Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Department
Doc No.
Inspection
Procedure
QA/QC
AJM23-19-IP-MS-000
INSPECTION PROCEDURE
METERING SKID SERVICE PREMIUM
Client
: PT.CONTROL SYSTEMS
End User
Project
Project No.
23-01-2013
: AJM 13.01.09
For Review
Yanto
Arya
Arya
Page 1 of 3
Rev
Date of Issue
Document
Department
Doc No.
Inspection
Procedure
QA/QC
AJM23-19-IP-MS-000
Status
Prepared
Checked
Approved
1.
Scope
This procedure covers the minimum requirement of inspection have to be done on
Metering Skid start from material receiving inspection up to ready for shipment.
2.
Reference
2.1 ASME Section VIII Div. 1 Edition 2007
2.2 ASME Section V
Edition 2007
2.3 ASME Section IX
Edition 2007
2.4 ASME B31.3
2.5 Customer Specification
2.6 Quality Plan of each Equipment
3.
Procedure
3.1 Material Receiving Inspection
3.1.1 All materials receiving have to be inspected for visual, dimensional and
material certificate. Visual and dimensional inspection has to be done to
make sure that all materials coming are met with Code and Customer
Specification.
3.1.2
All accepted materials will be segregated from rejected material to make sure
that only accepted materials are used for fabrication of these Pig Launcher &
Receiver
3.1.3
Make sure that all stamps have been done in accordance with Fabrication
procedure.
3.3
Fit up.
Prior to weld visual and dimensional inspection have to be done to make sure that all
dimensional conformed to fabrication drawing and Applicable Code.
3.4
Welding.
3.4.1 During welding visual inspections have to be done to make sure that all
parameters weld have been met with qualified Welding Procedure
Specification.
3.4.2
Page 2 of 3
3.5
3.6
Doc No.
Inspection
Procedure
QA/QC
AJM23-19-IP-MS-000
3.5.3
Make sure that all equipment, which will be used for hydrostatic test, has
been calibrated and the range of pressure has been met with requirements.
3.5.4
During hydrostatic test, visual inspection has to be done to make sure that
there are no leakages on weld seam and flange connections.
3.5.5
After Hydrostatic Test, visual inspection has to be done to make sure that all
test water was drain and inside of vessels dried.
Shipping Preparation.
3.7.1 Prior to shipment, visual inspection has to be done to make sure that all
shipping marking and packing conditions have been met with requirement.
3.7.2
3.8
Department
Final Inspection.
3.5.1 Prior to Hydrostatic Test final visual and dimensional inspection has to be
done to make sure that all dimensional have been met with fabrication
drawing and all parts have been weld completely.
3.5.2 Prior to Hydrostatic Test, inspection has to be done to make sure that there is
no defect.
3.6.2
3.7
Document
Visual check to make sure that lashing method has been met with
requirement and the equipment sitting on truck correctly.
Documentation.
All report of inspections has to be collected as Manufacturer Data Report
Page 3 of 3