Boiler Performance
Test Procedure
PROJECT : WPCPL 4135MW POWER PLANT PROJECT
WPCPL 4x135MW
OWNER :
Project
Document No.
WPCPL 4135MW
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.2of 16
Boiler Performance
Test Procedure
Revision
Date
/09/04/2009
Description
Released by (date/signature)
Compiled:
WangJianhua
Checked:
ChenMo
Approved:
LeiLi
Released:
SEDC
Table of Contents
1. Overview of Boiler Equipment.......................................................................3
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.3of 16
Project
Document No.
WPCPL 4135MW
Rev. 1
SCCTI-W1-TP-B01
Generation Project
System
Pg.4of 16
Data
440
14.29
540
358.7
2.46
540
247
86
Description
Symbol
Unit
1
2
3
4
5
6
7
8
9
10
11
Fixed carbon
Carbon as received basis
Hydrogen as received basis
Oxygen as received basis
Nitrogen as received basis
Sulphur as received basis
Total water
Ash as received basis
Water of air dried basis
Volatile of dry ash-free basis
High heating value as
received basis
FC
Car
Har
Oar
Nar
Sar
Mt
Aar
Mad
Vdaf
GCV
%
%
%
%
%
%
%
%
%
%
kCal/
kg
Design
Coal
37.51
49.61
2.80
8.50
1.10
0.50
11.49
26.00
Worst
Coal
30.00
41.85
2.75
3.30
0.50
0.60
15.00
36.00
Best
Coal
42.00
53.90
3.00
11.50
1.20
0.30
9.10
21.00
39.99
4600
38.78
4200
39.91
4900
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.5of 16
2.Technical Procedure
2.1 Items of Boiler Performance Acceptance Test
2.1.1 Boiler maximum continuous rating
2.1.2 Boiler efficiency (HHV, include piping loss)
2.1.3 Coal conveying capacity
2.1.4 Unburned carbon in bottom ash and fly ash
2.1.5 Fly ash evacuation rate/hr from ESP other ash hoppers of the boiler
2.1.6 Coal consumption based on GCV OF 4600kCal/kg
2.2 Test Standard and Technical Basis
2.2.1 Steam generating unit performance test code ASME PTC 4.1 -1998
2.2.2 Air heater performance test code ASME PTC 4.3-1991
2.3 Test purpose
The purpose of the acceptance tests is to prove the boiler performance
guarantee value in the delivery contract, and to check if the boiler operating
characteristic can reach the design requirement.
2.4 Measuring points, instruments and measuring method
2.4.1 Test Sampling
2.4.1.1 Coal sampling
Two representative samples of raw coal shall be taken at the coal
feeder. Sampling shall be made at an interval of 30 minutes, with each
sample having a weight of 5-6k. The coal sample shall be put into an
enclosed container in time. After test, the coal samples taken during test
period shall be mixed in manner of equal proportion and divided into three
parts by means of quartering, with each part having a weight of 5kg. One part
shall be delivered to the Owner for proximate analysis, one part to the
commissioning sub-contractor for proximate analysis, ultimate analysis and
HHV measurement, and one part to the Owner for spare purpose. The
analysis data of the commissioning sub-contractor will be accepted as the
final analysis data for the test.
Analysis contents of coal as fired:
1) ultimate analysis (Car, Har, Oar, Nar, Sar, Mar, Aar)
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.6of 16
Project
Document No.
WPCPL 4135MW
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.7of 16
Model and
Specificatio
n
MODEL3080
Manufacture
Measuring
Range
Accuracy
Class
Inspection
Beijing SDL
Instrument
Company,
China
O2: 0%
20.9%
CO2: 0%
20%
CO: 0%
0.1%
Full range
national
institute of
measurement
and testing
technology
Flue gas
analysis preprocessor
MODEL3080
NiCr-NiSi
thermocouple
K-type, class
I
Beijing SDL
Instrument
Company,
China
Sichuan
Instrument
Company,
China
0400
0.5 C
national
institute of
measurement
and testing
technology
Multi-component
infrared
analyzer
1.0%
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.8of 16
Nar 0.09%
HHV 70Btu/lb
2.5.2 Conditions and stabilization time of performance acceptance test
Before starting the test formally, the boiler must be in stable operation
under test load. Especially when carrying out the test and measuring the
boiler efficiency under rated operating conditions, the period for stable boiler
operation shall not be lower than four hours.
During test and when boiler is under stable operating conditions,
parameter variation shall be within following range:
Main steam volume:
Main steam temperature:
Main steam pressure
3% (relative value)
10 (absolute value)
3% (relative value)
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.9of 16
2.5.3.10 All preliminary tests shall be carried out according to formal test
procedures; after preliminary test, test conditions shall be studied
immediately. After study, in case consensus is reached among various
participants, preliminary test can also be deemed as formal test.
2.6 Guaranteed Test Value and Conditions
2.6.1 Boiler efficiency
2.6.1.1 Guaranteed value
Guaranteed value for boiler efficiency ( according to HHV, including pipe
loss) shall be: 86%.
2.6.1.2 Conditions of guaranteed value
(1) Airpreheater inlet temperature: 32, relative humidity 65%,
atmospheric pressure 983.6 hPa, boiler blowdown 0%.
(2) Design fuel , pulverized coal fineness is qualified.
(3) Rated feedwater temperature.
(4) Superheat steam temperature and pressure are rated values;
reheat steam inlet/outlet temperature and pressure are rated values.
(5)
10
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.10of 16
11
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.11of 16
Where:
: Boiler efficiency (including pipe loss), %
12
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.12of 16
: Boiler efficiency, %
p: Pipe efficiency, % (take the design value as 99%)
13
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.13of 16
14
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.14of 16
Duration: 2 hours
Inspection items:
Main steam flow
Main steam pressure
Main steam temperature
2.8.4 Coal conveying capacity
Inspection items:
Coal conveying capacity
2.8.5 Evacuation rate test of fly ash and bottom ash
Inspection items:
Fly ash evacuation rate
Bottom ash evacution rate
15
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
Pg.15of 16
4. Safety Measures
4.1 During the test duration, the unit shall be running stably with the load
required by the test. The running operation shall be adjusted by the
operators as per the test plan.
4.2 The test personnel shall demobilize from the site if any sign of accident is
found or any accident occurs during the test, and the personnel on duty
shall deal with such case as per the accident handling procedure. The
test personel shall be contacted promptly if any abnormal condition is
found during the test. The test shall be stopped if any event which may
cause injury or fault of equipment occurs, and the test can only be
continued after it is confirmed that the abnormal condition has been
eliminated.
Type
Flue gas
temperature
2
3
Air
temperature
Name
air preheater
inlet
temperature
air preheater
outlet
temperature
Inlet primary air
temperature of
air preheater
Qty
24
Description
Measuring holes at air preheater
inlet according to grid method
20
16
Project
WPCPL 4135MW
Document No.
SCCTI-W1-TP-B01
Rev. 1
Generation Project
System
4
5
Flue gas
sample
6
7
Raw coal
8
9
Pulverized
coal
Fly ash
10
Bottom ash
11
Ambient
conditions
12
13
14
Pg.16of 16
Others
Inlet secondary
air temperature
of air preheater
Air preheater
inlet sample
Air preheater
outlet sample
Raw coal
sample
Pulverized coal
sample
Fly ash sample
2
24
20
Bottom ash
sample
Ambient
temperature
Atmospheric
pressure
Air humidity
Main operating
parameter
As per
actual
conditions