Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Table of Contents
Introduction................................................................................................................ 2
Task 01: Contract Documents..................................................................................... 3
Identifying Contract Documents in Construction Contracts.....................................4
Various type of Standard form of contracts used in construction works..................5
JCT Standard Form of Contract................................................................................8
ICTAD Standard Form of Contract............................................................................9
Differentiating standard form of contract documents based on various types of
contracts............................................................................................................... 10
Usefulness of proper execution of the contract.....................................................13
Task 02: Cost Management....................................................................................... 15
Method of Payment for permanent works and preliminaries.................................16
Interim payment.................................................................................................... 17
Stage Payment...................................................................................................... 18
Items to be included in an interim valuation.........................................................19
Items to be included in a Final Account.................................................................21
Task 03 : Lump Sum................................................................................................. 22
Reasons for inclusions of Prime Cost Sums in a contract......................................23
Reasons for inclusions of Provisional Sums in a contract......................................24
Examples for Prime Cost....................................................................................... 25
Examples for Provisional Sum............................................................................... 26
Task 04 : Claims........................................................................................................ 27
Definition for variations as stipulated on FIDIC condition of Contract...................28
Identifying entitlements for claims........................................................................31
Task 05 : Dispute Resolution..................................................................................33
Potential causes for disputes during construction.................................................34
Eliminating or minimizing causes for dispute........................................................37
Methods of Alternative dispute resolution.............................................................38
Conclusion................................................................................................................ 39
Reference................................................................................................................. 40
1 | Page
Introduction
The contact document is a vital factor in the construction industry. It is the document that binds
the contractor and the client legally and it is a must to have a proper knowledge on how to
choose and how to execute work according to the contract document such as claiming for
damages from the client or the contractor also the methods how works are done according o the
contract document. Another important factor is finding resolutions for disputes any disputes can
occur when constructing, it can occur in various way but its highly disadvantageous if you go for
litigation there for its important that every Quantity Surveyor to know about the Alternative
dispute resolutions.
Thank you
2 | Page
3 | Page
4 | Page
5 | Page
FIDIC Condition of contract for Plant and Design Build (Yellow Book)
Condition of contract for Plant and Design Build or generally known as FIDIC Yellow Book.
This Standard contract is used specially in electrical or mechanical plant work but is used in
building construction also. The designing is usually done by the contractor by himself according
to the requirements of the client. The work may vary from civil, mechanical, electrical or from
general construction work.
6 | Page
The FIDIC Green book or FIDIC Condition of contract for Short Form of Contract is used for
projects with less capital value. It is used relatively for simpler and for repetitive work of short
duration time. Under the normal circumstances the construction work is carried on according to
the design provided by the client or by the representative of the client but it is also can be used
for projects designed by the contractor.
7 | Page
The Joint Contracts Tribunal, also known as the JCT, produces standard forms of contract for
construction, guidance notes and other standard documentation for use in the construction
industry. From its establishment in 1931, JCT has expanded the number of contributing
organizations. Following recommendations in the 1994 Latham Report, the current operational
structure comprises 8 members who approve and authorize publications. They are the
Association of Consulting Engineers, the British Property Federation, the Construction
Confederation, the Local Government Association, the National Specialist Contractors Council,
the Royal Institute of British Architects, the Royal Institution of Chartered Surveyors and the
Scottish Building Contract Committee. JCT is majorly used in European countries and most
other countries are unfamiliar with JCT contracts.
There are several publications by the JCT but following are the commonly used,
o
o
o
o
o
8 | Page
of works
ICTAD SBD 02 contracts value between over Rs. 100 million (Major
contracts).
ICTAD SBD 03 contracts up-to Rs. 10 million.( Minor contracts)
ICTAD SBD 04 contracts where the contractor is responsible for
9 | Page
Capacity for
variations
Complexity
The involvement
of the client is
relatively low in
FIDIC contracts
when comparing
with the other
contract
documents, but in
FIDIC Yellow
book- Plant and
design build The
involvement of
the client is
higher than other
FIDIC
documents. It
doesnt imply that
there is no client
involvement in
other FIDIC
contract
documents, they
require less
attention of the
client to the
projects when
following other
FIDIC Contract
documents.
