Sei sulla pagina 1di 44

CHAPTER VI

SUPERIMPOSED LOADS
ON BURIED PIPE
Summary of Recommendations, Relationships, and Data
Relevant to the Evaluation of External Loads
on Buried PVC Pipe

173

HANDBOOK OF PVC PIPE

CHAPTER VI
SUPERIMPOSED LOADS ON BURIED PIPE
Superimposed loads on buried PVC pipe fall into two categories earth loads and live loads. In the design of any buried piping system,
both categories of superimposed loads must be considered. In
accordance with common design practice, earth loads and live loads are
treated as separate design parameters.
Earth Loads: The first solution to the problem of soil-induced
loads on buried pipe was published by Professor Anson Marston at Iowa
State University in 1913. Since then, the Marston Theory of Loads on
Underground Conduits has been used in determination of loading on
buried pipe. Much of the work done on earth loading technology for
buried conduits throughout the world is related, in part, to Marston's
load theory.
FIGURE 6.1
DEVELOPMENT OF LOADS ON
RIGID PIPE IN TRENCHES

Where:

K'

Vh
Bd

the frictional force resisting settlement

174

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

KVh
Bd
Where: V
Bc
Bd
h

=
=
=
=

Cd
K

=
=

'

the force against the trench wall due to the


active lateral pressure

vertical pressure on any horizontal plane, lbs/Lft


outside diameter of pipe, ft
width of trench at top of pipe, ft
distance from ground surface down to any horizontal
plane in the backfill, ft
load coefficient for pipes installed in trenches
Rankine's ratio of active lateral pressure to vertical
pressure
coefficient of friction between the backfill and the
sides of the trench
change in h

The basic concept of the theory is that the load due to the weight of the
column of soil above a buried pipe is modified by the response of the pipe.
Marston's Load Theory may be summarized by referring to Figure 6.1.
The weight of the soil load seen or carried by the buried pipe is not simply
the weight of the soil column or prism that is above it (Bc x unit weight of
soil x h). The final load on the pipe actually depends on the relative
movement of columns of soil directly over the pipe and adjacent to the
pipe.
When the soil between the pipe and the trench wall (pipe zone) is more
compressible than the pipe, this causes the pipe to assume load generated
across the width of the trench. However, when pipe has the ability to
deflect without cracking, this produces a situation that allows the central
prism of soil (directly over the pipe) to settle more than the adjacent soil
prisms (between the pipe and the trench wall). This settlement produces
shearing forces which reduce the load on a flexible pipe to an amount less
than the weight of the prism directly over the pipe. Regardless of pipe
stiffness, as soil in the trench settles or moves downward compared to the
trench sidewall, friction forces are generated which act to reduce the
weight of the trench-wide soil column. Marston's Load Theory predicts
and accounts for these shearing forces.
Two cases of trench loading are shown in Figures 6.2 and 6.3.

175

HANDBOOK OF PVC PIPE

FIGURE 6.2
SHEARING FORCES OVER RIGID
PIPE

Shearing Forces Increase the Load

FIGURE 6.3
SHEARING FORCES OVER FLEXIBLE
PIPE

Shearing Forces Decrease the Load


176

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

Marston recognized that most flexible conduits would fall into the
category where the load imposed on the pipe is less than the weight of the
prism of soil over the pipe. The flexibility of the pipe insured that the
relative prism settlement above the pipe would be greater than the side
column in nearly all cases. Rigid conduits, such as concrete pipe, fall into
the category where the prism above the pipe imposes a greater load than
the weight of the prism itself. The lack of flexibility in a rigid conduit
dictates that the relative settlement of the backfill will be greater on the
sides of the pipe than over the pipe.
The inherent differences of the two types of pipe are expressed in the
formulas Marston developed for calculating the earth loads imposed on
pipe buried in a trench. They are as follows:
EQUATION 6.1

EQUATION 6.2

Rigid

Flexible

Wc = CdwBdBd

Wc = CdwBdBc

Where: Wc
w
Bc
Bd
Cd

=
=
=
=
=

load on the pipe, lbs/Lft


unit weight of backfill, lbs/ft3
outside diameter of pipe, ft
width of trench at top of pipe, ft
load coefficient for conduits installed in trenches

Analysis of the two equations reveals that the ratio of the load on a
flexible pipe or conduit to the load on a rigid pipe or conduit is equal to
the ratio of diameter of the pipe to the width of the trench, for identical
conditions of installation.
EQUATION 6.3
CdwBd x Bd Bd
(Wc) Rigid
=
=
(Wc) Flexible CdwBd x Bc Bc
Therefore, if the trench is twice as wide as the pipe being buried (12 in
pipe in a 24 in wide trench), the load imposed on a rigid pipe will be twice
the load imposed on a flexible pipe, as indicated by the Marston equations.
When calculating loads on buried pipe, the term Cd must be determined
for particular installation conditions. Cd is a function of the ratio of fill

177

HANDBOOK OF PVC PIPE

height (H) to trench width (Bd) and of the friction coefficient of the backfill
and the sides of the trench. Cd is computed as follows:
EQUATION 6.4
1 - e-2k'H/Bd
Cd =
2k'
Where:

e is the natural logarithm base


k = Rankine's ratio of lateral to vertical pressure
' = the coefficient of friction between backfill
material and sides of trench
A diagram has been developed (Figure 6.4) for various values of k '
and ratios H/Bd that eliminates the need for computation of Cd in most
instances. According to Marston's equation, the width of the trench
directly affects the loads imposed on flexible and rigid pipe. The height of
the backfill material and the trench width again appear in the Cd
computations.
An increasing width of trench does increase the load imposed on a
pipe, but the load does not continue to increase indefinitely. There is a
trench width for a given depth and size of pipe beyond which no
additional load is imposed on the pipe. This is called the "transition
width" and is a limiting value for calculating loads based on Marston's
trench formulas. At transition width and beyond, the loads can be
calculated using Marston's positive projecting conduit or "embankment"
equations. Embankment installation is realized if the top of the pipe
projects above the natural ground surface or is in a relatively wide trench
(beyond transition width). The maximum loads imposed on a pipe are
those obtained in the embankment mode of installation.

178

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

FIGURE 6.4 - VALUES OF Cd

Computation diagram for earth loads on trench conditions (completely buried in trenches).
SOURCE: GRAVITY SANITARY SEWER DESIGN AND CONSTRUCTION. "MANUALS & REPORTS
ON ENGINEERING PRACTICE NO. 60," AMERICAN SOCIETY OF CIVIL ENGINEERS AND
"MANUAL OF PRACTICE FD-5," WATER POLLUTION CONTROL FEDERATION, 1982.

179

HANDBOOK OF PVC PIPE

Marston developed the following formula for computing loads on both


flexible and rigid positive-projecting conduits (embankment installation):
EQUATION 6.5
Wc = CcwBcBc
Where: Cc replaces Cd as the load coefficient, and
Bc appears twice to replace the Bd
The load coefficient Cc in this case depends on the projection ratio
(p), the settlement ratio (rsd), and the ratio of fill height (H) to pipe width
(not trench width) (Bc).
As in the case for Cd, a graph has been developed for Cc (Figure 6.6)
that eliminates the need for the complex computations required to generate
Cc. Settlements that influence loads on positive-projecting pipe are
shown in Figure 6.5.

180

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

FIGURE 6.5
SETTLEMENTS THAT INFLUENCE
LOADS ON POSITIVE-PROJECTING
CONDUITS

Where:

SOURCE:

sg
sm
dc
sf
rsd
p

=
=
=
=
=
=

settlement of natural ground adjacent to pipe


compression of columnns of soil of height pBc
deflection of pipe
settlement of bottom of pipe
settlement ratio = [(sm + sg) (sf + dc)]/sm
projection ratio

GRAVITY SANITARY SEWER DESIGN AND CONSTRUCTION. "MANUALS & REPORTS


ON ENGINEERING PRACTICE NO. 60," AMERICAN SOCIETY OF CIVIL ENGINEERS AND
"MANUAL OF PRACTICE FD-5," WATER POLLUTION CONTROL FEDERATION, 1982.

181

HANDBOOK OF PVC PIPE

FIGURE 6.6 - VALUES OF Cc

Diagram for coefficient Cc for positive-projecting conduits.


SOURCE: GRAVITY SANITARY SEWER DESIGN AND CONSTRUCTION. "MANUALS & REPORTS
ON ENGINEERING PRACTICE NO. 60," AMERICAN SOCIETY OF CIVIL ENGINEERS AND
"MANUAL OF PRACTICE FD-5," WATER POLLUTION CONTROL FEDERATION, 1982.

