Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
December 1 - 2, 2009
Holiday Inn Bangkok, Bangkok, Thailand
CONTENTS
Tsunami Research - Its past, present and near future - ..................................................1
Nobuo Shuto
Tsunami Risk Assessment and the Planning and Implementation of Strategic Mitigation
Measures- Case Study City of Galle..............................................................................25
Samantha Hettiarachchi, Saman Samarawickrama and Nimal Wijeratne
Real Time Monitoring for Mega Thrust Earthquakes and Tsunamis around the Nankai
Trough Southwestern Japan - Towards to understanding mega thrust earthquakes and
disaster mitigation - .......................................................................................................37
Yoshiyuki Kaneda, Katsuyoshi Kawaguchi, Eiichiro Araki, Hiroyuki Matsumoto,
Takeshi Nakamura, Shinichiro Kamiya, Keisuke Ariyoshi, Takane Hori, Hide Sakaguchi,
Maddegedara Lalith and Toshitaka Baba
TSUNAMI RESEARCH
ITS PAST, PRESENT AND NEAR FUTURE
Nobuo SHUTO
ARISH, Nihon University, Tokyo, Japan, shuto@nihon-u.ac.jp
Abstract
Each time when a tsunami occurred, research seeds were found and tsunami research made
progress.
After the 1933 tsunami, a small scale experiment began to understand the
Need of the
In
1960, large-scale experiments and numerical simulation started. After 1970s, numerical
simulations with the shallow-water theory have been growing with remarkable speed. The
Mansinha-Smylie method provided a way to determine the initial profile of homogeneous
fault model, which is being replaced by heterogeneous fault model.
In 1983, a video
clearly showed soliton fission in the sea that requires the non-linear dispersive equation.
In 1993, a tsunami trace in a narrow valley urged the introduction of the 2D/3D hybrid
simulation. In addition to the analysis and simulation of tsunamis, there are many needs
from a viewpoint of disaster mitigation.
Keywords: Numerical simulation, initial profile, propagation, run-ups, damage assessment
1. Introduction
From the birth to the coastal effects of tsunamis, each research topics are described in order of time.
In Section 2, causes of tsunami are summarized. Although sub-marine earthquakes are the major
subject in the present paper, another cause such as volcanic activity should be paid attention, if we
consider the Krakatau eruption that claimed over 36,000 lives.
In Section 3, generation of tsunamis and related problems is discussed. A sub-marine earthquake
generates not only tsunami but also T-wave.
Static and
propagation diagram was used. With the Mansinha-Smylie method, the fault parameters determined
from seismic data are used to estimate tsunami initial profile. After several experiences, assumption of
-1-
theory with bottom friction included. If a tsunami front shows cnoidal bore, dispersion effect should be
taken into consideration. There is no theory applicable to edge bores, running along the shoreline with
breaking front.
Section 7 is for tsunamis on land.
hybrid simulation is introduced. For a judgment whether or not a numerical simulation is carried out
satisfactorily for practical application, Aida measures K and are used.
In Section 8, four topics important from a practical point of view are selected; damage to houses and
buildings, impact of waves and floating materials, erosion due to tsunami-induced currents, and tsunami
control forests.
Section 9 is for research topics to be solved in the near future. Section 10 is concluding remarks.
2. Causes of Tsunamis
2.1 The oldest document
Thucydides, a Greek historian, was the first person who recorded a tsunami and thought that the
tsunami was generated by an earthquake. In summer of 426 B.C. during the Peloponnesian war, the sea
receded after an earthquake, and then a huge wave hit the city of Orobiae at the northwestern coast of
Euboea Island. A part of the city subsided and became the sea. At the island of Atlanta at the other side
of the strait was also hit by the tsunami.
Thucydides
considered that the full force of the earthquake drew the seawater from the shore and then the sea
suddenly swept back again even more violently.
can be generated.
2.3 Landslide
Landslides can also generate tsunamis. Lituya Bay in Alaska repeatedly experienced huge local
tsunamis in 1958, 1936, 1899, 1853-1854, and probably in 1900. This bay is about 11 km long, 1 km
wide and 169 m deep. On July 10, 1958, an earthquake caused 30 million cubic meters of rocks
weighing 90 million tons to slide from the northern shore from an average height of 600 m with the
dimensions of 700 m to 900 m and the average thickness of 90 m.
-2-
the height of 520 m on the opposite shore. Then, the water ran down into the bay to form a huge tsunami
higher than 30 m in the bay (Lander, 1996).
It claimed more than 36,000 human lives. Its maximum runup was higher than 30 m Simkin and
Fiske).
He found that a large stroke with the high speed of the piston
movement yielded high waves.
Kajiura (1970) discussed theoretically the generation
efficiency based upon the long wave approximation.
The
energy transfer from the sea bottom to the water was examined
in relation to the duration of the bottom movement. If the
duration is less than several minutes, the deformation may be
considered to be abrupt as far as the tsunami is concerned.
This idea leads to the static theory of tsunami generation; that
setup
-3-
profile.
approaches the water wave period that is determined by the water depth, the tsunami is amplified.
For a
tsunami generated in the shallow sea, this mechanism may become non-negligible.
Iwasaki (1992)
discussed the relation between the movement of sea bottom surface and characteristics of T-wave. The
generation of the compressional water waves was proved by a record of the 2004 Indian Ocean Tsunami
(Okal et al., 2007).
Ocean Tsunami hit Sri Lanka and Thailand, elephants detected this low-frequency sound and evacuated
from the sea shore. This sound also recorded on a CTBT microphone (Garces, M. et al., 2005).
characteristics), the static displacement of sea bottom surface can be computed, assuming that a fault
movement occurred in a semi-infinite elastic, homogeneous body.
-4-
movement in a fault plane that leads us to a simple tsunami profile: one crest and one trough in the area of
the generation.
More complete study was carried out by Okada (1985) with correction of misprints in
tsunami.
and measured.
The main shock of MJ=7.4 occurred at 23:57 off the Kii Peninsula generated a tsunami (Fig.2).
The
record of a GPS wave gauge, after 150 second moving average, shows the tsunami as in Fig.3. The upper
line in Fig. 3 is the computed by Koike et al. (2005).
1964 tsunami.
-5-
Only one example of the measured initial tsunami profile is found in the case of the 1964 Great
Alaska earthquake.
Figure 5 is obtained by Plafker (1965). A section along the line A-A is shown in
the lower figure. There is a gentle wavy deformation 450 km long with one crest and one trough. Its
wave height is about 6 m.
Near the crest, there is a sharp rise about 6 m high and about 30 km wide at
its base. We can compute this long deformation with the Mansinha-Smylie method but not the sharp rise,
a result of a sub-fault developed in the accretionary prism, although this rise makes the tsunami height
almost double.
Inversion introduced by
(1)
The slip xj on each subfault can be estimated by a least-squares inversion of the above set of equation.
Figure 6 is for the 1968 Tokachi-oki tsunami by Satake.
Recent development of asperity accelerates the need of the heterogeneous fault estimation.
For example, the average depth of the Pacific Ocean is about 4.2 km.
categorized as long waves, for which the hydrostatic water pressure is a good, first-order approximation.
The initial height of the tsunami is several meters, quite small compared to the water depth and the wave
length. This water wave belongs to the small amplitude waves and is analyzed with the linear long wave
theory.
In the sea shallower than 200 m, a tsunami height becomes of finite magnitude, not infinitesimally
small compared with the water depth. The shallow-water theory, the first-order non-linear long wave
equation, is used. If its water surface develops to have a non-negligibly wavy shape, the effect of
surface curvature that is called as the dispersion effect should be taken into consideration.
-6-
value propagates slower. Once the second and third terms cancel out each other, a long wave of finite
amplitude can propagate keeping its profile. Typical example is a solitary wave.
non-negligible deformation in wave profile, if the travel distance is long as in case of a far-field tsunami.
A parameter pa proposed by Kajiura (1970) is used to judge whether the dispersion effect should be
included or not:
pa = (6h/R)1/3(a/h)
(3)
where h is the water depth, a the horizontal dimension of the tsunami source and R the distance from the
source. If pa is smaller than 4, the dispersion effect should not be neglected and the linear Boussinesq
equation that includes the first-order effect of the phased dispersion should be used. The Coriolis effects
are also required. In placed of the Cartesian coordinates, the latitude-longitude coordinate system is
used.
-7-
(x/t). Select the spatial grids and time steps so as to make the coefficients of the third terms in both
equations the same, and then the linear long wave difference equation gives the same result as the
physically correct linear Boussinesq equation.
(6)
where is the wave number and f is the Coriolis coefficient. For a huge tsunami such as the 1960
Chilean tsunami, the Pacific Ocean behaves like a small pond. Average water depth of the Pacific
Ocean 4.2 km, gives the tsunami a propagation velocity faster than 730 km/hr. The tsunami traveled
17,000 km from the source off Chilean coast to Japan within 23 hours. It started toward Japan with the
crest at its front but arrived at Japan with a big ebb. The first crest became unrecognizably small and the
following trough began to grow near the Hawaiian Islands. This change was the result of the dispersion
due to the Coriolis Effect.
In case of the 1960 Chilean tsunami, 40% of the incident tsunami was lost due to
wave scattering during its travel from the coast of Chile to Japan. Mofjeld et al. (2001) analyzed the
scattering capability of the topography in the Pacific Ocean, and found a narrow band of strong scattering
running across the ocean from the northwest (Emperor Seamount Chain) to the southeast (Easter Island
Fracture Zone).
Based upon their results, they recommend that numerical models of trans-Pacific
tsunamis must resolve the effects of the small-scale topography in order to accurately simulate their wave
patterns and amplitudes.
(2) Transmission by Submarine Ridge
A submarine ridge acts as a good wave guide. The shallower the water depth is, the slower is the
wave propagation. Waves change their propagation direction toward the shallower ridge crest.
This
refraction causes concentration and effective transportation of tsunami energy along an ocean ridge. The
energy of the 1996 Irian Jaya tsunami was transported to Japan although Japan is not located on the major
direction of initial tsunami energy radiation. A numerical simulation clarified that the South-Honshu
ridge acted as an effective wave guide (Koshimura et al., 1999).
(3) Edge Waves on the Continental Shelf
Tsunamis behave as edge waves on the continental shelf. When a far-field tsunami is incident
almost parallel to the shoreline, multiple reflected waves are excited and are trapped on the slope. The
-8-
interference between these reflected waves and incoming incident waves could be a cause of unexpected
tsunami amplification on the shelf (Koshimura, 2002).
extension, the tsunami front enters the slope with locally different incident angle. The first wave at a
site is the component that propagates relatively deep area, and then other components of high energy
arrive later after a slow propagation on the slope along the shore.
H ~ h-1/4B-1/2
(7)
(8)
where l is the length of the bay and T is the wave period of the tsunami.
The water pressure is still assumed to be hydrostatic. The non-linear effect in the
phase velocity makes the higher rear part to go forward faster, then tsunami profile becomes step-wise,
and the tsunami front steepens. This is a bore.
When the steep bore front continues breaking, it is the breaking bore and is solved with the
shallow-water theory.
When the effect of the local water surface curvature prevents the breaking, a train of short-period
waves appears and develops at the front. This is the soliton fission that was clearly recorded on videos
(NHK, 1983).
Tsunamis in river often take this type of bore. This bore is called as a wavy bore or a
cnoidal bore, according to cn(x, k) of the Jacobian elliptic function that is a periodic solution of the
non-linear dispersive long wave equation.
wave becomes a solitary wave. The water pressure is modified by the centrifugal acceleration from the
hydrostatic distribution. For a tsunami initial profile that has high frequency components, the dispersion
terms should be taken into consideration, even if the source area is close to land.
-9-
An edge bore
propagates sometimes following the ordinary refraction law and sometimes neglecting the topography.
A small difference in the side boundary condition introduces a big difference in wave profile, thus
suggesting also a big difference in wave force.
different basic parameters for perturbation. The Peregrine (1967) used the section-averaged velocity as
the fundamental variable. Madsen & Sorensen (1992) selected the depth-integrated variable, i.e. the
discharge flux.
Equations by Iwase et al. (1998) are composed of the same terms as those of the
Peregrine equations but expressed in terms of the discharge flux. Other perturbations are possible, using
the bottom velocity (Mei & LeMehaute, 1966) or the surface velocity (Dingemains, 1973). Iwase et al.
(2002) carried out numerical computation using different 8 equations and compared the results with the
theoretical prediction and hydraulic experiments. The best agreement was obtained with the Iwase et al.
equations and the Madsen & Sorensen equation. The former, in other word, the Peregrine equation in
terms of the discharge flux is more convenient because it is simpler than the latter.
(9)
The use of the Iwase et als modified Peregrine equation is recommended for numerical simulation of a
near-field tsunami from its source in deep sea to the shallow water region.
electronic computer was introduced, such simple but basic problem as one-dimensional run-up on a
sloping beach needed a skilful method of the Carrier-Greenspan transform (1958) for waves of finite
amplitude.
The same problem was solved with the linear long wave theory expressed in the Lagrangian
description (Shuto, 1967). These kinds of theoretical consideration can not be applied to solve any
practical problems but only supply data necessary for examination of the numerical scheme.
In order to ensure a stable computation, the grid lengthx and the time stept should
x/t(2gh)1/2
(10)
It is not easy to solve the tsunami front that runs up and down the land with the shallow-water
theory expressed in the Eulerian description.
In the
leap-frog numerical scheme, grid points are alternatively located for velocity and water level. Assume
- 10 -
that the water level is already computed at a computation cell. Then, compare the water level with the
bottom height of the next landward cell. If the water level is higher than the latter, the water may flow
into the landward cell. Iwasaki and Mano (1979) assume that the line connecting the water level and the
bottom height gives the surface slope to the first-order approximation. Hibberd and Peregrine (1979)
proposed more accurate method that required repeated computation. Aida (1977) and Houston - Butler
(1979) used weir formula to determine the discharge into the landward dry cell. For the practical
application, the Iwasaki and Mano assumption is widely used, because of its simplicity.
When a difference equation is solved, we have to control numerical errors that depend upon the
scheme used in the computation. Under the condition that the shallow-water equations are discretized
with the leap-frog scheme, one local tsunami wavelength should be covered by more than 20 grid points.
Otherwise, the computed tsunami height experiences numerical decay (Shuto et al., 1986).
Imamura and
Goto (1988) discussed more thoroughly the possible numerical errors in relation to local wave length.
If the Iwasaki-Mano boundary condition is used, the following condition should be satisfied at the
front.
x/gT2<410-4
(11)
where is the slope inclination and T is the wave period (Goto and Shuto, 1983).
Fujima and Shigemura (2000) proposed a way to control the numerical error in relation to the local
bottom topography.
deformation and destruction of structure, the idea of 2D/3D is now used enthusiastically to develop new
numerical methods such as SPH (Smoothed Particle Hydrodynamics), DEM (Discrete Element Method),
and so on.
7.4 Aida Measures, K and
There are five sources of error in tsunami simulation.
in Section 4, there is no way to measure it.
refraction and concentration of tsunamis. An accurate bathymetry in the sea shallower than 200 m is
- 11 -
essentially important. The third is the selection of basic differential equations. If the original equations
are used without any approximation, the CPU time is too long for practical application.
An
approximation, in which some terms are neglected or simplified, does not express the real phenomena.
In the difference equations, we have to expect inevitable truncation errors. Accuracy of measured data
that are used to verify the numerical results is not always reliable.
reflect the splash that cannot be simulated.
Based upon
rich experience of simulation in Japan, if K falls between 1.2 and 0.8 andis less than 1.4, the simulation
is judged satisfactorily carried out for practical use.
(14)
where a is the number of houses washed away and completely destroyed, b is the number of houses
partially damaged, and c is the number of houses only flooded without structural damage.
Degree of
damage is judged by on-site inspection. Number of data thus obtained is of the order of several tens at
most.
He tried to find a relation between RHD and tsunami height. If numerical results are available,
- 12 -
withstands if the inundation depth is smaller than 1 m and is completely washed away if the inundation
depth is larger than 2 m.
All the reinforced concrete buildings in the past example could withstand
tsunami forces even if the inundation depth was 5 m, except one example, the Scotch Cap Lighthouse that
was completely washed away by the 1946 Aleutian tsunami of 20 m inundation depth.
Iizuka and Matsutomi (2000) expressed quantitatively damage conditions in terms of inundation depth,
current velocity and/or hydrodynamic force. A wooden house will be destroyed if the inundation depth
is over 2 m, or if current velocity is over 4.9 m/s, or if hydrodynamic force is over 27 kN/m.
Koshimura et al. (2000) obtained that the structures were significantly vulnerable when the local
inundation depth exceeds 2 or 3 m, the current velocity exceeds 2.5 m/s or hydrodynamic load on a
structure exceeds 5 kN/m.
Two types of
as
PH(z) /g = (3hc z)
(15)
For a run-up front with solitons, the lower part of the pressure distribution is modified as shown in
Fig.8 and the total pressure increases by 20 %. Including the two conditions, pressure distribution is
expressed as follows.
PH(z)/g = max(5.4 hc z, 3hc z)
(16)
Arikawa et al. (2006) carried out large-scale hydraulic experiments and showed that the equation
above was applicable for Froude number smaller than unity.
tsunami can break just in front of wall to generate larger impact force.
(17)
where CD (=1.1~2.0) is the drag coefficient and B is the breadth of building. Large range of variation in
the value of CD means that the shape of tsunami hitting the wall is important factor to generate whether
impact force or hydrostatic pressure.
- 13 -
(18)
where H is the height of breaking bore, h is the water depth, is the total water depth andis the resistance
coefficient.
The impact total force, Pi, due to breaking bore was expressed in terms of this propagation velocity.
Pi = Kgc4/g2 H
(19)
where K is non-dimensional coefficient that takes 0.51 for vertical wall and tends to 0.33 as the wall slope
becomes gentle (Fukui et al, 1962b).