Designing is
mostly done by
the client or by a
design team
appointed by
the client. There
for most of the
highly
managerial
decisions are
taken by the
clients, but in
FIDIC Silver
book EPC &
Turn Key or
FIDIC Yellow
Book Design
and bill The
main contractor
plays a main
role in
managing of the
project.
Because of the
less
Involvement of
the Client the
capacity for
variations
might be
higher than
other contracts
FIDIC Contract
documents are
easy to follow
and easily
understandabl
e for either
parties there
for FIDIC is
popular among
many
construction
companies.
Speed
Design and
Management
FIDIC
Client
Involvement
Because of the
less
complexity of
the
documentation
works and the
designing is
done by the
client the
process can
flow faster but
again with the
less
involvement of
the client
overall the
speed of the
project can be
average
10 | P a g e
Capacity for
variations
Complexity
As in FIDIC in
generally the
involvement of
the client in JCT
contract
documents are
comparatively low
and the client has
a low
er risk
Designing is
mostly done by
a 3rd party or by
a team
appointed by
the client
however there
are some
contracts which
allows the main
contractor to
carry on the
designing of the
project
Because of the
less
Involvement of
the Client the
capacity for
variations
might be
higher than
other contracts
JCT contracts
are much
more
complicated
comparing to
other contracts
maybe it can
be one of the
reasons that
its only used
in Europe
countries. In
FIDIC
documents
they narrowed
down all
constructions
for four main
contract
documents but
in JCT there
are many
minor and
major contract
documents
which can be
relatively an
advantage
also because
of the many
number of
documents it
makes the
Speed
Design and
Management
JCT
Client
Involvement
Because of the
complexity of
the
documentation
work and due
to the less
involvement of
the client the
overall speed
of work can be
slow
comparing to
other
contracts.
11 | P a g e
Capacity for
variations
Complexity
ICTAD is only
used in Sri Lanka
and it is much
similar to the
FIDIC
publications. In
Sri Lanka if its a
normal
construction such
as a building or a
housing project
the involvement
of the client is
relatively low due
to the lack of
knowledge in
construction but
however some
tends to appoint a
consulting team
but in generally
involvement of
the client is really
low therefore the
contract
document is
favoring less
involvement of
the client
As in JCT and
FIDIC the client
has the freedom
to choose the
contract type, if
he is capable of
managing the
designs he has
to choose a
separate
contract
document or if
he wishes to let
the contractor or
a 3rd party to do
the designing
and
management
there is a
separate
contract
document the
client should
follow therefore
designing and
managing
depends
according to the
will of the client
Because of the
less
Involvement of
the Client the
capacity for
variations
might be
higher than
other contracts
ICTAD
Contract
documents are
easy to follow
and easily
understandabl
e for either
parties there
for ICTAD is
popular among
many
construction
companies
another
advantage is
because of its
a Sri Lankan
publication it is
published in
the native
language
therefore it is
highly used
among Sri
Lankan
companies but
it cannot be
used outside
of the country
Speed
Design and
Management
ICTAD
Client
Involvement
contract
process more
complicated
Because of the
less
complexity of
the
documentation
works and the
designing is
done by the
client the
process can
flow faster but
again with the
less
involvement of
the client
overall the
speed of the
project can be
average
12 | P a g e
When two parties enter an agreement or sign a contract, the purpose of having a contract is to
make sure that neither party will neglect his or her obligations. According to the type of the
contract document the employer and the contractor agrees on, the obligations differs from one
another therefore the parties can choose an appropriate contract document according to his or
her needs or according to the type of the project and keep a flexible relationship with possible
obligation to one another. The contract document is the valid document that binds the parties
legally and the document that explains what parties are liable for. The following are the factors
affects and the usefulness of execution a proper contract.
14 | P a g e
15 | P a g e
The work contractor is responsible to execute under the contract is known as permanent works,
as in an example in a building project construction of the building is the permanent work the
works thats come under the contract that client is entitled to use after the construction works
are completed.
