NDT LEVEL-III SPECIFIC EXAMINATION

RT TESTING
Answer Question I thro 6 W.R to QC/WP/00/02
1)

Vision examination requirement for Radiographic Interpreter


A)
B)
C)
D)

2)

near distance acuity checked annually


Color Perception using pseudo Is chromatic color vision
Both A & B
Radiographic Interpreter need not be examined for vision

Training requirements for RT is.


A)
B)
C)
D)

Level I 12 hours
Level I 24 hours
Level I 40 hours
None of the above

Level II 24 hours
level II 48 hours
Level II 40 hours

3)

Experience requirements for RT Level II is


A)
Minimum 65 hours in RT & min. 130 hours in NDT
B)
Minimum 35 hours in RT & min. 130 hours in NDT
C)
Minimum 630 hours in RT & min. 1200 hours in NDT
D)
minimum 200 hours in RT min. 400 hours in NDT

4)

The LEVEL II Radiographic Interpreter is


A)
Qualified to perform radiographic testing and interpret the films according to applicable
Codes.
B)
Qualified to perform radiographic testing if assisted by a RT Level II
C)
Qualified to interpret films according to applicable codes
D)
None to the above

5)

Requirements for RT specific examination is


A)
It shall be approved by the NDT Level III
B)
Is shall address the equipment, operating procedures and the techniques that the
candidate
C)
May encounter in his job assignments and acceptance criteria of generally used codes
Both A & B
D)
None of the above

Answer Question 6 thro 9 W.R. to QC/PROC/05/31


6)

procedure AHS/GEN-RT/01 is acceptable to


A)
Radiography of groove weld joints in plates pipes, vessels.
B)
Radiography of forgings & castings as valves
C)
Use of X & Gamma ray sources

D)

All of the above

7)

Surface preparation requirements prior to radiography


A)
Surfaces shall satisfy the requirements of the applicable materials specifications.
B)
The weld ripples or welds surface irregularities on both inside (where accessible) and
Outside shall be removed to such a degree that the resulting radiographic image cannot
mask or be confused with the image of any discontinuity.
C)
All of the above are true
D)
D) Only A is true

8)

Which of the following statements are true


A)
The finished surface of at butt welded joints may be flushed with the base material.
B)
Butt welded joints may have reasonably uniform crowns with reinforcement not to
exceed that specified in the referencing code section.
C)
All of the above are true
D)
none of the above are true

9)

All field radiography shall be performed by


A)
Only A Level III
B)
Either a level II, level II or a level I
C)
A crew consisting of 2 personal at least a level II and I
D)
Field radiography is not applicable to this procedure

Answer Question 10 thro 27 shall be answered W.R. to ASME sec. V


10)

As per the above procedure primary reference standard is


A)
B)
C)

11)

Calibration of reference SWF shall be


A)
B)
C)
D)

12)

National standard step tablet or step wedge calibration film


Reference transmission density SWF
Calibrated transmission density film which is calibration by manufacture.

Done by using densitometer calibrated using secondary reference standard


Done at the frequency of 3 months
Done by using densitometer calibrated using primary reference standard at the
frequency of 12 months
A & B above

Step wedge calibration film shall have been verified within the last year by comparison with
A)
B)
C)
D)

Calibrated densitometer of the factory


Comparison with reference step wedge film
Comparison with national standard step tablet
None of the above

13)

Which of the statements below is false for densitometer


A)
B)
C)
D)
E)

14)

The penetrameter is used to


A)
B)
C)
D)

15)

B)
C)
D)

Source to film distance


Object to film distance
Source strength
Source size

As per this procedure for a tube of outer diameter and a wall thickness of 6mm, the
penetrameter to be used is
A)
B)
C)
D)

18)

Penetrameter thickness 2*the specimen thickness with the required penetrameter hole
2% of the specimen thickness
Penetrameter thickness 2% of specimen thickness with the required penetrameter hole
2 x the penetrameter thickness
Penetrameter thickness 2% of specimen thickness with the required penetrameter hole
2% of the specimen thickness
Penetrameter thickness 2% of specimen thickness with the required penetrameter hole
4% of the penetrameter thickness

Which of the following is not a factor to be considered to reduce geometric unsharpness?


