ROTARY ENGINEERING LIMITED

INSPECTION TEST PLAN


FOR PIPE FIELD FABRICATION

: REL-SPT-QC-002

Rev. No

: 00

Page 1 of 2

DRAWING NO :
S / No.

Form No

LINE NO :
Inspection and Test Items

Test Inspection
Requirements
* Check material certificates and heat no:

ITP
Method
* Document review

Type of Inspect. & Acc. Sign


Rotary
SHAW
(R)

Ensure all the materials used as per the


specification

All erected spools, straight pipe etc,


clean prior to erection

* sediments, miscellaneous items removed

* Visual Inspection

(S)

Correct drawing

Latest ISO revision as per drawing register

* Document review

(R)

Bolted piping spools released from


Fabrication Shop installed and torque as
required

* Uncoated lubricated (molly coat) prior to


install
* Flange faces primed / painted / coated /
surface correct if required. Other cleaned
and prepare for gasket

* Visual & Dimensional

(W)

Verify check valves installed correctly

* Correct valves
* Position and flow direction correct

* Visual Inspection

(W)

Ensure welder is qualified and correct WPS


used

* Check welder ID
* Check welder qualification table
* check welder procedure table

* Visual & Dimensional

(S)(R)

Check Fit up - Butt welded piping, Socket


welded piping and pre heat if required

* As per drawing

* Visual & Dimensional

(W)

Spools, field run pipe and components


installed correctly

* 30 Degree staggering of longitudinal seams


above center horizontal line for all adjacent
butt welds
* Two holes alignment correct
* As per isometric
* Monitor end caps and cleanliness

* Visual & Dimensional

(W)

All Anchors Supports to be welded to pipe


complete. Branches w/reinforced pads
installed as applicable

* Visual inspection as per stress analysis


* Vent hole drilled on reinforcement pads
and dummy legs

* Visual & Dimensional

(W)

Record
Form No.
F-QA-03A

Remarks

F-QA-07A

Refer to
REL-SPT-QC-001
WPS & PQR
F-QA-07A

ROTARY ENGINEERING LIMITED

INSPECTION TEST PLAN


FOR PIPE FIELD FABRICATION

10

Inspection and Test Items


Visual examination of completed weld,weld

NDE examination of completed weld as


applicable

12

Rev. No

: 00

Hand Class

: Specific

LINE NO :
Test Inspection

ITP

Requirements

Method

* 100% Visual inspection

spatters, scale, grease dirt etc, removed


11

: REL-SPT-QC-002

Page 2 of 2

DRAWING NO :
S / No.

Form No

* 100% Visual

Type of Inspect. & Acc. Sign


Rotary

Record

Remarks

Form No.

(W)

F-QA-07A

(R)

Third Party

inspection
* 5% RT for the butt joints in accordance

* Radiography

with owner specification

All documents complete and conformanable

Client

Report

* Release

* Document review

(R)

* Refer REL-SPT-QC-008 ( Procedure

* 100 % Visual

(W)

F-QA-09A

(W)

F-QA-04A

(W)

F-QA-10A

Release for pressure test


13

Pressure test (Hydro / Pneumatic or service


required

14

for Hydrostatic Test Piping )

Flushing and Cleaning of the line

* 100% Visual inspection

Inspection
* 100 % Visual
Inspection

15

Painting Inspection / Applicable only for

* 100% Visual inspection

Carbon steel
Legend :

Inspection

S - Surveillance Inspection, W - Witness Inspection Point, H - Mandatory Hold Point For Inspection, R - Record Review
QC Inspector

Name
Signature
Date

* 100 % Visual

Clients Representative

Painting
Report

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point
INSPECTION ACTION

EM

THIRD
PARTY

Global Practice, Refinery Inspection Standard, Foster Wheeler Procedures,ASME

WPS

GP 18-07-01,GP GP 03-10-03, Foster Wheeler Procedures , ASME SEC IX

H/R

FW WP Index 1

WQT

Basing on Current approved WPS,ASME SEC IX

H/R

SWS Qualified Welders

Applicable Codes / Standards and Specification Acceptance Criteria Reference

QC Form to be used to Verify Compliance

Documents Required for Approvel

1.1

Submission of Piping & Mechanical Equipment Procedures

1.2

Weld Procedure Specifications

1.3

Welder Qualification Test

1.4

Test Log of Qualified Welders/Tack Welders,,Dialy Weld Report

1.5

Pressure Test Procedure

1.6

Insulation Procedure

1.7

Painting & Holiday Test Procedure

1.8

Preservation and Maintainance Approval

1.9

Transportation & Lifting.

