Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Presentation In-charge
Yashobanta Naik
(Faculty)
Counter Signed
Director / Principal of the institute
ACKNOWLEDGEMENT
I take immense pleasure in thanking Mr. A.N Srivastava, Director(NSM) for having permitted
me to carry out this project work. I would also like to acknowledge Chopra mam for his valuable
support and guidance throughout this project.
Special thanks go to all the staff members of MINISTRY OF NEW AND RENEWABLE
ENERGY Without their insights and helpful thoughts, I would not have gained as much
information as I have. Their help has sparked my interest even more! Thanks!
I wish to express my deep sense of gratitude to my Internal Guide, Mrs. Manju Mam (Dy.
Director), NPTI for her able guidance and useful suggestions, which helped me in completing
the project work, in time. I also thank Mr. J. S. S. Rao, Principal Director (CAMPS), NPTI,
Mr. S.K. Choudhary, Director (MBA), NPTI, Mrs. Indu Maheshwari (Dy. Director) &
Mr. K.P.S. Parmar, Asst. Director, NPTI and Miss Farida Khan, Asst. Director, NPTI for
providing constant support and assistance whenever required.
Finally, yet importantly, I would like to express my heartfelt thanks to my beloved parents for
their blessings, my friends/classmates for their help and wishes for the successful completion
of this project.
ii
EXECUTIVE SUMMARY
India, with abundant sunlight, unutilized manufacturing potential, readily available labor and
significant demand for power, is one of the most promising markets for solar energy. The
country is currently the seventh largest producer of solar photovoltaic (PV) cells and the ninth
largest producer of solar thermal energy.
Most of the country receives 4-7 kWh of solar radiation per square meter per day. There are
250-300 clear sunny days in a year. This puts the countrys solar potential at around 600TW per
year.
Still, solar energy is not the most popular source of renewable energy in India.
The Government of India started focusing on the solar energy segment when the Ministry of
New and Renewable Energy (MNRE) launched a countrywide solar PV programme as a part
of its renewable energy programme. India has since transformed into a low-cost hub for
manufacturing solar PV cells and module, a proportion of which is exported to other
countries.
Till date, the union government has made various concessions for solar energy development
in India. The MNRE, in an effort to promote large-sized grid-interactive solar power
generation projects, introduced a generation based incentive (GBI).
In India various new schemes are coming very fast to promote solar power generation. These
schemes are to support various aspects of the solar generation like Financial- incentives, tax
benefits, Custom duty free, etc and Technological aspects of generation, grid connectivity
and metering, etc.
In the world various countries with lower solar irradiation and more problems have higher
installed capacity of the solar power generation. The policies used in these countries have
proved to be successful and can be implemented in India. Some of these have been covered
in this report.
iii
LIST OF FIGURES
iv
LIST OF TABLES
TABLE 3.3: Mission road map of JNNSM..19
TABLE 3.4: Phase I Batch I Bidding21
TABLE 3.5: phase I batch II Bidding24
TABLE 3.6: Livelization of tariff under Gujarat solar policy26
TABLE 3.7: Generation based incentives...34
ABBREVIATION
CEA...Central Electricity Authority
CERC..Central Electricity Regulatory Commission
EA 2003.Electricity Act 2003
FOR...Forum of Regulators
MWMega Watt
NEP...National Electricity Policy
OA..Open Access
Rs.Rupees
SERC...State Electricity Regulatory Commission
SLDC....State Load Dispatch Centre
STU...State Transmission Utility
GW...Giga Watt
AT&C...Aggregate technical and Commercial
MNRE..Ministry of New and Renewable Energy
vi
Table of contents
CHAPTER 1
INTRODUCTION
1.1 INDIA POWER SCENARIO ................................................................................................................. 1
1.2 SOLAR POTENTIAL IN INDIA ........................................................................................................... 2
1.3.OBJECTIVE ........................................................................................................................................... 3
1.4. SCOPE ................................................................................................................................................... 4
1.5. RESEARCH METHODOLOGY:.......................................................................................................... 4
1.6. ORGANISATION PROFILE ................................................................................................................ 5
CHAPTER 2
LITERATURE REVIEW
2.1 Electricity Act 2003- ............................................................................................................................... 8
2.2 National Tariff policy- ............................................................................................................................ 8
CHAPTER 3
JAWAHARLALNEHRU NATIONAL SOLAR MISSION
3.1. INTRODUCTION ............................................................................................................................... 10
3.2. OBJECTIVES AND TARGETS ......................................................................................................... 11
3.3. MISSION ROAD MAP ....................................................................................................................... 12
3.4. FRAME WORK FOR JNNSM ............................................................................................................ 13
3.5 NSM PHASE I BATCH I ..................................................................................................................... 18
3.6. NATIONAL SOLAR MISSION PHASE I BATCH II ....................................................................... 21
3.7. HIGHLIGHT AND COMPARISON OF PHASE I BATCH II BIDDING RESULTS....................... 24
CHAPTER 4
STATE LEVEL INITIATIVES AND DEVELOPMENTS TARGETS
4.1. THE GUJURAT SOLAR POLICY ..................................................................................................... 26
vii
CHAPTER 5
GENERATION BASED INCENTIVE UNDER RPSSGP SCHEME OF MNRTE
GENERATION BASED INCENTIVE UNDER RPSSGP SCHEME OF MNRE..................................... 32
CHAPTER 6
6.1. INTRODUCTION ............................................................................................................................... 35
6.2. GRID HYBRID ROOFTOPS .............................................................................................................. 38
6.3. AN INSIGHT INTO ROOFTOP PROJECTS ..................................................................................... 39
6.3.1 Delhis first utility-scale solar plant commissioned ....................................................................... 39
6.3.2 OMAX AUTOS LIMITED ............................................................................................................ 41
CHAPTER 7
BANKABILITY AND FINANCING IN INDIAN MARKET
7.1. INTRODUCTION ............................................................................................................................... 42
7.2. TERM AND CONDITION OF FINANCING ..................................................................................... 46
CHAPTER 8
FINANCIAL MODELING OF SOLAR PV POWER PLANT
8.1 INTRODUCTION ................................................................................................................................ 47
8.2. NEED FOR FINANCIAL MODEL .................................................................................................... 48
8.3. ADVANTAGES AND APPLICATIONS ........................................................................................... 48
8.4. FINANCIAL INDICATORS ............................................................................................................... 49
8.4.1. NET PRESENT VALUE(NPV) ................................................................................................... 49
8.4.2. INTERNAL RATE OF RETURN (IRR) ...................................................................................... 50
8.4.3. DEBT SERVICE COVERAGE RATIO (DSCR) ........................................................................ 51
8.4.4 WEIGHTED AVERAGE COST OF CAPITAL (WACC) ............................................................ 51
viii
CHAPTER 9
CONCLUSION AND RECOMMENDATION
9.1. CONCLUSION .................................................................................................................................... 55
9.2. LIMITATION ...................................................................................................................................... 55
BIBLIOGRAPHY
ix
CHAPTER-1
INTRODUCTION
1.1 INDIA POWER SCENARIO
Indias power sector has witnessed drastic changes in the past decade. The Electricity Act, 2003
paved way for the advent of reforms and competition in the power sector. A slew of policies and
regulations followed, to facilitate an accelerated growth in the sector. The process started with
the restructuring of power distribution utilities, with some states corporatizing the functional
entities for power generation, transmission and distribution.
