Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Fundamentals of
Commercial Geothermal
Wellfield Design
Intended for general distribution to:
Geothermal Wellfield Designers, Engineers & Architects
Distributed by:
GHP Systems, Inc.
1000 N 32nd Ave
Brookings, SD 57006
Prepared by:
Kris Charles Jeppesen
About the Author:
Kris Jeppesen is the President of GHP Systems, Inc.,
a leading manufacturer and supplier of commercial geothermal wellfield
products. Jeppesen has been involved in the geothermal industry
for many years as a contractor, researcher, geothermal training center instructor
and design engineer. He is an IGSHPA Certified Trainer and an AEE Certified
GeoExchange Designer. He received his B.S. and M.S. in Mechanical Engineering
from South Dakota State University.
2010 GHP Systems, Inc.
NOTICE: THIS DOCUMENT REPORTS ACCURATE AND RELIABLE INFORMATION TO THE BEST OF OUR KNOWLEDGE BUT OUR SUGGESTIONS AND
RECOMMENDATIONS CANNOT BE GUARANTEED BECAUSE THE CONDITIONS OF USE ARE BEYOND OUR CONTROL. THE USER OF SUCH INFORMATION
ASSUMES ALL RISK CONNECTED WITH THE USE THEREFORE. THE AUTHOR AND DISTRIBUTOR ASSUMES NO RESPONSIBILITY FOR THE USE OF THE
INFORMATION PRESENTED HEREIN AND HEREBY DISCLAIMS ALL LIABILITY IN REGARD TO SUCH USE.
INDEX
INTRODUCTION
Definition ............................................................................................. 2
GROUND CONDITIONS
Land Area Availability and Drilling Conditions ................................ 2
Test Bore ............................................................................................. 3
Formation Thermal Conductivity Test .............................................. 4
VERTICAL HEAT EXCHANGER DESIGN LENGTH
Effects of Heating versus Cooling of Wellfield Sizing ..................... 5
Effects of Equipment .......................................................................... 6
Geothermal Borehole Resistance ..................................................... 6
Sensitivity Analysis ............................................................................ 7
SYSTEM PIPING DESIGN
Pipe Sizing .......................................................................................... 9
Header Design Using Multiple Circuits ............................................. 9
Reverse Return ................................................................................. 10
Reduced Header ............................................................................... 10
Single Supply and Return Mains ..................................................... 11
Multiple Supply and Return Mains .................................................. 11
Manifolds ........................................................................................... 12
MATERIALS
Pipe .................................................................................................... 13
Grout .................................................................................................. 13
Antifreeze .......................................................................................... 13
APPENDIX
Mean Water Temperature Graph ..................................................... 14
Flow Characteristics of HDPE Pipe ................................................. 15
Example VHE Report ....................................................................... 18
Example Formation Thermal Conductivity Analysis ..................... 19
Detailed Drawings
VHE Borehole Detail ........................................................................ 20
Geothermal Wellfield Layout ............................................................ 21
Vault Detail ...................................................................................... 22
Example Geothermal Wellfield Specifications ............................... 23
INTRODUCTION
With the rapidly growing interest in commercial geothermal heat pump systems, the
demand for qualified designers, engineers and architects who can successfully tackle these
projects has also increased. In many cases, designing the geothermal wellfield causes the
main difficulty for the designer. A poorly designed geothermal wellfield can lead to poor
system performance, excessive installation costs, and unnecessary liability. The intent of
this design guide is to outline procedures and design techniques necessary to optimize the
geothermal wellfield design.
Definition
A closed-loop geothermal wellfield
exchanges energy with the earth by
circulating a water or
water/antifreeze solution through
plastic pipe buried beneath the
earths surface. A vertical closedloop geothermal wellfield typically
consists of multiple vertical heat
exchangers (VHEs). VHEs are
constructed by drilling holes
generally ranging from 50 to 400
feet deep in the earth and then
inserting two pipes with a fitting
joining the two pipe ends at the
bottom (called a u-bend pipe
assembly). The remaining open
annulus of the drilled borehole is
then backfilled or grouted, thereby
encasing the u-bend pipe assembly
(see diagram at right).
EARTH
GROUT OR BACKFILL
SPECIFIED DEPTH
U-BEND PIPE
GROUND CONDITIONS
Land Area Availability and Drilling Conditions
A geothermal system can usually be implemented by any heating/cooling application -- providing
that favorable conditions exist to do the geothermal wellfield installation. Available and suitable
land area may be a constraint as to the feasibility of installing a geothermal heat pump system.
A rough rule of thumb is that there should be a minimum of 225 sq-ft of land area available per ton
(12,000 Btuh) of design load capacity. However, designing longer VHE depths and/or tighter VHE
grid spacing can accommodate land area constraints. Installation areas should be relatively level,
dry, free of trees, underground utilities and other obstacles complicating the installation. Once the
geothermal wellfield is installed, this land area can become a parking lot, park, football field or a
variety of other applications.
Another significant factor determining the feasibility of the wellfield is whether or not the drilling
conditions are favorable. Drilling logs from wells drilled in the area can usually be obtained from the
State and can provide the designer with general expectations of the subsoil formation. Additional
information on drilling difficulty can be obtained by contacting local drillers from the area. Obviously,
the more difficult the drilling conditions the more expensive the wellfield installation.