For flexible pipe under most conditions, the product rsdP, is less than
zero (a negative value). Only flexible pipes with very high pipe stiffness
would ever have an rsdP product greater than zero. Therefore, use of a
rsdP product equal to zero will result in a conservative design approach
for most buried flexible pipe installations. As can be seen on the Cc
computation graph (Figure 6.6), when rsdP equals zero, the coefficient Cc
is equal to the ratio of H/Bc.
182

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

Replacing the Cc in Marston's embankment load formula with the ratio


H/Bc yields:
EQUATION 6.6
Wc = HwBc
This is commonly known as the prism load, and simply stated, it is the
weight of the column of soil directly over the pipe for the full height of the
backfill. This is the maximum load that will be imposed by the soil on a
flexible pipe in virtually all cases and is a conservative design approach.
Below is a comparison of the Marston earth-load determination
formulas:
(EQUATION 6.1)
Rigid Pipe Load
(Trench Condition)

Wc = CdwBd2

(lbs/Lft)

(EQUATION 6.2)
Flexible Pipe Load
(Trench Condition)

Wc = CdwBdBc

(lbs/Lft)

(EQUATION 6.5)
Pipe Load
(Embankment Condition) Wc = CcwBcBc

(lbs/Lft)

(EQUATION 6.6)
Flexible Pipe Load
(Prism Load)

Wc = HwBc

(lbs/Lft)

The prism load may also be expressed in terms of soil pressure as


follows:
EQUATION 6.7
Wc
(Soil Pressure)
P = wH =
Bc
Where: P
= pressure due to soil weight at depth H, lbs/ft2
w = unit weight of soil, lbs/ft3

183

HANDBOOK OF PVC PIPE

H
Wc
Bc

=
=
=

depth at which soil pressure is desired, ft


trench load, lbs/Lft
pipe outside diameter, ft

Calculation of soil pressure on both rigid and flexible pipes of the


same diameter in the same burial conditions demonstrates the difference
between the load on flexible conduit in trench and embankment conditions
and load on rigid conduit in trench condition.
Example: Find the trench load for a rigid pipe and a flexible pipe
given the following information:
Pipe Outside Diameter (Do or Bc)
Burial Depth of Cover (H)
Trench Width (Bd)
Rankine's Ratio (k)
Soil Density (w)
Coefficient of Soil Friction (')

12 in
12 ft
3 ft
0.33
120 lbs/ft3
0.5

Rigid Pipe Load (trench condition) Use Equation 6.1


Cd =

1 - e-2(0.33)(0.5)(12/3)
= 2.221
2(0.33)(0.5)

Wc = 2.221 (120)32 = 2,398 lbs/Lft or 16.7 lbs/in2


Flexible Pipe Load (trench condition) Use Equation 6.2
Wc = 2.221(120)(3)(1) = 800 lbs/Lft or 5.6 lbs/in2
Flexible Pipe Load (assume prism condition) Use Equation 6.6
Wc = 120(12)(1) = 1440 lbs/Lft or 10.0 lbs/in2
For all practical purposes, research and actual long-term data confirm
that the prism load provides a conservative, simplified approach for
designing flexible PVC piping systems to accommodate earth load. In a
trench, friction forces can reduce the load on the pipe through arching

184

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

action of the soil; however, frost and water action may dissipate these
forces, and in the long term, the load may approach the prism load.
The following tables have been developed for use in determining
Marston earth loads on PVC sewer pipe. The table is dependent on
outside-diameter dimensions and can be used with any flexible pipe with
the same or similar Do. Actual diameters appear parenthetically next to
nominal pipe size in the table. If the condition of installation is known to
be a "trench" condition, then Table 6.1 will provide the computed earth
load. For unknown conditions or in trenches beyond transition width, the
more conservative prism earth-loads are recommended. Prism earth-loads
in lbs/lineal foot are listed in Table 6.2. Prism earth-loads in lbs/in2 are
listed in Table 6.3. Tables 6.1, 6.2 and 6.3 utilize the most common ranges
for H (depth of cover, ft) and w (unit weight of soil, lbs/ft3). The table
limits do not imply application limits.
TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft)
Wc = CdwBdBc
Depth
of
Cover

Trench
Backfill

4" (Do = 4.215) PIPE


6" (Do = 6.275) PIPE
Width of Trench (ft)
0.75 1.00 1.25 1.5
1.0
1.5
2.0
2.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

56
67
71
79
91

66
77
80
88
100

72
84
86
94
106

77
89
91
99
111

98
115
119
131
149

115
132
136
147
165

125
142
145
156
174

132
149
152
162
179

Granular w/o Cohesion


Sand and Gravel
3.5 Sat. Top Soil
Dry Clay
Sat. Clay

60
72
76
85
100

71
84
88
97
111

79
92
96
105
119

85
99
102
111
125

106
125
130
144
166

127
147
151
165
186

140
160
164
176
197

149
169
172
184
205

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

63
76
81
91
108

75
90
94
105
121

85
100
104
114
131

92
107
111
122
138

112
134
140
156
181

137
160
166
181
206

153
176
181
196
220

164
187
191
205
229

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

69
85
92
106
129

86
106
112
128
152

101
122
128
144
169

113
135
141
157
182

129
157
167
191
226

168
200
210
234
271

195
229
238
261
299

215
249
257
280
317

185

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

4" (Do = 4.215) PIPE


6" (Do = 6.275) PIPE
Width of Trench (ft)
0.75 1.0
1.25 1.5
1.0
1.5
2.0
2.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

71
89
97
114
141

91
114
122
142
172

110
134
144
164
196

125
152
161
182
215

136
169
182
211
256

187
226
240
272
320

224
267
280
312
362

253
297
309
341
390

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

71
91
99
118
147

94
118
128
150
185

114
142
153
177
215

133
163
175
200
240

140
176
190
223
275

198
243
260
298
357

244
294
311
351
412

280
334
350
390
452

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
91
100
120
151

95
120
131
155
193

117
147
159
186
228

137
171
184
213
258

141
179
195
231
287

204
254
273
317
384

257
314
335
381
453

300
362
382
430
504

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
92
101
121
154

96
122
133
159
200

119
150
164
194
241

141
177
192
225
277

142
181
198
236
298

209
263
286
335
412

269
334
359
414
499

321
393
418
477
566

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
92
101
121
155

96
122
134
161
204

119
152
166
198
249

142
180
196
232
289

143
182
200
239
303

212
268
292
346
430

276
346
374
436
533

334
413
443
511
614

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
92
101
121
155

96
122
134
161
205

120
152
167
199
252

143
181
198
236
295

143
182
200
240
305

213
270
295
351
439

279
351
381
447
550

340
423
456
528
640

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
92
100
122
156

96
122
135
162
207

120
153
168
202
256

144
183
201
240
303

143
182
200
241
308

214
272
299
357
452

283
349
391
464
578

349
439
476
559
687

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

72
92
101
122
156

96
122
135
162
207

120
153
168
202
258

144
183
201
242
308

143
182
200
241
309

214
273
300
360
458

284
363
396
473
595

353
447
487
577
717

186

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

8" (Do = 8.400) PIPE


10" (Do = 10.500) PIPE
Width of Trench (ft)
1.5
2.0
2.5
3.0
2.0
2.5
3.0
3.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