In every construction there should be some work done before the work starts on the
construction such as building the site offices, store rooms, labour huts, yards to store
aggregates or sand etc. For these work the contractor will have bear an additional cost other
than the construction work therefore therefore the cost for these works are billed as preliminary
Items. Also as in for construction of these items each month there will be an additional cost for
maintenance, electricity, food and lodging for labours as well as for engineers and the staff etc.
these items are also billed under the preliminary bill but the cost for these items are included to
the preliminary bill monthly.
However for both preliminary and permanent works the method of payment is done through a
Interim payment or by a lump sum payment it depends on the contract the employer wished to
follow.
16 | P a g e
Interim payment
Interim payment is done for a period of time as agreed on the contract, if it is a smaller project
and the scope of work is comparatively low the contractor can apply for the interim payment
once in 3 months or once a month but if it is a large project the contractor can apply for the
interim payment once in 10 or 15 days because the value of the work done is high.
The payment for preliminary items such as labour huts, site office stores are included in first
interim payment or 1st, 2nd and 3rd interim payments depending on the performance of the
contractor and for items such as electricity, water, lodging, food, sanitary etc. they are added to
every interim payment additional to the permanent works.
The method of payment differs from contract document to contract document, there is one
method of payment mentioned in FIDIC publications and there is another method mentioned in
the ICTAD publications but relatively they are similar there are only some slight differences.
According to the FIDIC publications the contractor should submit a statement to the Engineer
with including the following items,
The estimated contract value of the works executed and the contractors documents
produced up to the end of the interim payment period (including variations)
Any items to be added and deducted for changes in legislation and changes in cost
Any amount to be deducted for retention, calculated by applying the percentage of retention
stated in appendix to tender to the total of the above amounts, until the amount so retained
by the employer reaches the limit of Retention money stated in the appendix to tender
Any amounts to be added and deducted for the advance payment and repayments.
Any amounts to be added and deducted for plants and materials
Any other additions or deductions which may have become due under the contract or
otherwise including them under extra works, claims, dispute and arbitration etc.
The deduction of amounts certified in all previous payments certificates.
17 | P a g e
Stage Payment
In stage payment the payments are done according to the stages the project is divided, The
project is divided for several stages and the contractor can obtain his payment once he has
complete the stage. If its a building project the stages can be divided as follows
The method of payment is similar to the Interim method the items included are also the same
only the time period may differ according the work scopes on certain stages.
18 | P a g e
The estimated contract value of the works executed and the contractors documents
produced up to the end of the interim payment period (including variations)
The contractor should submit the value of the work done within the interim payment
period with evidence. For an example if the contractor has completed constructing a
certain structure the measurement sheets for the structure should be attached together
with the interim bill including the quantities of concrete volume, reinforcement weight,
form area etc. For each structure separate supporting documents should be submitted
as evidence and to justify the value of work done within the interim period. The total cost
for preliminaries or for mobilization and overheads are also added to the interim bill
Any items to be added and deducted for changes in legislation and changes in cost
Price fluctuations, change in taxes or adding of new taxes by the government can cost
the contractor more than the agreed rates on the agreement. Also the costs can be
increased due to unforeseeable events or because of clients ignorance such as, if the
client is responsible for clearance and maintenance of access roads but due to weather
changes or other events if the contractor has to bear extra costs to transport materials to
site the cost will be changed there for it should be added as an extra cost to the interim
bill.
Any amounts to be added and deducted for the advance payment and repayments.
The contractor receives an advance payment from the client before starting the work on
the project, this advance payment is deducted from each interim bill. The recovery of the
advanced payment is also done to an agreed percentage to be deducted from each
interim bill. Also if the contractor is entitled to any other payments regarding the project
the contractor has the ability to add that amount to the interim bills.
Any other additions or deductions which may have become due under the contract or
otherwise including them under extra works, claims, dispute and arbitration etc.
Variation in the structure can occur in any construction project. It can occur due to the
fault of the contractor or due to faults of the client, also there can be extra works claims
for losses of the contractor . The contractor can calculate the extra costs with supporting
documents and obtain the additions through the interim bill.
20 | P a g e
Variations.