Test Bore
The primary unknown factor that changes from one geothermal wellfield project to the next is the
VHEs borehole composition. The borehole soil/rock composition plays a significant role
determining drilling costs and total required VHE lengths. For smaller geothermal wellfield projects
(30 ton or less), drilling logs of water wells can provide reasonable assumptions. However, a test
bore should be drilled on site to obtain accurate drilling conditions and to increase the design
reliability for larger commercial wellfield projects. In addition, it is also recommended to install a ubend pipe in accordance with the anticipated design length so that a formation thermal conductivity
test can be performed as described in the following section.
Drilling contractors will assume the worst case drilling conditions in their bids if they are unfamiliar
with the drilling conditions and if a drilling log is not provided with the bidding documents. Inflated
drilling costs will significantly increase the bid price for the entire geothermal wellfield project. A
detailed drilling log similar to the one below should be included with bid documents.
TEST BORE DRILLING LOG
DRILLING LOCATION
PERMIT NO
CONTRACTOR
DRILLING LICENSE
NA
JOHN JAMES
XXXX1234
DEPTH IN FEET
FROM
0
3
22
85
153
159
165
187
200
STATIC WATER LEVEL
DRILLING METHOD
TOTAL DRILLING TIME
U-BEND INSTALLED
GROUT TYPE
TO
3
22
85
153
159
165
187
200
DESCRIPTION
TOP SOIL
BROWN CLAY
GRAY CLAY
BROWN CLAY
SAND & GRAVEL
SOFT SAND STONE
GRAY SHALE
RED SHALE
LIMESTONE HARD
15 FEET
MUD ROTARY
1.5 HOURS
YES HDPE PIPE
Thermally Enhance 1:4 ratio bentonite: silica
The drilling log above indicates that drilling becomes difficult at 200 feet when bedrock is hit.
Drilling deeper into the hard limestone would be more expensive per linear foot than the first 200
feet, so the VHEs specified design depth would typically not go beyond 200 feet. If there is an
available land constraint the designer may have to consider going deeper than 200 feet with the
VHE depth.
TEMP (F)
-5.00
100
80
60
40
20
0
0.00
5.00
LN TIME (HOURS)
AVG
HEATING
Cooling: For the theological geothermal heat pump in
cooling, every three units of energy that are removed from
the conditioned environment are added to one unit of energy
from the electricity required to run the compressor to be
rejected into the wellfield. Therefore, not only is the entire
building load rejected into the wellfield, but an additional
33% of that load in electrical input is also rejected into the
wellfield.
The purpose of the above example is to demonstrate the
influence of the buildings dominant load on the sizing of the
wellfield. In theory, a building that requires only cooling
could require twice the wellfield capacity as a building with
the same size load that requires only heating. Likewise, a
building with even larger loads -- seasonally diversified in
heating and cooling -- may require a smaller wellfield
capacity, then a building with smaller loads but highly cooling
or heating dominant.
ELECTRIC
LOOPFIELD
(2 UNITS ENERGY IN)
GEOTHERMAL
HEAT
PUMP
(300% EFFICIENT)
COOLING
(3 UNITS ENEGY IN)
ELECTRIC
LOOPFIELD
(4 UNITS ENERGY OUT)
GEOTHERMAL
HEAT
PUMP
(300% EFFICIENT)
Effects of Equipment
Geothermal heat pump equipment selection also significantly affects the wellfield design lengths.
This should be clear if the basic theory presented in the preceding section is understood.
Geothermal heat pump models vary in efficiencies. A more efficient heat pump will require a lower
capacity wellfield in cooling, but a larger capacity wellfield in heating, compared to a lower efficiency
heat pump. This is supported by the fact that the more efficient a heat pump is, the less electricity it
will require to provide the same capacity. This means that in the cooling mode, less electrical
energy needs to be rejected into the wellfield along with the energy removed from the building.
However, in the heating mode, a more efficient geothermal heat pump will provide less electrical
energy into the heated environment, so more energy is absorbed from the wellfield to obtain the
same capacity. A geothermal heat pump that has a high heating and low cooling efficiency will
require a much larger wellfield capacity than a geothermal heat pump that will produce the same
capacities, but has a low heating, high cooling efficiency.
ENERGY APPLIED
ENERGY APPLIED
ENERGY APPLIED
The diagram above illustrates how the energy flux of a VHE is affected by its configuration. The first
configuration uses no performance enhancing technology; therefore, the borehole resistance
greatly inhibits the exchange of energy of the circulating fluid and the earth. The energy flux
increases significantly with the use of u-bend pipe separators in the second configuration. An even
greater increase in capacity is gained by incorporating a T.E. grout with the u-bend pipe separator
as shown in the third borehole configuration. A key point to consider is that there is a balance
between the added cost of increasing VHE performance and the savings incurred by shortening the
total VHE length.
Sensitivity Analysis
The objective in sizing and designing a VHE is to obtain the required wellfield capacity for the
lowest installation cost. The areas of control when designing a VHE include pipe placement, grout
thermal conductivity, u-bend pipe size and VHE grid spacing. The following graphs show how each
parameter influences the VHE design lengths.