The generation capacity of the country stands at over 203 MW (as in 31st May, 2012) with a
dominant share of the state sector. The private sector, which currently contributes 28% of the
generation capacity, is expected to increase its share to 52% by 2017. Even with such an installed
base, about 15% of the villages in India are non-electrified, which would translate to about 450
million people. With a growing economy, the demand for energy is growing at about 6% every
year and the peak load demand is expected to reach 778 GW by 2030.
PRIVATE
SECTOR
CENTRAL
SECTOR
28%
42%
STATE
SECTOR
30%
To meet the 778 GW demand for power by 2030, the government of India is planning heavy
investments in coal based generation, where cost of production is lower than any other source.
1.3.OBJECTIVE
The objective of the report is:1. To study and analyze the present condition of solar power in the country.
2. To know the details that what all work has been done in the solar sector.
3. To have an insight into what all problems are being faced by the solar project
developers.
4. To know the present status of the country compared to the internationally developed
countries in power.
5. To obtain the appropriate conclusions for proper development of solar power sector in
India.
6. To study the market from the perspective of the players who are developing solar power
plants.
7. To study the financial models of 1 MW solar PV plants.
1.4. SCOPE
With an ever increasing demand for power in the country, renewable energy plants with a
longer techno economic life have a better scope for taking up a larger share in addressing the
industrial & consumer demand for electricity without further affecting the eco system and
without compromising or depleting the non-renewable sources.
Thus there is ample scope for private players in the renewable energy space to be the preferred
but alternate route of power supply to cater to the industrial and economic growth.
The role of new and renewable energy has been assuming increasing significance in recent times
with the growing concern for the country's energy security. Energy self-sufficiency was
identified as the major driver for new and renewable energy in the country in the wake of the two
oil shocks of the 1970s. The sudden increase in the price of oil, uncertainties associated with its
supply and the adverse impact on the balance of payments position led to the establishment of
the Commission for Additional Sources of Energy in the Department of Science & Technology
in March 1981. The Commission was charged with the responsibility of formulating policies and
their implementation, programmes for development of new and renewable energy apart from
coordinating and intensifying R&D in the sector. In 1982, a new department, i.e., Department of
Non-conventional Energy Sources (DNES), that incorporated CASE, was created in the then
Ministry of Energy. In 1992, DNES became the Ministry of Non-conventional Energy Sources.
In October 2006, the Ministry was re-christened as the Ministry of New and Renewable Energy.
Mission
The Mission of the Ministry is to ensure
Increase in the share of clean power: Renewable (bio, wind, hydro, solar, geothermal &
tidal) electricity to supplement fossil fuel based electricity generation.
Energy Availability and Access: Supplement energy needs of cooking, heating, motive
power and captive generation in rural, urban, industrial and commercial sectors;
5
Energy Equity: Per-capita energy consumption at par with the global average level by
2050, through a sustainable and diverse fuel- mix.
Vision
To develop new and renewable energy technologies, processes, materials, components, subsystems, products & services at par with international specifications, standards and performance
parameters in order to make the country a net foreign exchange earner in the sector and deploy
such indigenously developed and/or manufactured products and services in furtherance of the
national goal of energy security.
Allocation of Business
The Ministry of New and Renewable Energy (MNRE) is a Scientific Ministry which has been
assigned the following subjects/business under the Allocation of Business Rules:
1. Research and development of Biogas and programmes relating to Biogas units;
2. Commission for Additional Sources of Energy (CASE);
3. Solar Energy including Solar Photovoltaic devices and their development, production
and applications;
4. Programme relating to improved chulhas and research and development thereof;
5. Indian Renewable Energy Development Agency (IREDA);
6. All matters relating to small/mini/micro hydel projects of and below 25 MW capacity;
7. Research and development of other non-conventional/renewable sources of energy and
programmes relating thereto;
8. Tidal energy;
9. Integrated Rural Energy Programme (IREP);
10. Geothermal Energy;
11. Bio-fuels: (i) National Policy; (ii) research, development and demonstration on transport,
stationary and other applications; (iii) setting up of a National Bio- fuels Development
Board and strengthening the existing institutional mechanism; and(iv) overall
coordination.
Functions
6
Facilitate research, design, development, manufacture and deployment of new and renewable
energy systems/devices for transportation, portable and stationary applications in rural, urban,
industrial and commercial sectors through:
1. Technology Mapping and Benchmarking;
2. Identify Research, Design, Development and Manufacture thrust areas and facilitate the
same;
3. Lay down standards, specifications and performance parameters at par with international
levels and facilitate industry in attaining the same;
4. Align costs of new and renewable energy products and services with international levels
and facilitate industry in attaining the same;
5. Appropriate international level quality assurance accreditation and facilitate industry in
obtaining the same;
6. Provide sustained feed-back to manufacturers on performance parameters of new and
renewable energy products and services with the aim of effecting continuous upgradation
so as to attain international levels in the shortest possible time span;
7. Facilitate industry in becoming internationally competitive and a net foreign exchange
earner especially through (ii) to (v) above and related measures;
8. Resource Survey, Assessment, Mapping and Dissemination.
9. Identify areas in which new and renewable energy products and services need to be
deployed in keeping with the goal of national energy security and energy independence;
10. Deployment strategy for various indigenously developed and manufactured new and
renewable energy products and services.
CHAPTER-2
REVIEW OF EXISTING LITERATURE
2.1 Electricity Act 2003Section 3. (1) says..The Central Government shall, from time to time, prepare the national
electricity policy and tariff policy, in consultation with the State Governments and the
Authority for development of the power system based on optimal utilisation of resources
such as coal, natural gas, nuclear substances or materials, hydro and renewable sources
of energy.
Section 4. Stipulates ..The Central Government shall, after consultation with the
State Governments, prepare and notify a national policy, permitting stand-alone systems
(including those based on renewable sources of energy and non-conventional sources of
energy) for rural areas.
Under section 6 of the act it is given as The Appropriate Commission shall, subject to the
provisions of this Act, specify the terms and conditions for the determination of tariff, for
the promotion of co-generation and generation of electricity from renewable sources of
energy
Under section 86 The State Commission shall promote cogeneration and generation of
electricity from renewable sources of energy by providing suitable measures for
connectivity with the grid and sale of electricity to any person, and also specify, for
purchase of electricity from such sources, a percentage of the total consumption of
electricity in the area of a distribution licensee
2.2 National Tariff policyPara 6.4 of National tariff policy on Non-conventional sources of energy generation including co
generation:
1.Pursuant to provisions of section 86 (1) (e) of the Act, the Appropriate
Commission shall fix a minimum percentage for purchase of energy from such sources
taking into account availability of such resources in the region and its impact on retail
8
tariffs. Such percentage for purchase of energy should be made applicable for the
tariffs to be determined by the SERCs latest by April 1, 2006.
It will take some time before non-conventional technologies can compete with
conventional sources in terms of cost of electricity. Therefore, procurement by
distribution companies shall be done at preferential tariffs determined by the
Appropriate Commission.
2. Such procurement by Distribution Licensees for future requirements shall be done,
as far as possible, through competitive bidding process under Section 63 of the Act
within suppliers offering energy from same type of non- conventional sources. In the
long-term, these technologies would need to compete with other sources in terms of
full costs.
3. The Central Commission should lay down guidelines within three months for
pricing non-firm power, especially from nonconventional sources, to be followed in
cases where such procurement is not through competitive bidding.
CHAPTER-3
10
Phase 1: Remaining period of the 11th Plan and first year of the 12th Plan (up to
2012-13)
Targets:
To ramp up capacity of grid connected solar power generation to 1000 MW within three
years by 2013.
Additional 3000 MW by 2017 through the mandatory use of the renewable purchase
Renewable Purchase Obligation (RPO) mandated for power utilities, with a specific solar
component.
