Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1 INTRODUCTION
1.1
Objective
This procedure is intended to provide the frequency planner with a set of guidelines and checklists
when doing a frequency plan. It encompasses the planning process using the following frequency
planning tools:
Asset
Optimisation Tool Box (O:\PlanOpt\Apps\FPlanWizard\OTB.exe)
CellOpt 2.1 or CellOpt 2.2
Planning Toolbar (O:\PlanOpt\Apps\PlanningToolbar\PlanningToolbar.exe) for
1.2
Scope
This document describes the procedure for preparing and implementing a frequency plan, which
entails the generation of an interference matrix, the generation of a carriers required file, the running
of the AFP and the implementation of the plan.
1.3
Definitions
CTR - Cell Traffic Recording
FER - Frame Erasure Rate
NetCfg - Network Configuration Workbench
NCC - Network Control Centre
1.4
Responsibility
The overall responsibility of preparing, implementing a frequency plan is that of the Planning and
Optimisation Team Leader(s) for the area(s) where the plan is implemented. All members of the team
are required to assist.
1.5
References Documents
1)
2)
3)
4)
5)
6)
2 PROCEDURE
2.1
Document Structure
A quick overview of the OTB, that helps one to prepare the files required for CellOpt is given in
Section 3 - this will give a contexts in which the rest of the preparation needs to take place.
The pre-planning process is described in Section 4. This pre-planning process is critical for a
conventional prediction based plan but also applies to a measurement-based plan.
Site lists need to be prepared for each plan the Plan-list is a list of site for which you would like to
find new frequencies. For a prediction based plan an Affected-list which should include all sites that
will affect or be affected by the frequency changes also needs to be generated. Tips on how to
prepare these are described in Section 5.
Section 6 provides methods to obtain traffic information traffic file. This will be used in many steps of
the planning process.
Section 7 describes how to obtain an interference matrix. 1) In the conventional way: using
predictions and traffic distribution in Asset. This is well suited in cases where a large number of new
cells need to be brought up. Or 2) Measurement based using CTRs. This will require that no major
sites were brought up in the last 2 weeks or so. For radio network quality reasons, a measurementbased plan is strongly recommended. A Combined measurement and prediction based plan is
recommended for rural areas.
How to prepare a carrier file and determine the number of required carriers per cell is described in
Section 8.
Section 9 gives two methods to obtain exception files from two possible sources: drive test and handover statistics. For a measurement-based plan it is recommended that one do not use exceptions as
this will only skew the interference matrix and provide less than optimum results.
A step by step procedure for generating a plan in CellOpt 2.1 follows in Section 10.
In Section 11 it is suggested to prepare backup data to recover if something went wrong during the
implementation of the plan.
Section 12 informs one how to update the Asset database and validate the sanity of the plan.
Section 13 describes how to implement the plan into the network using NetCfg.
Drive tests need to be performed after the implementation of the frequency plan to give final
validation and to allow for optimisation. Section 14 describes this process.
For future reference it is necessary and interesting to keep a record of the all the data pertaining to
the frequency plan. Section 15 stipulates what need to be recorded.
4 PRE-PLANNING PROCESS
Get a Remedy Reference number by logging it yourself in Remedy or contact the NCC (083-182) for
implementing the plan on the scheduled date. Note that in most practical situations it is wise to start a
months before the time with the preparation of a frequency plan, at the rate that you would have if the
plan was due the next week - this is required due to the ever changing environment that we work in.
4.1
4.2
4.3
4.4
Asset Database
A list of all sites (Plan-list) to be included in the plan must be maintained at least one month before
the plan. This includes all new sites and all new sectorisations. Co-ordinate with the implementation
and transmission division and finalise a list of sites that will definitely be included in plan, i.e., sites
without any transmission, lease or equipment shortage problems. Note that for a measurement
based plan all the sites included in the plan must be up for at least a month before the plan .
Used the MoreFreq.exe tool to find frequencies to bring it up with.
All new sites and sectorisations that will be activated in the frequency plan must be entered into
Asset. Ensure that all the sites involved in the frequency plan have the correct data (this includes all
existing sites that can affect the planning area):
Antenna Height.
Azimuth.
EIRP.
Mechanical Tilt.
Antenna Type.
Correct Flags, e.g., the incorrect BSC and location area will affect the cell data generated after
the frequency plan.
Ensure that sites that have recently become operational are marked as operational in Asset, and
that the necessary change has also taken place in the WA system.
Once the site database has been updated, changes to this database and the sites should be limited
to sites well outside the planning area.
Predictions
Ensure that the correct prediction models and appropriate prediction radii are applied to all cells:
All major metropolitan sites must be predicted to a minimum of 40 km. The Suburban model is
recommended
Small town/road sites must be predicted to a minimum of 80 km. The General200 model is
recommended for towns and the Rural model can be used for the rural sites
Neighbours
Enter the neighbours for all new cells in NetCfg (the Cell relation tap) Neighbours could be identified
by inspection of the service area plot in Asset. Generate command files to run in new sites / sectors
with their neighbour relations.
Undefined neighbours can be identified using the Optimisation Toolbox - Neighbour Relation
Identification option. The previously undefined neighbours should be run into the switch and be active
for a while before the plan.
This is a good time to have a look at existing sites with too many (> 15 typically) neighbours and
delete unnecessary neighbours. Unnecessary neighbours can be removed, using the OTB or the
handover counts. Neither method should be used blindly. The OTB also enable one to identify
unnecessary neighbours that might be defined and have a high handover count, but where the
handovers are mostly ping-pong handovers.
Files must be generated remove excessive neighbours from existing sites.