154
177
182
197
221

168
190
194
209
233

177
199
203
216
240

183
206
209
222
245

209
238
243
261
291

221
249
254
271
300

229
257
261
277
306

235
263
266
282
311

3.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

170
196
203
220
249

187
214
219
236
264

199
226
230
246
274

207
234
238
254
281

234
268
274
295
330

249
282
288
308
343

259
292
297
317
351

267
300
304
324
357

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

184
214
222
242
275

205
236
242
262
294

220
250
256
275
307

230
261
265
284
315

256
295
303
328
368

274
313
320
344
384

287
326
332
355
394

297
335
341
363
402

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

225
268
281
313
363

262
307
318
350
400

288
334
344
375
424

308
354
363
393
442

327
383
398
437
500

360
417
430
469
530

385
442
454
491
552

404
461
472
508
569

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

250
303
321
363
429

300
358
375
418
484

338
398
414
456
523

368
428
443
485
551

375
447
469
522
605

423
497
517
570
653

460
535
554
606
688

489
565
583
633
715

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

264
325
348
399
477

326
394
417
470
552

375
447
469
522
605

414
488
509
562
645

408
493
521
588
690

469
559
586
653
756

518
610
636
702
806

557
652
676
741
844

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

273
340
366
424
514

344
421
448
510
606

402
485
512
576
674

450
536
563
627
726

430
526
560
638
758

503
606
640
720
843

563
670
703
783
908

612
723
754
834
958

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

280
352
382
449
552

361
447
480
554
668

430
526
560
638
758

489
591
625
705
828

451
559
600
693
835

538
657
700
797
947

612
739
782
881
1035

675
808
849
950
1105

187

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) Continued
Depth
of
Cover

Trench
Backfill

8" (Do = 8.400) PIPE


10" (Do = 10.500) PIPE
Width of Trench (ft)
1.5
2.0
2.5
3.0
2.0
2.5
3.0
3.5

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

284
359
392
463
576

370
463
501
584
713

448
553
593
683
822

516
631
672
766
909

463
579
626
730
891

560
691
742
854
1027

645
720
788
872
840
923
957 1042
1137 1226

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

285
361
395
469
587

374
470
510
598
736

456
566
610
707
856

529
651
696
798
955

467
587
637
748
920

569
708
762
883
1070

661
743
813
905
870
963
997 1094
1193 1295

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

286
364
400
478
605

379
480
524
621
774

467
587
637
748
920

550
685
739
858
1043

474
600
655
776
968

584
687
782
734
856
966
797
924 1036
935 1073 1193
1149 1303 1434

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

286
365
402
482
613

381
484
531
633
797

473
598
653
772
960

561
705
765
897
1103

476
606
663
791
996

591
701
805
748
881 1004
816 9956 1084
965 1122 1261
1200 1379 1535

Depth
of
Cover

Trench
Backfill

12" (Do = 12.500) PIPE


15" (Do = 15.300) PIPE
Width of Trench (ft)
2.0
2.5
3.0
3.5
2.0
2.5
3.0
3.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

249
283
289
311
346

263
297
302
322
357

272
306
310
330
365

280
313
317
336
370

305
347
354
380
424

322
363
369
394
437

333
375
380
404
446

342
383
388
411
453

3.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

279
319
326
351
393

296
336
342
367
408

308
348
354
377
418

318
357
362
385
425

341
390
399
430
482

362
411
419
449
499

378
426
433
462
512

389
437
443
472
521

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

305
351
360
390
438

327
372
381
409
457

342
388
395
423
469

354
399
406
433
479

374
429
441
477
536

400
456
466
501
559

419
474
483
517
575

433
489
497
529
586

188

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

12" (Do = 12.500) PIPE


15" (Do = 15.300) PIPE
Width of Trench (ft)
2.0
2.5
3.0
3.5
2.0
2.5
3.0
3.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

389
456
474
521
595

428
496
512
558
631

458
526
540
585
657

480
549
562
605
677

476
558
580
637
728

524
608
627
683
773

560
644
662
716
805

588
672
688
741
828

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

447
532
558
622
720

503
592
616
679
778

547
637
660
721
820

582
673
694
754
851

547
651
683
761
882

616
724
754
831
952

670
780
807
883
1003

712
824
849
923
1042

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

485
587
620
699
821

558
665
698
777
901

616
727
757
836
960

663
776
804
882
1005

594
718
759
856
1005

683
814
854
951
1102

754
889
927
1023
1175

812
949
985
1080
1231

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

512
626
667
759
902

599
721
762
857
1004

670
798
837
933
1081

729
861
898
993
1141

627
766
816
930
1104

733
883
932
1049
1228

820
977
1025
1141
1323

892
1053
1099
1215
1397

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

537
665
714
825
995

640
782
833
949
1128

728
880
931
1049
1232

804
962
1011
1131
1315

657
814
874
1009
1217

783
957
1020
1162
1380

891
1077
1139
1284
1508

984
1177
1238
1384
1610

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

551
689
745
869
1061

666
823
883
1017
1223

768
939
1000
1139
1353

857
1038
1099
1241
1459

674
843
912
1064
1299

815
1008
1081
1245
1497

940
1149
1224
1394
1656

1049
1270
1345
1519
1786

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

556
699
759
890
1095

678
843
908
1052
1274

787
968
1036
1187
1421

884
1078
1146
1302
1542

681
856
929
1090
1340

830
1032
1111
1287
1559

963
1185
1268
1453
1739

1083
1319
1403
1593
1887

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

564
714
780
924
1152

695
874
949
1113
1368

818
1019
1100
1277
1551

931
1150
1234
1420
1707

690
874
955
1131
1410

851
1070
1161
1362
1675

1001
1248
1346
1563
1899

1140
1408
1510
1738
2089

189

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

30

Depth
of
Cover

Trench
Backfill
Granular w/o Cohesion
Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

Trench
Backfill

12" (Do = 12.500) PIPE


15" (Do = 15.300) PIPE
Width of Trench (ft)
2.0
2.5
3.0
3.5
2.0
2.5
3.0
3.5
567
704
835
958
721
890 1049 1195
790
971 1138 1291
942 1149 1335 1501
1186 1429 1642 1827

694
861
882 1090
967 1188
1153 1406
1451 1749

1021
1284
1393
1634
2010

1173
1463
1580
1838
2237

18" (Do = 18.701) PIPE


21" (Do = 22.047) PIPE
Width of Trench (ft)
2.5
3.0
3.5
3.0
3.5
4.0

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

393
444
452
482
534

407
458
464
494
546

418
468
474
503
554

480
540
548
582
643

493
552
559
593
653

503
562
568
601
661

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

489
557
569
612
683

512
580
591
632
702

530
597
607
647
717

604
684
697
745
828

624
704
715
763
845

641
720
730
777
858

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

641
743
767
835
944

685
787
809
875
983

719
821
841
905
1013

807
928
953
1031
1159

847
968
991
1067
1194

879
1000
1021
1095
1221

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

753
885
922
1016
1164

819
953
987
1079
1226

871
1007
1038
1128
1274

965
1124
1163
1272
1446

1027
1187
1223
1330
1502

1076
1237
1271
1375
1546

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

835
995
1044
1163
1347

922
1087
1133
1251
1436

993
1160
1204
1320
1504

1087
1281
1336
1475
1693

1170
1368
1419
1556
1773

1239
1439
1486
1621
1837

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

895
1079
1140
1282
1501

1002
1194
1252
1395
1617

1090
1288
1343
1485
1707

1181
1408
1476
1645
1906

1286
1518
1584
1751
2013

1373
1609
1672
1837
2098

190

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

18" (Do = 18.701) PIPE


21" (Do = 22.047) PIPE
Width of Trench (ft)
2.5
3.0
3.5
3.0
3.5
4.0

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

957
1170
1247
1420
1687

1089
1316
1392
1570
1843

1202
1439
1513
1691
1968

1284
1552
1641
1851
2173

1417
1696
1784
1994
2320

1532
1818
1903
2112
2440

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

997
1232
1321
1522
1830

1149
1404
1496
1704
2025

1283
1553
1644
1856
2183

1355
1656
1764
2009
2387

1512
1830
1938
2189
2574

1650
1981
2087
2339
2729

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1014
1261
1358
1574
1906

1178
1449
1550
1777
2125

1323
1612
1714
1948
2306

1388
1708
1827
2094
2506

1560
1901
2021
2296
2719

1712
2069
2189
2467
2897

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1040
1308
1419
1665
2047

1224
1525
1645
1911
2321

1393
1721
1846
2124
2553

1443
1798
1939
2252
2736

1642
2029
2176
2505
3010

1824
2235
2385
2724
3245

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1053
1332
1453
1719
2138

1249
1569
1703
1998
2457

1433
1788
1931
2246
2734

1472
1850
2008
2355
2896

1690
2108
2277
2648
3223

1893
2345
2520
2909
3509

Depth

Trench

of

Back-

Cover

fill

24" (Do = 24.803) PIPE

27" (Do = 27.953) PIPE


Width of Trench (ft)

3.0

3.5

4.0

3.5

4.0

4.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

540
607
616
655
724

555
621
629
667
735

566
632
639
676
743

625
700
709
752
828

637
712
720
762
837

647
721
728
770
845

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

679
769
784
838
932

702
792
805
858
950

721
810
821
874
965

792
893
907
967
1071

812
913
926
985
1087

829
929
941
998
1100

191

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

24" (Do = 24.803) PIPE


27" (Do = 27.953) PIPE
Width of Trench (ft)
3.0
3.5
4.0
3.5
4.0
4.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