Run-up and force by breaking bores were experimentally studied by Mizutani and Imamura (2000).
They found three peaks in wave pressure on structures. The first is the dynamic wave pressure (D.W.P)
caused by impact of an incident bore. The second, the sustained wave pressure (S.W.P.), appears during
the high rise of water level because of continuous incidence of the bore. The third, the impact standing
wave pressure (I.S.W.P), is a result of impulsive collision between the incident and reflected bores.
Takahashi, Fujima and Asakura (2001) succeeded the numerical simulation of this phenomenon with a
method of numerical wave flume, CADMAS-SURF (SUper Roller Flume for Computer Aided Design of
MAritime Structure) (CDIT, 2001; Fujima, 2002). Figure 9 compares the time series of pressure along
the bottom surface and Fig. 10 compares the vertical distribution of wave pressure.
of wave pressure.
distribution.
Figure 11: Pressure distribution with impact of lumber. Figure 12: Matsutomi diagram for lumber impact.
- 14 -
Hydraulic experiments (for example Matsutomi, 1993) showed the increase of force due to floating
materials.
Fig. 11 is an example of the vertical distribution of pressure when a lumber hits with the breaking
bore front. In addition to bore-induced water pressure, impact of a lumber acts locally but strongly.
Matsutomi (1999) provided a diagram (Fig.12) in terms of dimensionless impact and dimensionless
collision velocity to evaluate the impulsive force due to lumbers floated by breaking bores and surging
fronts.
In the figure, Fm is the impact, , D and L are the unit weight, diameter and length of lumber,
to be floated if the tsunami inundation depth exceeds their diameter and those in a timber basin when
tsunami force on timbers exceeds the strength of mooring wire.
The first
embankment, the water concentrates to the openings such as underpass or bridge with increasing velocity.
Then, the neighborhood of the openings is soured.
structures and hit the rear slope and rear toe that are usually not protected with solid covers. The
overflowing tsunami is an unsteady flow that is sub-critical on the crest, super-critical on the rear slope
and returns to sub-critical after a hydraulic jump. Erosion process under this complicated flow is solved
by Fujii et al. (2009). They used CADMAS-SURF for flow computation combining with an erosion law
they established through hydraulic experiments.
(2) Toe of Quay Eroded by Backwash Water Falls
When a tsunami recedes after landing, the water falling from the top of quay wall directly hit the sea
bottom nearly exposed. The toe is scoured to lead to destruction of quay walls (Shuto, 2009).
Gotoh et al. (2002) used the moving-particle semi-implicit method (MPS) to solve the nap
formation of the falling water from the quay and the erosion of sand bottom at the toe.
Their result qualitatively explained the results of scouring obtained in large-scale hydraulic
experiments of Noguchi et al. (1997). However, there is no trial to explain some of damage
examples in the past.
(3) Tsunami-Induced Current in Narrow Waterways (Shuto, 2009)
The second case is the tsunami-induced current at narrow waterways in harbors or bays.
- 15 -
Strong
currents scour the sea bottom just at the toe of structures and destroy them.
case of the gravity-type quay wall of the Konakano Fish market, Hachinohe Harbor, in Iwate Prefecture,
Japan.
The fish market was completed in August, 1959, one year before the 1960 Chilean Tsunami, near the
entrance of Hachinohe Industrial Harbor which was built by using the mouth of the Niida River. Near
the entrance of the water area 200 m wide and 2 km long, the Fish
harbor was very much influenced by the 1960 Chilean Tsunami.
maximum ebb flow velocity was estimated to be 13 m/s and the maximum flood flow velocity 8 m/s.
By this current, the Fish Market was affected and damaged.
before and after. The maximum amplitude of the 1960 Chilean Tsunami was about 6 m.
quay wall -3m deep was scored to -9 m.
during abnormally low water destroyed the basis of caissons and pushed them forward.
Five of 8 caissons, each of which was 10 m long, were overturned or subsided, as shown in Fig.13.
A person, who witnessed from the opposite side of harbor 200 m far, told that the quay wall collapsed
during an ebb tide from 06:31 a.m. to 07:03 a.m.
From the movement of floating materials and the Cameron effect, they determined
the current velocity distribution and compared with the results of their numerical simulation as in Fig. 15.
White circles were obtained from the numerical simulation for the sea bottom bathymetry before the
tsunami and black triangles are for that after the tsunami.
The computed current velocity are less than half the measured, although their computation simulated very
well a tide record in the bay.
Nagai et al. (2004) concluded the generation of edge waves along an arch-shaped coast of Hokkaido
in case of the 2003 Tokachi-Off Earthquake Tsunami, using the records obtained with super-sonic current
meters installed by NOWPHAS (Nationwide Ocean Wave Information network for Ports and HAbourS) .
Use of videos was begun with the 2004 Indian Ocean Tsunami.
- 16 -
eyewitness video record with PIV (planar particle image velocimetry) and obtained time series of flow
velocity at two locations which were within the range of 2 to 5 m/s.
The
- 17 -
Experiences in 2004 are attracting many researchers to this topic, for example,
Im OK, and do not take necessary action. Due to this normalcy bias, many people have lost their
lives.
In order to break this preconception, CG animation works well. Katada et al (2004) developed a
education.
Visit
his home
page
http://dsel.ce.gunma-u.ac.jp/, you can down load some of his results. Another use of CG technique is
the virtual realty, in which visitors can have a pseudo-experience of tsunami risk.
computer and the Mansinha-Smylie method to determine the tsunami initial profile, both appeared in
1970s, tsunami science began a big step of progress with quite a few tsunami researchers.
In 1983 when a huge tsunami hit the Japan Sea coast and gave tremendous damages, USA people
- 18 -
were awoken and number of tsunami researcher in Japan began to increase, in the field of science and
engineering.
In September, 1992, the first international tsunami survey team (ITST) was formed to study the
Nicaraguan tsunami.
Then, in December of the same year, another tsunami hit the Flores Island,
Indonesia, ITST was also organized. In July, 1993, a huge tsunami occurred in the Japan Sea. This
frequent occurrence of tsunami disaster worked to increase number of tsunami researchers in the world.
Knowing a fact that the 1993 tsunami easily overflowed the man-made structures, it was confirmed that
human action was vitally important in an emergency.
References
Aida, I. (1977): Numerical Experiments for Inundation of Tsunamis, Susaki and Usa, in the Kochi
Prefecture, Bulletin of Earthquake Research Institute, University of Tokyo, Vol.52, pp.441-460 (in
Japanese).
Aida, I. (1978): Rreliability of a Tsunami Source Model Derived from Fault Parameter, Journal of Physics
of Earth, Vol.26, pp.57-73.
Anno, K., T. Nishihata and Y. Moriya (2007): Numerical and Experimental Study on Drift Due to
Tsunami for Several Drifting Bodies, Annual Journal of Coastal Engineering, JSCE, Vol.54,
pp.866-870. (in Japanese)
Arikawa, T. et al. (2006): Large Model Test on Surge front Tsunami Force, Annual Journal of Coastal
Engineering, JSCE, Vol.53, pp.797-800.
Asakura, R. et al. (2000): An Experimental Study on Wave Force Due to Tsunamis That Overflow the
Upright Seawall, Proc. Coastal Engineering, JSCE, 47, pp.911-955 (in Japanese).
Carrier, G. F. and H. P. Greenspan (1958): Water Waves of Finite Amplitude on a Sloping Beach, Journal
of Fluid Mechanics, Vol.4, Part 1, pp.97-107.
CDIT (Coastal Development Institute of Technology) (2001): CADMAS-SURF, Research and
Development of Numerical Wave Channel, 296p (in Japanese) .
Dingemans, M. W. (1973): Water Waves Over an Uneven Bottom A Discussion of Long-Wave
Equations, Report R 729-II, Delft Hydraulic Laboratory, Delft, The Netherlands.
Fritz, H. M., J. Borrero, C. E. Synolakis and J. Yoo (2006): 2004 Indian Ocean Tsunami Flow Velocity
Measurements from Survivor Videos, Geophysical Research Letters, Vol.33, L24605,
doi:10.1029/2006GL026784, 5p.
Fujii, H., S. Hotta and N. Shuto (2000): Numerical Simulation of Damage to Soil Embankment Caused
by Overflowing Tsunamis, Journal of Disaster Research, Vol.4, No.6 (in press).
Fujii, N., M. Ohmori, M. Takao, S. Kanayama and H. Ohtani (1998): On the Deformation of the Sea
Bottom Topography Due to Tsunami, Proc. Coastal Engineering, JSCE, 45, pp.376-380 (in
- 19 -
Japanese).
Fujii, N., et al. (2007): Experimental Study on Variability in Drifting Behavior Due to Tusnmi and Its
Evaluation Method, Annual Journal of Coastal Engineering, JSCE, Vol.54, pp.241-245 (in
Japanese).
Fujima, K. and T. Shigemura (2000): Determination Grid Size for Leap-frog Finite Difference Model to
Simulate Tsunamis around a Conical Island, Coastal Engineering Journal, Vol.42, No.2,
pp.197-210.
Fujima, K., K. Masamura and C. Goto (2002): Development of the 2D/3D Hybrid Model for Tsunami
Numerical Simulation, Coastal Engineering Journal, Vol.44, No.2, pp.373-397.
Fujima, K. (2002): Review: Development of Numerical Wave Flume CADMAS-SURF ((SUper Roller
Flume for Computer Aided Design of MAritime Structure), Proceedings of Coastal and Ocean
Engineering in Korea, Vol.13, pp.1-14.
Fukui, Y., H. Siraishi, M. Nakamura and Y. Sasaki (1962a): A Study on Tsunami; (1) Propagation Velocity
of Bore, Proceedings of Coastal Engineering in Japan, JSCE, Vol.9, pp.44-49 (in Japanese).
Fukui, Y., H. Siraishi, M. Nakamura and Y. Sasaki (1962b): A Study on Tsunami; (2) Effect of Bore on
Coastal Dikes, Proceedings of Coastal Engineering in Japan, JSCE, Vol.9, pp.50-54. (in Japanese)
Fukuyama, E. and K. Irikura (1986): Rupture Process of the 1983 Japan Sea (Akita-Oki) Earthquake
Using a Waveform Inversion Method, Bulletin of the Seismological Society of America, Vol.76,
No.6, pp.1623-1640.
Garces, M. et al. (2005): Deep Infrasound Radiated by the Sumatra Earthquake and Tsunami, EOS,
Transactions, American Geophysical Union, Vol.86, No.36, pp.317-320.
Goto, C (1983): Numerical Simulation of Timbers Transported by Tsunamis, Proceedings of Coastal
Engineering in Japan, JSCE, Vol.30, pp.594-597 (in Japanese).
Goto, C. and N. Shuto (1983): Numerical Simulation of Tsunami Propagations and Run-up, in K. Iida and
T. Iwasaki (eds), Tsunamis: Their Science and Engineering, Terra Science Publication Co.,
Tokyo/Reidel, Dordrecht, pp.439-451.
Gotoh, H., T. Sakai, M. Hayashi, K. Oda and H. Ikari (2002): Gridless Analysis of Toe Scouring of
Seawall Due to Tsunami Return Flow, Proc. Coastal Engineering, JSCE, 49, pp.46-50 (in Japanese).
Harada, K. and F. Imamura (2003): Utilization of Forest Control to Mitigate the Tsunami Damage and Its
Evaluation, Proc. Coastal Engineering, JSCE, Vol.50, pp.341-345 (in Japanese).
Hatori, T. (1984): On the Damage to Houses Due to Tsunamis, Bulletin of Earthquake Research Institute,
Vol.59, pp.433-439 (in Japanese).
Hibberd, S. and D.H. Peregrine (1979): Surf and Run-up on a Beach: A Uniform Bore, Journal of Fluid
Mechanics, Vol95, pp.323-345.
Houston, J. R. and H. L. Butler (1979): A numerical model for tsunami inundation, WES Technical
Report HL-79-2.
Ikeya, T. et al. (2006): Experimental and Analytical Study of Impulsive Forces by a Drifter Due to
Tsunami, Annual Journal of Coastal Engineering, JSCE, Vol.53, pp.276-280 (in Japanese).
Iizuka, H. and H. Matsutimi (2000): Estimation of Damage Caused by Tsunami Flow, Proceedings of
Coastal Engineering, JSCE, Vol.47, pp.381-385 (in Japanese).
- 20 -
Imamura, F. and C. Goto (1988): Truncation Error in Numerical Tsunami Simulation by the Finite
Difference Method, Coastal Engineering Journal, Vol.31, No.2, pp.245-263.
Imamura, F., N. Shuto and C. Goto (1990): Study on Numerical Simulation of The Transoceanic
Propagation of Tsunami, Part 2: Characteristics of Tsunami Propagating Over the Pacific Ocean,
Zisin, Journal of the Seismological Society of Japan, Vol.43, pp.389-402 (in Japanese).
Iwasaki, S. (1992): Tsunami Forecasting Technique Using Underwater Sounds and Air pressure waves,
Tsunami Engineering Technical Report, DCRD Tohoku University, No.9, pp.65-83. (in Japanese)
Iwasaki, T. and A. Mano (1979): Two-dimensional Numerical Simulation of Tsunami Run-ups in the
Eulerian Description, Proceedings of 26th Conference on Coastal Engineering, JSCE, pp.70-74 (in
Japanese).
Iwase, H., T. Mikami and C. Goto (1998): Practical Tsunami Numerical Simulation Model by Use of
Non-linear Dispersive Long Wave Theory, Journal of Hydraulic, Coastal and Environmental
Engineering, JSCE, No.600/II-44, pp.119-124 (in Japanese).
Iwase, H., T. Mikami, C. Goto and K. Fujima (2002): A Comparative Study of Nonlinear Dispersive Long
Wave Equations for Numerical Simulation of Tsunami, Journal of Hydraulic, Coastal and
Environmental Engineering, JSCE, No.705/II-59, pp. 101-114 (in Japanese).
Izumiya, T. and H. Nagaoka (1994): Generation of Acoustic Gravity Waves by Tsunamis and Possibility
of Tsunami Forecasting, Proceedings of Coastal Engineering, JSCE, Vol.41, pp. 241-245 (in
Japanese).
Kajiura, K. (1970): Tsunami Source, Energy and the Directivity of Wave Radiation, Bulletin ERI, Vol.48,
pp. 835-869.
Katada, K., N. Kuwasawa and H. Yeh (2004): Development of Tsunami Comprehensive Scenario
Simulator for Disaster Education and Risk Management, National Geophysical Research Institute,
Hazards2004, 75p.
Koike, N. et al. (2005): Tsunami Height Survey of the 2004 Off the Kii Peninsula Earthquake, Annual
Journal of Coastal Engineering, JSCE, Vol.52, pp. 1336-1340 (in Japanese).
Koshimura, S. (2002): Multiple Reflection of Tsunamis Incident on a Continental Slope, Journal of
Hydraulic, Coastal and Environmental Engineering, JSCE, No.705/II-59, pp. 151-160 (in
Japanese).
Koshimura, S., F. Imamura and N. Shuto (1999): Propagation of Obliquely Incident Tsunamis on a Slope,
Part II Characteristics of On-ridge Tsunamis, Coastal Engineering Journal, Vol.41, No.2, pp.
165-182.
Koshimura, S., T. Oie, H. Yanagisawa and F. Imamura (2009): Developing Fragility Functions for
Tsunami Damage Estimation Using Numerical Model and Post-tsunami Data from Banda Ache,
Indonesia, Coastal Engineering Journal, Vol.51, No. 243-273.
Kumagai, K., K. Oda and N. Fujii (2007): Simulation Model for Drift Behavior of Container Due to
Tsunami and Collision Force, Annual Journal of Coastal Engineering, JSCE, Vol.54, pp. 236-240
(in Japanese).
Lander, J. F. (1996): Tsunamis Affecting Alaska 1737-1996, NGDC Key to Geophysical Research,
Documentation No.31, 195 p.
- 21 -
Madsen, P. A. and O. R. Sorensen (1992): A New Form of the Boussinesq Equations with Improved
Linear Dispersion Characteristics, Part 2; A Slowly-Varying Bathymetry, Coastal Engineering,
Vol.18, pp.183-204.
Manshinha, L. and D. E. Smylie (1971): The Displacement Fields of Inclined Faults, Bulletin of
Seismological Society of America, Vol.61, pp.1433-1440.
Matsutomi, H. (1993): Laboratory Study on Maximum Impulsive Force of Timbers Drifted by Bore-like
Tsunamis, Journal of Hydraulic, Coastal and Environmental Engineering, JSCE, No.467/II-23,
pp.19-28 (in Japanese).
Matsutomi, H. (1999): A Practical Formula for Estimating Impulsive Force Due to Driftwoods and
Variation Features of the Impulsive Force, Journal of Hydraulic, Coastal and Environmental
Engineering, JSCE, No.621/II-47, pp. 111-127 (in Japanese).
Mei, C. C. and B. LeMehaute (1966): Note on Equations of Long Waves Over an Uneven Bottom,
Journal of Geophysical Research, Vol. 71, pp. 393-400.
Mizutani, M. and F. Imamura (2000): Experiments on Bore Wave Pressure on Structures, Proceeding of
Coastal Engineering, Vol. 47, pp. 946-950 (in Japanese).
Mofjeld, H. O., V. V. Titov, F. I. Gonzalez, and J. C. Newman (2001): Tsunami Scattering Provinces in the
Pacific Ocean, Geophysical Research Letters, Vol. 28, No. 2, pp. 335-337.
Nagai, N., H. Ogawa, K. Nukada and M. Kudaka (2004): Characteristics of the Observed 2003
Tokachi-Off Earthquake Tsunami Profile, Annual Journal of Coastal Engineering, JSCE, Vol. 51, pp.
276-280 (in Japanese).
NHK (1983): A Huge Tsunami Witnessed Records of the Nihon-Kai Chubu Earthquake-, Video or DVD.
