Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Willamette river in Eugene, OR), we would take a hard look at this scenario.
Where we have bedrock with very little in the way of overburden to drive thru, I
would say that we would do a trial run. Wherein, wed drive a pile with the D25
to bearing. Then wed put the D36 hammer on the pile to prove to ourselves that
the D25 could do the job at hand. This is what we did at the McKenzie. We
found that while the Gates Equations states that the D25 wont be able to drive a
pile to the 720 KIP bearing by blow count, it would however, drive the pile to the
bedrock layer. Wherein, blow count testing wasnt needed to assure ourselves
that we were indeed on bedrock. Getting the pile to some level of fixity on the
bedrock is our goal. For this example, this is somewhat easy. In areas like
Portland, wherein you are driving pile anywhere from 60-160 long piling to get
to the Troutdale Formation, it becomes a lot more complex. A more regimented
look at the geology of the overburden is required.
6. So to summarize, we are comfortable in our planning to drive the 24 can pile in
the workbridge with our D25-32 hammer to such a level as to achieve 12-15
blows per inch with a 10 stroke.
7. Our past experience on this particular site has shown that we can anticipate
driving the pile (on average) 4to 5 deep. The first 1 will go somewhat fast with
the remaining 3-4 driving slow. Using the Gates equation it would look
something like this:
Top 1 of driving (4 blows per inch) =
48 blows
Middle 2 of driving (6 blows per inch) =
144 blows
Btm 1 of driving (10 blows per inch avg) =
120 blows
Total =
312 blows/pile
8. Total Time to drive each pile.
During driving operations, the pilebucks will frequently shut the hammer
and give the operator a quick direction to ensure that the piles are plumb.
For discussion purposes say they stop 3 or 4 times on each pile for an
average of 2 minutes.
So
i. D25-42 operates at an average of 44 bpm
ii. 312 blows/pile / 44 bpm=
7 min. of drvg
iii. Operating changes delay =
8 min (non-driving)
Total
In summary, I was hoping not to confuse everyone, but rather to show the process that is
common to most contractors on sizing hammers, sizing the pile, anticipating production
rates, loading requirements, etc for temporary work bridge style piling.
If you have any questions, please feel free to contact me.
Con OConnor
541-913-0725