(1.10.)

FW

WEC

INSPECTION

ITEM

Contractor / Subcontractor
Controlling Procedure /
Document

Equipment Calibration and logsheet (Welding Machine, Backing/Holding


Ovens Digital Thermometer, Clampmeter,Electrode,Ovens,etc.)

WEC Method Statements

Welder's Log Sheet


WEC Hydrotest Procedure

ASME B31.3,GP 03-19-01,

Insulation Procedure

GP 17-01-01,GP 14-01-01

WEC Method Statements

GP-19-01-01,RIS 1-1,RIS 1-10

WEC
Procedure/Manufacturer's
Recommendation.

0376A-8710-PR-0024

GP 04-14-01

Log Sheet to maintain,Global Practice

GP 18-12-01,ASME B31.3

Manufacturer's Recommendations

ASME B31.3 Sec 345,GP 03-19-01 SEC 4.3,

0376A-8760-PR-0002, 0376A-8760-PR-0003, 0376A-8760-PR-0004, GP170301,


GP170501

Contractor Lifting Plan

Calibration Cert Log Sheet


UT/PT/MPT/RT/PMAI
Procedures

1.11

NDE Procedures

1.12

Vendor Specific Requirements

1.13

Test Package Preparation

Set of Foster Wheeler QC


Forms

1.14

JSA/TRA for Site Activities

Approved JSA/TRA

1.15

Method Statements of Site Activities

259543259.xls

ASME SEC IX,

Vendor Procedure

Approved Method Statements

GP040901, GP041401,GP030601,GP030701,GP031601,GP040102 &


8710-PR-0001

3 of 9

0376S-

FOR PIPING ONLY

WQT Log,FW Test Rec,FW3407,FW3409 Weekly,FW 3414

FW3313,Fw4088,

Approved Test PackBV(FOR STEAM LINE ONLY

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

INSPECTION

QC Form to be used to Verify Compliance

ASME Sec.2 Part C,Manufacturer's Recommendations

Witness inspection

Foster Wheeler Forms

FW3269,FW3408,

Consumable Control
Procedure

GP180701, 0376A-8710-PR-0008,ASME SEC IX

Reports Issuance, Return,Baking & Re-Baking Records

QC Reports

GII-2007,0376A-8710-Pr-0016,GP 03-18-01

QC Reports

GII-2007,0376A-8710-Pr-0016,GP 03-18-01

FW3460

First Production NDT Report

Gp 03-18-01 Sec 15.12),ASME B31.3

Welder's Performance Record

Certified Welding Inspectors

Gp 18-17-01,Gp 03-18-01

WQT

Certified NDT Technicians

Gp 18-17-01,Gp 03-18-01

FW apprv_nd (NDE CERTIFICATES)

PT Procedure

GP 03-18-01,0376A-8710-PR-0008

FW 0005 (FOR STEAM LINE ONLY

Radiographic Examinatin

RT Procedure

GP 03-18-01,0376A-8710-PR-0008

FW 3410 (FOR STEAM LINE ONLY

2.11

Ultrasonic Examination

UT Procedure

GP 03-18-01,0376A-8710-PR-0008

FW3412 (FOR STEAM LINE ONLY

2.12

Magnetic Particle Examination

MPI Procedure

GP 03-18-01,0376A-8710-PR-0008

FW 0005,FW3411 (FOR STEAM LINE ONLY

2.13

PAMI Examination

PAMI Procedure

GP 18-12-01 , ASME B31.3

Fw5005 (FOR STEAM LINE ONLY

2.14

Hardness Testing Procedure

HT Procedure

GP 18-12-01 , ASME B31.3

FW3416 (FOR STEAM LINE ONLY

Welding & NDE

2.1

Welding Consumables Purchases,Drying & Storage

2.2

Request for Inspection

2.3

Storage of Welding Consumables,Calibrations of Ovens,Issue of Consumables

2.4

Fit Up Inspection

2.5

Visual Inspection

2.6

First Production and Progressive Sampling of Welder's Work

2.7

Welding Inspectors

2.8

NDE Technicians

2.9

Dye Penetrant Examination

(2.10.)