Noguchi, K., S. Sato and S. Tanaka (1997): Large-scale Experiments on Tsunami Overtopping and Bed
Scour around Coastal Revetment, Proc. Coastal Engineering, JSCE, Vol. 44, pp. 296-300 (in
Japanese).
Okada, Y. (1985): Surface Deformation Due to Shear and Tensile Faults in a Half-space, Bulletin of the
Seismological Society of America, Vol. 75, pp. 1135-1154.
Okal, E. A., J. Talandier and D. Reymond (2007): Quantification of Hydrophone Records of the 2004
Sumatra Tsunami, Pure and applied Geophysics, Vol. 164, pp. 309-323.
Omachi, T., H. Tukiyama and H. Matsumoto (1999): Evaluation of Tsunami Simulation Considering
Dynamic Crustal Displacement Accompanying a Fault Movement, Proceedings of Coastal
Engineering, JSCE, Vol. 46, pp. 321-325 (in Japanese).
Peregrine, D. H. (1967): Long Waves on a Beach, Journal of Fluid Mechanics, Vol. 71, Part 4, pp.
815-827.
Plafker, G. (1965): Tectonic Deformation Associated with the 1964 Alaska Earthquake, Science, Vol. 148,
pp. 1675-1687.
Satake, K., M. Okada and Ku. Abe (1988): Tide Gauge Response to Tsunamis: Measurements at 40 Tide
Gauge Stations in Japan, Journal of Marine Research, Vol. 46, pp. 557-571.
Satake, K. (1989): Inversion of Tsunami Waveforms for the Estimation of Heterogeneous Fault Motion of
Large Submarine Earthquakes: 1968 Tokachi-oki and 1983 Japan Sea earthquakes, Journal of
Geophysical Research, Vol. 98, pp. 4553-4565.
- 22 -
Shuto, N. (1967): Run-up of Long Waves on a Sloping Beach, Coastal Engineering in Japan, JSCE, Vol.
10, pp. 23-38.
Shuto, N. (1987): The Effectiveness and Limit of Tsunami Control Forests, Coastal Engineering in Japan,
Vol.30, No. 1, pp. 143-153.
Shuto, N. (1993): Tsunami Intensity and Disasters, Advances in Natural and Technological Hazards
Research, Vol.1, pp197-216.
Shuto, N. (2009): Damage to Coastal Structures by Tsunami-Induced Currents in the Past, Journal of
Disaster Research, Vol. 4, No. 6 (in press).
Simkin, T. and R, S, Fiske, (1983): Krakatau 1883, Eruption and its Effects, Smithsonian Institution Press,
464p.
Takahashi, R. (1934): A Model Experiment on the Mechanism of Seismic Sea Wave Generation, Part 1,
Bulletin ERI, Supplementary Vol.1, Tokyo University, pp. 152-181.
Takahashi, T., F. Imamura and N. Shuto (1991): A study on Tsunami-induced Current and Sea Bottom
Deformation, Proc. Coastal Engineering, JSCE, Vol. 38, pp. 161-165 (in Japanese).
Takahashi, T., F. Imamura and N. Shuto (1992): Tsunami Simulation with Movable Sea Bottom, Proc.
Coastal Engineering, JSCE, Vol. 39, pp. 231-235 (in Japanese).
Takahashi, T., F. Imamura, and N. Shuto (1993): Examination of Applicability of Movable Bed Model by
Tsunamis, Proc. Coastal Engineering, JSCE, Vol. 40, pp. 171-175 (in Japanese).
Takahashi, T., T. Takahashi, N. Shuto, F. Imamura and M. Ortiz (1995): Source Models for the 1993
Hokkaido Nansei-Oki Earthquake Tsunami, Pure and Applied Geophysics, Vol. 144, No. 3/4, pp.
747-767.
Takahashi, T., K. Fujima and R. Asakura (2001): An Application of Numerical Wave Flume to
Transformation of Bore, Proceedings of Civil Engineering in the Ocean, JSCE, Vol. 17, pp.
281-286 (in Japanese).
Tanimoto, K. (2007): Numerical Simulation of Tsunami Prevention by Coastal Forest with Several
Species of Tropical Tree, Annual Journal of Coastal Engineering, JSCE, Vol. 54, pp. 1381-1385 (in
Japanese).
Tomita, T., T. Kakinuma and A. Shimada (2004): Numerical Simulation of Tsunamis around and Behind
Breakwater using a 3D Model, Annual Journal of Coastal Engineering, JSCE, Vol. 51, pp. 296-300
(in Japanese).
Tanaka, N., T. Takemura, Y. Sasaki and M.I.M. Mowjood (2006): Breaking Condition of the
Representative Coastal Tree Species in Sri Lanka and the Effect of Vegetation on the Delay in
Tsunami Arrival Time, Annual Journal of Coastal Engineering, JSCE, Vol. 53, pp. 281-285 (in
Japanese).
Thucydides, (for example): History of The Peloponnesian War, Penguin Classics, p.247.
Tsuji, Y. (1977): A Study on the Scattering Wave Induced by Tsunami Passing Over a Sea Mount or Rise,
Ocean Science, Vol. 9, pp. 117-125 (in Japanese).
Uda, T. et al. (1988): Two-dimensional Deformation of Nonlinear Long Waves on a Beach, Report No.
2627, Public Works Research Institute, Ministry of Construction (in Japanese).
Yoneyama, N., M. Matsuyama and H. Tanaka (2002): Numerical Analysis for Locally High Runup of
- 23 -
1993 Hokkaido Nansei-Oki Seismic Tsunami, Journal of Hydraulic, Coastal and Environmental
Engineering, JSCE, No. 705/II-59, pp. 139-150 (in Japanese).
- 24 -
Samantha HETTIARACHCHI
Department of Civil Engineering, University of Moratuwa, Moratuwa, Sri Lanka, sslh@civil.mrt.ac.lk
Saman SAMARAWICKRAMA
Department of Civil Engineering, University of Moratuwa, Moratuwa, Sri Lanka, sslh@civil.mrt.ac.lk
Nimal WIJERATNE
Faculty of Engineering, University of Ruhuna, Galle, Sri Lanka, nimal@ce.ruhuna.ac.lk
25
Episodic hazards include severe storms, earthquakes, tsunamis and oil spills all of which have limited
predictability and may result in major disasters. The communities should be made aware of these hazards,
their vulnerability and risks and should be educated on the importance of preparedness in responding to
potential disasters which usually require long term post event recovery efforts. Chronic conditions include
shoreline erosion, flooding, sedimentation, sea level rise and coastal environmental and resource degradation.
These condition which may result or increase from disasters arising from episodic hazards, relate to processes
which could be measured and monitored. They require long term planning measures and restoration efforts to
reduce risks.
Risk is usually expressed by the notation Risk = Hazard x Vulnerability. In this expression hazard includes
exposure. Risk represents the probability of harmful consequences or expected losses (in terms of deaths,
injuries, property, livelihoods, economic activity disrupted or environment affected) arising from interactions
between natural or human hazards and vulnerable conditions. Vulnerability can be broadly classified into
several components including, physical, human, socio- economic, functional and environmental vulnerability.
Hence vulnerability is dependent on several factors belonging to the said components, including population
density, building density and status, distance from the shoreline, elevation and evacuation time. Prior to the
Indian Ocean Tsunami (IOT), Sri Lanka had not adopted a planned approach towards preparedness in relation
to disasters, an aspect which is considered vital in saving lives. Hence the notation, Risk = Hazard x
Vulnerability x Deficiencies in Preparedness seems more appropriate. The additional term represents certain
measures and tasks the absence of which could reduce the loss of human lives and property in the specific
interval of time during which the event is taking place. This term is also commonly identified as the inverse of
Capacity. Hence there are many literature in which the notation, Risk = (Hazard x Vulnerability)/ Capacity is
used.
For detailed assessment of risk it is necessary to quantify the three main components of risk. However
quantifying all three terms is a challenging task in view of the wide range of diverse parameters associated
with the respective components of risk. In particular, there are no standard techniques for such assessment and
a number of methods have been used by researchers. These include qualitative methods, quantification based
on qualitative description and quantification based on detailed analysis of respective parameters. It is
therefore difficult to develop comprehensive risk assessment studies which capture the significance off all the
three components. However it is important that risk assessment studies are conducted within the framework
defined by the above formulae. This aspect has to be kept in mind when reviewing the outputs from studies on
risk assessment. The assessment of risk is an important element of coastal community resilience.
Communities must be made aware of the hazards, their exposure, vulnerability and be encouraged to address
issues on awareness, early warning, emergency planning, response and recovery and hazard mitigation.
Enhanced coastal community resilience enables populations at risk to live with risk with a greater degree of
confidence.
26
Incidentally the first recorded Tsunami to have affected Sri Lanka was on 27th August 1883, arising from the
eruption of the volcanic island of Krakatoa. On this occasion too, unusually high water levels followed by the
receding beach were observed in Galle around 1.30 pm. The water level fluctuations were not severe and
there was no inundation. The said time corresponds well with the tsunami travel time for tsunami waves
which would have been generated by the largest eruption of the volcano earlier in the morning. However, on
26th December 2004, Galle received the severe impact of Tsunami waves, their magnitude having increased
due to near-shore transformations. Galle is one of the many coastal cities around the world, which remains
heavily exposed to the tsunami hazard. Poorly constructed buildings and inadequate drainage contributes to
the vulnerability.
The tsunami waves, which reached the offshore waters of Galle were primarily diffracted waves,
diffraction taking place around the southern coast of Sri Lanka. In the context of Tsunamis the location of
Galle is extremely vulnerable. It lies besides a wide bay and a natural headland on which is located the
historic Galle Fort with very reflective vertical non-porous walls on all sides. Furthermore, there exists the
Dutch canal west of the headland, conveying water through the city centre. The waves in the vicinity of Galle,
which were increasing in height due to reduced water depths were further subjected to a series of near-shore
processes which increased their heights even further. The canal was a facilitator in conveying the massive
wave and associated flow towards the city centre.
In the vicinity of the headland on which the Galle Fort is located, the wave energy concentrates due to
refraction. These waves then reflected from the vertical solid walls of the Fort and moved around the
headland. Such walls reflect almost all the incident wave energy with very high wave heights at the wall itself.
There is hardly any dissipation. On the west of the headland the waves moved ferociously into the Dutch
Canal. On the east it moved along the bay. The wide bay in Galle further contributed to the increase in wave
height by modifying the shoaling process via reduced wave crest width to accommodate the bay shape. The
combined effect of this phenomenon and the wave coming around the eastern side of the Fort caused a
massive wave of destruction along the Marine Drive (see Fig. 3). It is certainly not surprising that many
survivors referred to a moving large black wall similar to that of the Galle Fort.
The city of Galle is therefore not only exposed to tsunami waves which will diffract around the southern
part of Sri Lanka it is even more exposed in the context of near-shore coastal processes which will further
increase wave heights. This aspect is identified as increased exposure within the risk assessment framework.
Figs. 1 and 2 give the testified tsunami wave heights and arrival times around Sri Lanka. Project location
Galle is indicated in Fig. 1.
Inundation height
27
34
9:20
9:00
5
58
<1
610
8:45
515
12
10:10
23
11:05
712
45
11
410
49 79
11:30
79
10:00
511
9:50
9:20
9:40
in meters.
(highest wave).
28
Area under the study was divided into 250m x250m grids and people living within the respective areas were
interviewed for all grids. The collected data were used to identify the
Inundated area
29
inundation modeling. In the ANUGA model the study area is represented by a mesh of triangular cells having
the flexibility to change the resolution of the mesh according to the area of importance. A major capability of
the model is that it can simulate the process of wetting and drying as water enters and leaves an area and
therefore suitable for simulating water flow onto a beach or dry land and around structures such as buildings.
High resolution near shore bathymetric data obtained for new Galle Port Development (2007) and high
resolution Topographic Data obtained after the 2004 Tsunami were used for study. (LIDA Surveys, 2005).
Broad scale deep water propagation Modeling was carried out for a number of source scenarios selected
from the Sunda/Java Trench (Table 1). Fault length of 500 km, a width of 150 km, Dip angle of 80, a Slip
angle of 1100 and a displacement of 40 m was used for the study.
Table 1: Source details and the maximum and minimum wave amplitudes from the propagation modeling
Longitude
Latitude
Strike Angle
Max. Amplitude
Min.
(m)
Amplitude (m)
Scenario 1
92.00' E
8.52' N
350'
2.015
-1.501
Scenario 2
94.26' E
3.09' N
329'
3.477
-2.391
Scenario 3
97.01' E
2.07' N
329'
1.419
-1.33
Scenario 4
97.60' E
-0.60' N
329'
2.608
-2.081
Based on the results of the deep water model, inundation modeling was carried out using the ANUGA
model. Modelling results give valuable information on the coastline of Galle that could be affected by
potential tsunamis. The model results are very useful for the preparation of Hazard maps. Fig. 5 gives the
inundation modeling results for 4 scenarios.
30
(a) Scenario 1
(b) Scenario 2
(c) Scenario 3
(d) Scenario 4
1.
2.
3.
4.
5.
31
The implementation of artificial measures for protection including tsunami breakwaters, dikes
and revetments
2.
The effective use of natural coastal ecosystems including Coral Reefs, Sand Dunes and Coastal
Vegetation (Mangrove Forests)
3.
32
achieved not only by artificial methods via Coastal Engineering Design but also by harnessing the full
potential of natural coastal ecosystems. The types of interventions and typical examples for each category are
listed below.
(i)
(ii)
Protect the coastal zone by preventing the inland movement of tsunami waves.
(eg. Tsunami Dike, Sand Dunes)
(iii)
On many occasions both methods can be adopted in parallel to develop well-integrated hybrid solutions
satisfying environmental concerns.
5.4 Development of Guidelines for tsunami resistant buildings
The coast is an area of high economic activity and it is not possible to transfer all activities to areas that are
completely free from potential tsunami hazards. For some areas of the coast, safe evacuation areas may be too
far away for citizens to reach on foot thus necessitating vertical evacuation structures. Therefore there is a
need to develop Design Guidelines and Construction Manuals for tsunami resistant housing and infrastructure
for the benefit of the public and wider usage.
Given the background of discussion in Sections 5.1.2 and 5.2, two types of guidelines are required.
1) Overall Design Guidelines providing advice on location, layout, orientation, structural configuration,
geo-technical considerations and other considerations relating to good design practice.
2) Detailed Design Guidelines leading to hydraulic and structural loads, geo-technical issues and
detailed design information.
The Overall Design Guidelines could be developed from the experience gained from Damage Assessment
from different parts of the country and such assessment should be analyzed in the context of the hydraulic
regime which would have been generated by the tsunami at that location. Relevant information from other
countries that have been affected by tsunamis will also be very useful for this exercise. It is important that
Damage Assessment should cover infrastructure that was (i) Destroyed (ii) Damaged (iii) Survived (least
affected).
33
8. Concluding Remarks
The paper presented the approach adopted for risk assessment in the context of hazard, vulnerability and
capacity and provided a summary of the investigative studies carried for the tsunami risk assessment study for
the Port City of Galle. It discussed the mitigation measures with respect to coast conservation via bio-shields
and the development of a tsunami breakwater as part of strategic port development. It focused on the
development of building codes for new construction, enhancing the strength of existing buildings and their
field applications. Finally the paper discussed risk management measures in the form of community
preparedness, evacuation maps and evacuation zones and shelters.
34
References
Juan Carlos Villagran de Leon (2008): Rapid Assessment of Potential Impacts of Tsunami- Lessons from the
Port of Galle in Sri Lanka, United Nations University, Bonn, SOURCE No.9/2008.
Working Group on Risk Assessment of the Intergovernmental Coordination Group for the Establishment of
the Indian Ocean Tsunami Warning and Mitigation System (ICG/IOTWS) (2009): Guidelines on
Tsunami Risk assessment and Mitigation fro the Indian Ocean: Knowing your Tsunami Risk and What
to do about it., To be published as a UNESCO-IOC Manual and Guideline No 52 by UNESCO, Paris.
35
36
Katsuyoshi KAWAGUCHI
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
kawak@jamstec.go.jp
Eiichiro Araki
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
araki@jamstec.go.jp
Hiroyuki MATSUMOTO
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
hmatsumoto@jamstec.go.jp
Takeshi NAKAMURA
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
t_nakamura@jamstec.go.jp
Shinichiro KAMIYA
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
kamiya@jamstec.go.jp
Keisuke ARIYOSHI
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
Ariyoshi@jamstec.go.jp
Takane HORI
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
horit@jamstec.go.jp
Hide SAKAGUCHI
Institute for Research on Earth Evolution, JAMSTEC, Yokosuka, Japan, sakaguchih@jamstec.go.jp
- 37 -
Maddegedara LALITH
Institute for Research on Earth Evolution, JAMSTEC, Yokosuka, Japan, lalith@jamstec.go.jp
Toshitaka BABA
Earthquake and Tsunami Research Project for Disaster Prevention, JAMSTEC, Yokosuka, Japan,
babat@jamstec.go.jp
Abstract
Around the Nankai trough southwestern Japan, mega thrust earthquakes over M8 class such as
the Tokai, the Tonankai and the Nankai earthquake are occurring with intervals of 100-200
years.
In past two mega thrust earthquakes in 1944/1946 and 1854, first ruptures were
starting from the Tonankai seismogenic zone. Therefore, to elucidate the recurrences of the
Tonankai mega thrust earthquakes and mitigate geohazard, ocean floor network systems for the
real time monitoring of seismogenic zone are quite important. We are starting to develop the
Dense Ocean floor Network system for Earthquakes and Tsunamis (DONET) as Japanese
government funded MEXT project during 2006-2010.
Advantages of DONET system are as follows,
1) Early warning of mega thrust earthquakes and tsunamis,
2) Precise observation of crustal activities around seismogenic zones using a dense network
array with multi kinds of sensors, and
3) Data from ocean floor network system are quite important to improve recurrence cycle
simulation.