450
400
350
300
250
200
5
10
15
20
25
1" U-BEND
1 1/4" U-BEND
260
240
220
200
180
160
140
3 GPM
3 GPM
3 GPM
3 GPM
3 GPM
3 GPM
3 GPM
3 GPM
3 GPM
30 GPM
3 GPM
Reduced Header
Once the headering process is complete, the entire wellfield piping system needs to be flushed of
all debris and purged of air. This process is performed by circulating water through all of the
wellfield piping system at high flow rates. The industrys accepted standard is to obtain a minimum
velocity of 2 feet per second through all piping. If a reduced header is not used, it may be
impossible to obtain this flow rate through portions of the header.
3/4"
1"
1 1/4"
2"
2"
1 1/4"
1"
3/4"
The reduced piping in the above header diagram can be explained by reviewing the required
velocities needed to purge the VHEs (see Appendix page 16 for Flow Characteristics of High
Density Polyethylene (HDPE) Pipe). This example uses HDPE DR11 pipe for the VHEs which
requires a flow rate of approximately 3.75 GPM to obtain a velocity of 2 feet per second through
each VHE. The main line, which is 2 HDPE DR 11, requires a flow rate of 19 GPM to obtain the
necessary 2 feet per second velocity. If the main line does not reduce in size as it approaches the
last VHEs hooked up in parallel to the main line, the flow rates will fall well below the required 2 feet
per second velocity, thus allowing air and debris to remain in that portion of the header pipe. In this
example, 13 VHEs need to be flushed and purged, at the same time requiring a total flow rate of
about 48 GPM at 3.75 GPM through each VHE. The reduced header system shown will flush and
purge all header piping as well as all the VHEs and not add excessive head pressure to the system
under normal operation.
10
D
E
D
N
E
M
M
O
C
E
R
T
NO
TO BUILDING
11
Manifolds
A typical manifold (interior manifold shown below) includes butterfly isolation valves, combination
balancing/isolation valves and pressure/temperature ports for each circuit. With this design setup,
circuit isolation, pressure testing and flow balancing can be easily performed. Each circuit can be
individually flushed and purged and accessed by connecting to the fill port. The mains should also
have isolation valves so the wellfield contractor can complete his portion of the installation
independent of the interior mechanical. Having temperature and pressure indicators installed on the
mains can aid in quick system checks during startup as well as during normal operation (see
appendix page 23 for vault layout).
12
MATERIALS
Pipe
High density polyethylene (HDPE) pipe is the geothermal industrys standard piping material.
The specific pipe used is a PE3408 HDPE with a minimum cell classification of 345464C per
ASTM D-3035. Typically, a DR 11 (160 psi) rating is used for u-bends and header pipe diameters
two inches and smaller; and a minimum of DR 15.5 (110 psi) is used for header pipe diameters
greater than two inches. Pipe produced specifically for the geothermal industry generally carries
a 50-year or longer warranty and has a life expectancy of over 100 years.
Advantages to using HDPE pipe include the following characteristics: toughness, durability,
and chemical and corrosion resistance. Another advantage of HDPE pipe is that it requires no
mechanical or glued fittings that could corrode or fail. All joints are permanently joined (welded)
with heat fusion, providing a leak proof joint when properly joined. The smooth wall of this pipe
accommodates low-pressure losses.
Grout
Many State and local regulatory agencies dictate grouting material and procedures for VHE
installations. In most cases, a 20% solids bentonite grout that is pumped from the bottom of the
borehole up in a continuous fashion will meet those requirements. The purpose of grouting with
bentonite is to form a hydraulic seal which will prevent contamination of aquifers. The permeability
rate of bentonite is approximately 1 x 10-9 centimeters per second; therefore, it is an excellent
medium for sealing a borehole. Bentonite grout products are usually bagged in a dry powder or
granular form; and, when mixed with water, will hydrate swelling to many times its dry size.
The primary drawback of using straight bentonite grout in VHEs is that it has a poor thermal
conductivity (K = 0.4 Btu/hr ft-F). Since the u-bend pipes are encased in the bentonite grout,
they are restricted from exchanging energy with the surrounding soil/rock. Thermally Enhanced
bentonite grouts add silica sand in with the bentonite/water slurry to increase its thermal
conductivity ranging up to 1.4 Btu/hr -ft-F. However, these thermally enhanced bentonite grout
products are expensive and labor intensive; therefore, it is rarely cost effective to increase the
thermal conductivity higher than 0.9 Btu/hr-ft-F.
Antifreeze
An ideal antifreeze solution for use in a geothermal wellfield system would be non-corrosive,
non-toxic, economical, possess low flammability and low viscosity, and meet all state & local
regulations. Currently, there is no particular antifreeze product that meets all of the desired
characteristics. For commercial geothermal heat pump systems, the most common antifreeze
used is propylene glycol (usually with inhibitors) and in many States, it is the only antifreeze
solution allowed in vertical wellfields. Propylene glycol is non-corrosive, non-toxic, possesses
low flammability and moderate heat transfer characteristics and meets State regulations. On the
negative side, propylene glycol is very viscous at low temperatures and is relatively expensive.
It is not recommended to use less than 20% propylene glycol by volume, in order to avoid dilution
of the products inhibitors and to avoid the promotion of organic growth. It is also not recommended
to exceed 30% propylene glycol by volume, because it may lower the performance of the
geothermal heat pumps. At 25% propylene glycol by volume, a water/antifreeze circulating solution
is freeze protected down to around 15 F. At this same concentration, propylene glycol at low
temperatures will increase the head loss of the circulating solution by approximately 36% over
straight water.