EM

FW

Applicable Codes / Standards and Specification Acceptance Criteria Reference

WEC

ITEM

THIRD
PARTY

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

259543259.xls

Batch Certificate

4 of 9

Consumable Log Sheet

FW5024,FW4044 (FIRST FIT UP ONLY)

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

INSPECTION

QC Form to be used to Verify Compliance

GP 03-18-01,GP 20-01-01

Fw7013

manufacturer's Recommendations

FW5024

QC Reports

GII-2007,0376A-8710-PR-0016,GP 03-18-01

H/W

FW4044

Visual Inspection

QC Reports

GII-2007,0376A-8710-PR-0016,GP 03-18-01

FW3460

3.5

Erection

QC Reports

GII-2007,0376A-8710-PR-0016,GP 03-19-01

3.6

Cleaning

QC Reports

GII-2007,0376A-8710-PR-0016,GP 03-18-01

FW5024

3.7

Suface Preparation for Coating & Holiday Test

Wrapping Procedure

GP 19-01-01

Fw3456,FW5021

3.8

Coating, Wrapping & Holiday Testing

Wrapping Procedure

RIS 1-5

Holiday Test Report,FW5021

3.9

Galvanisation

Manufacturer Procedure

GP 19-01-01

Vendor Report/Shop Report

Painting

Manufacturer Procedure

GP 19-01-01

Painting Report,FW345C,FW3461

Isometric Drawings as per site condition

Survey Report

GP 04-09-01

FW7009

FABRICATION,Painting & Erection

3.1

Material Tracebility, Receiving,Segregation and Protection

3.2

Material Preservation & Maintainence

3.3

Fit Up Inspection

3.4

(3.10.)
3.11

Acceptance of the site

3.12

Structural Steel Support Acceptance and interface with Existing Facilities for
Equipment Installation works

EM

FW

Applicable Codes / Standards and Specification Acceptance Criteria Reference

WEC

ITEM

THIRD
PARTY

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

Material control Procedure


Manufacturer
Recommendations

Survey Report
Equipment Installation
Procedure

PRESSURE TESTING, INSULATION & SYSTEM HANDOVER

4.1

Line Check & Punch listing Upon Package Approval

Hydrotest Procedure

GP 03-18-01,RIS 12-2,0376A-8710-PR-0012

4.2

Pre-Pressure Test

Hydrotest Procedure

GP 03-18-01,RIS 12-2,0376A-8710-PR-0012

259543259.xls

5 of 9

R/I
H

H/W

Punch list,FW3454
FW3419

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

INSPECTION

QC Form to be used to Verify Compliance

4.3

Pressure Testing (Shop & Site)

Hydrotest Procedure

GP 03-18-01,RIS 12-2,0376A-8710-PR-0012

4.4

Flushing and Cleaning

Hydrotest Procedure

GP 03-19-01 Sec 5,GP 18-08-01 SEC 2 & 4

FW3421,FW3426

Drying and Protection

Hydrotest Procedure

GP 03-19-01 SEC 5,GP 18-08-01 SEC 2 & 4

FW5035

RIS 13-1,

FW3433

GP 17-01-01,

GP 18-10-01 SEC .5

0376A-8710-PR-0023

Isometric Drawings as per site condition

0376A-8710-PR-0020

D126170-PS-QA-001,0376A-8710-PR-0013

4.5
4.6

4.7
4.8

4.9
(4.10.)

