Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PURPOSE
The following narrative describes the procedures associated with the
installation of anodes and cables. This procedure is to ensure that the
installation work is conducted properly, which is essential for the cathodic
protection system to work properly.
RESPONSIBLE PERSONS
2.1
PROJECT COORDINATOR
Project Coordinator is responsible for the installation plan and ensure
the capability of person who work.
2.2
CONSTRUCTION SUPERVISOR
Construction Supervisor is responsible to evaluation of intended work
and inspection of the work site. Monitoring job step according to the
site-specific design drawings.
2.3
3.1
Thermit Welding
2. The area shall be thoroughly cleaned using a power brush or grinder and
then roughened to bright metal using a course file. Note that it may also
be necessary to use degreaser such as xylene.
3. Strip cable sheathing and/ or insulation so as to expose the copper core
for a length appropriate to the size of mould being used.
Place metal disc within the mould, so as to obscure the hole through
the mould.
OPERATION PROCEDURE
INSTALL MAGNESIUM ANODES AND CABLE
Revision : 0
Empty powdered contents of the thermit weld charge into the mould.
Squeeze the polythene container so as to ensure discharge of the
igniter powder from the bottom of the container. Close the mould lid.
Lay the exposed cable core on the pipe and across the exposed area.
Place the carbon mould over the exposed cable core, such that it lies
in the slot at the bottom of the mould.
Hold the mould firmly in the position with one hand and ignite the
powdered charge by operating the flint gun with the other hand. Safety
goggles and gloves must be worn.
An exothermic reaction takes place in which the powder is
transformed to the molten metal and melts the metal disc and drops
onto the cable below. Allow the molten metal to cool slightly say 5
seconds, before removing the mould.
4. Test the strength of the connection by hitting the completed weld with a
500 grams copper headed hammer.
5. The connection and surrounding coating should be cleaned and primed
for re-coating all as per the project pipe coating specifications. Note that
there will be a small amount of slag that must be removed.
Following coating repair, the cable and connection area may require
holiday testing using a proprietary instrument.
3.2
Test Station
1. The subcontractor shall construct foundations for the test station in
accordance with the project drawings.
2. Test cables shall be routed through conduit connected to the appropriate
terminals within the test box.
3. Cable slack shall be provided minimum 100 mm each within the test
station.
4. When necessary, any damaged paint coating shall be repaired to the
satisfaction of the client.
5. All cables shall be marked for future identification.
3.3
Magnesium Anodes
1. The proposed location of excavation shall be checked against the contract
drawings.
2. The excavation shall be as per the project design document and be of
sufficient depth and width to accommodate the installation of the vertical
anode.
3. Soak the packaged magnesium anode in the fresh water before install the
anode.
4. Backfilling of the anode shall be as per the project drawings. The selected
backfill shall be installed around and above the anode(s) to ensure
compaction and good anode to soil interface without voids. The
installation may be wetted and tamped to compaction as per site
requirements.
5. Anode cable tail/ header cable shall be installed within soft sand as per
the project drawings and specifications. The cable shall normally be
protected by cable tiles and electrical warning tape.
OPERATION PROCEDURE
INSTALL MAGNESIUM ANODES AND CABLE
Revision : 0
Typical Applications
Pole- and condulet-style test stations are used to
perform various corrosion-related electrical tests
on buried metallic structures. These include
structure-to-earth potentials, and the presence of
stray currents. Pole-mount test stations, which
can be selected in various color combinations,
are typically used in areas where an identifiable
marker is necessary. Condulet-style stations are
most often installed in the vicinity of buildings
or plant facilities.
Ordering Procedure
Corrpro distributes an assortment of pole- and
condulet-style test stations. To order the
required station for your application, indicate the
brand and model desired, and specify the
quantity, terminal configuration, and mounting
style needed. An example is provided to help
illustrate this process.
EXAMPLE
Quantity
Test Station
Manufacturer
Test Station Model
200
Number of Terminals
Mounting Style
Colors:
Pole
Test Head
Locking Device
Plastic Pole
Cott
Big Fink
White
Orange
Yes
STANDARD
TERMINAL
LEADS
MAXIMUM
TERMINAL
LEADS
MOUNTING
STYLE
OTHER
OPTIONS
Flange
Mounting
Zap Guard
Terminals
Locking Lids
Flange
Mounting
Zap Guard
Terminals
Locking Lids
Banana
Terminals
COTT (Manufacturer)
Big Fink
11
Six-Foot
Polyethylene
Poles
Little Fink
Five-Foot
Polyethylene
Poles
Finklet
1, 2, 3, 4
3/4" Conduit
Polyethylene
Poles
3/4" - 2 1/2"
Conduit
1" - 2 1/2"
Conduit
3/4" - 1 1/4"
Conduit
1" - 1 1/4"
Conduit
1 1/2" - 3 1/2"
Conduit
GEROME (Manufacturer)
100 Series
700 Series
10
800 Series
(Screw Cvr)
1000 Series
(Dual Hub)
2000 Series
(Dual Hub)
(Customer
Specs)
(Customer
Specs)
Thread or Slip
Fit
Thread or Slip
Fit
Thread Fit
Thread or Slip
Fit
Thread or Slip
Fit
Flush-To-Grade
Typical Applications
Corrpro flush-to-grade test stations are designed
for use in areas where maintaining a landscape's
aesthetic quality is important. The stations are
also ideal for use in human or vehicle traffic
areas, such as roads, parking lots, or sidewalks.
Using the test stations, readings can be obtained
to determine structure-to-soil potentials and the
level of stray currents.
Flush-To-Grade
EXAMPLE
Quantity
Test Station
Manufacturer
Test Station Model
200
Number of Terminals
Cott
Flush Fink
C. P. Test
Services
MODEL
Flush Fink
Street Fink
M2
T2
T4
NM
Mini
Glenn
STANDARD
TERMINAL
LEADS
5
5
2
1, 2, 5
1, 2, 5
4, 5, 7
2
4
MAXIMUM
TERMINAL
LEADS
11
9
2
5
5
7
5
5