FUNDAMENTALS OF GEOTHERMAL WELLFIELD DESIGN
2010 GHP Systems, Inc.
NOTICE: THIS DOCUMENT REPORTS ACCURATE AND RELIABLE INFORMATION TO THE BEST OF OUR KNOWLEDGE BUT OUR SUGGESTIONS AND RECOMMENDATIONS
CANNOT BE GUARANTEED BECAUSE THE CONDITIONS OF USE ARE BEYOND OUR CONTROL. THE USER OF SUCH INFORMATION ASSUMES ALL RISK CONNECTED WITH
THE USE THEREFORE. THE AUTHOR AND DISTRIBUTOR ASSUMES NO RESPONSIBILITY FOR THE USE OF THE INFORMATION PRESENTED HEREIN AND HEREBY DISCLAIMS
ALL LIABILITY IN REGARD TO SUCH USE.
13
APPENDIX
MEAN WATER TEMPERATURE GRAPH
14
APPENDIX
Pipe Size:
Pipe Volume:
Pipe Size:
Pipe Volume:
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
4.25
4.50
4.75
5.00
5.25
5.50
6.00
6.50
7.00
7.50
8.00
0.41
0.55
0.69
0.83
0.97
1.10
1.24
1.38
1.52
1.66
1.80
1.93
2.07
2.21
2.35
2.49
2.62
2.76
2.90
3.04
3.31
3.59
3.87
4.14
4.42
0.13
0.18
0.22
0.27
0.80
1.01
1.24
1.49
1.76
2.05
2.36
2.68
3.03
3.39
3.35
3.71
4.09
4.48
4.89
5.32
6.21
7.17
8.19
9.27
10.41
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00
9.50
10.00
11.00
12.00
13.00
14.00
15.00
0.18
0.35
0.53
0.71
0.88
1.06
1.24
1.41
1.59
1.77
1.94
2.12
2.30
2.47
2.65
2.83
3.00
3.18
3.36
3.53
3.89
4.24
4.60
4.95
5.30
0.04
0.07
0.11
0.15
0.52
0.71
0.93
1.17
1.44
1.74
1.82
2.13
2.46
2.81
3.18
3.57
3.98
4.41
4.86
5.33
6.32
7.39
8.53
9.75
11.03
Pipe Size:
1-1/4 DR 11, 1.358 I.D.
Pipe Volume: 7.52 Gallons/100 ft
Velocity
Head Loss
GPM
(ft/sec)
(ft/100ft)
4.00
4.50
5.00
5.50
6.00
6.50
7.00
7.50
8.00
8.50
9.00
9.50
10.00
10.50
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
0.89
1.00
1.11
1.22
1.33
1.44
1.55
1.66
1.77
1.88
1.99
2.10
2.22
2.33
2.44
2.66
2.88
3.10
3.32
3.54
3.77
3.99
4.21
4.43
4.65
0.39
0.48
0.57
0.68
0.79
0.91
0.92
1.04
1.17
1.30
1.44
1.59
1.74
1.90
2.06
2.41
2.78
3.18
3.60
4.04
4.50
4.99
5.50
6.03
6.58
Pipe Size:
1-1/2 DR 11, 1.554 I.D.
Pipe Volume: 9.85 Gallons/100 ft
Velocity
Head Loss
GPM
(ft/sec)
(ft/100ft)
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
23.00
25.00
27.00
29.00
31.00
33.00
35.00
37.00
39.00
41.00
1.18
1.35
1.52
1.69
1.86
2.03
2.20
2.37
2.54
2.71
2.88
3.04
3.21
3.38
3.55
3.89
4.23
4.57
4.91
5.24
5.58
5.92
6.26
6.60
6.94
0.54
0.61
0.75
0.91
1.08
1.26
1.46
1.67
1.88
2.12
2.36
2.61
2.88
3.16
3.45
4.06
4.72
5.42
6.16
6.94
7.77
8.64
9.55
10.50
11.48
15
APPENDIX
FLOW CHARACTERISTICS OF WATER IN HDPE PIPE (PE345464C)
Pipe Size:
2 DR 11, 1.943 I.D.
Pipe Volume: 15.40 Gallons/100 ft
Pipe Size:
3 DR 15.5, 3.048 I.D.
Pipe Volume: 37.90 Gallons/100 ft
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
10.00
11.50
13.00
14.50
16.00
17.50
19.00
20.50
22.00
23.50
25.00
26.50
28.00
29.50
31.00
34.00
37.00
40.00
43.00
46.00
49.00
52.00
55.00
58.00
61.00
1.08
1.24
1.41
1.57
1.73
1.89
2.06
2.22
2.38
2.54
2.71
2.87
3.03
3.19
3.35
3.68
4.00
4.33
4.65
4.98
5.30
5.63
5.95
6.28
6.60
0.31
0.40
0.50
0.61
0.73
0.85
0.99
1.13
1.28
1.45
1.62
1.79
1.98
2.17
2.38
2.81
3.27
3.76
4.28
4.83
5.42
6.03
6.67
7.34
8.04
40.00
45.00
50.00
55.00
60.00
65.00
70.00
75.00
80.00
85.00
90.00
95.00
100.00
105.00
110.00
120.00
130.00
140.00
150.00
160.00
170.00
180.00
190.00
200.00
210.00
1.76
1.98
2.20
2.42
2.64
2.86
3.08
3.30
3.52
3.74
3.96
4.18
4.40
4.62
4.84
5.28
5.72
6.16
6.60
7.04
7.47
7.91
8.35
8.79
9.23
0.43
0.54
0.65
0.77
0.90
1.04
1.19
1.34
1.51
1.68
1.86
2.06
2.25
2.46
2.68
3.13
3.62
4.14
4.69
5.26
5.87
6.51
7.18
7.88
8.61
Pipe Size:
