Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Planned PI: Focuses on activities yet to be performed. Durations Days sum the durations
of activities yet to be performed, and Performance Period reflects the time available to
perform those activities.
Actual PI: Measure activities that have been performed, fully or partially. Durations
Days sum the durations of activities that have been earned during a designated period
of time (Performance Period).
Catch-Up PI: Focuses on activities that remain to be performed. Durations Days sum
the durations of remaining activities. Performance Period reflects the time remaining to
perform those activities.(Top of Page)
Compound PI: This is where various Core Formulas are combined to derive insightful
statistics about performance.
Trending PI: Various extrapolations of PI across time so as to show trends.
Targeted PI: This is where PI is applied to any subset of activities that can be isolated,
using the filtering functionality of the scheduling software, and the activity codes
assigned to the activities. Examples include:
o Area PI: By building, by floor, by area
o Phase PI: By project phase
o Responsibility PI: By performing entity
o MCP PI: PI by Momentum Checkpoint (see below)(Top of Page)
With the establishment of these intermediate Work Scope Containers, for the first time work
performance can be planned, executed, monitored, and analyzed with greater granularity that the
Overall Project, but without getting into the minutia of activity-by-activity comparisons (as is
now the common practice under Dominant Project Management). Said bluntly, Activity Paths
and Path Segments allow us to still be able to spot the forest from the trees. (Top of Page)
Momentum Checkpoints
Concept of Momentum Checkpoints (MCPs)
Another innovation of Momentum Science is the concept of a Momentum Checkpoints (MCPs).
These temporal markers (timestones) act just like distance markers (milestones), by helping to
orient the Project Execution Team to where they are with respect to intermediate progress
"checkpoints."
Momentum Tracking
Concept of Momentum Tracking
All we need to do is combine the two previous innovations and we have a new science with
which the Contractors Project Execution Team can self-manage: Momentum Tracking.
First we establish the three levels of MCPs and sprinkle them across the Project Schedule. Next,
for each Activity Path we calculate and report Performance Intensity against the nearest
MCP. By referring to the Performance Intensity associated with a given Activity Path or Path
Segment, the Contractor (or subcontractor) can regulate its own performance effort in real time!
Those last three words reflect a phenomenal distinction between Momentum Management and
conventional Project Time Management under Dominant Project Management.
Where the latter reports progress after-the-fact by statusing the schedule (monthly or
even weekly) after the work has been performed, Performance Intensity is an
instantaneous, real time feedback that allows the Project Execution Team to speed up or
slow down on a momentary basis.
Where the latter compares actual performance to planned performance (looking
backward), Performance Intensity values are correlated to upcoming MCPs (looking
forward).
Where the latter monitoring is performed by an external watchdog (Project Controls),
Performance Intensity is an automated feedback loop that allows self-monitoring by the
Project Execution Team. (Top of Page)
Formulation: First, Total Float is defined as the difference between Earliest Dates and
Latest Dates. This, in itself, is problematic, since both sets of dates are theoretical and
without practical significance.
o Earliest Dates represent what would happen if everything went flawlessly for the
entire length of the project. No same, living person with any practical real life
experience would sign up for that assumption.
o Latest Dates represent the last possible moment one can procrastinate to, again
based on the assumption that everything will go flawlessly from now until the end
of the project. What responsible perform leaves everything until the last possible
moment?
o Total Float, as a numeric value, represents the difference between these two sets
of extreme dates, neither of which a responsible Project Executor would rely
upon!
Depiction: Second, Total Float is redundantly reported. Total Float does not belong to an
individual activity; it belongs to an entire Activity Path that spans two bulkhead Date
Constraints. Accordingly, the Total Float should not be reported separately for each
activity along that Activity Path, but only once for the entire Activity Path.
Since Dominant Project Management does not recognize the Activity Path as a discrete Work
Scope container within the schedule, it has no choice but to erroneously report Total Float
alongside each activity that resides on the (unrecognized) Activity Path. This is seen in any
standard CPM tabular, where Total Float is reported in the far-right column.
Individual contractors, seeing that their activity has Total Float (even though, it does not
see previous point), take advantage of the extra time. At the other end, the Owner sees the
Total Float and decides to add additional scope to the Contractors contract, without having to
extend the contract completion deadline. (Top of Page)
It secures each Project Participants discrete portion of the overall Activity Path float.
This Discrete Float is theirs to use or lose. But because it has been determined by formula
(and policy) it can be protected.
Once and for all, it rids Project Time Management of a great nemesis, Float Usurping,
which is where, on a first-come-first-served basis, whoever can gobble up the Total Float
first enjoys it. All others, downstream, work without a net.
It also provides for a new set of statistics that can be correlated to the Activity, Activity
Path Segment, and Activity Path.
Finally, because activities quite often reside multiple Activity Paths simultaneously,
Discrete Activity Float can be aggregated thus yielding a composite Float value for
each activity that is distinct and telling. Applying Discrete Activity Float, one will see
that activities lying side-by-side on the same Activity Path can actually have different
Discrete Activity Float values! (Top of Page)
The answer depends on how the activities related to the activities before and after them. And
were not just talking about immediately before or after! Here is what we consider under Flow
Rate Measurement:
As to What Precedes
As to what Succeeds
The same as above, just reversed. (Top of Page)
We must never lose sight of our goal: to provide the Project Execution Team with as much good
information as possible about what lies ahead. Our focus is always forward. Look where you
are going and go where you are looking.
All of the above technical clap-trap can be reduced to two separate perspectives that can be used
to vector in and predict likely Momentum Hotspots the basis for Dilemma Forecasting (see
Volume 7)
Likewise, thanks to Vulnerability and Resiliency, when we vector the two values across a project
schedule, we can identify areas in the schedule where activities have the highest likelihood of
experiencing upstream delay AND the lowest intrinsic ability to rebound from the hit. These
Soft Ground areas warrant special, closer attention by Project Management.