11
Set up 20 million standalone rural solar power plants in special category states such as
Lakshadweep, Andaman & Nicobar Islands and Ladakh region of J&K by 2022.Border
areas would also be included.
To achieve 15 million sq. meters solar thermal collector area by 2017 and 20 million by
2022.
The ambitious target of 20,000 MW or more for 2022 will be dependent on the learning
of the first two phases, which if successful, could lead to conditions of grid competitive
solar power. The transition could be appropriately up scaled, based on availability of
international finance and technology.
Solar collectors
1000-2000 MW
4000-10000 MW
20000 MV
200 MW
1000 MW
solar
7
million
meters
square 15 million
meters
2000 MW
square 20 million
meters
square
For PV, the highest discount offered on the CERC tariff was INR 6.96 ($0.17) per unit
and the lowest successful discount was INR 5.15 ($0.12) per unit7. The tariff range is INR10.95
to INR12.76 ($0.27 to $0.31) per unit with an average tariff of INR12.16 ($0.30) per kWh. With
12
a 32.1% fall, the new tariff is significantly lower than the feed-in-tariff announced by CERC
earlier in the year. Some of the successful bidders include well known players such as
SunEdison, Azure Power Rajasthan, Mahindra Solar One and IOC Ltd. However, most of the
successful bidders are less well-known companies. The promoters behind these companies are
often unknown. Some of the larger industrial houses were not awarded projects as they did not
bid aggressively. A possible reason is that the 5MW cap on projects made them too small to be
of any interest. Such companies are instead looking at 10-15 MW projects available under state
programs. A total of 21 successful NSM bids are for projects in Rajasthan. Eight of these are for
a single district, Nagaur, followed by five in Jodhpur and four in Jaisalmer. Other projects are
located in the states of Tamil Nadu, Andhra Pradesh, Karnataka and Maharashtra8.
For CSP projects, the highest discount offered was INR 4.82 ($0.12) per unit and the lowest
was INR 3.07 ($0.07) per unit9. All CSP projects have made use of accelerated depreciation of
80% in the first year. Therefore, the base feed-in-tariff was INR 13.45 or $0.33 (without
accelerated depreciation the feed-in-tariff was INR 15.40 or $0.38). The new tariff range taking
into account accelerated depreciation is therefore INR 8.63 to 10.38 ($0.21 to 0.25) per unit.
With an average tariff of INR 9.50 ($0.23) per unit, the new tariff is 29.3% lower than the
original base feed-in-tariff.
3.4. FRAME WORK FOR JNNSM:
The National Solar Mission, being a country level initiative that has ambitious targets of a
large magnitude, demanded an effective implementation framework to ensure successful fruition.
The government has responded to this demand by putting a robust institutional framework in
place for the effective implementation of the Mission. The following figure gives a description of
the institutional framework in place and identifies the various agencies involved along with their
roles:
13
Ministry of Power:
The Ministry of Power (MoP), directly under the purview of the Government of India, is
primarily responsible for the development of electrical energy in the country.
It plays a significant role in the implementation of JNNSM. The ministry through NTPC; a major
entity involved in the execution of the JNNSM, has appointed NVVN, a fully owned subsidiary
of NTPC, for entering into PPAs and power sale agreements (PSAs) with power developers and
state utilities respectively. The Mission states that in order to incentivize a large number of solar
power projects and minimize tariffs, solar power will be bundled with cheap unallocated power
from central power stations and then sold to distribution utilities. The Ministry is responsible for
allocating an equivalent megawatt capacity, from the Central unallocated quota to NVVN for
bundling together with solar power.
CERC:
CERC, the chief regulatory body in the country, issues guidelines for fixing feed-in-tariff for
purchase of solar power taking into account current cost and technology trends. Under the
14
National Solar Mission guidelines, CERC has been mandated to provide the benchmark tariff for
selection of projects under the bundling scheme. CERC has also been entrusted to discharge the
formulation of guidelines and solar specific regulations in order to achieve 3% solar RPO by
2022. Additionally, the CERC also notifies the Ministry of Power about the rates at which the
unallocated power from the Central quota is to be bundled with solar power and sets durations
for the PPA between NVVN and the project developers.
NTPC:
Set up in 1975, NTPC is Indias largest power company. Apart from power generation, which
is the mainstay of the company, NTPC has also ventured into consultancy, power trading, ash
utilization and coal mining.
NTPC has a total installed capacity of 34,854 MW. NTPC has 15 coal based and 7 gas based
stations, located across the country, under its purview. In addition, under joint ventures, there are
5 coal based stations & another naptha/LNG based station. The company has set a target to have
an installed power generating capacity of 1,28,000 MW by the year 2032. The capacity, it is
envisaged, will have a diversified fuel mix comprising 56% coal, 16% gas, 11% nuclear and 17%
renewable energy sources (RES) including hydro. NTPC plans to expand its non fossil fuel based
generation capacity to nearly 28% of its portfolio by 2032.
NVVN :
NVVN is a fully owned subsidiary of NTPC engaged in the business of power trading. The
Mission provides for NVVN to be the designated nodal agency for procuring the solar power by
entering into a PPA with solar power generation project developers who will be setting up solar
projects during the next two years, i.e., before March 2013 and are connected to the grid at a
voltage level of 33 kV or above. For each MW of installed capacity of solar power for which a
PPA is signed by NVVN, the Ministry of Power shall allocate to NVVN an equivalent amount of
MW capacity from the unallocated quota of NTPC coal based stations and NVVN will supply
this "bundled" power to the distribution utilities.
the bundled power for meeting their RPOs as mandated under the Electricity Act, 2003. Further,
the Mission document states that at the end of the first phase, well-performing utilities with
proven financial credentials and demonstrated willingness to absorb solar power shall be
included in the scheme, in case it is decided to extend it into Phase II.
Policy incentives:
Guidelines laid out by the JNNSM and the NVVN Mission statements have raised large
business opportunities within the country. JNNSM Mission document, in particular,
encompasses the objective of maximizing indigenous content which, it is envisaged, will lead to
the establishment of manufacturing facilities as well as R&D centres in the country. However,
the issue of domestic content restrictions laid out by the Mission is an important concern. The
following diagram highlights this challenge.:
16
17
pv segment
CSP segment
Benchmark tariff Rs
17.91/Kwh
Benchmark tariff Rs
15.40/kWh
150 MW on offer
500 MW on offer
maximum size for a PV bid-100MW
Reverse Bidding
PV segment
CSP segment
19
PV projects worth a cumulative capacity of 150 MW and seven CSP projects worth a cumulative
capacity of 470MW were selected under Batch I of the scheme. Remarkably, the bidding process
did result in exceedingly competitive bids. PPAs have been signed at an average levelized tariff
of Rs. 12.16 / kWh for PV projects and Rs. 9.50/ kWh (taking accelerated depreciation into
account) for CSP (thermal) projects, i.e., the government has secured 32.1% and 29.3% discount
respectively in PV and CSP projects.
Among solar PV projects, the highest discount offered during the round of bids invited for the
first batch of Phase I was Rs 6.96/ kWh whereas the lowest successful discount offered was Rs
5.15/ kWh. Therefore, the tariffs varied from Rs 10.95/ kWh to Rs 12.76/ kWh. Notably, most of
the successful bidders were new players in the sector. It can be deduced that the larger industrial
houses failed to qualify as they did not bid aggressively, partly because of the 5 MW cap
imposed on the size of the projects, presumably rendering the size of the project vis--vis the
organizational commitment required, unattractive. New entrants have, as has emerged, made
good use of the opportunity afforded by the minimal pre qualification requirements in the policy.