4 DR 15.5, 3.92 I.D.
Pipe Volume: 62.69 Gallons/100 ft
Pipe Size:
6 DR 15.5, 5.771 I.D.
Pipe Volume: 135.88 Gallons/100 ft
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
53.00
58.50
64.00
69.50
75.00
80.50
86.00
91.50
97.00
102.50
108.00
113.50
119.00
124.50
130.00
141.00
152.00
163.00
174.00
185.00
196.00
207.00
218.00
229.00
240.00
1.41
1.56
1.70
1.85
1.99
2.14
2.29
2.43
2.58
2.72
2.87
3.02
3.16
3.31
3.46
3.75
4.04
4.33
4.63
4.92
5.21
5.50
5.80
6.09
6.38
0.21
0.26
0.30
0.35
0.40
0.46
0.51
0.57
0.64
0.70
0.77
0.85
0.92
1.00
1.08
1.25
1.43
1.62
1.83
2.04
2.27
2.50
2.75
3.00
3.27
200.00
220.00
240.00
260.00
280.00
300.00
320.00
340.00
360.00
380.00
400.00
420.00
440.00
460.00
480.00
520.00
560.00
600.00
640.00
680.00
720.00
760.00
800.00
840.00
880.00
2.45
2.70
2.94
3.19
3.43
3.68
3.93
4.17
4.42
4.66
4.91
5.15
5.40
5.64
5.89
6.38
6.87
7.36
7.85
8.34
8.83
9.32
9.81
10.30
10.79
0.37
0.44
0.51
0.59
0.67
0.76
0.86
0.96
1.06
1.17
1.28
1.40
1.52
1.65
1.78
2.06
2.36
2.67
3.00
3.35
3.72
4.10
4.50
4.92
5.35
16
APPENDIX
FLOW CHARACTERISTICS OF WATER IN HDPE PIPE (PE345464C)
Pipe Size:
8 DR 15.5, 7.513 I.D.
Pipe Volume: 230.30 Gallons/100 ft
Pipe Size:
10 DR 15.5, 9.362 I.D.
Pipe Volume: 357.60 Gallons/100 ft
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
GPM
Velocity
(ft/sec)
Head Loss
(ft/100ft)
300.00
320.00
340.00
360.00
380.00
400.00
420.00
440.00
460.00
480.00
500.00
520.00
540.00
560.00
580.00
620.00
660.00
700.00
740.00
780.00
820.00
860.00
900.00
940.00
980.00
2.17
2.32
2.46
2.61
2.75
2.89
3.04
3.18
3.33
3.47
3.62
3.76
3.91
4.05
4.20
4.49
4.78
5.07
5.36
5.64
5.93
6.22
6.51
6.80
7.09
0.21
0.24
0.27
0.30
0.33
0.36
0.39
0.43
0.46
0.50
0.54
0.58
0.62
0.66
0.71
0.80
0.89
0.99
1.10
1.21
1.32
1.44
1.57
1.69
1.83
550.00
600.00
650.00
700.00
750.00
800.00
850.00
900.00
950.00
1000.00
1050.00
1100.00
1150.00
1200.00
1250.00
1350.00
1450.00
1550.00
1650.00
1750.00
1850.00
1950.00
2050.00
2150.00
2250.00
2.56
2.80
3.03
3.26
3.50
3.73
3.96
4.19
4.43
4.66
4.89
5.13
5.36
5.59
5.83
6.29
6.76
7.22
7.69
8.16
8.62
9.09
9.55
10.02
10.49
0.22
0.26
0.30
0.34
0.39
0.44
0.49
0.54
0.60
0.66
0.72
0.78
0.85
0.91
0.98
1.13
1.29
1.46
1.63
1.82
2.01
2.21
2.42
2.64
2.87
17
APPENDIX
EXAMPLE VERTICAL HEAT EXCHANGER REPORT
18
APPENDIX
EXAMPLE FORMATION THERMAL CONDUCTIVITY ANALYSIS
Project:
Washington School
1000 32nd Ave
Brookings, SD 57006
Test Date:
01/01/03 01/02/03
Drilling Log:
FORMATION T.C. TEST
TOP SOIL
SAND/GRAVEL
CLAY
GRAY SHALE
80
TEMP (F)
0 - 3
3 - 10
10 - 191
191 - 200
60
AVG WATER TEMP
40
20
0
2 pipe
200
3/4
5
20% solids
10 spacing
10
20
30
TIME (HOURS)
Water
215.71
12.86
2,774
24 hours
12 - 24 hours
TEMP (F)
In-situ Testing/Analysis:
100
90
80 y = 3.1385x + 66.348
.
