to the
applicable procedures set out in the relevant ASTM and BS specifications shall include at
least the tests specified below. Samples for compressive strength tests shall be taken as
specified in the Table below with a minimum of one sample taken every day that the mix is
used. A sample consists of 6 cubes, 3 to be tested at 7 days and 3 at 28 days. Additional
cubes may be taken as directed by the Engineer.
Sampling to Represent a
Volume of m3
Critical structures e.g. masts, cantilevers, columns
10
Intermediate structures e.g. beams, slabs, bridge decks
50
Heavy concrete construction e.g. breakwaters, solid rafts
100
Structure Type

For each component of the structure (such as pier, abutment etc.), permeability samples
shall be tested in accordance with these Specifications for permeability compliance.
5.1.4.9

Provisions for Equipment at Site

1.
The Contractor shall provide and maintain the equipment listed in the table below on
site for the Engineer's use during the contract period.
S No.
1
2
3
4
5
6
7
8

Description
2mm Sieve to BS EN 933-2
150mm standard molds for test cubes and accessories
Standard slump cones and accessories
Lab grade glass thermometer 0-500 degree C
Tape measures (readability 1mm)
Portable anemometer
Hygrometer (with humidity chart)
Spirit Level

&

5.1.6

'

"

Basis of Payment

Add the following after item 1:


1a.
No separate payment will be made for the material including shutter and labor used
in the preparation of architectural finish for the structures as shown in the Drawings or as
required by the Engineer. The cost for architectural finish shall be considered as included in
the rate of Concrete for the relevant item in the Bill of Quantities. The architectural finish
shown in the Contract Drawing is indicative only. It may be modified during the tenure of the
Contract as required by the Engineer.

Potrebbero piacerti anche