908
1044
1072
1160
1304

953
1089
1115
1201
1343

989
1125
1148
1232
1373

1074
1228
1257
1353
1514

1115
1268
1294
1389
1548

1148
1300
1325
1417
1575

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1086
1265
1309
1431
1626

1155
1335
1376
1496
1689

1211
1392
1430
1547
1739

1302
1505
1551
1686
1904

1365
1569
1612
1744
1960

1417
1621
1661
1791
2005

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1223
1442
1503
1659
1904

1317
1539
1596
1750
1995

1394
1619
1672
1824
2067

1484
1735
1799
1973
2248

1571
1824
1885
2055
2329

1644
1898
1955
2123
2395

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1329
1584
1661
1850
2144

1446
1708
1782
1970
2264

1545
1811
1881
2067
2360

1630
1925
2008
2220
2552

1741
2041
2120
2329
2660

1835
2138
2213
2419
2749

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1445
1746
1847
2082
2444

1595
1908
2006
2243
2610

1723
2045
2140
2377
2744

1797
2150
2261
2528
2941

1942
2305
2412
2678
3093

2067
2437
2540
2804
3219

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1524
1863
1984
2260
2685

1701
2059
2180
2462
2896

1857
2229
2348
2632
3070

1917
2321
2457
2775
3264

2092
2512
2646
2966
3460

2247
2677
2808
3128
3625

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1562
1921
2055
2356
2819

1755
2139
2274
2583
3059

1927
2328
2462
2776
3259

1978
2410
2562
2911
3447

2171
2623
2775
3128
3673

2343
2810
2959
3315
3864

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1623
2023
2182
2534
3078

1848
2282
2448
2818
3387

2052
2515
2683
3064
3650

2082
2572
2759
3175
3817

2313
2834
3024
3454
4114

2523
3069
3259
3697
4369

192

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

30

Depth
of
Cover

Trench
Backfill
Granular w/o Cohesion
Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

Trench
Backfill

24" (Do = 24.803) PIPE


27" (Do = 27.953) PIPE
Width of Trench (ft)
3.0
3.5
4.0
3.5
4.0
4.5
1656
2081
2259
2649
3258

1901
2372
2561
2979
3626

2130
2639
2835
3273
3947

30" (Do = 31.496) PIPE


Width of Trench (ft)
3.5
4.0
4.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

704
789
798
847
933

718
802
811
858
944

729
813
821
868
952

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

892
1006
1022
1090
1207

915
1028
1043
1109
1225

934
1046
1060
1125
1240

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1211
1383
1416
1525
1705

1256
1428
1458
1565
1744

1293
1465
1493
1597
1774

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1466
1696
1748
1900
2145

1538
1768
1816
1965
2208

1597
1827
1871
2018
2259

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1672
1954
2027
2223
2533

1770
2055
2123
2316
2624

1852
2139
2203
2392
2699

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

1837
2169
2262
2501
2875

1962
2299
2388
2624
2997

2068
2409
2493
2726
3098

193

2142
2673
2886
3358
4087

2401
2974
3195
3689
4448

2640
3248
3474
3983
4765

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

30" (Do = 31.496) PIPE


Width of Trench (ft)
3.5
4.0
4.5

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2025
2423
2548
2849
3314

2188
2597
2718
3018
3485

2329
2746
2862
3160
3627

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2160
2615
2769
3126
3677

2358
2830
2981
3342
3899

2531
3016
3164
3524
4084

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2229
2716
2887
3280
3884

2446
2956
3127
3525
4139

2640
3166
3334
3735
4354

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2346
2898
3108
3578
4301

2606
3193
3407
3891
4635

2843
3458
3672
4165
4923

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2414
3012
3252
3783
4605

2705
3351
3600
4156
5012

2975
3660
3915
4488
5369

Depth
of
Cover

Trench
Backfill

36" (Do = 39.370) PIPE


Width of Trench (ft)
4.0
4.5
5.0

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

898
1003
1014
1073
1180

912
1016
1026
1084
1190

923
1027
1036
1094
1199

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1144
1285
1304
1387
1531

1167
1308
1325
1406
1550

1186
1326
1342
1422
1564

194

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

36" (Do = 39.370) PIPE


Width of Trench (ft)
4.0
4.5
5.0

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1570
1786
1823
1956
2180

1617
1831
1866
1996
2218

1655
1869
1901
2029
2249

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1922
2210
2270
2456
2760

1996
2283
2339
2522
2824

2058
2345
2397
2577
2876

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2213
2569
2654
2895
3281

2315
2674
2754
2990
3374

2403
2762
2837
3070
3450

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2452
2874
2985
3280
3747

2585
3011
3116
3408
3872

2699
3127
3227
3515
3976

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2735
3247
3397
3772
4356

2911
3432
3577
3950
4534

3065
3592
3732
4100
4683

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2947
3537
3726
4177
4873

3164
3771
3955
4406
5105

3356
3974
4153
4602
5303

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3058
3695
3908
4406
5173

3300
3958
4168
4668
5443

3516
4189
4394
4895
5673

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3258
3992
4259
4864
5794

3554
4322
4591
5207
6154

3823
4619
4885
5508
6467

195

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover
30

Depth
of
Cover

Trench
Backfill
Granular w/o Cohesion
Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