A)
B)
C)
D)

17)

Determine the size of the cracks and pores that can be detected
Determine the crack depths that can be detected
Determine the critical flaw size
Indicate the quality of the radiographic technique

The sensitivity requirement 2-2t represents


A)

16)

Initial calibration shall be done using a primary reference standard


Densitometer shall be calibrated every 90 days using a reference SWF
Tolerance for densitometer readings is 0.05 density units from the readings marked on
the SWF
Periodic verification of densitometer shall be done at the beginning of each shift
None of the above are false

12
15
17
25

Using the DWDI technique, the image recorder on a radiographic film is


A)
B)
C)

Circular
Linear
Elliptical

D)
19)

While taking radiograph of a tube 3in diameter using this procedure which of the following
statements is true
A)
B)
C)
D)

20)

B)

1.8 min for single film viewing and 4.0 max


2.0 min for single film viewing and 4.0 max
1.3 min for single film viewing and 4.0 max
None of the above

For penetrameter design the reference standards are;


A)
B)
C)
D)

24)

Where inaccessibility prevents hand placing the penetrameter on the sources side it
shall be placed on the film side in contact with the part being radiographed.
A lead letter F shall be placed adjacent or on the penetrameter but shall not mask the
essential hole or wire

Transmitted film density at the body of the body of the hole penetrameter or adjacent to the
designated wire and the area of interest for radiographs made with gamma-ray shall be
A)
B)
C)
D)

23)

Increase sources to film distance


Use a smaller physical sources size
Change from class II to class I film
Change from lead to fluorescent screens

Which of the statements below are true


A)

22)

3 penetrameter need to be placed each separated by 120


Wire type penetrameter should not be used
The image quality indicator can be placed on the source side only.
Use by penetrameter is optinal.

Poor definition can be improved by doing all but one of the following
A)
B)
C)
D)

21)

None of the above

SE 94
SE 1025, SE 747
SE 199
None of the above

For double wall exposure- double wall view the diameter of wires (in penetrameter) shall be based
on :
A)
B)
C)
D)

Nominal single wall thickness of specimen


Nominal double wall thickness of specimen
OD of pipe
None of the above

25)

In double wall exposure- double wall view, the penetrameter shall be used on :
A)
B)
C)

26)

In double wall exposure double wall view, SFD calculation for determination of Ug, is based on :
A)
B)
C)
D)

27)

Film side
Source side
There is no specific requirement

The thickness of pipe


The ID of pipe
The OD of pipe
None of the above

Which of the statements below is applicable to shim?


A)
B)
C)

Shim shall be of material radiographically similar to the weld metal


Shall be placed between the part and penetrameter
The thickness of shim shall be such that the radiographic density throughout the area of
interest is no more minus 15% from the density throughout the penetrameter
D)
All of the above
Question 28 shall be answered with ref. to ASME Sec. VIII Div. 1
28)

On a radiograph of a welded joint of thickness 25mm an isolated rounded indication appears size
of which is 0.375
A)
B)
C)

This is acceptable
This is not acceptable
Sec. VII does not give acceptance criteria for elongated indications

Question 29 shall be answered W.R.T. AWS D1.1


29)

As per AWS D1.1 a rounded discontinuity is one


A)
B)
C)

In which its length is 3 times its width or less and may be round or irregular and may
have tails
In which its length is more than 3 times its width
In which its length is equal to 6 times its width

Question 30 shall be answered W.R.T. ASME B31.3


30)

Random Examination as per ASME B31.3 is


A)
B)

Complete Examination or a percentage of a specified kind of item in a designated lot of


piping
100% examination of joints

C)
D)

Specified partial examination of each of a specified kind of item in a designated lot of


piping
None of the above