We are developing DONET system and will deploy around the Tonankai seismogenic zone.
DONET is equipped with multi kinds of sensors such as accelerometers, broad band
seismometers and precise pressure gauges etc.
There are three important concepts in DONET as follows,
1) Redundancy of system by the looped backbone cable,
2) Extendable and Replaceable system by nodes and brunch cables, and
3) Advanced technology and maintenance system by ROV / AUV applications.
The dense array data from DONET will be applied to the early warning earthquakes and
tsunamis. Furthermore, the precise data of crustal activities from DONET will improve the
recurrence cycle simulation model using data assimilations.
Furthermore, to understand the mega thrust recurrence system, expeditions by the drilling
vessel CHIKYU are carried out around the Tonankai seismogenic zone. Finally, for 4
dimensional real time monitoring of the Tonankai seismogenic zone, borehole observatories by
CHIKYU drilling will be connected to DONET system. These monitoring data will be
applied to improve the simulation model and the advanced early warning system.
Keywords: Tsunami; earthquake; geohazard; seismogenic
- 38 -
1. Introduction
In the Nankia trough, there are 3 mega thrust rupture zones such as the Tokai, Tonankai and Nankai
seismogenic zone (Fig. 1). In these rupture areas, mega thrust earthquakes over M8 are occurring with
intervals of 100-200years (Table1).
yeasr
684
887
1096/1099
1361
1498
1605
1707
1854
1944/1946
Nankai
Tonankai
Tokai
In 1854, 1944/46, actually, the initial rupture were starting from the Tonankai earthquake rupture zone
ahead of the Nankai earthquake rupture zone with intervals of 32 hours and 2 years in each event. In previous
simulation researches, the result of recurrence cycle simulation indicates the difference patterns and intervals
of mega-thrust earthquake recurrences in each cycle. And, according to results of simulations, first ruptures
are starting from the Tonankai earthquake rupture zone. These results are consisted with recent historical
earthquakes in 1854, 1944/46 around the Nankai trough.
The new research project for the evaluation of seismic linkage around the Nankai trough mega thrust
earthquakes is starting as MEXT project which is a kind of Japanese government.
- 39 -
Around the Nankai trough, especially, off Kii peninsula, this new research project including observations,
simulations and disaster mitigation researches, the advanced ocean floor network system (DONET) and
CHIKYU drilling as IODP (http://www.iodp.org/) Integrated Ocean Drilling Program are carrying out.
2. Previous Researches
We could have the detailed information of the 1944 Tonankai earthquake and1946 Nankai earthquake. The
1944 Tonankai and the 1946 Nankai earthquakes, each hypocenter was located off the Kii peninsula. So, the
imaged irregular structure such as a key structure at the segment boundary between the Tonankai and Nankai
earthquake rupture zone seems to be the controller of the Nankai Trough mega-thrust seismogenic zone
system (Fig. 1). Furthermore, the results of recent simulation study of mega-thrust earthquakes recurrence
cycles indicates that these irregular structures seem to act as a controller of recurrence cycle and pattern of
mega-thrust earthquakes in the Nankai trough. And in each simulation cycles, the first ruptures are starting
from the Tonankai earthquake rupture zone ahead of the Nankai earthquake rupture zone. These results are
consistent with the past two earthquakes in 1854, 1944/1946. (Table1)
Therefore, for real time monitoring of seismogenic zone, DONET will be deployed around the Tonankai
rupture zone.
1) Redundancy, extension and advanced maintenance system using the looped cable system, junction boxes
and the ROV/AUV etc (Fig. 3)
We are carrying out the development of ROV for the 10km cable extension and heavy weight operation.
2) Multi kinds of sensors to observe broad band range phenomena such as long period tremors, low
frequency earthquakes and strong motion of mega thrust earthquakes over M8.(Fig. 4)
3) Speedy evaluation and notification for earthquakes and tsunamis.
This function is most important for disaster reduction /mitigation. JMA is starting the early warning
system, therefore, the ocean floor network data will contribute to this early warning system for disaster
mitigation. Especially, in the tsunami early warning, ocean floor network is absolutely necessary and
important (Fig. 5 (1), Fig. 5 (2)).
4) Provide observed data such as ocean floor deformation derived from pressure gauges to improve the
simulation and modeling researches about the mega thrust earthquakes. These ocean floor deformation
data are quiet necessary for the data assimilation to improve simulation models (Fig. 6).
5) Next Ocean floor network as DONET2 is planning to deploy around the western part of the Nankai
trough shown in Fig. 7
6) DONET2 has high voltage system to extend backbone
7) Cable and to equip with many nodes/sensors more. The outline of DONET2 system is shown in Fig. 8.
8) New research project for the estimate of seismic linkage around the Nankai trough mega thrust
earthquakes is starting from FY 2008 as 5 years project (Fig. 9).
This project is entrusted by MEXT project which is a kind of Japanese government.
DONET data will be applied to this new research project.
- 41 -
Figure 5 (1): The flow of speedy evaluation and notification for earthquakes and tsunamis.
- 42 -
Figure 9: New research project for the estimation of seismic linkage around the Nankai trough-Observation
Simulation and Disaster mitigationThis project is entrusted by MEXT project which is a kind of Japanese government.DONET data will be
applied to this new research project
4. Future Plan
We will deploy the advanced ocean floor network off Kii peninsula not only the Tonankai earthquake
rupture zone but the Nankai earthquake rupture zone as a local network system. We have to apply the data
from network to understand the detailed crustal activities, to improve simulation model, and to mitigate
disaster damages.
In the second step, we would like to develop and deploy the advanced ocean floor network as a regional
system and integrate ocean and land observatory network data using advanced ocean floor observatory
technologies.
In the next step, we would like to collaborate with international network systems such as NEPTUNE,
ESONET etc. to progress geosciences and contribute the early warning system for huge earthquakes and
tsunamis (Figure10).
Finally, we would like to enhance to the importance of practical database to improve structures and
simulation such as data assimilation.
- 43 -
References
Ariyoshi, K., T. Hori, J.-P. Ampuero, Y. Kaneda, T. Matsuzawa, R. Hino and A. Hasegawa: Influence of
Interaction between Small Asperities on Various Types of Slow Earthquakes in a 3-D Simulation for a
Subduction Plate Boundary, Gondwana Research.
Hori, T. (2006): Mechanisms of Separation of Rupture Area and Variation in Time Interval and Size of Great
Earthquakes along the Nankai Trough, Southwest Japan, J. Earth Simulator, Vol. 5, pp. 8-19.
Hori, T., N. Kato, K. Hirahara, T. Baba and Y. Kaneda (2004): A Numerical Simulation of Earthquake Cycles
along the Nankai Trough, Southwest Japan: Lateral Variation in Frictional Property Due to the Slab
Geometry Controls the Nucleation Position, Earth Planet. Sci. Lett., Vol. 228, pp. 215-226.
Kaneda, Y., DONET Group, AGU2007
Kaneda, Y., DONET Group, ICDP2007
Kaneda, Y., DONET Group, IUGG2007
Kaneda, Y., DONET Group, PICES2007
Kaneda, Y., DONET Group, SubFac-SEIZE2007
Kaneda, Y., DONET Group, WSEAS2008
Kaneda, Y., Ocean Observatory Summit
Kaneda, Y. (2008): Observational Research Group for the Next Nankai Trough Mega Thrust Earthquakes,
ASC2008
Kaneda, Y. (2009): Earthquake and Tsunami Research Pproject for Disaster Prevention, EGU2009
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, JPGU2009
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, ESONET NoE
Training 2009, Guest Speech.
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, IFREMER Mtg. 2009,
Guest Speech .
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, VISO WS 2009, Guest
Speech.
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, INGV Mtg. 2009,
Guest Speech.
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, Ocean Obs 09.
Kaneda, Y. (2009): Earthquake and Tsunami Research Project for Disaster Prevention, 2nd All Regions WS
- 44 -
- 45 -
- 46 -
Kenji NAKATA
Japan Meteorological Agency, Tokyo, Japan, ken-nakata@met.kishou.go.jp
Abstract
JMA has been operating the tsunami warning service for decades. Tsunami warning system
has recently acquired improvements such as utilization of GPS buoy data, change to Two
Main Centers system. JMAs international tsunami information for the northwest Pacific
area and Indian Ocean area provided as an international contribution is also described.
Keywords: Tsunami warning; GPS buoy; two Main centers; international information;
1. Introduction
Japan is located in the circum-Pacific tectonic zone where
seismic activity is extremely high in the world, and more than
ten percent of earthquakes in the world take place in and
around Japan. That leads Japan, surrounded by seas, to one of
the most tsunami-prone countries in the world, having
suffered from a lot of serious tsunami disasters. Under such
circumstances, the Japan Meteorological Agency (JMA)
established a national system of tsunami warning service in
1952. JMA has been operating the system since then, with
continuous improvement by introducing newest technologies
of the time.
Warning
local authorities as well as for broadcasting stations. Governors of municipalities are responsible for
directing or instructing the residents to evacuate from tsunami hazardous areas.
In case of a large earthquake distant from Japan, JMA also determines the hypocenter and magnitude
using seismic data from global seismological observation network as well as domestic ones, and
exchanges information on the earthquake with PTWC and USGS. If there is a possibility of tsunami
generation, JMA conducts the domestic tsunami warning operation in the same manner and criteria as the
local tsunami procedure. If the location of the earthquake is in the northwest Pacific area on the Indian
Ocean, JMA also issues an international tsunami advisory or information.
warnings/advisories
and
updates
it
in July 2008 to use GPS buoys floating about 20 km offshore from the coasts for monitoring tsunami. (Fig.
2) This system is installed and operated by Ports and Harbours Bureau, Ministry of Land, Infrastructure,
Transport and Tourism (MLIT) and Port and Airport Research Institute (PARI). Early detection of
tsunami is expected by this equipment before tsunami arrives at the coasts. JMA uses 8 GPS buoys
around Japanese islands at present for detecting tsunami and issuing tsunami information. JMA has not
issued tsunami information including GPS buoys observation so far.
accidents. It is also expected that costs of update and maintenance will become smaller.
Main center
Osak
Regional
Tokyo
Main center
Regional
Figure 3: Updated structure of warning centers of JMA
- 49 -
- 50 -
Taro ARIKAWA
Tsunami Research Center, Port and Airport Res. Inst., Yokosuka, Japan, arikawa@pari.go.jp
Abstract
This report describes surge front tsunami force using physical model experiments. Wooden
house walls and concrete walls 6 cm and 10.0 cm thick in a flume to investigate the
land-structure destruction mechanism of tsunami inundation force broke the instant the 2.5m
tsunami hit walls.The difference of the failure mode of concrete wall due to impulsive tsunami
force was clarified. If the strength of wall is small, then the bending failure or punching shear
failure is occurred. When the strength of wall is increasing, the failure mode is shifting local
failure to whole destruction.
Keywords: Tsunami; Large scale experiments;
1. Introduction
The December 26, 2004 Indian Ocean Tsunami killing over 200,000 and damaging innumerable land
structures reminded the world again of the terrific power of such tsunamis.
Regarding tsunami force hitting land structures called surge front tsunami force (Matsutomi, 1991), Iizuka
and Matsutomi (2000) proposed a logic-based empirical formula stating that surge front force was
proportional to the square of flow velocity. Asakura et al. (2000) suggested that force has a triangular
distribution equivalent to hydrostatic load distributed over a vertical distance equal to three times the
inundation height.
Photo 1 shows damage to a house in Galle, Sri Lanka hit by a tsunami with an average inundation height
of 2.5m, further shown by the tsunami trace to have peaked at 3.8m. The house wall was made of mortar and
brick. Key tsunami parameters are unknown, so basic experiments on surge front tsunami force were
conducted.
Photo 1: Housing damage in Galle City, Sri Lanka, photographed on Apr. 21, 2005.
1
- 51 -
- 522 -
max
(1)
density, and g acceleration due to gravity. Accordingly, maximum vertical sustained pressure distribution is
the same as hydrostatic pressure distribution. They also proposed the following pressure when the inundated
tsunami undergoes soliton fission, resulting in a bore:
p z g max max5.41 z 1.35 max ,31 z 3 max
for 0 z max 3
(2)
This apparently represents maximum sustained pressure, but because pressure is force per unit area,
pressure distribution is required.
Iizuka and Matsutomi (2000) proposed force associated with the steady state flow:
FH 1 2 C D u 2 h f B h
(3)
FH is the horizontal sustained force on the structure, u tsunami inundation velocity, C D the drag
coefficient (=1.1 to 2.0), h f tsunami inundation height in front of a structure, and B h the structures width.
u is proportional to the square root of tsunami inundation height, so FH is proportional to its square.
Part of Eq. 2 appears to be maximum impulsive pressure, but this is unclear. Impulsive pressure vertical
distribution and magnitude are unknown. Eq. 3 indicates that force is proportional to inundation speed, but
the effect of velocity is not included in Eq. (1) or (2).
The size of the large hydro-geo flume is a maximum of 184m long, 3.5m wide and 12m deep. The wave
paddle has a 14m stroke with piston type wave maker and generates a tsunami wave 2.5m high. The facility
generates either positive or negative tsunami waves. Fig. 3 shows the relationship between the wave paddle
stroke and positive tsunami height. Tsunami height is defined as the wave crest elevation above the still water
level. H T is tsunami height, S stroke, and T D wave paddle motion duration. Wave paddle motion is
based on the sine function as shown in Fig. 4. Fig. 5 shows the experimental arrangement cross-section for
model tests. The 1/10 slope was in the middle of the wave flume, followed by a flat part 20m long.
3
(m)
TD=10
TD=20
TD=30
TD=40
HT
0
6
10
S (m)
12
14
3
- 53-
Positive tsunami
Negative Tsunami
Figure 4: Example of wave paddle motion (above) and tsunami profile (below)
Wave Paddle
Wave
Gauges
24.0
Slope 1/10
z
x
26.0
2.6
40.0
30.0
20.0
Unit
(m)
(m)
3.0
184.0
(2) Destruction
Photo 2 shows the post-tsunami wooden wall And Photo 3 a plan view at the instant the tsunami front
reaches the wall. Note that the wall is destroyed at the moment water hits the wall.
- 55-
G19 P6
P5
G13 G3 G15
P4
G17
G11
G5
P3
G7
P2
G20
G1
G21
G9
G2
G16 G4 G14
G18
G12
G6
G8
G10
P1
G22
Front view
Back view
D6@200
G1,2
G19,20
G3,4
A
G11,12 G5,6
G17,18
G13,14
G15,16
G21,22
A
A-A
G7,8
D6@200
G9,10
D6@200
Unit (mm)
(mm)
Bar arrangement
60
21
60
33
75
21
75
33
80
32.7
90
32.7
100
21
100
32.7
6
- 56-
2.0
Maximum
Impulsive
Bore Pressure
1.8
1.6
Maximum Sustainable
Pressure
z (m)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
0
20
40
60
P (kN/m2)
Fig. 10Tsunami pressure time histories (left: wide range, right: detailed)
7
- 57-
Photo 5Concrete wall failure for 6cm (left) and 10cm (right) thicknesses
8
- 58-
4. Concluding Remarks
Wooden house walls and concrete walls 6 cm and 10.0 cm thick in a flume to investigate the land-structure
destruction mechanism of tsunami inundation force broke the instant the 2.5m tsunami hit walls.
The difference of the failure mode of concrete wall due to impulsive tsunami force was clarified. If the
strength of wall is small, then the bending failure or punching shear failure is occurred. When the strength of
wall is increasing, the failure mode is shifting local failure to whole destruction.
References
Matsutomi, H. (1991), Distribution of impulsive pressure and impulsive force due to the collision of
bore, Proceedings of Coastal Engineering, JSCE, 38(1), 626-630. In Japanese.
Iizuka, H. and Matsutomi, H. (2000), Damage due to the Flooding Flow of Tsunami, Proceedings of
Coastal Engineering, JSCE, 47(1), 381-385. In Japanese.
Asakura, R., Iwase, K., Ikeya, T., Kaneto, T., Fujii, N. and Omori, M. (2000), An experiment study on
wave force acting on on-shore structures due to overflowing tsunamis, Proceedings of Coastal Engineering,
JSCE, 47(1), 911-915. In Japanese.
9
- 59-
- 60 -
Koji FUJIMA
Department of Civil and Environmental Engineering, National defense Academy, Yokosuka, Japan,
fujima@nda.ac.jp
Abstract
Hydraulic experiments were carried out for estimating tsunami wave force for onshore
rectangular structure. Building models were placed at several distances from a shoreline.
Wave pressure was measured at several points on the exposed structure. Because impact
and standing-wave pressures at each point reach the maximum values at different instants,
estimation of tsunami force by integrating an envelope of maximum wave-pressure
distribution tends to overestimate total force. Thus, measured force was used to formulate
an estimation equation for tsunami force. Hydrostatic formula was successful for cases of
structure near a shoreline, although it had a large scattering for cases of the structure far
from a shoreline. Hydrodynamic formula was successful for all cases, although an inertial
force was not negligible for cases of structure near a shoreline. These results showed the
necessity of advanced tsunami damage index.
Keywords: Tsunami force, design formula, damage estimation, wave pressure, drag
coefficient
1. Introduction
The 2004 Sumatra Earthquake and Indian Ocean Tsunami gave a vivid description of the menace of
major tsunamis. Most buildings in coastal areas were destroyed by the tsunami, and this wreckage became
the weapons which destroyed other buildings. Thus, it is important for tsunami-damage reduction that
buildings near a shoreline withstand tsunami. Besides, a solid structure near a shoreline can be utilized for
an evacuation building.