For example, there was an absence of any technical experience requirements in the Policy. The
policy merely required a bank guarantee of Rs 3 million per MW along with unconsolidated,
audited accounts for the last four years as a proof of the net financial worth of the companies.
Among CSP projects, the highest discount offered was Rs 4.82/ kWh while the lowest
successful bid was for Rs 3.07/ kWh. As such, the average discount offered on the benchmark
tariff of Rs 15.40/ kWh was Rs 3.65/ kWh. Notably, all CSP projects have made use of the
accelerated depreciation of 80% in the first year. Consequently, the base feed-in-tariff before
discount worked out to Rs 13.45/ kWh instead of Rs 15.40/kWh. The new tariff range taking into
account the accelerated depreciation was from Rs 8.63 to Rs 10.38 per kWh and the average
tariff offered was Rs 9.50/ kWh.
20
PV segment
Reverse Bidding
PV segmeent
21
Plant capacity could be in multiples of 5 MW. In other words, a developer could bid for
projects of size 5 MW, 10 MW, 15 MW or 20 MW.
Winners of projects under the previous round of bidding or under the Gujarat Solar
Policy were allowed to bid for these projects.
A company in any form (including parent, affiliate, ultimate or any group company)
could bid for a maximum of 3 projects totalling 50MW.
Financial Criteria for bidding: The net worth of the company was required to be greater
than or equal to the value calculated at the rate of Rs 3 crore per MW of the project
capacity up to 20 MW. For every MW additional capacity beyond 20 MW, an additional
net worth of Rs 2 crore had to be demonstrated.
Foreign companies could participate in the bidding process. But before signing of the
PPA, the policy mandated such companies to form an Indian company registered under
the Companies Act ,1956.
Deadline for achieving financial closure has been raised to 210 days (7 months) from the
earlier 180 days (6 months). The timeline for the commissioning of the project has also
been extended by a month to 13 months from the date of signing PPA from 12 months
earlier.
Part commissioning of the Project shall be accepted by NVVN subject to the condition
that the minimum capacity for acceptance of part commissioning shall be 5 MW and in
multiples thereof. The PPA will remain in force for a period of 25 years from the date of
acceptance of respective part commissioning of the project.
As per the revised guidelines, the controlling shareholder of the project must now
maintain 50% share for 1 year (up from 26% earlier)
Domestic requirement Both cells and modules have to be manufactured in India. This
domestic content requirement does not apply for thin film and Concentrating
Photovoltaic (CPV) technologies.
The bidder will have to deploy only commercially proven technology those that have at
least one project successfully operational for at least one year, anywhere in the world.
22
Crystalline Silicon and most of the Thin Films Technologies (CdTe, CIGS, a-Si) easily
meet this criteria.
Interconnection point or metering point shall mean the point at 33kV or above where the
power from the solar power project is injected into the CTU or STU transmission system.
The Project Developer shall submit the RfS within 30 days of the invitation by NVVN
The Project Developer shall submit non-refundable processing fee of Rs. 1 Lac for each
Project along with the RfS.
Interconnection with the DISCOM network may be accepted in exceptional cases where
the DISCOM is the ultimate buyer of the entire quantity of power from that project; and
NVVN has signed Power Sale Agreement with that DISCOM and DISCOM agrees to an
agreed interconnection point and at an agreed voltage. This arrangement would be subject
to arrangement of energy accounting with the SLDC.
The entire cost of transmission including cost of construction of line, wheeling charges,
losses etc. from the project up to the interconnection point will be borne by the Project
Developer and will not be reimbursed by NVVN or met by the STU/DISCOM. This
connectivity can also be achieved through a shared line with any agency or any existing
line of DISCOM or STU, provided the energy accounts are bifurcated and clearly
demarcated for the power generated at solar project and are issued by the STU/ SLDC
concerned.
Short listing. In the event, the total aggregate capacity of the Solar PV Projects shortlisted by NVVN in Second Batch is higher than 350 MW or the capacity available and
disclosed at the time of short-listing, the final selection of the Projects from the list of
short-listed projects shall be done on the basis of discount to be offered by Project
Developers on CERC Approved Tariff as applicable on the date of submission of bids as
detailed in the next sub-section.
The Projects offering the maximum discount in Rs/kWh on the CERC Approved
Applicable Tariff would be selected first and so on.
23
Bid Bond:
Sr.no
1.
Up to 10% or 10%
Rs. 10000
2.
Rs. 20000
3.
Rs. 30000
4.
Rs. 40000
5.
Rs. 50000
Batch I. Such a steep drop in tariffs, that too within a short of one year, augurs well for the
Indian solar industry and may to some extent be attributed to the adaptive policy framework.
Hence Other Developers such as Welspun quoted for 3 Projects at Rs.7.97, Rs.8.05 & Rs.8.14
respectively, Sun Edison at Rs.9.28 Mahindra Bids at Rs.9.34, Sai Sudhir at Rs.8.22, VS Lignite
at Rs.8.54, Sunborne Energy at Rs.8.99. Azure Power quoted at a price of Rs.7.91 (50 MW),
Sujana Energy at 9.09,and Kiran Energy quoting Rs.9.34 for a 50 MW Project.
For example, besides prevalent market conditions such as dropping module prices, we
understand that by relaxing the 5MW size capping on PV projects to 20MWlarger companies
were encouraged to participate and it was one of the contributing reasons that resulted in
aggressive discounts. Some of the other highlights of Batch II bidding were:
As many as five developers have won bids in both rounds of JNNSM bidding. This goes
to show that developers are confident of sustaining their projects even at tariffs that are
still widely considered to be too low to guarantee viability.
The lowest quoted tariff in Batch II bidding is approximately 32% lower than lowest
tariff quoted in Batch I, Similarly, the highest quoted winning tariff is lower by nearly
26%.
CHAPTER-4
STATE LEVEL INITIATIVES AND DEVELOPMENT TARGETS
Spurred by national level initiatives and policy push, several states like Gujarat, Rajasthan,
Madhya Pradesh, Karnataka and Jammu & Kashmir have also formulated and adopted solar
policies for development of solar energy projects in their respective states. Salient Features of
these policies have been discussed herewith.
years
Tariff(per kWh)
Levelized
kWh)
tariff(per
PV
1-12
13-25
Rs.15
Rs.5
Rs 13.30 for 25
years
CSP
1-12
13-25
Rs.12
Rs.3
Rs.10.54
years
for
25
PPAs as early as January 12th 2009, many awaited the formalization of the NSM as its draft
policy indicated a more attractive tariff of INR 17.91 ($0.44) per kWh for PV and INR 15.40 for
CSP. Until late 2009, many developers had not signed PPAs in Gujarat. After the NSM policy
was formalized in December 2009, developers moved away from Gujarat towards the NSM. In
the first phase of the Gujarat policy, only 396.5MW worth of PPAs were signed out of 716MW
allotments, leading to a conversion rate of 55% (PPAs signed as a percentage of projects
allotted).
The tremendous interest from developers from the NSM let to the competitive bidding for
projects and a subsequent fall in tariffs. The fall in the NSM tariff below the levelized tariff in
Gujarat suddenly made the Gujarat policy very attractive again to developers. Further, a
significantly higher feed-in-tariff in the first 12 years in Gujarat matches investors timelines, as
they would look to cover the cost of debt during this period.
To ensure developer commitment, Gujarats solar policy for the second phase has been
amended to include a deposit that would be encashed, if the developers fail to sign the PPAs.