Trench
Backfill

36" (Do = 39.370) PIPE


Width of Trench (ft)
4.0
4.5
5.0
3381
4188
4500
5195
6265

3719
4575
4894
5610
6711

4031
4927
5249
5980
7104

42" (Do = 44.375) PIPE


Width of Trench (ft)
4.5
5.0
5.5

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1027
1145
1156
1222
1341

1040
1157
1168
1233
1351

1051
1168
1177
1241
1359

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1315
1474
1493
1585
1747

1337
1495
1512
1603
1763

1355
1512
1528
1617
1777

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1822
2064
2103
2250
2500

1866
2107
2143
2287
2535

1903
2143
2176
2318
2564

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

2250
2574
2637
2843
3183

2319
2643
2702
2904
3242

2379
2702
2757
2956
3291

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2610
3014
3104
3371
3802

2708
3113
3198
3460
3889

2793
3198
3278
3536
3962

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

2913
3394
3513
3841
4364

3042
3525
3638
3961
4482

3153
3638
3745
4064
4582

196

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

42" (Do = 44.375) PIPE


Width of Trench (ft)
4.5
5.0
5.5

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3282
3869
4032
4452
5110

3455
4049
4206
4622
5279

3607
4206
4356
4768
5422

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3566
4250
4458
4966
5754

3783
4479
4681
5187
5977

3975
4681
4876
5379
6168

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3720
4461
4697
5262
6134

3963
4722
4953
5517
6394

4180
4953
5178
5740
6618

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

4005
4872
5174
5869
6937

4309
5206
5506
6208
7289

4584
5506
5803
6508
7597

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

4192
5156
5516
6323
7565

4544
5554
5916
6740
8007

4869
5916
6279
7114
8398

Depth
of
Cover

Trench
Backfill

48" (Do = 50.570) PIPE


Width of Trench (ft)
5.0
5.5
6.0

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1185
1319
1331
1405
1540

1197
1331
1341
1414
1549

1208
1340
1350
1423
1556

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

1523
1704
1723
1826
2009

1544
1723
1742
1843
2025

1561
1740
1757
1857
2038

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

2126
2401
2442
2606
2889

2168
2442
2480
2642
2922

2204
2477
2512
2672
2951

197

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

48" (Do = 50.570) PIPE


Width of Trench (ft)
5.0
5.5
6.0

Granular w/o Cohesion


Sand and Gravel
Sat. Top Soil
Dry Clay
Sat. Clay

2643
3012
3079
3310
3694

2711
3079
3142
3369
3751

2769
3137
3195
3419
3798

10

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3086
3548
3644
3943
4432

3183
3644
3735
4030
4515

3266
3728
3814
4104
4586

12

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3466
4017
4146
4514
5108

3593
4146
4268
4631
5221

3704
4257
4373
4732
5318

15

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

3937
4614
4793
5267
6016

4110
4793
4965
5433
6179

4263
4950
5114
5578
6321

18

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

4311
5105
5334
5911
6811

4529
5334
5556
6129
7029

4724
5537
5752
6320
7219

20

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

4516
5381
5644
6288
7287

4764
5644
5900
6541
7542

4986
5878
6127
6765
7765

25

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

4910
5933
6275
7075
8306

5224
6275
6613
7416
8658

5511
6584
6916
7720
8967

30

Granular w/o Cohesion


Sand and Soil
Sat. Top Soil
Dry Clay
Sat. Clay

5178
6329
6742
7681
9125

5549
6742
7155
8107
9571

5892
7119
7530
8490
9968

198

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

54" (Do = 56.960) PIPE


60" (Do = 63.400) PIPE
Width of Trench (ft)
5.50
6.00
6.50
6.50
7.00
7.50

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

1349
1499
1511
1593
1744

1360
1510
1521
1602
1753

1370
1519
1529
1610
1760

1525
1691
1702
1792
1959

1534
1700
1710
1800
1966

1542
1708
1718
1806
1972

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

1739
1941
1962
2076
2281

1758
1960
1979
2092
2296

1775
1976
1994
2105
2308

1976
2199
2219
2344
2569

1992
2215
2233
2357
2582

2006
2228
2246
2368
2592

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

2442
2750
2793
2976
3292

2482
2790
2830
3009
3323

2517
2823
2861
3038
3351

2802
3143
3184
3382
3730

2835
3175
3215
3410
3756

2865
3204
3241
3434
3779

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

3053
3468
3539
3794
4225

3119
3533
3599
3851
4278

3176
3589
3651
3900
4325

3535
3995
4064
4341
4814

3591
4049
4115
4388
4858

3640
4097
4160
4429
4898

10

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

3585
4105
4207
4539
5086

3679
4199
4296
4622
5166

3761
4281
4372
4695
5235

4187
4764
4867
5225
5827

4268
4845
4942
5296
5894

4339
4915
5008
5358
5953

15

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

4629
5399
5592
6120
6960

4802
5575
5760
6283
7120

4955
5731
5909
6425
7258

5515
6379
6577
7151
8079

5667
6534
6723
7291
8215

5804
6672
6853
7416
8335

18

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

5102
6008
6258
6904
7918

5321
6237
6479
7119
8131

5518
6441
6674
7309
8318

6142
7169
7428
8135
9258

6340
7372
7622
8322
9442

6519
7554
7796
8490
9605

20

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

5366
6358
6646
7368
8495

6730
7868
8161
8948
10198

6937
8081
8364
9146
10392

5616
6621
6901
7619
8746
199

5842
6857
7128
7842
8967

6503
7632
7934
8728
9980

HANDBOOK OF PVC PIPE


TABLE 6.1 - EARTH LOADS IN TRENCH CONDITIONS (lbs/Lft) - Continued
Depth
of
Cover

Trench
Backfill

54" (Do = 56.960) PIPE


60" (Do = 63.400) PIPE
Width of Trench (ft)
5.50
6.00
6.50
6.50
7.00
7.50

25

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

5885
7068
7448
8353
9752

6208
7415
7789
8696
10100

6502
7730
8097
9001
10409

7238
8604
9012
10019
11586

7538
8922
9321
10325
11893

7814
9212
9602
10601
12169

30

Granular w/o Cohesion


Sand and Gravel
Saturated Top Soil
Dry Clay
Saturated Clay

6250
7594
8059
9131
10780

6637
8019
8481
9562
11227

6993
8408
8865
9951
11627

7784
9358
9868
11076
12941

8152
9755
10258
11468
13341

8493
10120
10615
11824
13703

200

TABLE 6.2 - PRISM LOAD (lbs/Lft)


Nominal Pipe Diameter, Inches
Height of
Cover (ft)
3

10

12

Soil Wt.
(lb/ft3)

10

12

15

18

21

24

27

30

36

42

48

54

60

100
110
120
130

105
116
126
137

157
173
188
204

210
231
252
273

263
289
315
341

313
344
375
406

383
421
459
497

468
514
561
608

551
606
661
717

620
682
744
806

699
769
839
908

787
866
945
1024

984
1083
1181
1280

1109
1220
1331
1442

1264
1391
1517
1644

1424
1566
1709
1851

1584
1742
1901
2059

100
110
120
130

141
155
169
183

209
230
251
272

280
308
336
364

350
385
420
455

417
458
500
542

510
561
612
663

623
686
748
810

735
808
882
955

827
909
992
1075

932
1025
1118
1211

1050
1155
1260
1365

1312
1444
1575
1706

1479
1627
1775
1923

1686
1854
2023
2191

1899
2089
2278
2468

2112
2323
2534
2746

100
110
120
130

211
232
253
274

314
345
377
408

420
462
504
546

525
578
630
683

625
688
750
813

765
842
918
995

935
1029
1122
1216

1102
1213
1323
1433

1240
1364
1488
1612

1398
1537
1677
1817

1575
1732
1890
2047

1969
2165
2362
2559

2219
2441
2663
2884

2529
2781
3034
3287

2848
3133
3418
3702

3168
3485
3802
4118

100
110
120
130

281
309
337
365

418
460
502
544

560
616
672
728

700
770
840
910

833
917
1000
1083

1020
1122
1224
1326

1247
1371
1496
1621

1470
1617
1764
1911

1654
1819
1984
2150

1864
2050
2236
2423

2100
2310
2520
2730

2625
2887
3150
3412

2958
3254
3550
3846

3371
3708
4046
4383

3797
4177
4557
4937

4224
4646
5069
5491

100
110
120
130

351
386
422
457

523
575
628
680

700
770
840
910

875
963
1050
1138

1042
1146
1250
1354

1275
1403
1530
1658

1558
1714
1870
2026

1837
2021
2205
2388

2067
2274
2480
2687

2329
2562
2795
3028

2625
2887
3150
3412

3281
3609
3937
4265

3698
4068
4438
4807

4214
4636
5057
5478

4747
5221
5696
6171

5280
5808
6336
6864

100
110
120
130

422
464
506
548

628
690
753
816

840
924
1008
1092

1050
1155
1260
1365

1250
1375
1500
1625

1530
1683
1836
1989

1870
2057
2244
2431

2205
2425
2646
2866

2480
2728
2976
3224

2795
3075
3354
3634

3150
3465
3780
4094

3937
4331
4724
5118

4438
4881
5325
5769

5057
5563
6068
6574

5696
6266
6835
7405

6336
6970
7603
8237

NOTE: For OD used in calculations, see end of Table.

TABLE 6.2 (continued) - PRISM LOAD (lbs/Lft)


Nominal Pipe Diameter, Inches
Height of
Cover (ft)
14

16

18

20

22

24

Soil Wt.
(lbs/ft3)

10

12

15

18

21

24

27

30

36

42

48

54

60

100
110
120
130

492
541
590
639

732
805
879
952

980
1078
1176
1274

1225
1348
1470
1593

1458
1604
1750
1896

1785
1964
2142
2321

2182
2400
2618
2836

2572
2829
3087
3344

2894
3183
3472
3762

3261
3587
3913
4240

3675
4042
4409
4777

4593
5052
5512
5971

5177
5695
6213
6730

5900
6490
7080
7670

6645
7310
7974
8639

7392
8131
8870
9610

100
110
120
130

562
618
674
731

837
920
1004
1088

1120
1232
1344
1456

1400
1540
1680
1820

1667
1833
2000
2167

2040
2244
2448
2652

2493
2743
2992
3242

2940
3234
3528
3821

3307
3638
3968
4299

3727
4100
4472
4845

4199
4619
5039
5459

5249
5774
6299
6824

5917
6508
7100
7692

6743
7417
8091
8765

7595
8354
9114
9873

8448
9293
10138
10982

100
110
120
130

632
695
759
822

941
1035
1130
1224

1260
1386
1512
1638

1575
1733
1890
2048

1875
2063
2250
2438

2295
2525
2754
2984

2805
3086
3366
3647

3307
3638
3968
4299

3720
4092
4465
4837

4193
4612
5032
5451

4724
5197
5669
6142

5906
6496
7087
7677

6656
7322
7988
8653

7586
8344
9103
9861

8544
9398
10253
11107

9504
10454
11405
12355

100
110
120
130

703
773
843
913

1046
1150
1255
1360

1400
1540
1680
1820

1750
1925
2100
2275

2083
2292
2500
2708

2550
2805
3060
3315

3117
3429
3740
4052

3675
4042
4409
4777

4134
4547
4961
5374

4659
5125
5591
6056

5249
5774
6299
6824

6562
7218
7874
8530

7396
8135
8875
9615

8428
9271
10114
10957

9493
10443
11392
12341

10560
11616
12672
13728

100
110
120
130

773
850
927
1005

1150
1265
1381
1496

1540
1694
1848
2002

1925
2118
2310
2503

2292
2521
2750
2979

2805
3086
3366
3647

3429
3771
4114
4457

4042
4446
4850
5255

4547
5002
5457
5911

5125
5637
6150
6662

5774
6352
6929
7507

7218
7940
8661
9383

8135
8949
9763
10576

9271
10198
11125
12053

10443
11487
12531
13575

11616
12778
13939
15101

100
110
120
130

843
927
1012
1096

1255
1381
1506
1632

1680
1848
2016
2184

2100
2310
2520
2730

2500
2750
3000
3250

3060
3366
3672
3978

3740
4114
4488
4862

4409
4850
5291
5732

4961
5457
5953
6449

5591
6150
6709
7268

6299
6929
7559
8189

7874
8661
9449
10236

8875
9763
10650
11538

10114
11125
12137
13148

11392
12531
13670
14810

12672
13939
15206
16474

NOTE: For OD used in calculations, see end of Table.