Many researches had been conducted to investigate tsunami force acting on structures, and many
estimation equations for tsunami force have been previously proposed. Most of them (e.g. Asakura et al.,
2000; Yeh, 2007; Simamora et al., 2007) introduced inundation depth value where there is no structure for
evaluation of external force. Yeh and Simamora et al. considered both inundation depth and velocity when
there is no structure. In addition, Simamora et al. examined using inundation depth at the front of a
building based on the assumption of hydrostatic pressure. In this paper, these are classified into two
groups. One is `equations in hydrostatic form' where only inundation depth is considered as the variable,
because an equation of this type has a similar expression to that based on the assumption of hydrostatic
- 61 -
pressure. Another is `equations in hydrodynamic form' where both inundation depth and velocity are
considered.
At present, inundation depth is widely used as an external force index for tsunami damage estimation
(Shuto, 1992). Therefore, if hydrostatic equations work well, it may support the validity of classical
tsunami damage estimation. However, we cannot sufficiently understand applicability and characteristics
of these formulas at present. In this paper, fundamental experiments were conducted to understand
characteristics of time history of wave pressure and total force. Besides, applicability of tsunami force
formulas was checked by the data of Yeom et al. (2007, 2008) in addition to the present data.
2. Experimental Setup
Hydraulic experiments were carried out in a two-dimensional wave basin with 11 m length, 7 m width,
and 1.5 m depth. This basin is equipped with a piston device for generating waves. The sea bed in the
basin was set to model a sea floor deformation from offshore, shallow water and to onshore areas. The
experimental setup is shown in Fig. 1.
Several cases of experiments were conducted by varying the scale of a building's model, distance from
shoreline, and stroke type of incident wave. There were two kinds of model used in the experiments. One
was the model of B = W = H = 10 cm where B = breadth in alongshore direction, W = width in
cross-shore direction and H = height. Another was of B = 20 cm, W = H = 10 cm. The distance from
shoreline to structure, D, was set to 20, 50, 80 and 150 cm. The wave paddle was programmed to move
backward slowly once and then move forward with stroke of the paddle set to 10, 15 and 20 cm. In all
cases, the incident wave had broken in shallow water area, and hit the vertical wall (seawall). Then, a part
of wave inundated the onshore area, and hit the vertical wall (structure model) again. The wave profile in
the offshore and shallow water areas and inundation depth in onshore area (with and without obstacle
model) was measured by wave gages. Wave velocity was measured by propeller current meter, wave
force on the model by load cell, and wave pressure by pressure gages. Inundation depth and velocity in
the onshore area were also measured with the same conditions of runup distance and wave stroke without
structure.
Characteristics of wave pressure on structures placed 20-cm onshore from the shoreline were
investigated. Only wave stroke of 15 cm was applied to avoid wave overtopping the model. Pressure
gages were mounted for several lines as shown in Fig. 2 for observing wave pressure for each element on
the exposed area of the model. Visual observation using high speed cameras (250 fps) was conducted to
examine the relation of the pressure and the wave form in front of the model.
- 62 -
45
257
55
Land
Sea
Wave paddle
695
2.5
60
1.4
B=10,20cm
W=10cm
H=10cm
1:3
0.8
181
175
383
3.75
2.2
80
3
2.5
585
B
W
2.5
370
P1
P1
P1
P2
P2
P2
P2
1.4
P3
P3
P3
P3
1.4
P4
P4
P4
P4
1.4
2.2
P5
P5
P5
P5
Line1
Line2
Line3
Line4
20.0
Unit:cm
1.8
P1
1.4
Unit:cm
There appear two peaks in the time history of the wave pressure at P5. The visual observation by high
speed camera shows that the first peak at P5 occurred approximately when the splash in front of the
structure reached the maximum height and the second peak occurred approximately when the splash
rushed in with the main flow. We consider that the first peak is the impact pressure and the second peak is
the maximum standing-wave pressure. The maximum pressure at the upper position appears at 6.2 to 6.3 s,
almost the same time as the second peak at P5. However, there is a small time-gap. The time gap exists in
not only height-direction, but also breadth-direction. The time gap of wave pressure was caused by the
complicated motion of the wave hitting the structure and the irregularity of the wave. This fact is also
supported by the visual observation in Fig. 4; the wave form in front of the structure is clearly not
uniform in breadth-direction.
500
Standing wave
Pressure
Impact Pressure
3.0
P1
P2
P3
P4
P5
Load Cell
300
2.5
2.0
1.5
200
Force (N)
Pressure (Pa)
400
1.0
100
0.5
0
0.0
5.0
5.5
6.0
6.5
7.0
7.5
8.0
Time ( s )
Figure 3: Time history of wave pressure at line 1 for B = 20 cm model (center line).
- 63 -
(a)
(b)
Figure 4: Images of splash in front of the model ((a) B = 10 cm; (b) B = 20 cm).
Asakura et al. (2000) proposed the empirical equation to estimate maximum tsunami force by
integrating the envelope of maximum standing-wave pressures. Fig. 5 shows the maximum pressures
(including impact pressure) observed in the present measurements. The envelope of maximum pressures
obtained by Asakura et al. is also drawn in the figure where is the density of water, g the gravitational
acceleration, z the measurement height from the bottom, p the pressure, and hi the inundation depth at the
point of interest when there is no obstacle. It should be noted that the subscript 'm' expresses the
maximum value in the measured time history, so that pm denotes the maximum pressure and him the
maximum inundation depth at the point of interest when there is no obstacle. This figure shows that the
results of the present experiments were similar to those of Asakura et al. regarding the maximum wave
pressure distribution. However, as described before, measured pressures do not reach maximums in all
points at the same time. In addition, the total wave force reaches its maximum between the times of
maximum impact and standing-wave pressures. Thus, integration of the envelope of maximum
standing-wave pressures possibly overestimates tsunami forces, while it cannot guarantee that the
obtained equation does not underestimate the wave force.
z
him
pm
ghim
Figure 5: Non-dimensional relationship between the maximum wave pressure (pm) and the measurement
height (z).
- 64 -
(1)
where is a coefficient. Asakura et al. integrated the envelope of maximum standing-wave pressures, and
proposed = 4.5 for estimating maximum tsunami force. Tanimoto et al. (1984) proposed the maximum
standing-wave pressure distribution for the case of a breakwater. Integrating Tanimoto's distribution
above sea level yields = 3.3. Both Asakura's and Tanimoto's equations are aimed at establishing the
safety-estimation formula for structural design. Namely, it was important for them not to underestimate
tsunami forces.
The measured maximum tsunami forces are compared with the estimated force by Asakura's equation
in Fig. 6. The experimental data by Yeom et al. (2007, 2008), Simamora et al. (2007), and the present
study are also plotted in this figure. Fm denotes the maximum value in the measured time history of total
horizontal force. The figure shows that the hydrostatic formula has very large scattering. Asakura's
equation overestimates the tsunami force twice on average; however, there are some cases in which
Asakura's equation underestimates the force.
Locations where a large scattering occurs are examined in Fig. 7. The ordinate of the figure is ,
which was computed inversely from the experimental results. This figure shows that in most cases are
in range of 1 to 3, with an average value of 1.9. However the data is scattered from 0.7 to 7 for him /D <
0.05 (for cases of structures far from a shoreline). This might be caused by a variety of phenomena in the
onshore area. From this view, the hydrostatic form is not appropriate for the estimation equation of
tsunami force in him /D < 0.05. It may suggest that the tsunami damage estimation based on only
inundation depth is inaccurate for structures far from a shoreline. An advanced tsunami damage index is
required to estimate damage of structures far from a shoreline. In addition, Asakura's equation ( = 4.5)
does not underestimate the force for him /D > 0.05, although it does provide an overestimated value.
Because the average value of for him /D > 0.05 is 1.8, Asakura's equation overestimates tsunami force
2.5 times on average. Tanimoto's equation ( = 3.3) seems more acceptable for the safety estimation for
FD =
CD
B(hi ui2 )m
2
(2)
- 65 -
100
6
5
4
4.5ghim2 [N/m]
3
2
10
6
5
4
3
2
Yeom(2008)
Yeom(2007)
Simamora(2007)
Present Study
1
6
5
67
4 5 67
10
4 5 67
100
Fm/B [N/m]
Figure 6: Comparison of measured wave force with estimated force by Asakura's equation.
Yeom(2008)
Yeom(2007)
Simamora(2007)
Present Study
Asakura eq.(=4.5)
Tanimoto eq.(=3.3)
7
6
Fm/gh im B
5
4
3
2
1
Average 1.90
0.00
0.05
0.10
him/D
0.15
- 66 -
0.20
h
CD1
B(hi ui2 )m , CD1 = 2.0 + 5.4 im
2
D
(3)
Applying Eq.(3) gave an effective approximation as shown in Fig. 9. Scattering of the data shown in
this figure is about half of that in Figure 6.
There is a possibility that the increase of drag coefficient near a shoreline is caused by an inertial force.
Thus, Morrison's formula has also been applied to estimate wave force.
u
C
FD 2 = D 2 Bhi ui2 + CM BWhi i , CD 2 = 2.0 , CM = 1.0
2
t m
(4)
where CM is mass coefficient and W is width of the model in cross-shore direction. Fig. 10 shows that CD2
= 2.0 and CM = 1.0 is appropriate on average and Fig. 11 shows that the agreement of Eq.(4) does not
depend on him /D. Thus, increase of CD1 in Eq.(3) might be caused by the inertial force.
- 67 -
Figure 10: Comparison of measured wave force with estimated force by Eq. (4).
CD 3
h
2
Bhim uim
, CD 3 = 1.3 + 6.3 im
2
D
(5)
- 68 -
Figure 13: Comparison of measured wave force with estimated force by Eq.(5).
The above examinations indicated that the tsunami damage estimation based on only inundation depth
was inaccurate for structures far from a shoreline. The estimation equations in hydrodynamic form in
Eqs.(3), (4) and (5) are successful for all cases. Thus, these parameters may be serviceable for new
tsunami damage index.
Equation (4) seems superior to the other two equations because the coefficients do not depend on
him/D. However, it is doubtful whether the time history of velocity is predicted accurately by the usual
tsunami numerical simulation. Applicability of the proposed equation should be examined including the
accuracy of prediction of inundation depth and velocity in the numerical simulation.
The upper limitations of data in Figs. 9, 10 and 13 are about twice the average values (Eqs.(3), (4) and
(5)) and the lower limitations are about half of the averages. The magnitude of these scatterings is almost
similar to that for him /D > 0.05 in Figure 7. Thus, one natural idea is that the hydrostatic formula is used
for him /D > 0.05 and the hydrodynamic form is applied for him /D < 0.05. If Eq.(3) or (5) is used for him /D
< 0.05, the increase of drag coefficient by him /D is not so important. Then, CD1 and CD3 may approximate
2.1 and 1.5, respectively, in this range. For example, it is possible to formulate the average estimation and
safety estimation of tsunami force as follows:
1.5
2.1
2
B(hi ui2 ) m or
Bhim uim
2
2
=
F
average estimation: m
2
1.8 ghim
B
2.6
4.7
2
B(hi ui2 ) m or
Bhim uim
2
safety estimation: Fm = 2
2
3.3 ghim
B
(him /D<0.05)
(6)
(him /D>0.05)
(him /D<0.05)
(7)
(him /D>0.05)
Note that the safety-estimation equations are obtained by formulating the upper limitation of data. The
coefficient in the safety-estimation equation for him /D < 0.05 was determined by the fact that the
maximum values of the drag coefficient in Figure 8 and 12 were about 4.7 and 2.6, respectively; and
Tanimoto's equation was adopted for safety estimation for him /D > 0.05.
Based on Eqs. (6) and (7), him is serviceable as tsunami damage index for him /D > 0.05. However,
- 69 -
(hiui2)m or himuim2 should be used for tsunami damage index for him /D < 0.05.
4. Concluding Remarks
The conclusions from this study can be summarized as follows:
1. The standing-wave pressure at different points becomes maximum at different moments in time
because of the complicated motion of the wave hitting the structure and the irregularity of the wave.
Moreover, the total wave force also becomes maximum at different moments. Thus, integrating the
envelope of maximum wave pressure possibly causes the overestimation of maximum tsunami
forces.
2. In hydrostatic form, Tanimoto's equation is more acceptable for safety estimation in him /D > 0.05 than
Asakura's equation. The hydrostatic form seems inappropriate to model tsunami force for him /D <
0.05. This fact suggests that the tsunami damage estimation based on only inundation depth is
inaccurate for structures far from a shoreline.
3. Hydrodynamic form was tried to reproduce the tsunami force. Three types of estimation equations
were proposed. Because an inertial force is not negligible for cases of a structure near the shoreline,
CD1 and CD3 are formulated as functions of him /D. As a result, these gave satisfactory results for all
cases.
4. New tsunami-force estimation formulas are proposed as in Eqs.(6) and (7). The applicability of
equations should be examined including the reproducibility of inundation depth and velocity by
numerical simulation.
References
Asakura, R., K. Iwase, T. Ikeya, M. Takao, T. Kaneto, N. Fujii and M. Omori (2000): An Experimental
Study on Wave Force Acting on On-shore Structures Due to Overflowing Tsunamis, Proc. of Coastal
Engineering, JSCE, Vol. 47, pp. 911-915, (in Japanese).
FEMA-CCM (2005): Coastal Construction Manual, FEMA 55 Report, Ed.3.
Shuto, N. (1992): Tsunami Intensity and Damage, Tsunami Engineering Technical Report, DCRC,
Tohoku Univ., No.9, pp.101-136 (in Japanese).
Simamora, C., Y. Shigihara and K. Fujima (2007): Experimental Study on Tsunami Forces Acting on
Structures, Annual Journal of Coastal Engineering, JSCE, Vol. 54, pp. 831-835 (in Japanese).
Tanimoto, K, H. Tsuruya and S. Nakano (1984): Examinations on Tsunami Force and Damage of
Bulkhead by 1983 Nihonkai-Chubu Earthquake Tsunami, Proc. of Coastal Engineering, JSCE, pp.
257-261 (in Japanese).
Yeh, H.(2007): Design Tsunami Forces for Onshore Structures, Journal of Disaster Research, 2(6), pp.
531-536 .
Yeom, G.-S., N. Mizutani, K. Shiraishi, A. Usami, S. Miyajima and T. Tomita (2007): Study on Behavior
of Drifting Containers Due to Tsunami and Collision Forces, Annual Journal of Coastal Engineering,
JSCE, Vol. 54, pp. 856-860 (in Japanese).
Yeom, G.-S., T. Nakamura, A. Usami and N. Mizutani (2008): Study on Estimation of Collision Force of a
Drifting Container Using Fluid-structure Interaction Analysis, Annual Journal of Coastal
Engineering, JSCE, Vol. 55, pp. 281-285 (in Japanese).
- 70 -
Takashi TOMITA
Tsunami Research Center, Port and Airport Res. Inst., Yokosuka, Japan, tomita@pari.go.jp
Daisuke TATSUMI
Tsunami Research Center, Port and Airport Res. Inst., Yokosuka, Japan, tatsumi@pari.go.jp
Kazuhiko HONDA
Nagoya Research and Engineering Office for Port and Airport, Chubu Regional Bureau, Ministry of Land,
Infrastructure, Transport and Tourism, Nagoya, Japan, honda-k852a@pa.cbr.mlit.jp
Abstract
Tsunami disaster mitigation would be initiated by imaging and recognizing possible
damages. Two methods are presented to estimate tsunami damages in this paper. One is the
numerical simulation system to estimate the detailed tsunami features which lead to realize
possible tsunami damages. In order to calculate the tsunami propagating in the open ocean,
inundating coastal areas and interacting with structures, a multi-scale and multi-models
system named STOC (Storm surge and Tsunami simulator in Oceans and Coastal areas) has
been developed. Validations of the models have been conducted through comparison with
hydraulic experimental results. The other method is the real-time tsunami estimation in the
coastal areas. To predict the tsunami profiles along coasts precisely and quickly, the
inversion method with the offshore tsunami observation data is improved by using the
location of the epicenter as a priori information. From numerical experiments conducted
around the Nankai Trough, Japan, the initial water surface elevation offshore and the
tsunami profiles along coasts can be predicted with good accuracy using the tsunami
profiles observed at 5 offshore locations for 15 minutes.
Keywords: Tsunami; numerical simulation; damage estimation; real-time estimation;
three-dimensional model; dynamic hazard mapping
1. Introduction
As shown by disasters due to the 2004 Indian Ocean Tsunami and recent other tsunamis, a tsunami
causes various types of damage to coastal areas such as inundation, destruction of houses, drift of vessels,
beach erosion and etc. To develop more effective plans and measures for disaster management including
- 71 -
business continuity after the disaster, we should predict and understand tsunami disasters as realistic as
possible. Furthermore, from storm surge disasters by the Hurricane Katrina in 2005, we have realized that
storm surge and waves strike weak points of coastal defense system and cause disasters even in a
protected city. Since we can easily image that the tsunami would cause disasters in a similar way, we
should also understand defense performance of existing and planning structures against tsunamis.
To predict and understand the tsunami propagating in the ocean we already have useful numerical
models, which are based on the long wave theory. In shallow water the wave nonlinearity is usually
considered. The wave dispersion should be significantly considered for the tsunami propagating a long
distance (Fujima et al., 2007). Application of a Boussinesq-type model to the tsunami in s coastal area has
shown that the wave dispersion is also important even in the coastal tsunami (Iwase et al., 2002).
Recently hydrodynamics of tsunami is also focused on to understand tsunami flow velocity, tsunami wave
load, interaction with structures and structural response in order to develop effective tsunami mitigation
measures. The Reynolds-Averaged Navier-Stokes equation (RANS) models, Smooth Particle
Hydrodynamics (SPH) model and Moving Particle Semi-implicit (MPS) model have been developed and
applied to estimate tsunami hydrodynamics. For example, the RANS model was applied to the tsunamis
running up on a hill surface with complicated configuration at the Monai area of the Okushiri Island
struck by the 1993 Okushiri Tsunami (Yoneyama et al., 2002).