Larger available project sizes and the relative ease of land acquisition have seen the larger
developers getting serious about the Gujarat policy, signing PPAs and starting the
implementation of projects. This has led to an increase in the conversion rate from 55% to 95%,
with 537MW worth of PPAs signed for 565MW of the projects allotted. With an increase of over
44% in the number of PPAs signed, Gujarat significantly improved the credibility of its solar
program from the first to the second phase.
As compared to the NSM, the Gujarat policy has longer timelines for the execution of the
projects. At the same time, it has a stringent penalty mechanism for delays and intends to levy
penalties on redundant projects. Delays in commissioning the projects can incur penalties of INR
10,000 ($250) a day per MW for the first 60 days and INR 15,000 ($375) thereafter. The
enforcement of these penalties is yet to be decided on. An initial 48.5MW of the first phase were
required to be commissioned by December 31st 2010. However, a 5MW project by
LancoInfratech and a 1MW project by SunEdison were the only ones that have met their
deadlines. Six projects, including a 10MW solar PV project by Zebasolar and projects by Azure
27
Power and Dreisatz GmbH were delayed despite their initial commitment to start operations
(please refer to Appendix A for a complete list of projects in Gujarat).
On December 29th 2010, Indias first solar park was inaugurated at Charanaka in Patan
district of northern Gujarat. So far, land has been allotted in the solar park for projects worth
176MW to 16 companies from the first and second phases. The total capacity of the solar park is
500MW with 30,000 sq. m per MW land allotted to CSP and 20,000 sq. m per MW of land
allotted to PV projects. The solar park has been financed with over INR 12 billion ($300m) by
financial institutions like the International Finance Corporation (IFC), the Asian Development
Bank (ADB) and the Infrastructure Development Finance Corporation (IDFC).The park tackles
land procurement, water availability and grid connectivity issues and offers a single-window
clearance process. Sixteen companies, including SunEdison Energy India (25MW), Alex Astral
Power (25MW), Roha Energy (25MW), GMR Gujarat Solar (25MW), Kiran Energy (20MW),
Emami Cement (10MW) and Azure Power (5MW) have been allotted projects worth a total of
176MW in the park.They have all signed PPAs with the state government.
28
project sizes will attract small as well as large developers looking to invest in projects of
different scale.
The Rajasthan Renewable Energy Corporation Limited (RRECL), the nodal agency
responsible for implementing the states solar policy, has published the revised draft for the
Request for Selection (RfS) document for 250MW worth of projects in July 201113. The revised
draft incorporates some crucial suggestions from industry players and will most likely be
released as the official document to be used by developers looking to submit their bids for
projects under the Rajasthan solar policy. The RRECL has also published the draft for the Power
Purchase Agreements (PPA) for these projects.
According to the draft document, the competitive bidding for the 250MW worth of projects
will include 50 rooftop projects of 1MW each, 100MW of Solar PV and 100MW worth of CSP
projects. The bidding will take place in the latter half of September this year, while the period for
submission of the bids will be from August to September. The benchmark tariffs offered are
INR15.32 ($0.38) per kWh for PV and INR12.58 ($0.31) per kWh for CSP projects for 25 years.
Developers will be required to offer discounts on these in order to win the bid. Bids are open
to both Indian as well as international companies. Out of the 250MW being auctioned, a single
parent company can bid for 61MW worth of projects - one rooftop project of 1MW, up to 10MW
worth of PV and 50MW of CSP projects.
Unlike the National Solar Mission, there is no domestic content requirement in the Rajasthan
solar policy. The developer can choose any established and operational technology from India or
abroad. The draft also gives clear parameters for setting up evacuation infrastructure from the
plant to the nearest substation. This has been an issue between the distribution utility and
developers in other solar policies. For solar PV and CSP projects, if the power plant lies within
15km of the nearest substation, the cost will be borne by the distribution company (DISCOM).
For any length above 15km, the cost will be borne by the developer. For rooftop projects, the
cost will be borne by the DISCOM but the developer will need to take permission from the
DISCOM before finalizing the location of the project.
29
The policy has taken up lessons from forerunners like the NSM and the Gujarat solar policy it declined to have the 5MW limit on individual projects that made the NSM less attractive to
large players but, unlike the Gujarat policy, it has placed fixed limits on overall capacity
allocation. The policy also addresses the concerns of the developers, with regards to the
allocation of land and water, availability of an evacuation network and the localized supply
chain. Finding the right location and acquiring land is one of the major bottlenecks so far for
projects in India. To solve this problem, the policy looks to create land banks from government
land. Some of these land banks are situated near cities like Bikaner and Barmer. Under the
policy, after the 25 years of the PPA, the developer can use the land for commercial.
be a hub of conventional power generation in India with an installed capacity of around 38GW
by 2017. The significant increase in conventional power generation will increase the states
RPOs manifold. This is expected to create a tremendous opportunity for solar power
development in the state.
The DISCOMS may provide concessions on the electricity bills of house owners based on their
earnings from the sale of electricity generated by their rooftop solar systems. North Delhi Power
Limited (NDPL), a distribution company owned by the TATA group, is currently trying to
implement this model. The company has approached its customers with an offer to install solar
rooftop projects for which the house owners will get a fixed rent. The billing for the amount of
power the house owner consumes from NDPL will be done based on the net metering system
according to the State Grid Code. NDPL targets 100MW through rooftop installation in the next
two financial years. Other DISCOMS have shown a lack of initiative in the absence of fixed
RPOs by the state government. The state government has initiated the process of enacting the
statesRPO. The draft of the policy is with the Delhi Electricity Regulatory Commission (DERC)
for approval.
31
CHAPTER-5
The Project Proponents would be selected as per these guidelines for development of
solar power projects to be connected to distribution network at voltage levels below 33
kV.
The projects should be designed for completion before March 31, 2013.
The local distribution utility in whose area the plant is located, would sign a Power
Purchase Agreement (PPA) with the Project Proponent at a tariff determined by the
appropriate State Electricity Regulatory Commission (SERC).
Project schemes from States wherein Tariff tenure for duration of 25 years with Tariff
structure on levellised basis has been determined by SERCs shall alone be considered to
be eligible to participate in this Programme (RPSSGP).
Generation Based Incentive (GBI) will be payable to the distribution utility for power
purchased from solar power project selected under these guidelines, including captive
consumption of Solar Power generated (to be measured on AC side of the inverter).
The GBI shall be equal to the difference between the tariff determined by the Central
Electricity Regulatory Commission (CERC) and the Base Rate, which will be Rs 5.50
per kWh (for Financial year 2010-11), which shall be escalated by 3% every year.
GBI shall be payable to the distribution utility for period of 25 years from the date of
commissioning of the project.
IREDA has been designated as 'Programme Administrator' by the Ministry of New and
Renewable Energy for administering the generation based incentive programme for
rooftop PV and other small solar power plants.
32
The Projects under these guidelines fall within two broad categories:
1. The projects connected to HT voltage at distribution network (i.e. below 33 kV)
2. The projects connected to LT voltage i.e. 400 volts (3-phase) or 230 volts (1-phase).
Accordingly, the projects have been divided into following two categories.
The Projects with proposed installed capacity of less than 100 kW and connected
to the grid at LT level (400 Volts for 3-phase or 230 V for 1-phase) shall fall within this
category.
Projects connected at LT level of distribution network with installed capacity lower than
100kW.
33
Sr.no
Project category
Capacity limit
90MW
2 MW
Projects Connected at LT Level of Distribution
2.
10MW
34
CHAPTER-6
6.1. INTRODUCTION
India could potentially generate over 230 GW of power just from putting up solar panels on the
rooftops of all households and institutions. However, in its quest for large-scale utility grade
solar power to drive volumes, the government has so far ignored the potential of rooftop solar
power.