This neighbour information may be retrieved from the BSC at a later stage for the purpose of a
neighbour exception file. In the future the neighbour relation file will also be used for BCC planning.
4.5
4.6
4.7
One of the three methods below can be used to determine the traffic per cell - the first is the preferred
method, because of the simplicity and accuracy. It is always recommended that the traffic be checked.
6.1
6.2
6.3
6.4
Traffic (Asset Format) and Traffic per Site Sector running this query would create tables in the
Frequency Planning Access database, which can be exported and used with other tools.
The queries provide the third highest traffic level recorded in any hour over the previous month a
scale factor is entered as parameter to allow for future growth.
7.1
7.2
Optimisation Toolbox provide the facility to extract carrier data from the Planned Database (MTNIS)
The number of carriers are then calculated based on the amount of traffic, whether the site is
synthesised hopping or not. The number of Carriers will always be equal or bigger than the number of
TRX's. The tool requires the following inputs, which can be provided through cell and or site lists or
from queries off the database.
The synthesised hopping site list is a list of all sites with RBS2000s (Site T number). It can be
obtained using the query RBS2000 Sites from the database (O:\PlanOpt\Data\MTN Network
Information\Frequency Planning.mdb database. A table called List of 2000 will be created. This
can then be exported. If you choose to have the number of carriers equal to the number of TRX's
this is not required.
A list of cells with CDU-D on in Planet format. (SiteTnumber <tab> sectorNumber). (A query is
available on the Frequency Planning database, but the results need to be double checked)
A list of donor cells to cell-extenders (SiteTnumber <tab> sectorNumber). A query is also
available to determine these in the Frequency Planning database. Note that this table is only as
accurate as the database and must be double-checked.
The recommended settings for a measurement based plan are
Assume 4.5 Erlang is not carried in the Hopping Set, but on the BCCH (BCCH preferred)
Minimum Carriers 2
Assume 4.5 Erlang is not carried in the Hopping Set, but on the BCCH (BCCH preferred)
Minimum Carriers 2
9.1
9.2
Both exception files can be used, but is not advisable when doing a measurement based plan. It is
still advisable to prepare both exception files when doing a frequency plan - they come in handy as
emergency measures.
Run CellOpt.
Load the model file (Prediction.txt or CTR_FER.txt).
Carefully note in the General Application log at the bottom of the CellOpt Screen that everything
loaded successfully.
Start the Optimiser, and log the CQI (CellOpt Quality Index) in a log file.
From time to time, without stopping the optimiser export a carriers file in Planet format.
Let the optimiser run for at least 12 hours. (A good time to generate backup data.)
From time to time Export the carrier file without stopping the optimiser, these file can be used as a
backup.
Stop the optimiser after it is clear that it has converged and that no further improvements could be
made. Export the carriers in Planet format.
In future the BCC (Base Station Colour Code) must be planned in CellOpt. Choose the exception list
as neighbours and the NonHopFER or Traffic Interference as penalties. Export the carriers in Planet
format. Import this back into the OTB where the NCC will be planned. One will use the OTB to import
the carriers into the Asset database.
Currently (2000/03) the BSICs are planned when the BCCH carriers are accepted. So the carrier file
exported from need to be imported into the Asset database using the tool Asset Import from the
Planningtoolbar.
Before starting with this process ensure that any changes that you want to make in Asset has been
committed and those that you don't want to make restored.
Import the carriers file that has been exported from CellOpt using the import tool Asset Import from
the Planningtoolbar.
Before the new plan is run in, a frequency dump must be taken from all relevant BSCs (i.e., RLCFP:
CELL=ALL). This information is read into the Oracle database and will allow the RLCFE command to
end the current frequencies. This should happen automatically, but you can ask Daniel to force a
dump.
Once you are satisfied with a particular plan, commit the changes in Asset (Asset Utilities (Commit All
button) in the Planningtoolbar). Note that only the sites allocated to you will be changed - if you are
combining a plan with a neighbouring region, they must also apply and commit the frequency
changes. After it is committed in Asset it the data is downloaded in the planned database.
Queries are available to group approve the changes - ask Daniel. The BCCH approval currently
(2000/03) triggers the calculation of the BSIC
Command files can now be generated to implement the new plan on the various switching centres.
Essential commands for celldata are:
RLSTC ! Halt the cell/site.
RLDEC ! Change BCCH and BSIC.
RLCFE ! End old traffic channels.
RLCFI ! Enter new traffic channels.
RLMFE ! End old measurement frequency list.
RLMFC ! Enter new measurement frequency list.
RLCHC ! To change hopping sequence numbers.
External_cell BSC definition must also be changed to update BCCH and BSIC changes.
After the plan has been successfully run, another frequency dump must be taken from all relevant
BSCs. This will be used as a consistency check to confirm that the new active frequencies are the
same as the planned frequencies.
Generate a new TEMS cell list from the Oracle database and drive test the network.
Verify all the inter BSC handovers
Note any interference or drops due to interference.
Note any missing neighbours or missing measurement frequencies
15 KEEPING RECORDS
DEFINITIONS
N/A
RECORDS
Frequency Planning form, stiffy and interference plots as specified under 15 Keeping Records.
PROCEDURE DETAILS
Originator/Author Name:
Location:
Position:
Originators Manager:
Location:
Position:
National Quality Manager:
Distribution List:
Magdaleen Snyman
Head Office
Assistant Manager Optimisation
Hendi van der Merwe
Head Office
Optimisation Manager
Andrew Portokallis
Network Group
AUTHORIZATION
Designation:
Name:
Signature:
Date:
Group Executive
Originators
Manager
Document
Originator/Author
DCS Administrator