70
60
0.00
2.00
4.00
50
AVG WATER
TEMP
Linear (AVG
WATER TEMP)
LN TIME (HOURS)
T .C. =
Q
47.34
=
= 1.20
4m 4 (3.1385)
where:
Q = Power input (Btuh) per liner foot of VHE
m = slope of the regression line
19
APPENDIX
EXAMPLE DETAIL DRAWINGS
VHE Detail Example 1
FOILED BACK WARNING TAPE
(ALONG ENTIRE LENGTH OF HEADER PIPING)
TRACER WIRE
(ALONG ENTIRE LENGTH OF HEADER PIPING)
EARTH BACKFILL
(COMPACT AS SPECIFIED)
18"
FINAL GRADE
SAND BACKFILL
18"
6'
300''
PREMANUFACTURED U-BEND
FINAL GRADE
SAND BACKFILL
18"
200'
10' TYP
6'
PREMANUFACTURED U-BEND
20
APPENDIX
EXAMPLE GEOTHERMAL WELLFIELD LAYOUT
21
APPENDIX
EXAMPLE VAULT DETAIL
1 1/4" HDPE
Sump Pump
Discharge
Number of
Circuits
Typ. of 20
To
To Sump
Sump
4" Valved
Bypass
Number of
Circuits
Typ. of 20
Little Giant
Giant Sump
Sump Model
Model 6
6 CIA-RFS
CIA-RFS
Little
W/ Mercury
Mercury Switch
Switch (Provided)
(Provided)
W/
Sump Pit
W/ Pump
Pressure Ind.
(Typ of 2)
Temperature Ind.
(Typ of 2)
2" Fill Port (Typ of 2)
22
APPENDIX
EXAMPLE GEOTHERMAL WELLFIELD SPECIFICATIONS
Closed Circuit Vertical Heat Exchanger (VHE)
DESCRIPTION OF WORK
A.
This design has been prepared in accordance with the materials standards and
accepted installation practices of the International Ground Source Heat Pump
Association (IGSHPA). The wellfield contractor shall comply with these standards
and practices along with all State and local regulations pertaining to the installation.
B.
The wellfield contractor is responsible for all aspects involved with the complete
geothermal wellfield installation. All materials, drilling, water supply, excavation,
hauling of backfill, dewatering, building penetration, manifold/vault installation, leak
testing, soil compaction, final flushing/purging, adding glycol and labor required shall
be included in the bid price.
C.
The wellfield contractor shall take note: There is no guarantee to the wellfield
contractor that the location of any existing utilities are exactly as indicated on the
plans. Some areas may require hand digging to locate that utility. The wellfield
contractor must include in the bid price, the repair of any domestic water, electrical,
communication or any service line that may be damaged during the construction of
this project. Any offsets required to route over or under existing lines shall also be
included in the bid price of the project.
QUALIFICATIONS
A.
The wellfield contractor must have on this project a certified IGSHPA installer.
The wellfield contractor performing this work must have a minimum of two years
experience in performing underground closed circuit VHE work of this projects size
or larger.
B.
23
APPENDIX
PRODUCTS
A.
Pipe
The pipe shall be PE3408 HDPE with a minimum cell classification of 345464C per
ASTM D3035 and a DR11 (160 psi) rating for u-bends and header pipe two inches
and smaller and a minimum of DR15.5 (110 psi) for header pipe greater than 2 inch
in diameter. This pipe will carry a warranty of no less than 50 years.
Each pipe shall be permanently indent marked with the manufacturer's name,
nominal size, pressure rating, relevant ASTM standards, cell classification number
and date of manufacture.
The VHE will have a factory fused u-bend with pipe lengths long enough to reach
grade from the bottom of the bore so no field fusions are required below the header
pit. Approved pipe manufacturer is Performance Pipe.
B.
Fittings
Pipe fittings shall meet the requirements of ASTM D2683 (for socket fusion fittings)
or ASTM D3261 (for butt/saddle fusion fittings). Each fitting shall be identified with
the manufacturer's name, nominal size, pressure rating, relevant ASTM standards
and date of manufacturer. Saddle fusion is not allowed except when performed by a
manufacturer normally engaged in that type of work. No field installed saddle fittings
are allowed. Approved fabrication manufacturer is GHP Systems, Inc. and approved
fitting manufacturers are Performance Pipe, Central Plastics and Viega.
C.
D.
24
APPENDIX
materials shall be manufactured from high-density, high molecular weight PE 3408
polyethylene compound that meets or exceeds ASTM D 3350 cell classification
345464C, and is listed by the Plastic Pipe Institute in PPI TR-4 with HDB ratings of
1600 psi (11.04 MPa) at 73F (23C) and 800 psi (5.52 MPa) at 140F (60C). All 3"
and larger HDPE piping will be DR15.5 and all 2" and smaller HDPE piping will be
DR11. All circuits 2" and greater shall include butterfly valves constructed of lug
type/lever with cast iron body, aluminum-bronze disc, EPDM Seat, 416 stainless
steel stem, rated at 200 psi. All circuit setter flow balancing valves will have a fixed
port venture orifice, have blow-out proof stem, flow measurement function
independent of ball position, install in any position, and serve as a service shutoff
with a tamper resistant memory stop to accurately reset to balancing. Circuits
smaller than 2" and all fill ports shall be ball valves with full port opening with blow
out proof stem, 600 psi non-shock cold WOG. Pressure/temperature ports shall be
brass and have a dual seal core of Nordel, good up to 350F for water and shall be
rated zero leakage from vacuum to 1000 psig. Plug shall be capable of receiving a
1/8" pressure or temperature probe. A stainless steel pressure gauge with "
isolation valve will be included on both supply and return mains. The pressure gauge
will be Sisco brand with 4 " dial size and read 0 100 psig. A stainless steel
bimetal thermometer will be included on both supply and return mains. The
pressure gauge will be Ashcroft brand with 3" dial size with 4" stem and reads 0
250F. The manifold will be leak proof checked at factory with 100 psi pressure for a
period of 24 hours or more.