The Jawaharlal Nehru National Solar Mission (JNNSM), the flagship programme for the
development of solar power in India, provides for only 10 per cent of the first phase target to
come from rooftop power projects, a target that is woefully limited in its ambition and horizon to
showcase the real potential of rooftop solar power. The mission has awarded 78 projects across
12 states for 98 MW of rooftop capacity, of which only 3 projects are below 1 MW range.
In fact, India is probably the only country that is set to make significant process in solar power
without a significant rooftop programme. Industry experts tend to agree that this has been a
missed opportunity as far as JNNSM or the countrys overall solar plans are concerned. The solar
industry in Europe has grown primarily because of solar rooftop installations and not large-scale
utility plants. In fact, over 90 per cent of global solar installations are based on rooftop.
Even the small achievement that India has made on this front has been in the non-residential
segment, which is unlike what the experience has been internationally. Globally, solar rooftops
largely mean households installing PV panels on their rooftops and supplying the power
generated to the utility grid. In India, almost all the projects undertaken in this space have been
for the non-residential segment. This, in a scenario where the residential/household segment
alone accounts for over 180 GW of rooftop potential, of which 110 MW is in urban centers alone
35
as per analysis taken by Lanco Solar, based on 2011 census data. Given the high level of
economic growth witnessed in urban India during the past 10 years and the potential for rooftop
power generation through solar panels, this estimate is bound to go up significantly.
36
the state is also encouraging commercial establishments and new residential societies to install
solar panels.
The success of West Bengals net metering model has encouraged several other states to develop
their own solar rooftop programmes. The Tamil Nadu Electricity Board, for instance, is likely to
introduce the net metering scheme wherein residents will soon be able to generate electricity
through rooftop units. The state government is also planning to install meters at distribution
transformers and feeders, and use it for meter reading and billing. The Karnataka government
also has plans to install solar panels on major state buildings and public utilities.
Under its recently announced solar city project, the state government is planning to install PV
panels with a capacity 0f 2-5 kW on rooftops of over 10,000 houses in Bengaluru for residential
use, with the leftover energy to be fed into the state grid.
In February 2011, the Delhi government came up with a cabinet note to install solar power units
on rooftops of households across the capital. As per the draft policy, home owners can either
lease their roofs to a developer, who can then set up the unit, or they can pay 30 per cent of the
installation cost. The remaining 70 per cent could be financed through banks. The owners can
keep Rs 17 per unit for power produced through the solar panels, which would be fed directly
into the grid. The DISCOM stand to benefit too. Since the power produced from these units is
expected to be expensive, DISCOM will get about Rs 13 per unit as subsidy from the
government. The state government which plans to spend Rs 4.7 billion over 27 years for this
purpose is currently working out the final modalities of the schemes benefits.
In fact, Delhi already has an operational grid-connected project at the Thyagaraj Stadium that
hosted the netball event in the Commonwealth Games 2010. Implemented and commissioned by
Reliance Industries Limited, the 1 MW solar plant was built on the rooftop, using a total of 3,640
modules of 280 W. The project is expected to generate around 1.4 million kWh of electricity per
year to fulfill the power requirements of the stadium, with surplus electricity being fed into the
grid at 11 kV. Another initiative came from North Delhi Power Limited (NDPL) that installed
rooftop solar panels at seven places in Delhi. Most of these projects have been implemented on
existing substations/warehouses owned and operated by NDPL. The electricity generated is fed
directly into the utilitys grid. So far,
37
NDPL has installed around 1.2 MW of solar rooftop capacity and is in the process of installing
five more rooftop projects in the National Capital Region, aggregating 300 kW.
These projects, which have been by the utilitys internal accruals and without any subsidy from
the MNRE, are part of the DISCOMs renewable power obligation target.
connected PV system (at Rs 100 million) for captive usage in its Manapakkam, Chennai campus
in December 2009. The project availed 80 per cent accelerated depreciation benefit as per the
government guidelines. This was further scaled up to 1 MW in the next year. Also, in Delhi,
Kolkata, Bangalore, and Mumbai, malls and residential developers are considering implementing
rooftop solar energy units. One example is DLF, which implemented a solar unit at a Gurgaon
shopping centre and is now considering similar investments across its various shopping centres.
39
Project details:
Tata BP Solar provided engineering, procurement and construction services as well as equipment
for the project. The company was selected as the project developer through a competitive
bidding process. As the module supplier, Tata BP Solar is also subject to performance guarantees
for the project. The plant was commissioned at a total cost of Rs 140 million and was financed
through internal accruals.
The solar panel at the plant consists of 5,506 crystalline silicon modules of 180 kWp each.
The panel has four 250 kVA inverters manufactured by ABB and is designed to work for 25
years with minimal maintenance needs such as dusting and cleaning. A common bottleneck in
developing solar power projects is the issue of land acquisition. The high cost of land, especially
in cities like Delhi, makes such projects financially unviable. NDPL, however, did not face this
problem. Land for the plant site, which spans a total area of 13,000 square metres, was in the
companys possession as Delhis distribution licensee.
Moreover, NDPL developed a novel solution to utilize the arrangement of solar arrays as covers
storage, thereby doubling the use of the available land. The solar panel was built on the rooftop
of an open storage area, which was converted into a closed area for erecting the plant. A 925
million tonne steel structure, nearly 10 metres high, was designed and erected. It took the
company 10 months to commission the project as it involved the mounting of solar panels at a
height of about 10 metres
The plant is designed to produce 1.58 MUs of electricity annually and is currently generating
2,000-6,000 units of power per day. It is located at the Keshavpuram site of NDPLs distribution
circle, where the average daily insolation is estimated at 5.06 kWh per square
metre. At this insolation level, the company is expecting a plant load factor (PLF) of 18 percent
in the first year and an average PLF of 17 per cent over the 25 years of project life.
Currently, PLF is being recorded on a daily basis and is in the range of 16-18 per cent.
Accordingly, the cost of generation is estimated at Rs 10-Rs 12 per unit. The generation arm of
NDPL, which was responsible for setting up the project, will sell power to the companys
distribution division.
Four 250 kVA transformers are used to step up the voltage from 330 V to 415 V, while one
1,250 kVA transformer is used to step up the voltage to 11 kV. The output is synchronized to
40
NDPLs distribution network. Also, a central control room equipped with a micro supervisory
control and data acquisition system has been installed in order to monitor the generation of this
plant as well as NDPLs other small PV plants.
41
CHAPTER-7
7.1. INTRODUCTION
Bankability remains an issue for the vast majority of the 1,637.5MW worth of projects with
signed PPAs at the moment in India. Project developers are finding it difficult to attain financial
closure for projects under the NSM as well as the Gujarat Solar Policy. Especially difficult is
obtaining non-recourse debt financing.
Project financing is difficult because lenders feel uncomfortable with the level of risk in the
industry. With a lack of reliable irradiation data, it is difficult to calculate the generated output
and therefore, the return on investment. There are so far only a few projects in the country that
provide actual generation data as a reference. In addition, the majority of developers are new
entrants with no track-record to prove their ability to build and operate solar power plants. Indian
commercial banks are unsure about the generation capacities of power plants and hesitant to
extend debt to projects.
The banks are also concerned about the reliability of the PPAs. The power sector in India is
heavily subsidized and makes large losses. As a result, public power utilities have poor financial
health and a dearth of financial resources. The market perceives a risk that the utilities will
dishonor the PPAs and default on their payments. Given the present structure of the PPAs, the
risk of payment default by the utilities is passed on to the developers. There is a significant
counter-party risk for both Indian and overseas banks if they extend debt to projects.