Fluctuations
Provisional sums.
Statutory fees.
21 | P a g e
Contract claims imposed as a result of the contractor's operations (such as a thirdparty claim resulting from contractor negligence or contractual breach, for example,
flooding a neighbors property).
22 | P a g e
23 | P a g e
A prime cost sum (sometimes called a PC sum) is an allowance usually calculated by the cost
consultant for the supply of work or materials to be provided by a contractor or supplier that will
be nominated by the client. The allowance is exclusive of any profit mark up or attendance
(such as material handling, scaffolding and rubbish clearance etc.) by the main contractor.
The reasons for inclusion of prime cost sums are,
For long delivery items where design and manufacturing times could not wait for the
appointment of a main contractor. For example, lifts, switchgear or refrigeration plant.
Where specialist design input was required in the early stages of design development.
For example, for a cladding system.
Where the client directly orders a preferred piece of equipment on which design is to be
based. For example, an MRI scanner, laboratory fumes cupboards or bottling plant.
24 | P a g e
A provisional sum is an allowance usually estimated by the cost consultant and inserted into
tender documents for a specific element of works not yet defined in enough detail for
contractors to price. This, together with a brief description, allows tenderers to apply mark up
and attendance costs within their overall tender price and make allowance for this element of
work in the contract program.
An example of a situation where a provisional sum might be appropriate is where work is
required underground, or below an existing structure, where the conditions cannot be
determined until the work begins and the existing structure demolished or the ground opened
up.
Provisional sums can be 'defined' or 'undefined':
Defined provisional sums are considered to have been accounted for within the
contractor's price and program. In effect the contractor is taking the risk that their
estimate will be sufficient.
Undefined provisional sums are not accounted for in the the contractor's price and
program. This means that the client is bearing the risk for the works and the contractor
may be entitled to an extension of time and additional payments.
They should only be used as a last resort, they should not be an 'easy' fall-back position for
consultants when designs are incomplete or information is difficult to obtain, as this can burden
the client with considerable unnecessary risk and uncertainty. The risks are significant enough
that the NEC Engineering and Construction Contract does not have any allowance for
provisional sums.
25 | P a g e
white-goods
tap-ware
Light fittings.
Elevators
Tiling
Installation of machinery etc.
26 | P a g e
Excavation works
Constructing beneath an existing structure
Rock Excavation
Piling work
Demolition of a structure
And places where the condition cannot be determined until the work is being
executed
Obtaining Permits
Temporary Telephone/ Internet lines
Accommodation
27 | P a g e
Task 04 : Claims
28 | P a g e
Variation and change fall under the same definition, and mechanisms for managing the impact
of the variation or change are usually expressly provided for in terms of the contract .In other
words, there are generally contractual mechanisms, which enable the contractor or the
employer under certain construction contracts, the 1999 First Edition of the FIDIC contract to
claim additional payment or extensions of time when variation or change takes place. Usually
there is some benchmark against which to measure the extent or impact of the variation or
change which operates together with these change management mechanisms.
Variation or change usually follows from the occurrence of one or more of the following
circumstances:
30 | P a g e
31 | P a g e
32 | P a g e
Entitlement
Client (Employer)
Contractor
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Employers Entitlement
Contractors Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
33 | P a g e
Entitlement
Client (Employer)
Contractor
Employers Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Contractors Entitlement
Contractors Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
Contractors Entitlement
Employers Entitlement
Contractors Entitlement
Contractors Entitlement
34 | P a g e
35 | P a g e
Uncertainty
Uncertainty is the difference between the amount of information required to do the task and the
amount of information available (Galbraith, 1973). The amount of information required depends
on the task complexity and the performance requirements, usually measured in time or to a
budget. The amount of information available depends on the effectiveness of planning and
requires the collection and interpretation of that information for the task.
Contractual problems
Standard forms of contract clearly prescribe the risks and obligations each party has agreed to
take. Such rigid agreements may not be appropriate for long-term transactions carried out under
conditions of uncertainty.