E.
25
APPENDIX
steel pipe sleeves will be schedule 40 and have a continuous weld on interior side.
All reinforcement rods shall be located 3" within the concrete from the interior side
and welded to steel framing every 2 feet or less. The outer shell of the walls and
ceiling shall consist of 8" thick 4,000 psi concrete that is poured by the contractor onsite and vibrated into place. The manhole shall be constructed of " sheet steel with
a 3" flange that is anchored into ceiling concrete and welded to ceiling frame; all
manhole welds being continuous. The manhole cover shall be constructed of "
steel tread plate with framing constructed of " 3" x 3" angle iron. The manifold
stands support channel shall run continuous between circuits and be constructed of
" 3" x 3" angle iron with 1/8" 1" tube supports every 3 feet welded to the floor.
Manifolds: High density polyethylene (HDPE) pipe and fittings, joined together with
heat fusion, shall be used for all circuit and main header piping. All HDPE pipe and
heat fused materials shall be manufactured from high-density, high molecular weight
PE 3408 polyethylene compound that meets or exceeds ASTM D 3350 cell
classification 345464C, and is listed by the Plastic Pipe Institute in PPI TR-4 with
HDB ratings of 1600 psi (11.04 MPa) at 73F (23C) and 800 psi (5.52 MPa) at
140F (60C). All 3" and larger HDPE piping will be DR15.5 and all 2" and smaller
HDPE piping will be DR11. All circuits 2" and greater shall include butterfly valves
constructed of lug type/lever with cast iron body, aluminum-bronze disc, EPDM Seat,
416 stainless steel stem, rated at 200 psi. All circuit setter flow balancing valves will
have a fixed port venture orifice, have blow-out proof stem, flow measurement
function independent of ball position, install in any position, and serve as a service
shutoff with a tamper resistant memory stop to accurately reset to balancing.
Circuits smaller than 2" and all fill ports shall be ball valves with full port opening with
blow out proof stem, 600 psi non-shock cold WOG. Pressure/temperature ports shall
be brass and have a dual seal core of Nordel, good up to 350F for water and shall
be rated zero leakage from vacuum to 1000 psig. Plug shall be capable of receiving
a 1/8" pressure or temperature probe. A stainless steel pressure gauge with "
isolation valve will be included on both supply and return mains. The pressure gauge
will be Sisco brand with 4 " dial size and read 0 100 psig. A stainless steel
bimetal thermometer will be included on both supply and return mains. The
pressure gauge will be Ashcroft brand with 3" dial size with 4" stem and reads 0
250F. The manifold will be leak proof checked at factory with 100 psi pressure for a
period of 24 hours or more.
Keyed Entry: The manhole cover of the vault will be fastened with four stainless
steel pentagon head bolts requiring a special socket key for removal. These bolts
will be counter sunk a minimum of 1" in a circular hole just large enough to
accommodate the socket key to inhibit tampering/removal with conventional tools.
Two socket keys will be included with each vault.
Seals: All HDPE pipe penetrations in the vault will utilize a Link-Seal EPDM
modular hydrostatic seal to water proof and anchor the pipe. This seal will be
removable to allow replacement of the HDPE pipe should it ever be damaged at the
26
APPENDIX
point of vault penetration. The manhole cover and stainless steel sump pit will utilize
EPDM gaskets for seals where bolted connections are made.
Sump Pump: A Little Giant series 6 with mercury switch will be supplied with the
vault. The pump will be 1/3 HP, continuous duty rated, 60Hz, 120V - 9.0A. The pump
will discharge at a rate of 46 GPM at the point it exits the vault.
Ventilation: Vault will come with its own ventilation blower and 8" flexible ducting.
The blower will be industrial grade made with heavy duty metal construction and
produce high velocity air movement. The blower will be Aloha model 39008 rated for
60Hz, 120V - 1.4A. The blower will produce 1,580 CFM open and 1,200 CFM
connected to 20 feet of 8" industrial grade flexible ducting. The blower will be ceiling
mounted at the opposite end of the manhole within the vault. The 8" flexible duct will
be run from the blower up to the top of the manhole entry. The blower will be
switched with the lights with this switch being located right below the manhole cover.
Electrical: The electrical service required for the vault is 60 Hz, 120V - 20A with
GFCI breaker. The vault shall have all required electrical conduit and boxes ceiling
mounted with 1" conduit exiting the vault. All outlets, light fixture(s), switch and
weatherproof covers will be included with the vault. The vault is to be field wired by a
licensed electrician in the state of installation.
The electrical components include:
1.