TABLE 6.2 (continued) - PRISM LOAD (lbs/Lft)


Nominal Pipe Diameter, Inches
Height of
Cover (ft)
26

28

30

32

34

36

Soil Wt.
(lbs/ft3)

10

12

15

18

21

24

27

30

36

42

48

54

60

100
110
120
130

913
1005
1096
1187

1360
1496
1632
1767

1820
2002
2184
2366

2275
2503
2730
2958

2708
2979
3250
3521

3315
3647
3978
4310

4052
4457
4862
5267

4777
5255
5732
6210

5374
5911
6449
6986

6056
6662
7268
7873

6824
7507
8189
8871

8530
9383
10236
11089

9615
10576
11538
12499

10957
12053
13148
14244

12341
13575
14810
16044

13728
15101
16474
17846

100
110
120
130

984
1082
1180
1279

1464
1611
1757
1903

1960
2156
2352
2548

2450
2695
2940
3185

2917
3208
3500
3792

3570
3927
4284
4641

4364
4800
5236
5673

5144
5659
6173
6688

5787
6366
6945
7524

6522
7175
7827
8479

7349
8084
8819
9554

9186
10105
11024
11942

10354
11390
12425
13460

11800
12980
14160
15340

13291
14620
15949
17278

14784
16262
17741
19219

100
110
120
130

1054
1159
1265
1370

1569
1726
1883
2039

2100
2310
2520
2730

2625
2888
3150
3413

3125
3438
3750
4063

3825
4208
4590
4973

4675
5143
5610
6078

5512
6063
6614
7165

6201
6821
7441
8061

6988
7687
8386
9085

7874
8661
9449
10236

9843
10827
11811
12795

11094
12203
13313
14422

12643
13907
15171
16435

14240
15664
17088
18512

15840
17424
19008
20592

100
110
120
130

1124
1236
1349
1461

1673
1841
2008
2175

2240
2464
2688
2912

2800
3080
3360
3640

3333
3667
4000
4333

4080
4488
4896
5304

4987
5486
5984
6483

5879
6467
7055
7643

6614
7276
7937
8598

7454
8200
8945
9690

8399
9239
10079
10919

10499
11549
12598
13648

11833
13017
14200
15383

13485
14834
16182
17531

15189
16708
18227
19746

16896
18586
20275
21965

100
110
120
130

1194
1314
1433
1553

1778
1956
2134
2311

2380
2618
2856
3094

2975
3273
3570
3868

3542
3896
4250
4604

4335
4769
5202
5636

5299
5828
6358
6888

6247
6871
7496
8121

7028
7730
8433
9136

7920
8712
9504
10296

8924
9816
10709
11601

11155
12270
13386
14501

12573
13830
15088
16345

14328
15761
17194
18627

16139
17753
19366
20980

17952
19747
21542
23338

100
110
120
130

1265
1391
1517
1644

1883
2071
2259
2447

2520
2772
3024
3276

3150
3465
3780
4095

3750
4125
4500
4875

4590
5049
5508
5967

5610
6171
6732
7293

6614
7276
7937
8598

7441
8185
8929
9673

8386
9224
10063
10902

9449
10394
11339
12283

11811
12992
14173
15354

13313
14644
15975
17306

15171
16688
18205
19722

17088
18797
20506
22214

19008
20909
22810
24710

NOTE: For OD used in calculations, see end of Table.

TABLE 6.2 (continued) - PRISM LOAD (lbs/Lft)


Nominal Pipe Diameter, Inches
Height of
Cover (ft)
38

40

42

44

46

48

Soil Wt.
(lbs/ft3)

10

12

15

18

21

24

27

30

36

42

48

54

60

100
110
120
130

1335
1468
1602
1735

1987
2186
2385
2583

2660
2926
3192
3458

3325
3658
3990
4323

3958
4354
4750
5146

4845
5330
5814
6299

5922
6514
7106
7699

6982
7680
8378
9076

7854
8640
9425
10211

8852
9737
10622
11507

9974
10971
11968
12966

12467
13714
14961
16207

14052
15457
16863
18268

16014
17615
19217
20818

18037
19841
21645
23449

20064
22070
24077
26083

100
110
120
130

1405
1546
1686
1827

2092
2301
2510
2719

2800
3080
3360
3640

3500
3850
4200
4550

4167
4583
5000
5417

5100
5610
6120
6630

6234
6857
7480
8104

7349
8084
8819
9554

8268
9094
9921
10748

9318
10249
11181
12113

10499
11549
12598
13648

13123
14436
15748
17060

14792
16271
17750
19229

16857
18542
20228
21914

18987
20885
22784
24683

21120
23232
25344
27456

100
110
120
130

1475
1623
1770
1918

2196
2416
2636
2855

2940
3234
3528
3822

3675
4043
4410
4778

4375
4813
5250
5688

5355
5891
6426
6962

6545
7200
7854
8509

7716
8488
9260
10031

8681
9549
10417
11285

9784
10762
11740
12719

11024
12126
13228
14331

13780
15157
16535
17913

15531
17084
18638
20191

17700
19469
21239
23009

19936
21930
23923
25917

22176
24394
26611
28829

100
110
120
130

1546
1700
1855
2009

2301
2531
2761
2991

3080
3388
3696
4004

3850
4235
4620
5005

4583
5042
5500
5958

5610
6171
6732
7293

6857
7543
8228
8914

8084
8892
9701
10509

9094
10004
10913
11823

10249
11274
12299
13324

11549
12703
13858
15013

14436
15879
17323
18766

16271
17898
19525
21152

18542
20397
22251
24105

20885
22974
25062
27151

23232
25555
27878
30202

100
110
120
130

1616
1777
1939
2100

2405
2646
2887
3127

3220
3542
3864
4186

4025
4428
4830
5233

4792
5271
5750
6229

5865
6452
7038
7625

7169
7886
8602
9319

8451
9296
10142
10987

9508
10459
11409
12360

10715
11787
12858
13930

12073
13281
14488
15696

15092
16601
18110
19619

17010
18711
20413
22114

19385
21324
23262
25201

21835
24018
26202
28385

24288
26717
29146
31574

100
110
120
130

1686
1855
2023
2192

2510
2761
3012
3263

3360
3696
4032
4368

4200
4620
5040
5460

5000
5500
6000
6500

6120
6732
7344
7956

7480
8228
8976
9725

8819
9701
10583
11464

9921
10913
11905
12898

11181
12299
13417
14536

12598
13858
15118
16378

15748
17323
18898
20472

17750
19525
21300
23075

20228
22251
24274
26296

22784
25062
27341
29619

25344
27878
30413
32947

NOTE: For OD used in calculations, see end of Table.