(2006) applied their RANS models to calculate the tsunamis overflowing submerged sections of
breakwater, and obtained good results in comparison with physical model tests. Furthermore, Honda and
Tomita (2009) showed that non-hydrostatic effects appear in the tsunami obliquely overflowing a quay,
based on numerical simulations.
Precise and detailed numerical simulations are useful for understanding tsunami damages and provide
development of tsunami disaster mitigation measures with consideration of local characteristics such as
bathymetric and topographic features, arrangement of structures and buildings and social characteristics.
On the other hand, real-time simulation is also useful for secure evacuation of people and
disaster-reduction activities before tsunami arrival. The
tsunami
warning
system
by
the
Japan
Meteorological Agency (JMA) is very useful and effective to understand the tsunami striking coasts soon.
If we can estimate and understand inundation areas before tsunami arrival, it may be further useful for
disaster-reduction activities. Recently real-time estimation of tsunami have been investigated (Koike,
2002; Yasuda eta al., 2007; Tatsumi and Tomita, 2007), using the observation data of offshore tsunami
(Nagai et al, 2006)
In this paper are introduced two tsunami simulation methods to estimate precise and detailed tsunami
damages and to calculate the tsunami in coastal areas within a very short time after the earthquake
occurrence. The later model is part of a real-time tsunami inundation estimation model developed at the
present.
Simulator in Oceans and Coastal Areas) system (Tomita et al., 2006), which consists of three fluid models
named STOC-IC, STOC-ML and STOC-VF (CADMAS-SURF/3D) and a floating-bodies model named
STOC-DM. STOC-IC is a RANS model to calculate the detailed tsunami in a coastal area with
consideration of interaction between the tsunami and structures. STOC-ML is a hydrostatic model to
calculate the tsunami propagating in wide sea, and is combined with STOC-IC, as shown in Fig. 1.
STOC-IC is also connected to CADMAS-SURF to estimate impulsive wave pressure of the tsunami
acting on a structure. CADMAS-SURF is another RANS model with the VOF method to determine the
water free surface of tsunami. Arikawa and Yamano (2008) have shown that tsunami pressure including
the impulsive one is well calculated by CADMAS-SURF with a special treatment to remove numerical
noise in pressure calculation. STOC-DM is a practical model to estimate numerous tsunami-drifted bodies
such as vessels, cars and containers in actual ports and harbors (Honda et al., 2009).
Estimatetsunami
damagetoacoastal
city/town
STOCIC
Fully3D
STOCML
MultiLevelModel
hydrostaticpressure
ineachlevel
STOC-DM
Drifting Body
Model
Tsunami Source
STOCVF
Fully3D+VOF
Estimatedestructionof
structure
Estimatethetsunamis
propagatinginanocean
includinganinitialtsunamiprofile
( )
( )
( )
xu +
yv +
zw = 0
x
y
z
(1)
1 p
u
x uu +
y vu + z wu f 0 v = v
+
x
t x
y
z
u v
u
u w
+ x e 2 + y e + + z e +
x
x y
z x
y x z
v
(2)
1 p
+
x uv +
y vv +
z wv + f 0 u = v
t x
y
z
y
v u
v w
v
+ y e 2 +
+
+
+
x e
z e
x
y z
x y y
z y
- 73 -
(3)
v
+
1 p
+
g
x uw +
y vw +
z ww = v
t x
y
z
z
w v
w
w u
+
+ + z e 2
+ y e
x e
x
z
y
y
z
z
(4)
in which (x, y, z) are the Cartesian coordinates, (u, v, w) the water particle velocity components in the
directions of x, y and z, the fluid density, p the pressure, g the gravitational acceleration, e the eddy
viscosity, and fo the Coriolis coefficient. The porosity of v and transmissivity of x, y and z in the
directions of x, y and z introduced by Sakakiyama and Kajima (1992) are imposed to express
configuration of sea bottom and shape of structures smoothly. The eddy viscosity coefficient is estimated
by the following formula in the same way as Nakatsuji et al. (1992) and Fujima et al. (2002):
x j
u
e = (C s )2 i +
u j u i u j
+
xi x j xi
(5)
under the summation rule. In Eq. 5, = (xyz)1/3 and (x, y, z) the computational grid spaces in x,
y, and z directions, respectively. Cs is a constant vale equal to 0.2 in this study. Constant eddy viscosity
coefficient is also available for e. To reduce computational efforts to calculate the detailed tsunami in the
wide area, the free water surface is detected by means of the vertically integrated continuity equation in
the same way as Fujima et al. (2002).
The governing equations are solved by the finite difference method. A staggered mesh in space and
leapfrog method in time are applied. Conservation terms in the governing equations are discretized by
means of the control volume method. Diffusion terms are discretized with the second-order central
scheme, while the advection terms are expanded with a hybrid scheme in which the first-order upwind
scheme is combined with the second-order central scheme for stability. The pressure is calculated by the
method of Simplified Marker And Cell (SMAC).
2.3 STOC-ML
The governing equations of STOC-ML are almost same as those of STOC-IC. However, STOC-ML is
used the hydrostatic pressure assumption in order to reduce calculation efforts for the tsunami
propagating in open ocean.
2.4 Connection of STOC-IC and STOC-ML
STOC-IC and STOC-ML are connected each other in overlapping zones, in which the physical
quantities such as the water surface displacement, fluid velocity, wave pressure in each computational
area of STOC-IC or STOC-ML are adjusted, using the interpolation technique.
2.5 STOC-DM
STOC-DM is a practical model to calculate motion of numerous floating bodies by the tsunami. The
motion of each body is excited by drag and inertia forces depending on the fluid velocity calculated with
STOC-IC and STOC-ML, taking account of collision with other floating bodies and structures. Each body
is modeled by a rigid rectangular for easy computation. The drag and inertia coefficients to estimate
tsunami wave forces acting on the rectangular are based on the experimental values introduced by Ikeya
- 74 -
et al. (2005).
2.6 Validation of STOC
Figure 2: Outline of experimental basin (left) and submerged breakwater in the A-A section (right).
Before comparing the calculation results with the experimental results, the effects of the coefficient of
Cs in the eddy viscosity model of Eq. 5 and constant horizontal eddy viscosity coefficient of eh in
STOC-ML are investigated through a parameter study, as shown in Fig. 3. Even if the value of Cs is
changed from 0.13 to 0.25, discrepancy among the calculation results is little. The calculation results are,
therefore, not sensitive to the change of Cs in value. In the same way, there are not much differences
among the results by STOC-ML in the range of eh from 10-6 to 10-3 m2/s. However, it should be noted
that the water surface profile of STOC-ML is much different from that of STOC-IC. Based on these
comparisons, therefore, the default values of Cs and eh are set as 0.2 and 10-3 m2/s, respectively.
- 75 -
elevation above the top of weir at the upstream and at the downstream, respectively. The model scale of
the calculations is the same as the physical experiments. The discharge rates of 0.01, 0.02, 0.03 and 0.04
m2/s are set based on the experimental conditions. The horizontal grid size of whole computational
domain is gradually changed from 0.01 m around the weir to 1 m at each end of the channel. The channel
is vertically divided by grid size of 0.01 m for the computation by STOC-IC, whereas a single layer is set
from the bottom to the surface for the case of STOC-ML. The time step of marching calculation is 0.002 s,
depending on the CFL condition.
C = q h1 2gh1
0.35h1 2 gh1
q=
0.91h2 2 g (h1 h2 )
(h2 / h1 2 3)
(h2 / h1 2 / 3)
(7)
in which C is the discharge coefficient. The experimental and numerical results are compared in the
discharge coefficient, as shown in Fig. 6. The results of STOC-IC are good agreement with the
experimental results and Hom-mas formula, whereas STOC-ML provides slightly bigger values in the
cases of h2/h1 > 0.6 than the formula. Furthermore, the water surface profile above a wider weir 1 m wide
is shown in Fig. 7 to make the difference of STOC-IC from STOC-ML clearly. In the case of q=0.03 m2/s
shown as the figure, the critical water depth above the weir is 0.045 m theoretically, which is well
calculated by STOC-IC.
- 77 -
The STOC system is applied to actual bathymetry and topography. The topographic data is
constructed using the airborne laser scanning survey data with spatial resolution of 1 m approximately. In
the calculation, houses and structures are considered as rigid bodies, which reflect and diffract the
tsunami, since existence of houses in the tsunami inundation simulation is effective for reproduction of
the actual inundation area in the numerical simulation (Tomita and Honda, 2009). In the calculation, the
nesting grid system is used to calculate tsunami propagation in the open sea and inundation in a port area
simultaneously. STOC-IC is applied in Area-7, as shown in the right figure of Fig. 8, with the finest
horizontal grid of 2 m and nine layers of 1 m to 2.5 m high in the computation. In the other calculation,
STOC-ML with a single layer is applied in the same Area-7. The coarsest horizontal grid of 1458 m is set
in the open sea including the tsunami source as Area-1, and the grid size is gradually reduced to Area-7
with the nesting ratio of 1/3. STOC-ML is applied in Area-1 to 6 for both calculations.
- 78 -
(Fukuoka et al., 1998). The fluid velocity has important influence in occurrence and motion of floating
bodies by the tsunami.
ICML)
Figure 9: Maximum inundation depth (left) and difference between the calculated maximum inundation
depth by STOC-IC and STOC-ML (center).
IC ML)
Figure 10: Difference between the calculated maximum velocity by STOC-IC and STOC-ML.
Figure 11: Vessel motion excited by the tsunami 3.5 minutes (left), 5.0 minutes (center) and 6.5 minutes
(right) after the start of drift motion. The arrows indicate fluid velocity vectors around the initial water
level.
- 79 -
Fig. 11 shows motion of the vessels moored in the port calculated by STOC-DM. The vessel whose
mooring system is broken by the tsunami load acting on each vessel and the water surface elevation by
the tsunami starts to move and its motion is excited by the drag and inertia forces depending on fluid
velocity.
(8)
~1,1 L ~1, N
1
a1
= M , a = M , H = M O M
~
~
a
M
N
M ,1 L M , N
(9)
in which j is the measured water surface elevation at a certain point A at the time step j (j = 1 ~ M), ai is
the initial displacement of the segment i (i = 1 ~ N), and ~j,i is the water surface elevation at the point A
at the time step j generated by 1 m uplift of the segment i. The initial displacement of segments (the
vector a) to minimize the square residual is given by the solution of the following simultaneous linear
equations known as normal equations:
(10)
H T Ha = H T
The advantage of the inversion method is short computation time because all have to be done is just to
solve the simultaneous linear equations (Eq. 9) and the superposition of unit tsunamis. On the other hand,
the inversion method cannot be applied to the propagation in shallow water and runup because
nonlinearity effect cannot be ignored in shallow water and on the land.
(2) Improvement of the inversion method by the location of the epicenter
The simultaneous linear equations (Eq. 9) are often ill-posed systems, so Koike (2002) utilizes a priori
information that the initial water surface elevation is smooth in spatial direction. Smoothness of the initial
- 80 -
water surface elevation is represented by the spatial differentiation of the initial displacement of segments,
and this spatial differentiation needs to be minimized along with the square residual.
To shorten the length of observation time and improve the accuracy of prediction, the present study
utilizes other a priori information that the tsunami source is located near the epicenter. The location of the
epicenter can be determined in several minutes after the occurrence of an earthquake by the analysis of
seismic waves, so the utilization of the location of the epicenter is practical method.
The initial displacement of segments (the vector a) to minimize the distance between the epicenter and
the tsunami source together with the square residual and the spatial differentiation of the initial water
surface elevation is given by the solution of the following equation:
+ 12
Da
+ 22
Fa
)=0
L
4 1
0.0
4 1 L
D=
, F =
0.1
0.2
4
1
(11)
in which the term Da represents the spatial differentiation of the initial displacement of segments, and the
term Fa represents the distance between the epicenter and the tsunami source. Matrix F is a diagonal
matrix, and the diagonal elements correspond to the distance from the epicenter. 1 and 2 are the
weighting coefficients for a priori information. The sum of the weighting coefficients for a priori
information is assumed to be equal to the weighting coefficient for the observed data (the square residual),
so 1 and 2 are set to 0.5 respectively.
The following simultaneous linear equations are derived from Eq. 11, and the solution of Eq. 12 gives
the initial displacement of segments.
(H
(12)
H + 12 DT D + 22 F T F a = H T
- 81 -
34
23
19
18
21 22
20
16
3
15
25
13
8
11
9
32
28
35
38
37
36
33
26
39
40
41
29 31
10
17
27
12
14
24
30
A
2
1
Figure 12: Calculation domain. The area surrounded by a dashed line is the assumed tsunami source area.
Filled circles (A~E) indicate GPS Buoy, and white triangles (1~41) indicate the sample points for the
prediction respectively.
Table 1: Four historical earthquakes.
Earthquake
Year
Magnitude
Hoei
1707
8.4
33.2 N, 135.9 E
Showa Tonankai
1944
7.9
33.80 N, 136.62 E
Showa Nankai
1946
8.0
33.03 N, 135.62 E
Tokaido-Oki
2004
7.4
33.2 N, 137.1 E
Table 2: Comparison between the inversion method with and without earthquake information.
Earthquake
Evaluation indicator
Without earthquake
info.
RMSE (m)
0.53 (8 %)
8.60 (129 %)
Condition number
69
1759
Dirichlet spread f.
804
2775
Showa
RMSE (m)
0.12 (12 %)
0.17 (18 %)
Tonankai
Condition number
82
1759
In 1944
Dirichlet spread f.
810
2775
Showa
RMSE (m)
0.27 (11 %)
1.89 (78 %)
Nankai
Condition number
70
1759
In 1946
Dirichlet spread f.
803
2775
RMSE (m)
0.06 (8 %)
0.08 (10 %)
Condition number
98
1759
Dirichlet spread f.
819
2775
Hoei
In 1707
Tokaido-Oki
In 2004
As an example, the results for the Showa Tonankai Earthquake are explained in detail. Fig. 13 shows
the estimation results for the initial water surface elevation. Although the shape of the tsunami source is
not necessarily estimated with good accuracy, the location and the maximum water surface elevation of
the tsunami source is estimated precisely. The tsunami arrival time and the first tsunami height at 41
sample points along coasts are shown in Fig. 13. The tsunami arrival time is defined as the time when the
water surface elevation change exceeds 1 cm. The first tsunami is defined as the tsunami whose tsunami
height is over 5 cm. The tsunami arrival time is predicted precisely at almost all the sample points. The
first tsunami height is also predicted with good accuracy except for at the sample points No. 2 ~ 4 and No.
34 ~ 40.
Fig. 15 shows the prediction results for the tsunami profiles along coasts. As mentioned in Fig. 14, the
tsunami arrival time and the first tsunami height are predicted with good accuracy especially at the
sample points No. 9, No. 29, and No. 32. The length of observation time is 15 minutes after the
occurrence of the earthquake, and the calculation time for the prediction is only a couple of minutes. Thus,
the tsunami prediction information can be disseminated to the residents before the peak of the first
tsunami arrives.
-0.5
0.0
0.5
1.0 (m)
0.2
0.2
0.2
Figure 13: The true (left) and the estimated (right) initial water surface elevation for the Showa Tonankai
Earthquake. Contour lines are plotted with the interval of 0.2 m.
- 83 -
Figure 14: The first tsunami height and the tsunami arrival time for the observed and the predicted
tsunami profiles along coasts for the Showa Tonankai Earthquake.
0.4
0.2
0.5
0
-0.5
-0.2
No. 9
-0.4
No. 29
-1
0.5
-2
-0.5
No. 32
-4
0.5
No. 34
-1
1
0.5
0
-0.5
-0.5
No. 38
0
30
60
90
120
150
180
-1
GPS Buoy D
0
30
60
90
120
150
180
Figure 15: The observed (solid line) and the predicted (dot line) tsunami profiles at 5 sample points and
GPS Buoy. Their locations are shown in Fig. 12.
(4) Parametric studies
To investigate how the parameters such as the length of observation time and the number of offshore
observation points affect the accuracy of prediction, parametric studies are conducted.
Length of Observation Time
The length of observation time is varied from 5 minutes to 60 minutes after the occurrence of
earthquakes. The ratio of RMSE to the maximum value of the true initial water surface elevation is
plotted against the length of observation time in Fig. 16. Long observation time is confirmed to reduce
RMSE and improve the accuracy of prediction. However, RMSE for the Hoei Earthquake seems not to be
reduced by long observation time. It is because the observed data is dominant for the solution of the
inversion method when observation time becomes long. A priori information cannot be utilized
sufficiently because the weighting coefficients for a priori information (1 and 2 in Eq. 12) are fixed at
0.5 and do not change according to the length of observation time. As mentioned in Table 2, the
- 84 -
utilization of a priori information is important especially for estimating the vast tsunami source areas like
Hoei
Tonankai
Nankai
Tokaido-Oki
0.15
0.13
0.11
0.09
0.07
0.05
0.03
0
10
20
30
40
50
60
Figure 16: Ratio of RMSE to the maximum value of the true initial water surface elevation versus the
length of observation time.
Number of Offshore Observation Points
The number of offshore observation points is varied from 3 to 19. Offshore observation points are
assumed to be installed with even intervals along the coast, so the interval is set to be 25 km for 19, 50
km for 10, 100 km for 5, and 200 km for 3 offshore observation points respectively. The ratio of RMSE to
the maximum value of the true initial water surface elevation is plotted against the number of offshore
observation points in Fig. 17. A large number of offshore observation points are confirmed to reduce
Hoei
Tonankai
Nankai
Tokaido-Oki
0.15
0.13
0.11
0.09
0.07
0.05
0.03
0
10
15
20
Figure 17: Ratio of RMSE to the maximum value of the true initial water surface elevation versus the
number of offshore observation points.
4. Conclusions
Two estimation methods have been developed to create and enhance tsunami damage images, which
initiate disaster mitigation plan and measures of possible tsunamis.
- 85 -
One is the numerical models system named STOC to estimate the detailed damage by the possible
tsunami.