Light Fixture(s): Sealed glass lens with aluminum guard and aluminum
ceiling mounted base. The fixture is suitable for damp locations and uses
a 100 W bulb.
2.
Switch: The switch will be a 120V - 20A heavy duty double pole that will
power the lights as well the ventilation outlet
3.
Outlets: The two outlets used will be 120V - 20A heavy duty duplex.
The utility outlet will be wired continuous power for sump pump and servicing
equipment. The ventilation outlet will be switched with the lights for the
blower.
All alternate vaults must at a minimum meet the following criteria to be considered
for approval by engineer.
1.
Quality Assurance: The vault shall come from the factory with the HDPE
manifold mounted in place and all main and circuit piping stubbed out of vault
housing. The manufacturer shall be specialized in the manufacturing of
commercial geothermal vaults, have manufactured at least 200 geothermal
vaults and shall have manufactured geothermal vaults for a minimum of 5
27
APPENDIX
years. Proof of experience shall be required for approval.
F.
2.
Structural Integrity: Vault shall come from the factory traffic load rated and
capable of handling all traffic and service/utility equipment loads encountered
regardless of the vaults location. If additional structural support (such as a
concrete surface pad with manhole ring and cover) is required to meet this
criterion, it must have a PE stamped design. The vault shall have a flat base
that extends out to the complete width and length of the vault. This wide base
will have a reinforced footing surface area that carries a load of no more than
12 lb per square inch of the installed vaults weight.
3.
Buoyancy: The weight of the vault housing itself must overcome all bouncy
forces at the installed depth. The vault must not be able to float in a flooded
open vault pit during installation. If any additional vault weighting/anchoring is
required to meet this criterion, it must have a PE stamped design. The design
calculations will use complete saturated soil conditions.
4.
5.
Safety/Servicing: The vault shall have switched lighting, switched fresh air
ventilation (minimum 1200 CFM), service outlet and a sump pit/pump. The
vault shall have a minimum of a 30" square manway or a 34" diameter
manway with an OSHA approved ladder and a tamper resistant non skid
cover with a gasket seal. There must be a minimum 2' wide walkway between
circuits with a minimum 6 high unobstructed ceiling. All ceiling mounted
lights, ventilation blower, outlets and etc. must be mounted to the side of this
walkway.
28
APPENDIX
G.
H.
Warning Tape
Warning tape used must be foil backed, two inches wide or greater with a
continuous message printed every 36 inches or less reading: "CAUTION
GEOTHERMAL PIPELINE BURIED BELOW". The tape shall be highly resistant to
alkalis, acids and other destructive agents found in the ground.
EXECUTION
A.
Drilling
The vertical boreholes will be drilled to a depth allowing complete insertion of the
VHE to its specified depth. The maximum borehole diameter will be six inches. If a
larger diameter is required, it must be approved by the design engineer.
B.
C.
Grouting Procedures
The VHE is to be grouted from the bottom on up in a continuous fashion using a one
inch or larger HDPE tremie pipe. The tremie pipe will be pulled out during the
grouting procedure maintaining the pipes end just below grout level within the
borehole. All State regulations will be met for borehole grouting of the VHE.
D.
29
APPENDIX
E.
F.
Pipe Installation
The u-bend pipe ends will be sealed with fusion caps or tape prior to insertion into
the borehole. Reasonable care shall be taken to ensure that the geothermal wellfield
pipe is not crushed, kinked, or cut. Should any pipe be damaged, the damaged
section shall be cut out and the pipe reconnected by heat fusion.
The VHEs must be connected as indicated on the plans. The header design
accounts for balanced flow as well as flushing and purging flow rates. No variations
can be made in the circuit hookup or the pipe sizes that are indicated without
approval from the design engineer. The minimum bend radius for each pipe size
shall be 25 times the nominal pipe diameter or the pipe manufacturer's
recommendations, whichever is greater. The depth of all headers and supply and
return piping is indicated on the plans and must be maintained.
Circuits will be pressure tested before any backfilling of the header trenches is
executed. The individual circuits will be pressure tested with water at 60 psi;
however, not to exceed DR 11 pipe working pressure at bottom of the u-bend pipe.
G.
30
APPENDIX
water and then pressure tested. If connection to the manifold is not immediate,
piping must be capped. The wellfield contractor must coordinate with the mechanical
contractor on propylene glycol antifreeze installation. The mechanical contractor is
responsible for the interior pipings propylene glycol antifreeze. See Mechanical
Specifications for antifreeze specifics.
Glycol Charging: Follow all manufacturers instructions for product handling.
1.
Circuits: Isolate and charge one circuit at a time. Close all main valves and
all other circuits. Gradually introduce premixed propylene glycol solution,
through the fill port, until a concentration of 25% is obtained. Repeat
procedure for each remaining circuit.
2.
Mains: Close valves to all circuits, isolate and charge one pair of mains at a
time. Open valves on primary supply/return mains in mechanical room. Open
bypass valve in mechanical room or vault.
3.
4.
SHOP DRAWINGS
Before geothermal wellfield construction begins, the wellfield contractor must submit shop
drawings to the design engineer. The shop drawings shall include all applicable
manufacturers specifications, warranties, and material safety data sheets for all materials
used in the geothermal installation. No substitutions will be allowed without authorization
from the design engineer.
31