Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
voltage
DC
transmission,
Power
I. INTRODUCTION
and power ratings. The converter losses are a bit higher. The
VSC characteristics make it an ideal companion for off-shore
wind farms.
IV. WHERE IS THE TECHNOLOGY HEADING?
As the ratings of conventional LCC systems increase it is clear
that this mature technology is looked at favorably for very
large and/or remote renewable resources (including hydro in
that definition). As ratings of VSC systems increase and as
losses continue to reduce, applications for multi-terminal and
even grid systems in Northern Europe will become a reality.
The debate over the need for very fast dc circuit breakers will
heat up. The search for improved power semiconductor
materials (silicon carbide? diamond?) will continue. And
some of our professional colleagues will continue to state that
Edison was wrong and Westinghouse was right, alternating
current is the only way to deliver electrical energy.
V. HVDC PROJECT IMPLEMENTATION
The process of purchasing, installing and commissioning an
HVDC system is an activity that will extend over several
years. Obtaining permits can easily occupy 2 years by itself.
Once a contract is signed with a supplier, manufacturing and
installation can take an additional 2 to 3 years. This panel
session will assist a utility and its project manager in
organizing the staff needed to complete the project. Although
most of the design work, manufacturing and construction will
likely be carried out by suppliers or contractors, the purchaser
will still need dedicated staff to develop the specification,
analyze bids, execute the contract(s), monitor equipment
testing, inspect construction, work with the supplier on
commissioning, and ultimately to operate the system.
Design and construction of an HVDC system will necessarily
rely heavily on one of only a few world-wide suppliers of
such systems. As a utility begins the lengthy and expensive
process of purchasing an HVDC system, this presentation will
assist in developing plans for the execution of the project from
development of the specification to the completion of
commissioning.
A. Pre-Award Activities
Planning Studies
Cost Estimates
Permitting
Converter Station Specification
Bidding and Bid Analysis
B. Post-Award Activities
Manufacturing
Testing
Construction and Installation
Commissioning