For projects under the NSM, banks are especially wary of the heavily discounted tariffs that have
arisen from the bidding process. The present tariffs are among the lowest in the world for solar,
and banks are concerned that the project risks have been underestimated in order to win bids.
Banks are also wary of the small margins that projects are looking to operate on in order to be
42
viable at such low tariffs. In addition, the small size of the PV projects (5MW) is creating
unattractively high transaction costs for larger banks.
Considering the large number of projects waiting to attain financial closure and begin
construction, there is an immense pressure on the market to explore options other than nonrecourse project financing.
A majority of large players are taking loans based on the strength of their balance sheets while
providing corporate guarantees. Some players are in a large part funding their projects
themselves through equity. Overseas private equity funds also are actively investing in
companies to channel funds into projects that can provide a high rate of return. An example is
Kiran Energy which has received investments of nearly INR 1.2 billion ($30m) from three
overseas private equity players namely New Silk Route, Bessemer Ventures and Argonaut
Ventures for a majority stake in the company. It has signed PPAs for a 20MW PV project in the
second phase of the Gujarat Solar Policy.
Some investors with a stake in project development companies such as Kiran are looking to
monetize their investments about two years after commissioning, either by restructuring their
stakes into debt or issuing bonds. They would ideally look to sell back the stake to the developer
who would fund the buy-back through debt. The expectation is that two years into the running of
projects, banks would be more comfortable with the reliability of output and would be willing to
provide debt.
External credit agencies (ECA) are playing an increasingly prominent role in financing projects.
Components for projects have to be bought from a company in the domestic market of the
agency and debt is provided for 80-90% of the technology. These include agencies such as
Frances COFACE, Germanys KfW-IPEX Bank, the United States Export-Import Bank (US
Ex-Im Bank) and Israels Foreign Trade Risks Insurance Corporation. Reliance Power for
example has received INR 240 billion ($600m) from the US Ex-Im Bank, part of which will be
used to fund its solar projects in India. Such loans are for an eight to ten year period with
LIBOR-based interest rates averaging around 5%. While such rates are significantly lower than
the domestic lending rates of nearly 12%, high costs of 6-8% for hedging against foreign
exchange risk can make the advantage negligible.
Developers are also looking at obtaining debt from development agencies like the IREDA and
the private investment arms of international organizations like the International Finance
43
Corporation. International development organizations like the World Bank, the KfW Bank and
the Asian Development Bank provide large funds at low interest rates to IREDA which are then
available for projects (in such cases too, the considerable hedging costs reduce the advantages of
lower foreign lending rates). Such funds are backed by credit guarantees from these banks with
the intention of making lending to projects viable. However, many developers approaching
IREDA for funding do not provide adequate project information, fall short on regulatory
clearances or lack a track-record. As a result, only a limited number of projects have been able to
raise debt through this route. A 5MW PV plant, jointly being developed by Astonfield from India
and Spains Grupo T-Solar, has secured a 14-year combined loan on a non-recourse basis from
SBI Capital and the Export-Import Bank of India. The project is located in Osiyan in the western
Indian state of Rajasthan and falls under the Migration Scheme of the NSM. This is the first solar
project in the country to obtain a long-term loan and one of only three in the country that have
secured non-recourse project financing. The other two are a 10MW plant by Azure Power
financed by the Overseas Private Investment Corporation and a 10MW plant by SunEdison
financed by unnamed equity investors, both in the western Indian state of Gujarat. As a project
under the migration scheme of the NSM, it will receive a feed-in-tariff of INR17.91 ($0.44) for
25 years. The high feed-in-tariff increases the economic viability of the project and thereby
makes it easier for the two banks to extend non-recourse debt.
In order to reduce the payment default risks inherent in the PPAs with financially weak State
Electricity Boards (SEBs), the central government on June 2nd 2011 approved a Payment
Security Scheme worth INR4.86 billion ($121m) for projects under Phase 1 of the NSM. The
scheme will be implemented by the Ministry of New and Renewable Energy (MNRE), which
will allocate the funds to the NTPC VidyutVyapar Nigam (NVVN) through a Solar Payment
Security Account (SPSA). Given that the government is often slow to react to market
requirements, this is a significant and timely policy impetus from the government to provide
banks with the confidence to invest in solar projects.
Despite these developments, the bankability of the projects under the NSM and the Gujarat Solar
Policy remains an issue. Banks are still concerned about the larger package of risks that include
the lack of performance data and the inadequate track-record of developers. However, developers
that are partnering with established EPC companies and module manufacturers, mostly from
abroad, are now being considered very seriously by banks for project financing. Performance
44
guarantees from EPC companies and output guarantees by the module manufacturers are a
necessity as well. In general, Indian banks take a more positive view on financing solar power
projects. At the moment, they feel over-exposed to the conventional power sector and want to
diversify their portfolio into the renewable energy space. Given the technology risks, banks are
able to apply margins of up to 300 basis points on their debt. This offers potentially attractive
profit opportunities to those banks that are able to clearly circumscribe and limit the risks. To
further cover the risks, banks are incorporating strict default clauses in the contracts. In the case
of non-recourse financing, these could, for example, allow them to automatically receive project
equity if the actual electricity generation does not match the originally projected numbers.
From the point of view of project developers, in order to successfully raise debt from banks, the
focus should be on comprehensive and accurate Detailed Project Reports (DPRs) that form the
basis for a strong business case for their projects. In addition, they need to have all the required
regulatory clearances and statutory permits. Both these requirements are currently not easily met
by Indian developers as the entire industry as well as the government still lacks the experience
and established processes. A further boost for bankability would come from more reliable
irradiation data. Currently, there is an up to 30% variation between the satellite data provided for
example by the National Renewable Energy laboratory (NREL) of the U.S. Department of
Energy and the MNRE, and on the ground measurements. At the moment, the Indian
Meteorological Department manages a network of 45 radiation monitoring stations across India,
of which New Delhi, Patna, Jaipur and Thiruvananthapuram have data loggers installed. In
addition to these stations, the MNRE is currently in the process of establishing 50 new stations
across the country through the Centre for Wind Energy Technologies (CWET) in Chennai.
CWET is an autonomous body under the MNRE and has pioneered wind data measurement,
monitoring and modeling. It is expected to take over a similar role for Indian solar radiation
monitoring as well.
In the short-term, very few developers will be able to obtain non-recourse debt finance,
especially from Indian commercial banks. Some of the larger players will be able to finance
projects through a combination of balance-sheet financing, equity participation and loans from
various ECAs.
45
46
CHAPTER-8
8.1 INTRODUCTION
1. Financial modeling is an integrated part of financial planning.
2. It uses the past data to estimate the financial requirements.
3. The model makes it easy for the financial managers to prepare financial forecasts.
Financial Model has three parts
Input
1. Cost related to the Project.
2. Guidelines of regulator related to the Project
3. Terms and condition of the company.
4. Existing financial rules & regulations.
5. Taxation and Corporate laws.
Model
1. It defines the relation between financial variables and develops appropriate equations.
E.g. net working capital and fixed assets investment may be related to sales.
2. When one independent variable changes the corresponding variable also changes.
Output
1. Applying the model equations to the inputs, output in the form of projected financial
statements are obtained.
2. The output shows the investment and funds requirements given the sales objective and
relationship between the financial variables.
3. The use of excel applications can help develop the financial model.
47
48
Where
t - The time of the cash flow
n - The total time of the project
r - The discount rate
Ct - the net cash flow (the amount of cash) at time t.