The system consists of three fluid models and one floating-bodies model. To calculate the
tsunami propagating in the open ocean, inundating land and interacting with structures, two
non-hydrostatic and three-dimensional models are included into the system. The non-hydrostatic model
named STOC-IC to be applied is especially validated through comparison with experimental results and
then applied to an actual port area to estimate damage to the area. Based on these applications it is
confirmed that the non-hydrostatic effects appear in the tsunami overflowing and running up structures
and flowing in the bending part of channel.
The other method is the real-time estimation of coastal tsunami using the inversion method with
offshore observation data of the tsunami. The inversion method is improved by utilizing the location of
the epicenter as a priori information. The results of the numerical experiments confirm that the improved
inversion method can estimate the tsunami source and predict the tsunami profiles along coasts precisely
from the tsunami profiles observed at 5 offshore locations for 15 minutes after the earthquake occurrence.
Especially, the tsunami arrival time and the first tsunami height can be predicted with good accuracy. It is
clarified by the parametric studies how the length of observation time or the number of offshore points
affect the accuracy of prediction.
Acknowledgements
The authors would like to express our gratitude to Geographical Survey Institute Japan for supplying
the airborne laser scanning survey data of the model port. This research is partially supported by the
Ministry of Education, Science, Sports and Culture of Japan, Grant-in-Aid for Scientific Research.
References
Arikawa, T. and T. Yamano (2008): Large-Scale Simulations on Impulsive Wave Pressures by Using
CADMAS-SURF/3D, Annual J. Coastal Eng., JSCE, Vol. 55, pp. 26-30 (in Japanese).
Fujima, K., K. Masamura and C. Goto (2002): Development of the 2d/3d Hybrid Model for Tsunami
Numerical Simulation, Coastal Eng. J., Vol. 44, No. 4, pp. 373-397.
Fujima, H., Y. Shigihara, K. Honda and H. Yanagisawa (2007): Some Detailed Numerical Simulations of
2004 Indian Ocean Tsunami, Proc. 4th Int. Workshop on Coastal Disaster Prevention, pp. 56-64.
Fukuoka, S. and A. Watanabe (1998): Three Dimensional Analysis on Flows in Meandering Compound
Channels, J. JSCE, No. 586/II-42, pp. 39-50 (in Japanese).
Hom-ma, M. (1940): Discharge Coefficient on Overflow Weir (Part-2). JSCE Magazine, Civil
Engineering, Vo. 26, No. 9, pp. 846-862 (in Japanese).
Honda, K. and T. Tomita (2009): Tsunami Inundation Simulation by Three-Dimensional Model. Coastal
Eng. 2008, ASCE, pp. 1433-1445.
Honda, K., T. Tomita, D. Nishimura and A. Sakaguchi (2009): Numerical Modeling of Tsunami Drifted
Bodies, Ann. J. Civil Eng. in the Ocean, JSCE, Vol. 25, pp. 39-44 (in Japanese).
Ikeya, T., R. Asakura, N. Fujii, M. Ohmori, T. Takeda and K. Yanagishima (2005): Experiment on
Tsunami Wave Force Acting on Floating Body and Development of an Evaluation Method, Ann J.
Coastal Eng., JSCE, Vol. 52, pp. 761-765(in Japanese).
- 86 -
Iwase, H., T. Mikami, C. Goto, and K. Fujima (2002): A Comparative Study of Nonlinear Dispersive
Long Wave Equations for Numerical Simulation of Tsunami, Proc JSCE, No. 705, pp. 129-138 (in
Japanese).
Kawata, Y., and N. Koike (1997):. Numerical Tsunami Simulation Based on the Principle of
Superposition, Proc. Coastal Eng., JSCE, Vol. 44, pp.271-275 (in Japanese).
Koike, N (2002): Study on Estimation and Error of Tsunami Initial Displacement of Water Surface Using
Inversion Method with a Priori Information, J. Hydraulic, Coastal, and Environmental Eng., JSCE,
Vol. 712, pp. 117-135 (in Japanese).
Koshimura, S. (2004): Modeling a Tsunami Generated by the Tokaido-Oki Earthquake of Mw 7.3
[04/09/05], http://www.dri.ne.jp/koshimuras/tokaido04/case0/ (online).
Nakatsuji, K., S. Karino, and H. Kurita (1992): Finite Element Analysis of Tidal Flow in the Osaka Bay
with Subgrid Scale Eddy Coefficient, Proc. Hydraulic Eng., JSCE, Vol. 36, pp. 693-696 (in
Japanese).
Nagai, T., T. Kato, N. Moritani, H. Izumi, Y. Terada and M. Mitsui (2006): Offshore Tsunami
Monitoring Network Design Using GPS Buoys and Coastal Onsite Sensors, Proc. 30th Int. Con.
Coastal Eng., ASCE, pp. 1529-1540.
Sakakiyama, T. and R. Kajima (1992): Numerical Simulation of Nonlinear Wave Interacting with
Permeable Breakwaters, Proc. 23rd Int. Conf. Coastal Eng., ASCE, pp. 1517-1530.
Sato, R. (1989): Nihon no Jishin Danso Parameter Handbook, Kajima Institute Publishing Co., Ltd (in
Japanese).
Tanimoto, K., K. Kimura and K. Miyazaki (1988): Study on Stability of Submerged Dike at the Opening
Section of Tsunami Protection Breakwaters, Rep. PHRI, Vol. 27, No. 4, pp. 93-121 (in Japanese).
Tatsumi, D., and T. Tomita (2007): Real-Time Tsunami Prediction Based on Inversion Method Using
Earthquake Information, Proc. 3rd Asian-Pacific Cong. Computational Mech., MS24-2-2.
Tomita, T. and K. Honda (2009): Tsunami Estimation Including Effect of Coastal Structures and
Buildings by 3d Model, Coastal Structures 2007, ASCE, pp. 681-692.
Tomita, T., K. Honda, and T. Kakinuma (2006): Application of Three-Dimensional Tsunami Simulator to
Estimation of Tsunami Behavior around Structures. Coastal Eng. 2006, ASCE, pp. 1677-1688.
Yasuda, T., T. Takayama, K. Kawamura, and H. Mase (2007): Real-Time Tsunami Prediction by Inverse
Analysis of Tsunami Profiles Observed at Offshore Points, Ann. J. Coastal Eng., JSCE, 54, pp.
196-200 (in Japanese).
Yoneyama N., M. Matsuyama and H. Tanaka (2002): Numerical Analysis for Locally High Runup of
1993 Hokkaido Nansei-Oki Seismic Tsunami, J. JSCE, No. 705/II-59, pp. 139-150 (in Japanese).
- 87 -
- 88 -
Kentaro KUMAGAI
National Institute for Land and Infrasracture Management (NILIM), Yokosuka, Japan,
kumagai-k27n@ysk.nilim.go.jp
Abstract
A computer simulation of tsunami evacuation is applied in estimation of the human
suffering due to tsunami, in verification of the effect of the countermeasures assists tsunami
evacuation, and in engaging educational activity for inhabitant. In this paper, major
methods of tsunami evacuation simulation in Japan are classified by three fundamental
viewpoints, such as the estimation method of evacuation start time, modeling method of
evacuee's behavior and evaluation method of the safeness of the evacuee's behavior.
Keywords: Evacuation simulation; evacuation start; evacuee's behavior; safeness
verification
1. Introduction
A computer simulation of tsunami evacuation for residents is applied in estimation of the human
suffering due to tsunami, in verification of the effect of the countermeasures assists tsunami evacuation,
and is utilized for education of inhabitant.
In this paper, major methods of evacuation simulation in Japan are classified by three viewpoints, such
as the estimation method of evacuation start time, modeling method of evacuee's behavior and evaluation
method of the multiple risk of tsunami inundation, destroyed houses and fire. And a case study of tsunami
evacuation simulation was conducted.
- 89 -
Effect of disaster
information
Individual difference
Nagakawa K.
and F. Imamura
(2000)
- Earthquake intensity
- Time of occurrence
- Location of residence
- Tsunami experience
- Communication
channel and impact of
disaster information
No
Hayakawa T.
and F. Imamura
(2002)
- Earthquake intensity
- Time of occurrence
- Location of residence
- Tsunami experience
- Announce time
-Estimated percentage
of evacuee
Modeling method of evacuee's behavior: The second step of the simulation is to model the evacuee's
behavior. Model type can be classified by mainly four characteristics (Research report of Institute for Fire
Safety and Disaster Preparedness, 1983, Imamura, F., T. Suzuki and M.Taniguchi, 2001): Crowd of the
evacuee can be modeled as a fluid body or granular individual agent; Direction of the movement of
evacuee in the street can be restricted only one way flow or allow two way flow; Topography are modeled
into the square mesh, node-link network or without modification; Evacuation routes from the resident to
evacuation site are endogenously-generated in the model or exogenously-generated way.
Table 2 Modeling Method of evacuee's behavior
Crouwd model
Movement
Topography
Evacuation route
Hori M. et al.
(2005)
individual agent
One way
No modification
endogenously
Muti-agent
simulation
Kiyono J. et al.
(1996)
individual agent
One way
No modification
exogenously
DEM
Nishihata T. et
at (2005)
individual agent
One way
Node-Link network
endogenously
Potential Model
Shiraki W. et al
(2006)
individual agent
One way
Node-Link network
endogenously
Cellular
automaton model
Multiple risk: There are risks not only inundation risk but seismic risk such as house wreck or fire
spreading along the tsunami evacuation. Sato, H. et al (2002) includes inundation and house wreck
multiple risks in his simulation. Miyoshi, T. et al (2008) includes fire risks.
References
Hayakawa, T. and F. Imamura (2002): Model of the Determination of Tsunami Evacuation and Its
Application, Journal of Japan Society for Natural Disaster Science, Vol. 21-1, pp. 51-66.
Hori, M., Y. Inukai, K. Oguni and T. Ichimura (2005): Study on Developing Simulation Method for
- 90 -
- 91 -
- 92 -
Todays Topics
Part 1: Coast Administration in Japan
Part 2: Tsunami disaster reduction in
Japanese ports and harbors
- 93 -
Hokkaido Southwest
Offshore Earthquake (1993)
M = 7.8
Kushiro Offshore
Earthquake (1993) M = 7.8
Tokachi Offshore
Earthquake (1968) M = 7.9
Sanriku Offshore
Earthquake (1933) M = 8.1
Sanriku Offshore
Earthquake (1896) M = 8.5
- 94 -
Kobe City
Takamatsu City
Muroto City
Meiji Sanriku M
July 12,
Dead or Missing:
Max Tsunami Height:
June 15,
Dead:
Max Tsunami Height:
Showa Sanriku M
Nihonkai Chubu M
May 26,
Dead:
Max Tsunami Height:
January 17,
Dead or Missing:
Dead or Missing:
Mikawa M
January 13,
Dead:
Tonankai M
Showa Nankai M
Dead or Missing:
Max Tsunami Height:
September 1,
March 7,
Hyogoken Nanbu
M
Kanto M
Kita Tango M
Dead:
March 3,
December 7,
Dead:
December 21,
Dead or Missing:
Max Tsunami Height: m
Chile M
May 23,
Dead or Missing:
Max Tsunami Height:
- 95 -
Protection
Area
RB5,500km
15,200km
PHB4,400km
Constructing
Coastal
Protection
Facilities
Requiring
Permission for
Exclusive Use
Restricting
Activities
Area Regulated
by Coast Law
MAFF&RB200km
Other Public
Coast
Requiring
Permission for
Exclusive Use
Restricting
Activities
Public Land
8,500km
8,500km
Road, Railway,
Private Land, etc
MAFF
FA
RB
PHB
12,500km
Characteristics of Coast
in Ports & Harbors Bureau Jurisdiction
Density of Population & Assets is high in the hinterlands of coasts in Ports
& Harbors Bureau Jurisdiction.
Tokyo
Kure
Osaka
Length
PHB Jurisdiction
Other Jurisdiction
Port Located
Municipalities
Population
PHB Jurisdiction
Chiba
Other Municipalities
Industrial Sales
Port Located
Municipalities
Other Jurisdiction
Other Municipalities
- 96 -
National Government
Ports and Harbors Bureau,
Ministry of Land, Infrastructure
and Transport
Local Government
Maintenance
Subsidized Project
Construction, Major Improvement,
Amenity Oriented etc
Construction,
Major Improvement, etc
Amenity Oriented
(Beach, Green Belt, etc)
Subsidized
Project
Maintenance
(Seawall)
(Floodgate)
Hiranai
Tokyo Port
Hakata Port
9
- 97 -
10
February, 2005
Establishment of Tsunami protection
committee
March, 2005
Recommendations of the tsunami
protection committee
11
- 98 -
Pacific Plate
SANRIKU
MIYAGI
HYUGA
Southern KANTO
TOKAI
(Reference)
TONANKAI
NANKAI
13
- 99 -
25
20
15
10
5
0
Earthquake
Tokai
Earthquake
Chishimakaikou
&
Nihonkaikou
Earthquake
14
Steady
Promotion of
Tsunami Hazard Map
Repair of
Coastal
Protection Facilities
Facilitation of
Evacuation
For Lives
Construction of
Coastal
Protection Facilities
For Assets
15
- 100 -
Tsunami Breakwater
Constructed
Under Construction
Tsunami
Breakwater
16
Not investigated
23.9
Sufficient
59.5
- 101 -
17
Earthquake-proofing in Construction
Some
seawalls
could
be
damaged by a large earthquake.
Not earthquake-proofed
11.4
Not investigated
54.3
Anti-liquefaction work
18
Closed in time
54.5
Not investigated
23.9
- 102 -
19
Remote
Gate Control
Gates
Meteorological
Information
Tsunami Prevention
Station
Information
Wave/Sea Level
Observation
Evacuation
20
Already made
319 governments
Not yet
49
330 governments
51
- 103 -
Drill on land
Drill on the sea
Clearance of obstacles
Investigation of facilities
Withdrawal of oil
Transportation of
support goods
Patrol boat
Jet
Transportation of victims
22
23
- 104 -
Tide station
0:40 32cm
24
Information
Information
Base Station
Coast
Guard
Evacuation
Facilities,
Fence etc.
Hazard
Map
Automatic
Warning
1.5
Breakwater
Improvement
Elimination of
un-managed
boats
Warning
Ports and
Harbors Bureau
TSUNAMI
Automatic
Flood Gate
GPS
GPS Tsunami Buoy
Check,
Study
for Facilities
Coastal Protection
Facilities
Hard
Approach
Soft
Approach
- 105 -
25
- 106 -
Subandono DIPOSAPTONO
Director for Coastal and Ocean Affairs, Ministry of Marine Affairs and Fisheries, Jakarta Pusat, Indonesia,
subandono.diposaptono@yahoo.com
Enggar SADTOPO
Head of Coastal Disaster Mitigation Division, Ministry of Marine Affairs and Fisheries, Jakarta Pusat,
Indonesia
Abstract
Coastal areas in Indonesia are highly vulnerable to tsunami hazards that have considerable
impacts to human life and the environment. In this regards, the need for coastal disaster
reduction in Indonesia is growing along with the growing development and increasing
population in these areas. Many activities have been done to assess tsunami potentials,
human and natural vulnerabilities, and mitigation effort to reduce its impacts. The disaster
mitigation in this case should be done in all levels and by all related stakeholders.
Governance, policies and regulation are made to give directions and provide legal assurance.
Structural and non-structural countermeasures are done to strengthen the society social,
economical and environmental conditions.
1. Background
Indonesian coastal areas has developed along with the increased of population and cities since long
time ago. Coastal area provides space, ways for transportation and access for distribution of people and
goods that eventually accelerate the development of trading, settlement and city. Coastal area with white
sandy beaches becomes a beautiful place for recreation and tourism. Almost in every Indonesian main
island, we can find many big cities growing in coastal area that is now very developed and populated.
The problems arise as these coastal areas are also very prone to natural hazards such as erosion, floods,
cyclone, earthquake, and tsunami. Whether we are aware or not, we put ourselves in more risks and
danger by developing more infrastructures, economy landmarks, and settlements in coastal areas.
Tsunami is one of the most catastrophic natural hazards in the Indonesian coastal areas. Usually, these
tsunamis are very devastating and have considerable impacts, the highest ever impact was the Indian
Ocean Tsunami in 2004 and the South Java Tsunami in 2006.
This paper elaborate recent progress on tsunami disaster mitigation efforts done by stakeholder in
Indonesia both for the structural and non-structural countermeasures
- 107 -
- 108 -
built very close to the sea; no greenbelts, and only remnants of the original mangroves and coastal forests
remaining.
Eurasian Plate
Pacific Plate
BANDA ARCH
SUNDA ARCH
--- ---
Potential Tsunami
Indo-Australian Plate
Figure 1. Potential Tsunami in Indonesia
Tsunami disasters in Indonesia caused widespread damage and suffering as the ensuing Tsunami wave
impacted on the coastal zone. An estimated 300,000 lives were lost. The tsunami run-ups were reported
higher than 30 m. As Aceh is relatively close to the Earthquake epi-centre off the coast of Sumatra and
the velocity of the Tsunami wave was very fast, there was little time for alert and evacuation. In the wake
of the soul searching in the months after the catastrophe it was concluded that although Indonesians are
now more aware of the danger posed to population centers located in coastal areas more needs to be done
to pass on information about Tsunamis and how one may more away from the main danger area.
- 109 -
Island Management (Law No. 27/2007) provide Indonesia a strong legal basis for better disaster reduction
program.
The National Disaster Management Agency was formalized through Law Nr. 24/2007 and has a
coordinating role. According to this law, disaster reduction should be institutionalized through national
and local development plan. This perspective will ensure the sustainability of the program in term of
planning and budgeting. This also will reduce the inconsistency of the policy due to the change of
national and local leader.