4.11
5

Apply Insulation and correct support


Visual and Cleanliness
Reinstatement of system and final Alignment

Typical Insulation Procedure


Manufacturer
Recommendations
Complete documents

Final Punch List of of Completed System pipe work


Weld Map, As Built Drawings

As Built Drawings

System Turnover Documents

signed documents with all


Parties approval

EM

FW

Applicable Codes / Standards and Specification Acceptance Criteria Reference

WEC

ITEM

THIRD
PARTY

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

H/W

FW8711

FW3422
X

FW3291
R

As Built Drawings

System Punchlist,FW Handover

Mechanical Equipment Installation


Equipment Installation
Procedure

FW3201,FW3202,FW3314_Preliminary,FW3314_Final,Fw7006/1 - 6,
Fw7009,Fw7010,EIRR,

5.1

Equipment Set up

5.2

Equipment Maintainence

AFC Drawings

0376A-8710-PR-0024

FW4088

5.3

Preparation of Foundation & Base

AFC Drawings

AFC Drawings, Basing on Site Condition

FW7011

5.4

Lifting Equipment & Hoists

AFC Drawings

GP041401

FW3201,FW3202

5.5

Installation of Equipment

AFC Drawings

GP041002,GP150401, Foster Wheeler Procedure

FW3201,FW3202

5.6

Vendor Specific Requirements

Vendor Specific Requirements

5.7

Inspection of Level, orientaiton and alignment

As per Specification , Manufacturer Recommendations

259543259.xls

Vendor Procedure
Vendor Recommendations

6 of 9

FW7010,FW7011

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

Grouting

5.9

Painting Touching UP Works

259543259.xls

Approved Procedures
Manufacturer Procedure

QC Form to be used to Verify Compliance

GP041002, Foster Wheeler Procedures

FW3345_1,FW3345_2

GP 19-01-01

FW3461

7 of 9

EM

FW

5.8

Applicable Codes / Standards and Specification Acceptance Criteria Reference

WEC

INSPECTION

ITEM

THIRD
PARTY

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

INSPECTION

5.11
6

Vendor Procedure

GP, Foster Wheeler Procedures

EIRR, FW 3433

Final Inspection

Manufacturer
Recommendations

GP, Foster Wheeler Procedures

FW3314_ FINAL

NDT Procedures, B31.3

UT Report

GP Procedures, FW Procedures

FW3482,FW4341,FW4342,FW4343

Approved WPS, ASME Sec IX,GP Welding Procedures

Fit Up Report

B31.3

FW8711

ASME B31.3

AFC Drawings

Approved Constrution Drawings.

AFC Drawings

Approved Constrution Drawings & Approved Documents

Hot-Tapping Works
Check the Thickness of existing Pipe

6.2

Equipment Set up

6.3

Fit Up of Stub Weld

6.4

Pressure test

Hydrotest Procedure

6.5

Closure Weld

Closure Weld Procedure

UT Procedure
Vendor Procedure
As per Approved WPS

FW3410

Structural Steel Support Acceptance and interface with Existing Facilities


for Equipment Installation works

7.1

Foundation Acceptance

7.2

Temperory Works

7.3

EM

Insulaton Works

6.1

QC Form to be used to Verify Compliance

FW

(5.10.)

Applicable Codes / Standards and Specification Acceptance Criteria Reference

WEC

ITEM

THIRD
PARTY

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

Structural Steel Support Acceptance and interface with Existing Facilities

Layout Drawings & Field


Survey Reports

7.4

Coating of Steel Work & Supports

Manufacturer
Recommendations

7.5

Steel Work Erection

Method Statement

7.6

Coating System Inspection

7.7

Consolidated Line Check and Punch List to Cleared.

7.8

Turnover Documents

Prepared By : WEC QA/QC ENGINEER


PRINT NAME :
259543259.xls

Painting Inspection Form


Request for line check
Request for Review

Prepared By : WEC QA/QC MANAGER


PRINT NAME :

FW3344

Construction Procedures,GP, Foster Wheeler Procedures.

FW0005,FW3410_Struc

RIS 1-10,AFC Drawings

FW3356,FW3358_1,2,FW3359,FW3361,FW4089

GP 04-06-02,GP-18-07-01,GP 18-10-01,GP 20-01-01,GII-2007,RIS 1-10,RIS-10-5,RIS 1101

FW3359,FW3361

RIS 1-10

FW3456

Constractor Request

0376A-8710-PR-0023,0376A-8710-PR-0020

Approved / Reviewed By: FOSTER WHEELER QA /QC


PRINT NAME :
8 of 9

System Punch list

Approved / Reviewed By : EXXONMOBIL QA /QC


PRINT NAME :

Singapore Sulfur Disposition Project

Sub-Contractor:

PROJECT NAME: SSDP PROJECT

WEC Engineers & Constructors Pte Ltd

INSPECTION AND TEST PLAN

Main Contractor : Foster Wheeler

ITP NO : ITP - M&E-001

Equipment Installation, Pipe Fabrication, Testing, Painting,


Insulation,Structural & Fire Protection

Contract Number 1-PD-0376A


ITP TITLE: PIPING & EQUIPMENT

Key for Inspection Level: X=Mandatory, I= Surveillance,

REV. :C

R-Review,W=Witness,H-Hold Point

SIGN :

SIGN :

SIGN :

SIGN :

DATE :

DATE :

DATE :

DATE :

259543259.xls

9 of 9

THIRD
PARTY

Applicable Codes / Standards and Specification Acceptance Criteria Reference

EM

INSPECTION

FW

ITEM

WEC

INSPECTION ACTION
Contractor / Subcontractor
Controlling Procedure /
Document

QC Form to be used to Verify Compliance