TABLE 6.2 (continued) - PRISM LOAD (lbs/Lft)


Nominal Pipe Diameter, Inches
Height of
Cover (ft)
50

Soil Wt.
(lbs/ft3)

10

12

15

18

21

24

27

30

36

42

48

54

60

100
110
120
130

1756
1932
2108
2283

2615
2876
3138
3399

3500
3850
4200
4550

4375
4813
5250
5688

5208
5729
6250
6771

6375
7013
7650
8288

7792
8571
9351
10130

9186
10105
11024
11942

10335
11368
12402
13435

11647
12812
13977
15141

13123
14436
15748
17060

16404
18045
19685
21325

18490
20339
22188
24036

21071
23178
25285
27392

23733
26107
28480
30853

26400
29040
31680
34320

The following values were used for OD:


4" =
6" =
8" =
10" =
12" =
15" =
18" =
21" =
24" =

4.215
6.275
8.400
10.500
12.500
15.300
18.701
22.047
24.803

27" =
30" =
36" =
39" =
42" =
45" =
48" =
54" =
60" =

27.953
31.496
39.370
41.385
44.375
47.370
50.570
56.960
63.360

HANDBOOK OF PVC PIPE

TABLE 6.3 - PRISM LOAD SOIL PRESSURE (lbs/in2)


P = wH
Height of
Cover (ft)

100

Soil Unit Weight (lbs/ft3)


110
120
125

130

1
2
3
4
5

0.69
1.39
2.08
2.78
3.47

0.76
1.53
2.29
3.06
3.82

0.83
1.67
2.50
3.33
4.17

0.87
1.74
2.60
3.47
4.34

0.90
1.81
2.71
3.61
4.51

6
7
8
9
10

4.17
4.86
5.56
6.25
6.94

4.58
5.35
6.11
6.88
7.64

5.00
5.83
6.67
7.50
8.33

5.21
6.08
6.94
7.81
8.68

5.42
6.32
7.22
8.13
9.03

11
12
13
14
15

7.64
8.33
9.03
9.72
10.42

8.40
9.17
9.93
10.69
11.46

9.17
10.00
10.83
11.67
12.50

9.55
10.42
11.28
12.15
13.02

9.93
10.83
11.74
12.64
13.54

16
17
18
19
20

11.11
11.81
12.50
13.19
13.89

12.22
12.99
13.75
14.51
15.28

13.33
14.17
15.00
15.83
16.67

13.89
14.76
15.63
16.49
17.36

14.44
15.35
16.25
17.15
18.06

21
22
23
24
25

14.58
15.28
15.97
16.67
17.36

16.04
16.81
17.57
18.33
19.10

17.50
18.33
19.17
20.00
20.83

18.23
19.10
19.97
20.83
21.70

18.96
19.86
20.76
21.67
22.57

26
27
28
29
30

18.06
18.75
19.44
20.14
20.83

19.86
20.63
21.39
22.15
22.92

21.67
22.50
23.33
24.17
25.00

22.57
23.44
24.31
25.17
26.04

23.47
24.38
25.28
26.18
27.08

31
32
33
34
35

21.53
22.22
22.92
23.61
24.31

23.68
24.44
25.21
25.97
26.74

25.83
26.67
27.50
28.33
29.17

26.91
27.78
28.65
29.51
30.38

27.99
28.89
29.79
30.69
31.60

206

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

TABLE 6.3 - Continued


100

Soil Unit Weight (lbs/ft3)


110
120
125

130

36
37
38
39
40

25.00
25.69
26.39
27.08
27.78

27.50
28.26
29.03
29.79
30.56

30.00
30.83
31.67
32.50
33.33

31.25
32.12
32.99
33.85
34.72

32.50
33.40
34.31
35.21
36.11

41
42
43
44
45

28.47
29.17
29.86
30.56
31.25

31.32
32.08
32.85
33.61
34.38

34.17
35.00
35.83
36.67
37.50

35.59
36.46
37.33
38.19
39.06

37.01
37.92
38.82
39.72
40.63

46
47
48
49
50

31.94
32.64
33.33
34.03
34.72

35.14
35.90
36.67
37.43
38.19

38.33
39.17
40.00
40.83
41.67

39.93
40.80
41.67
42.53
43.40

41.53
42.43
43.33
44.24
45.14

Height of
Cover (ft)

Live Loads: Underground, PVC pipe may also be subjected to live


loads from different sources such as highways and railways. Live loads
should always be considered when designing for shallow burial depths.
However, under conditions of deep burial, the effect of live loads diminish
and can be ignored.
Several methods exist for calculating these live loads. The design
approach presented here is based on the Boussinesq formula for a point
load at the surface of a semi-infinite elastic soil:
EQUATION 6.8
C P(I )
WL = L f
12
Where: WL
CL
P
If
Note:

=
=
=
=

live-load on pipe, lbs/Lin


live-load coefficient per foot of effective length
wheel load, lbs
impact factor, dimensionless (If = 1.35 for 1 < H
< 2, If = 1.15 for 2 < H < 3, and If = 1.0 for H
> 3)

Standard AASHTO H20 truck loading results in an effective single wheel load of
16,000 lbs.

207

HANDBOOK OF PVC PIPE

Tables 6.4 and 6.5 give the live load coefficient CL for a single wheel
load and for two passing trucks, respectively. The design approach taken
in these tables conservatively represents a wheel load as a point load.
Analytical expressions for CL are given below the tables in terms of the
pipe diameter or radius and the height of cover.
TABLE 6.4
LIVE-LOAD COEFFICIENTS FOR SINGLE-WHEEL LOAD
Height of Cover Over Pipe H -- ft
2

0.055
0.068
0.080
0.092
0.104
0.114
0.125
0.143
0.165
0.183
0.196
0.206
0.214
0.219

0.018
0.022
0.026
0.031
0.035
0.039
0.043
0.051
0.062
0.072
0.082
0.090
0.097
0.104

0.008
0.010
0.013
0.015
0.017
0.019
0.021
0.025
0.030
0.036
0.041
0.046
0.051
0.055

Pipe
Diameter
in.
8
10
12
14
16
18
20
24
30
36
42
48
54
60

10

12

14

16

18

0.002
0.002
0.002
0.003
0.003
0.004
0.004
0.005
0.006
0.007
0.008
0.009
0.011
0.012

0.001
0.002
0.002
0.002
0.002
0.003
0.003
0.004
0.005
0.006
0.006
0.007
0.008
0.009

0.001
0.001
0.001
0.002
0.002
0.002
0.002
0.003
0.004
0.004
0.005
0.006
0.007
0.007

Live-Load Coefficient CL
0.005
0.006
0.007
0.008
0.010
0.011
0.012
0.014
0.018
0.021
0.024
0.028
0.031
0.034

0.003
0.004
0.005
0.005
0.006
0.007
0.008
0.009
0.012
0.014
0.016
0.018
0.020
0.022

0.002
0.003
0.003
0.004
0.004
0.005
0.005
0.007
0.008
0.010
0.011
0.013
0.014
0.016

NOTE 1: An effective length of 3.0 ft of pipe is assumed.


NOTE 2:
1 2

CL = 3 ARCSIN H
3

R2 + H2 + 1.52

(R2 + H2) (H2 + 1.52)

1
1

+
RH 2
R + H2 H2 + 1.52
R2 + H2 + 1.52

WHERE: H = earth cover, ft; R = pipe radius, ft; ARCSIN must be in radians.

208

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

TABLE 6.5
LIVE-LOAD COEFFICIENTS FOR TWO PASSING TRUCKS
Height of Cover Over Pipe H -- ft
2

0.0523
0.0654
0.0785
0.0916
0.1047
0.1177
0.1308
0.1570
0.1962
0.2355
0.2747
0.3140
0.3532
0.3925

0.0296
0.0369
0.0443
0.0517
0.0591
0.0665
0.0739
0.0887
0.1108
0.1330
0.1552
0.1773
0.1995
0.2217

0.0169
0.0211
0.0253
0.0295
0.0338
0.0380
0.0422
0.0506
0.0633
0.0760
0.0886
0.1013
0.1139
0.1266

0.0112
0.0140
0.0168
0.0196
0.0224
0.0252
0.0279
0.0335
0.0419
0.0503
0.0587
0.0671
0.0755
0.0838

Pipe
Diameter
in.
8
10
12
14
16
18
20
24
30
36
42
48
54
60

10

12

Live-Load Coefficient CL
0.0081
0.0101
0.0122
0.0142
0.0162
0.0182
0.0203
0.0243
0.0304
0.0365
0.0426
0.0486
0.0547
0.0608

0.0062
0.0077
0.0093
0.0108
0.0124
0.0139
0.0155
0.0186
0.0232
0.0279
0.0325
0.0371
0.0418
0.0464

14

16

18

0.0049
0.0061
0.0073
0.0085
0.0098
0.0110
0.0122
0.0147
0.0183
0.0220
0.0256
0.0293
0.0330
0.0366

0.0039
0.0049
0.0059
0.0069
0.0079
0.0089
0.0099
0.0118
0.0148
0.0178
0.0207
0.0237
0.0266
0.0296

0.0032
0.0041
0.0049
0.0057
0.0065
0.0073
0.0081
0.0097
0.0122
0.0146
0.0171
0.0195
0.0219
0.0244

NOTE 1: An effective length of 3.0 ft of pipe is assumed.


NOTE 2: Coefficients are for 6-ft axle widths, 3.0 ft between passing wheels.
NOTE 3:
CL =

3D
1.5 5
7.5 5
cos tan-1 H + cos tan-1 H



H2

WHERE: D = pipe diameter, ft; H = earth cover, ft.