Behavior
Since contracts cannot cater for every eventuality, wherever problems arise either party may
have an interest in gaining as much as they can from the other. Equally, the parties may have a
different perception of the facts. At least one of the parties may have unrealistic expectations,
affecting their ability to reach agreement. Alternatively, one party may simply deny responsibility
in an attempt to avoid liability.
Acceleration
It is not uncommon for commercial property owners to insist upon acceleration of a construction
project. Such examples might include the completion of a major retail scheme, and the need to
meet key opening dates or tenant occupation in an office development. The construction costs
associated with acceleration are likely to be less than the commercial risk the developer may
face if key dates are missed.
Co-ordination
In complex projects involving many specialist trades, particularly mechanical and electrical
installations, co-ordination is key, yet conflict often arises because work is not properly coordinated. This inevitably leads to conflict during installation which is often costly and timeconsuming to resolve, with each party blaming the other for the problems that have arisen.
Ineffective management control may result in a reactive defense to problems that arise, rather
than a proactive approach to resolve the problems once they become apparent.
36 | P a g e
Culture
The personnel required to visualize, initiate, plan, design, supply materials and plant, construct,
administer, manage, supervise, commission and correct defects throughout the span of a large
construction contract is substantial. Such personnel may come from different social classes or
ethnic backgrounds.
Differing goals
Personnel engaged on a large construction contract are likely to be employed by one of many
subcontracted firms, including those engaged as suppliers and manufacturers. Each of these
firms may have their own commitments and goals, which may not be compatible with each other
and could result in disputes.
Delays
Disputes frequently arise in respect of delays and who should bear the responsibility for them.
Most construction contracts make provision for extending the time for completion. The sole
reason for this is that the owner can keep alive any rights to delay damages recoverable from
the contractor. On international construction projects the question of any rights the contractor
might have to extend the time for completion was a matter often addressed towards the end of
the contract, when an overrun looked likely. From the owners point of view, this made the
examination of the true causes of delay problematical and inevitably led to disputes between the
contractor and the owner as to the contractors proper entitlement.
Design
Errors in design can lead to delays and additional costs that become the subject of disputes.
Often no planning or sequencing is given to the release of design information, which then
impacts on construction. Equally, the design team sometimes abrogate their responsibilities for
the design, leaving the contractor to be drawn into solving any design deficiencies by carrying
out that part of the work itself to try to avoid delays, and, in doing so, innocently assuming the
risk for any subsequent design failures.
Engineer and Employers Representative
The personality of the Engineer or the Employers Representative and their approach to the
proper and fair administration of the contract on behalf of the Employer is crucial to avoiding
disputes, yet a substantial proportion of disputes have been driven by the Engineer or the
Employers Representative exercising an uneven hand in deciding differences in favour of the
Employer.
Quality and workmanship
In traditional construction contracts, disputes often arise as to whether or not the completed
work is in accordance with the specifications. The specification may be vague on the subject of
37 | P a g e
38 | P a g e
39 | P a g e
1.
2.
3.
4.
5.
6.
7.
8.
9.
Arbitration
Party Autonomy
Legally Enforceable
Private and Confidential
Encouraged By every Legal
system
Power to grant order; court
powers
Time frame is limited
Independence and
impartibility
Regulated by the Arbitration
Act
Comparatively Expensive
10.
11.
12.
Adjudication
Party Autonomy
Not Legally Enforceable
Private and Confidential
Mediation
Party Autonomy
Not Legally Enforceable
Private and Confidential
No limitations
No Guarantee on
Independence or
impartibility
No limitations
No Guarantee on
Independence or
impartibility
Comparatively
inexpensive
Procedure may take
longer and decisions
might take longer
relatively
Final decision is not
certain
Comparatively
inexpensive
Procedure may take
longer and decisions
might take longer
relatively
Final decision is not
certain
40 | P a g e
Conclusion
This is the final page of the assignment & it was
really difficult to find information on some topics
even on the internet so I referred the tutorials I
was given regarding this subject. Most of my
conclusions on the topics are mentioned in the
assignment.
I hope Ive done the assignment according to the
proper criteria & I Thank you for spending your
valuable time to take a look at this assignment
41 | P a g e
Reference
42 | P a g e
43 | P a g e