The Law No. 27/2007 gives clear mandate for all stakeholders in reducing the negative impacts of
coastal disaster and increasing community participation and environmental conditions. The law 27/2007
absolutely gives a legal instrument to mitigate coastal hazards. The law 24/2007 also provides a direction
for better disaster governance. Law No. 27/2007 law has been translated in a more operational regulation
i.e. Government Regulation on Coastal Zone and Small Island Disaster Mitigation.
3.2 Integrated coastal planning and management
To reduce the impact of coastal disasters in Indonesia, nationally we always improve our capabilities to
mitigate these events. The Ministry of Marine Affairs and Fisheries (MoMAF), Republic of Indonesia is
also pro active in minimizing the impact of coastal disaster on coastal communities and on aquaculture
activities. The program emphasized the implementation of Integrated Coastal Zone Management (ICM).
The ICM will try to balances the utilization between natural resources, human needs, and disaster
mitigation aspects. The program have been implemented in 15 provinces in Indonesia and now started to
be replicated in other provinces.
Those three aspects are important to be noted because they influence and are related to each other that
eventually produce the coastal socio-ecology resilience. A healthy coastal ecosystem condition guarantees
that sustainability of exploitation activities by humans. For example, the health of mangroves and corals
affects the productivity of waters and fisheries, also effects under water tourism and building in the
coastal area from the wave attacks. On the contrary, exploitation of area and resources in the coastal area
will affect the balance and health of the environment due to waste, physical construction, or the profile
changes of the coast. And lastly, ecological condition, due to the exploitation by humans will be lost or
deter if there are no disaster mitigation concept in the coastal area.
Within this approach the hazard respond has changed from single agency to partnership and proactive
measure by assessing vulnerability to improve the risk management that developed with communities.
Accordingly, human activities in coastal area should not degrade and reduce the environment capacity to
absorb the hazard, increase human vulnerability by developing building and infrastructure that cannot
defend from hazard, and reduce their capacity to cope with and recover from hazard.
3.3 Disaster Mitigation Plan
According to ICM planning, the disaster mitigation plan is develop to give more emphasis on the
disaster reduction program. This mitigation plan reflects the change in disaster management paradigm in
Indonesia. It is reflected in more community planning such as land use planning, inundation management
plan, reduce vulnerability, and increase coastal community resilient. An integrated hazard mitigation plan
is important especially in very developed coastal area. This plan provides guidance for stakeholders in
reducing their vulnerability to coastal hazard for long time. Hazard mitigation or management plan is
- 110 -
directed to reduce the human vulnerability in all possible aspects. It covers activities to reduce the
weakness aspects and improve access to resource, social integration, institutional coordination, public
awareness, and building safety. The plan must be discussed and communicated with another area because
the hazard is not limited by administrative boundary.
MoMaF have been facilitating 4 local governments i.e. Padang, West Sumatra, Serang, West Java,
Denpasar Bali, and Lombok Tengah, West Nusa Tenggara in developing participatory local strategic plan
for coastal hazard mitigation. By doing this, it does not mean that the impact of coastal disaster can be
avoided, however, if planned accordingly, with good education and campaign in the community,
mitigation will eventually reduce the loss of lives, social, and economic and also improve the level of
resilience for future event.
As a final remark, it should be given a word about how to come up with holistic mitigation plan. The
key work is participatory strategic planning. Strategic planning is a planning method used by businesses,
governments, and NGOs to reach goals and get better results. A strategic plan consists of the following
element:
1) Identifies needs,
2) Clarifies goals,
3) Sets detailed objectives,
4) Establishes an action plan & timelines,
5) Provides for periodic progress review
By adopting strategic planning procedure for disaster strategic mitigation planning, it becomes easier to
incorporate holistic mitigation framework by setting priorities among economic, physical, and life.
In order to increase the compliance with the resulted strategic plan, many theories and practice
recommend soliciting participation of major stakeholders in strategic planning process. Workshops can be
a very effective tool for participation. With proper introduction of information and time pressure, group
of people participated in workshop can reach logical and reasonable conclusions, and they would show a
high commitment for their conclusions.
Participatory strategic planning process is really a capacity building process among stakeholders. For
any disaster mitigation, collaboration and cooperation among stakeholders are the indispensable element
for success. Participatory strategic planning process allows all stakeholders to be involved from the
beginning and avoid arbitrary imposition of top-down solutions. Along the planning process, proper
information of all aspects of disaster management would be provided so that the participants could enrich
their knowledge and deepen their understanding.
3.4 Coastal community empowerment
The empowerment in this context includes the improvement of economic livelihood, social
cohesiveness, community awareness, and access to capital and market. Those things area important in
enabling coastal community to prepare for disaster, recovery from event, and adapt to change that make
them more resilience in the future disaster.
In this regard, public education must be conducted regularly. Issues such as nature of hazard,
probability and magnitude, area likely to be flooded, proper responds and community preparation are
necessary to know. Picture, map, questioner, event scenario are useful in awareness and education
- 111 -
program.
The Ministry of Marine and Fisheries also use traditional and cultural events in the awareness
campaign. This method is intended to increase community resilience that should understand the nature of
hazard, able to mitigate the impact, disseminate and change information and have a disaster mitigation
planning.
In collaboration with Sea Grant Program USAID under Indian Ocean Tsunami Warning System
(IOTWS) we conduct training in coastal community resilience. This training intends to increase the
community understanding on their risk to coastal disaster and how they could increase their resilience to
cope with that event. The program covers activities such as: i) identification of issue, ii) conduct an
assessment on coastal community resilience for small community, iii) develop action plan to increase
community resilience.
The Indonesia Research Agency/community preparedness program provides outreach, education and
campaign material and implements community awareness programs to schools and community all over
Indonesia.
Local and Internationa NGOs has contributed much especially on community education and awareness.
Kogami, a local NGO in Padang provide education to the community on earthquake and tsunami, train
community on tsunami evacuation, and policy advocacy for disaster management in Padang and other
area. Here Surfaid provides community awareness and education programs and funds for tsunami
community preparedness for earthquake and tsunami for Padang and Mentawai and other areas in West
Sumatera. Yayasan IDEP, a local NGO based in Bali, provide community preparedness toolkit for
awareness raising for various hazards including tsunamis. MPBI, has advocated the passing of Law
Nr.24/2007 on Disaster Management and provide community preparedness books, brochure, posters, etc
for various hazards including tsunami
3.5 Coastal habitat rehabilitation
The objective of the habitat rehabilitation is to increase the coastal environment capacity to provide its
services for livelihood and protection from coastal hazards. It has been implementing in the form of
coastal forest and mangrove planting, coral reef transplantation, stock enhancement, and conservation.
Although Indonesia has suffered from a large number of tsunami events since ancient times, until now
there were few effective countermeasures against them. Tsunami countermeasures using hard structures
(seawalls, breakwaters, etc), require on-going maintenance and replacement perhaps every 50 to 100
years and present major infrastructure investment challenges for Indonesia. In general, these initiatives
may not be a good match in Indonesia for the following reasons:
these structures may be unpopular for people living on the coast as they may restrict movement
and social relationships,
tsunami countermeasure using hard structures raise aesthetical and environmental problems and
It may be that better information, restoring key areas and adapting to the coastal zone is more realistic.
Coastal areas and their economies are often highly productive as the activities are supported by the
renewable inputs from the sun, rivers and its organic matter, sediments and chemical potential, tides,
- 112 -
winds and especially waves. But often economic developments in the fossil fuel era diverted the original
values of the necessary support systems such as clearing much coastal forests because their contribution
was misunderstood. This was poor public policy because in the longer term, fisheries and aquaculture
have declined, wastes have accumulated, tourism has moved elsewhere, disasters impact more lives and
general well being is lower.
Learning from the above institutional weaknesses, and using principles of energy and self organisation
of eco-systems, naturally stabilizing structures such as coastal forests (greenbelt) may be a better
approach. Coastal forests are considered important in reducing the impacts of the Indian Ocean tsunami
based on preliminary environmental assessment, anecdotal evidence, and satellite photography before and
after the tsunami event. For example, in the Aceh coastal area, houses protected by coastal forests
suffered little damage compared to those bearing the full impact of the tsunami waves.
In addition to this potential for tsunami impact mitigation, coastal forests also have environmental
values such as storing Carbon and for wildlife habitat. There are also economic incentives: they are
largely self-organizing after being established (require little maintenance and last a long time) they reduce
nutrient enrichment of the coastal waters and improve the image of the area (important for tourism and
locals alike).
Many coastal areas in Indonesia prone to tsunamis are naturally high energy areas (see above).
Because wind and wave energy inputs are usually highest, they are often dominated by beaches and sand
and are generally not suitable as mangrove habitats4. The alternative for coasts may be to re-establish
them with coastal forests (local names are waru, ketapang, cemara).
A major purpose of the coastal forest is to reduce the tsunami force and its collateral effects landward.
As was seen after Aceh, the seaward coastal forested area, although impacted by tsunami waves or by
other hard debris borne by the waves, served to disperse the wave energy perhaps exponentially with
distance inland and so generally buffered the forested areas behind. In this way, tsunami waves and their
impacts may be reduced very significantly in a short distance and before reaching urban areas. Coastal
forest ecosystems in general also stabilize dunes in the beach zone. More sand retention on beaches also
serves to protect coastal areas from impacts from Tsunamis.
3.5.1. Coastal Forest Effects on Reducing Tsunami impact
Structural counter measures using natural protection methods (soft structure) such as coastal forests
against tsunamis are currently being developed by MoMAF. Activities include planting of Casuarinas,
Hibiscus tiliaceus, and Terminalia cattapa. The sites are located in tsunami prone coastal areas. The
overall goal of this effort is to establish enough coastal forest to significantly reduce the scale of tsunami
impacts. The degree or success of coastal forest in fulfilling this role is not, however, straightforward and
depends on a number of factors, e.g. the distance from the tsunami, the spatial extent and structure of
coastal forest which in turn are dependant of soil conditions, environmental and economic factors such as
available land and conflicting uses.
Although Indonesia has extensive and diverse coastal vegetation, technical research into the
engineering aspects and function of coastal vegetation in protecting coastal areas is still in its early stages.
Most of the research has been on mangrove effectiveness in reducing tsunami impacts in physical models
4
Locations suitable for mangroves are generally limited to areas where rivers flows and mixing, chemical
potential and tides are high such as river mouths, deltas and estuaries.
- 113 -
see for example Harada and Imamura (2003). The quantitative and concrete functions of non
mangrove (coastal forest) to reduce a tsunami in Indonesia are not yet established and
formulated.
- 114 -
architectural design is that it has to be responsive to the condition of the nature include infrequent natural
disasters. Traditional house is usually constructed in form of stilt house.
In the longer time frame of generations, Indonesias architectural design was adapted to the conditions
that are a feature of the region. In more recent times, however, much of this tradition has been ignored
with the result that when an earthquake and/or tsunami strikes, many buildings are destroyed and many
lives unnecessarily lost.
Based on the past experience, MoMAF has retrofitting houses in several coastal areas in Indonesia.
Some of the basic concepts are as follows: The first floor is two meters high from the ground so when the
sea water level rises, the water would only pass but not enter into the house. To make it stronger, the
footplate concrete foundation and the reinforced concrete column uses a reinforced concrete column with
diameter of 30 cm. This main post or column functions to deflect the impact of debris that is carried by
the tsunami. This debris can be quite large, for example, boats and tree trunks. The column is cylindrical
and of smaller diameter to deflect the impact caused by debris. The foundation is set to a depth of 1.5 m
(or to the level of the bedrock) to avoid the scouring by tsunami.
Even though the typology of the buildings used is the same, the form and construction differs from
each area. The houses and construction is adapted to the structure and characteristics of the soil.
Besides proper construction techniques, the use of building materials is being modified. In the planning
of the house, light weight materials are being used to reduce the weight of the building. Light bricks are
used for the wall or wooden paneling/plywood and zinc sheeting is used for the ceiling rather than heavy
clay roof tiles. The floor uses wooden boards. Only the floor in the kitchen uses reinforced concrete to
avoid fires. The MoMAF has also re-formulated the building code for earthquake and tsunami to include
the existing traditional design with some modern building techniques learnt from experience in
earthquake and tsunami friendly house construction.
The recently earthquake in Padang, Pariaman in West Sumatera (7,6 richter scale) on September 30,
2009 and in Jambi (7,0 richter scale) the next day has created economical losses of more than 2 billion
Rupiahs. The highest affect areas are Padang, Pariaman, Agam, Pasaman, and West Pasaman. As
observed, many houses were devastated in the event. This is due to those houses were not engineered
built. They did not have practical columns, ring balk and sloofs. The quality of the materials was low and
other imperfection.
Until 2008, MoMAF has built 497 houses in 18 Provinces. In Pariaman and Agam, these houses were
proven to be earthquake resistance. In other southern coastal areas, these engineered houses could stand
the Bengkulu earthquake of 7,4 RS and a ship of 10 GT pushes by a 1-2 meter tsunami.
In 2009, 2.236 disaster friendly fishermen houses were built in 55 cities. There are two types of houses
being built, stilt and non-stilt houses. The Stilt houses were built to let tsunami pass under. In normal
situation, the lower ground can be used for leisure location, parking place, and other purposes. The upper
level can be an evacuation place when a tsunami strikes.
3.7 Tsunami Early warning System
Early warning saves lives. Thats a very obvious lesson from the tsunami event. Early warning
systems are considered the foundation of disaster mitigation.
technology, accurate forecasting of the occurrence of a natural hazard has saved thousands of lives and
protected properties. It is very unfortunate indeed that the Indian Ocean lacks a tsunami warning system
- 115 -
Another challenge to overcome is the time imperative for issuing tsunami warning. Even in the event
that an early warning system is deployed, Indonesia is a vast Archipelago with over 3,000 inhabited
islands with all the concomitant communication challenges that this implies.
communication it may not be possible to adequately warn all people in all potential impact areas in a
timely fashion. In conclusion, this system has a role to play in Indonesia but to be more effective,
additional information transmission methods about Tsunami need to be developed.
Because Indonesia has suffered from a large number of tsunami events since ancient times, some local
cultures developed their own early warning systems. In many cases however, this knowledge has been
lost. As part of the Government of Indonesias efforts, the traditional knowledge systems about tsunami
are being revisited.
The buoy system is usually deployed in deep water in the open sea.
- 116 -
the first tsunami wave arrived. This was followed by a second wave that reached a height of around 15m9.
All villages in Alafan district on the northeast coast and facing to the source of the earthquake and
tsunami were destroyed. Although the maximum wave height was measured at only 4 m at Labuhan
Bakti village on the south end of the island, the village suffered large losses in the disaster.
At Simelue, the toll was only 7 people dead and 1 missing from a population of 78, 000 people. This is
less than 0.01% of the population, a figure that stands in sharp contrast to the number of casualties in
Aceh10. The difference is thought to lie in the culturally shared local wisdom about tsunamis. Because
the population is better adapted and has more knowledge about the risks it able to re-act accordingly in
the event.
The tradition of SMONG has been passed down for several generations by the Simeulue people.
Smong is a local word refers to a particularly severe tsunami that struck in 190711. The story of Smong
has been shared by the people of these islands for as long as anyone remembers. Applying the wisdom
passed on through local cultural information exchange networks, the local people interpreted the warning
signs (sensing a quake, seeing the sea level drop, etc.), to mean that one should immediately run to the
hills or high ground. Since the information about SMONG has life saving consequences and therefore of
high value, it was incorporated into the culture as part of local wisdom and survived to save most of the
local population in 200412.
Another example of the effectiveness of locally generated and shared wisdom was during the 2007
Bengkulu tsunami caused by earthquake on 12 September 2007. Even though the tsunami height reached
about 3-4 m in Serangai village there was no loss of life. Learning from the 2004 Aceh tunami, the
coastal community ran to the hills or other safe places when they observed the warning signs.
3.8 Risk Assessment.
A hazard map was developed using technical data from the historical data and numerical forecasting of
tsunami. All information was translated to the GIS platform, significantly refining areas which could
easily be inundated and where specific households, in times of emergencies, need to be evacuated
immediately. They now use GIS as an effective tool for upland and urban planning; and on the drawing
board are plans for appropriate coastal zone development.
Tsunami hazard map shows the information necessary for residents to take refuge to high place or
shelters alocated by local government. The tsunami hazard map usually indicates the inundation area,
infrastructure, land use, evacuation route, and location of safety places.
The Ministry of Research and Technology and The Ministry of Energy and Mineral Resources has
developed their own hazard map for Bali, Padang, Aceh and other areas. Also international agencies
provides expertise and assistance in making hazard maps i.e German-Indonesia Tsunami Early Warning
System (GI-TEWS) for Padang, Cilacap and Bali, vulnerability map and risk map. UNESCO IOC does
scientific survey in North Sumatera Island, community awareness on earthquake and tsunami programs in
10
11
According to historical tsunami databases (ITDB, 2004), there was a tsunami in this region in
1907.
12
The message was so well interpreted that the local people even ignored whales left by the
receding water.
- 117 -
Aceh, Nias, Padang, Mentawai. Geo Hazard International: scientific research for geological hazard in
West Sumatera. JICA: work with government institution and universities in developing hazard map and
other activities.
Conclusion
Indonesian coastal areas are prone to tsunami hazards that threaten the sustainability of social and
economic development. The mitigation program is essential for the country and it has been in right
direction under the new laws in disaster management and coastal and small island management.
The mitigation activity covers many aspects. It covers intervention of nine intervention areas: i)
legislation and regulation, ii) integrated coastal planning and management, iii) coastal disaster
mitigation plan, iv) coastal community empowerment,
vi)
retrofitting, vii) risk assessment, viii) development of evacuation route, and ix) tsunami early warning
system.
-
Enhance coordination between different stakeholders has provided leverages in information sharing,
implementing joint scientific research, and community awareness activities
High occurrence of earthquake and tsunamis provide experience to enhance better disaster
management, coordination, building of retrofitted houses, and community preparedness. Moreover
the societies are now more open to mitigation effort and have a higher willingness to understand
about earthquake and tsunamis.
- 118 -