C0 - the capital outlay at the beginning of the investment time (t = 0)
The Discount Rate
Choosing an appropriate discount rate is crucial to the NPV calculation. A good practice of
choosing the discount rate is to decide the rate which the capital needed for the project could
return if invested in an alternative Venture.
Relationship between the NPV and Discount rate
For some professional investors, their investment funds are committed to target a specified
rate of return. In such cases, that rate of return should be selected as the discount rate for the
NPV calculation. In this way, a direct comparison can be made between the profitability of
the project and the desired rate of return.
NPV > 0 the investment would add value to the firm the project should be accepted
NPV < 0 the investment would subtract value from the firm the project should be rejected
NPV = 0 the investment would neither gain nor lose value for the firm we should be
indifferent in the decision whether to accept or reject the project. This project adds no
monetary value. Decision should be based on other criteria, e.g. strategic positioning or other
49
To understand internal rate of return, we must first know what is NPV or net present value.
IRR is discounted rate of return derived based on the condition that net present value for an
investment is 0. IRR is then compared to the companys discounted rate of return. If IRR is
higher than the companys / projects discounted rate of returns, then the investment is
deemed to be worthwhile for the company or investor. The investors themselves determine
the discounted rate of return for the company. Discounted rate of return is derived based on a
number of factors. One of them is the consideration of risk. If the investor is evaluating a
more risky investment, he is likely to have a higher rate of return. This is to compensate the
risk that he is taking on this project. Another factor that could influence the discounted rate of
return is the general market rate of return.
50
as the cost of financing (capital) is regarded by some as a logical discount rate (required rate
of return) to use. Weighted Average Cost of Capital is the return a firm must earn on existing
assets to keep its stock price constant and satisfy its creditors and owners.
Corporations raise money from two main sources: equity and debt. Thus the capital structure
of a firm comprises three main components: preferred equity, common equity and debt
(typically bonds and notes). The WACC takes into account the relative weights of each
component of the capital structure and presents the expected cost of new capital for a firm.
The weighted average cost of capital is defined by:
Where
52
In India all the states have to make their own solar regulations. But in India most of
the states has followed the CERC regulations as it is. This is not a good step as the
conditions in all states are not same so the same regulation in all the states regarding
the T&C of tariff is not a welcome step. The SERCs should work on this aspect, as it
defines all the economical aspect of the plant.
The capacity utilization factor is a very major concern for the solar power plants. But
it has not been emphasized as it should be. The solar irradiation in the country varies
from 4-7 kWh/ square meter, but the CUF for all the states is almost equal. This CUF
changes the financials for a plant greatly. This should be calculated with due research.
The CERC or MNRE should make a guideline to calculate the CUF for any location.
As the SERCs are using different kind of technologies to calculate CUF. This is not
uniform throughout the country. The CERC guidelines for the same will bring the
harmony in this aspect.
The financial incentive should be provided upfront as the cost of solar plant set up is
very high. IREDA should come up with new regulations/guidelines to overcome this
problem.
The targets for generation of home Roof Top must be set. The target of Home Roof
A new scheme like Solar Credit should be introduces. In this kind of scheme the plant
set up can be promoted by the home Roof Top PV generation. Here the incentive
equal to the RECs generated by the plant capacity in a year or more could be provided
upfront.
For GBI selection the latest technology should be priorities. This must be one of the
selection parameter.
The GBI capacity eligibility can be changed to support the lower capacity generation
plant.
The limit of setting up at least 250 kW at one place could be removed as in stats like
53
Delhi the space is a very big constraint. This will help to promote the solar generation
as the plant can be of lower capacity or can be one of higher capacity with separate
generation location.
The Solar PV Module manufacturing in India is very negligible. The target of 20000
MW requires a large capacity installation for that enough manufacturing capacity is
not available. This should be emphasized more.
The latest technology for Solar Power generation should be used. The silicon thin film
has better efficiency and it requires lesser space. Technology like this can be used to
have better results.
New Research centers must be established to create new technology which provides
better result in lesser space as this field is immature a lot of possibilities are still there.
A Feed in Tariff policy can be introduced. This will clear all the aspects of the
scheme. The Feed in Tariff has very high possibilities to improve the solar
installation.
The utilities must be obliged to procure all the power generated using solar power
adoption.
Enact laws and pass mandates for expanding solar PV adoption and generation (both
national labs, with clearly defined, time-bound, technology and cost goals,
encompassing all aspects of the PV eco-system including materials, cell technologies,
process, equipment, packaging, test and characterization, manufacturing
engineering and automation, battery/storage technology, inverter and BOS
electronics, metering, etc.
Put a plan in place for achieving and sustaining true manufacturing scale. Create a
plan to develop and strengthen the entire PV supply chain from silicon feedstock,
wafer manufacturing, materials and equipment to end-systems Focus on training
and human resource development in collaboration with the college, university
and training eco-system .
54
Create awareness in the financing community about PV technology, its promise and
IREDA should be more aggressive towards project financing. They are afraid of
CHAPTER-9
9.1. CONCLUSION
Solar power generation in India has a very great potential. But as the solar generation is very
expensive the Indian govt. is trying hard to provide as much support as possible to promote
solar power generation. States like Gujarat and Rajasthan are doing a rigorous work in the
solar power aspect. Various regulations have been notified, various agencies are being made,
and the financial help is also being provided. This all is very much required as the country
has just started in this field and all states need to follow the likes of Gujarat and Rajasthan.
9.2. LIMITATION
All studies are surrounded by certain limitations and this project is not an exception. Apart
from constraint of time, it does involve certain limitations listed below.
55
Study and assessment of solar sector is entirely and wholly dependent on ones own
perspective. The market remains changing from time to time and so market reading
could be difficult.
Most the charges and figures involved in project are need to be updated time to time.
Since the project report comprises of solar power market scenario and was framed
earlier, so things like achievement of financial closure by project developers was missed.
9.3. BIBLIOGRAPHY
http://www.mnre.gov.in/
http://www.nvvn.co.in/
http://www.cercind.gov.in/
http://www.cea.nic.in/
http://www.ireda.gov.in/
http://www.forumofregulators.gov.in/
http://recindia.nic.in/
http://www.eai.in/
http://www.iea.org/
56
16. ANNEXURE
Annexure I project awarded under JNNSM phase I
Company
State
capacity
Camelot Enterprises
Private Limited
Maharashtra
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Karnataka
Rajasthan
57
Rajasthan
Rajasthan
Rajasthan
Azure Power(Rajasthan)
Pvt. Ltd
Rithwik Projects Pvt. Ltd.,
Rajasthan
Andhra Pradesh
Rajasthan
5
Rajasthan
5
Rajasthan
Rajasthan
Rajasthan
Rajasthan
5
Karnataka
Andhra Pradesh
58
Tamil Nadu
Orissa
PUNJ LLOYD
Infrastructure Ltd
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
Rajasthan
100
Rajasthan
100
Rajasthan
50
State
Capacity
Solairedirect(SA)
Rajasthan
Welspun solar AP
Rajasthan
45
Rajasthan
35
Andhra Pradesh
20
Rajasthan
10
Rajasthan
10
Symphony vyapar(p)
Rajasthan
10
Rajasthan
Jakson power
Rajasthan
20
59
JEPL projects
Rajasthan
10
Rajasthan
Tamilnadu
10
Fonroche Energy
Rajasthan
20
NVR Infrastructure
Rajasthan
10
Enfield Infrastructure
Rajasthan
10
Essel Infrastructure
20
Rajasthan
20
GAIL(India) Limited
Rajasthan
Mahindra solar
Rajasthan
30
Kiran Energy
Rajasthan
20
Rajasthan
20
Rajasthan
60