As mentioned previously, the influence of live loads on the


performance of PVC pipe is only significant in shallow depths. This is
graphically demonstrated by Figures 6.7 and 6.8, which show the total
load on a pipe exposed to live loads and earth loads for highway and for
railway traffic. As can be seen in both of the graphs, as the depth of cover
increases, the influence of the live load diminishes rapidly, illustrating that
there is a depth of cover at which the total load is a minimum. This is
approximately 5 feet for an H20 truck and 13 feet for an E80 Railway
Load. The influence of live loads on PVC pipe as projected for highway,
railroad and airport installations is shown in Table 6.6. The values shown
in Table 6.6 account for the impact and loading factors and can be
converted to live load per unit length (as used in Equation 6.8 - WL) by
multiplying these values by the outside diameter of the pipe.
209

HANDBOOK OF PVC PIPE

With an AASHTO H-20 live load, a 20 ton truckload is simulated in


which 80% (32,000 lbs) is distributed to the rear axle, and evenly divided
into two 16,000-lbs wheel loads. The remaining 20% (8,000 lbs) is
divided over the front axle into two 4,000-lbs wheel loads. The distance
between the front and rear axles is assumed to be 14 feet, with two dualtire wheel loads on each axle. One is centered over the point in question,
and the other located 6 feet away. With impact, the AASHTO LRFD
Bridge Design Specification distribution of the tire foot print is taken as
1.5 feet by 1.67 feet. Similarly, the AREMA2 Cooper E-80 live load
simulates the effect of four 80,000-lbs axles, located 5 feet apart. Each
axle load is assumed to be distributed over a 2-ft by 8-ft area.
TABLE 6.6
LIVE LOADS ON PIPE
Height Live Load Transferred to Pipe, lbs/in2
Of
Cover Highway Railway
Airport
3
(ft)
H201
E802
1
2
3
4
5
6
7
8
10
12

12.50
5.56
4.17
2.78
1.74
1.39
1.22
0.69
*
*

26.39
23.61
18.40
16.67
15.63
12.15
11.11
7.64
5.56

Height Live Load Transferred to Pipe, lbs/in2


Of
Cover Highway Railway
Airport
3
(ft)
H201
E802
14
16
18
20
22
24
26
28
30
35
40

13.14
12.28
11.27
10.09
8.79
7.85
6.93
6.09
4.76

*
*
*
*
*
*
*
*
*
*
*

4.17
3.47
2.78
2.08
1.91
1.74
1.39
1.04
0.69
*
*

3.06
2.29
1.91
1.53
1.14
1.05
*
*
*
*
*

1 Simulates 20 ton truck traffic + impact (Source: ASTM A 796)


2 Simulates 80,000 lbs/ft railway load + impact (Source: ASTM A 796)
3 180,000 lbs dual tandem gear assembly. 26 inch spacing between tires and 66 inch center-to-center spacing

between fore and aft tires under a rigid pavement 12 inches thick + impact.
* Negligible live load influence.

210

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

FIGURE 6.7 - H20 HIGHWAY LOADING

Vertical Soil Pressure (lbs/ft2)


SOURCE: AMERICAN IRON AND STEEL INSTITUTE, WASHINGTON, D.C.

FIGURE 6.8 - COOPER E-80 LIVE LOADING

Vertical Soil Pressure (lbs/ft2)


SOURCE: AMERICAN IRON AND STEEL INSTITUTE, WASHINGTON, D.C.

211

HANDBOOK OF PVC PIPE

AASHTO Design Method


The American Association of State Highway and Transportation
Officials (AASHTO) currently has published two design documents,
which provide specifications for estimation of the effects of live loads
Section 3, in the LRFD Bridge Specifications Manual, is entitled Loads
and Load Factors and from the Standard Specifications for Highway
Bridges, Division 1, Section 3 is entitled, "Loads." A summary of the
method of the former reference, being the more recent of the two, is
captured below.
The contact area of a dual-tire is assumed to be a singular rectangle
with a width (W) of 20 inches and a length (L) of 10 inches. The
equivalent area of loading distribution, realized at pipe depth, can be
calculated as follows:
EQUATION 6.9
A = (W + H)(L + H)
where:

= area of load distribution under fill, ft2


= width of dual-tire, ft
= length of dual-tire, ft
= 1.15 for granular soils
= 1.0 for all other soil types
H = height of cover, ft

A
W
L

Similar to the 60o rule often found in soil mechanics texts, the equation
above applies for burial depths exceeding 2 feet, but not exceeding 8 feet.
The distributive effect of the fill can be ignored at cover depths less than
2 feet, and live loads can be neglected where depth of fill is more than 8
feet. The enlarged contact area, defined in Equation 6.9, is used to
compute the distributed load experienced at the pipe surface, by simply
dividing the wheel load (P) by the area (A).
Design Software External Load Design for Flexible Conduits
The Uni-Bell PVC Pipe Association offers design software that can
calculate the loads described in this chapter, as well as apply the loadings
to estimate the long-term deflection discussed in Chapter VII, Design of
Buried PVC Pipe.
The program can account for either of the earth-loading scenarios
described earlier in this chapter. The Marston earth load (defined by
Equation 6.2) and the prism earth-load options (defined by Equation 6.6)
are both available to the user. Through interactive screens, such as that

212

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

shown in Figure 6.9, the design specifics are obtained (backfill material,
height of cover, compaction effort, etc.), in which the user is prompted to
input data or select from a listing of typical values. Furthermore, units for
input and output are user-defined, allowing for either metric or English
units.
FIGURE 6.9 SAMPLE INPUT SCREEN

With regard to live loads, several options are available. The software
has the capability to simulate standard highway (H20), railway (E80), and
airport live loads, as well as provide for custom live load situations. The
single-wheel, two-trucks-passing, and custom live-loads (in which the
loads and the pattern are user-defined) are all computed, using a method
similar to the Boussinesq method presented earlier in the text. The
software determines the live loads at user-defined depths using Holls and
Newmarks integration of the Boussinesq formula.5 Furthermore, the
software can be used to calculate long-term deflection for flexible pipe
using principles explained in the next chapter, Design of Buried PVC
Pipe.

213

HANDBOOK OF PVC PIPE

FIGURE 6.10 LIVE-LOAD MENU SCREEN

214

CHAPTER VI - SUPERIMPOSED LOADS ON BURIED PIPE

CHAPTER VI
BIBLIOGRAPHY
1.

Airport Runway Depth of Cover Tables, National Corrugated Steel Pipe Association,
Shiller Park, IL.

2.

American Railway Engineering Association Manual for Railway Engineering,


Landover, MD (2000).

3. Barnard, R. E., "Design and Deflection Control of Buried Steel Pipe Supporting Earth
and Live Loads," American Society for Testing and Materials, Philadelphia, PA, Proc.
57 (1957).
4. Cohn, Morris M., By the Magic of Chemistry: Pipe Lines for Progress, CertainTeed
Products Corp., Valley Forge, PA (1975).
5. Gravity Sanitary Sewer Design and Construction, "Manuals & Reports on Engineering
Practice No. 60," American Society of Civil Engineers and "Manual of Practice FD-5,"
Water Pollution Control Federation (1982).
6. Handbook of Steel Drainage and Highway Construction Products, American Iron and
Steel Institute, Donnelley and Sons, Co., New York, NY (1971).
7.

Howard, A. K., "Laboratory Load Tests on Buried Flexible Pipe," Journal AWWA,
Denver, CO (Oct. 1972).

8.

LRFD Bridge Design Specifications, American Association of State Highway and


Transportation Officials, Washington, DC (1999)

9. Manual of Recommended Practice, American Railway Engineering Assoc., AREA


Spec 1-4-28, Chicago, IL.
10. Marston, Anson and A. O. Anderson, "The Theory of Loads on Pipes in Ditches and
Tests of Cement and Clay Drain Tile and Sewer Pipe," Bul. 31, Iowa Engineering
Experiment Station, Ames, IA (1913).
11. Molin, J., "Principles of Calculation for Underground Plastic Pipes - Load, Deflection,
Strain," ISO/TC 138/WG6 (Sweden - 3) 47 (Jan. 1971).
12. Moser, A. P., R. K. Watkins and O. K. Shupe, "Design and Performance of PVC Pipes
Subjected to External Soil Pressure," Buried Structures Laboratory, Utah State
University, Logan, UT (June 1976).
13. Pipeline Design for Water and Wastewater, American Society of Civil Engineers,
New York, NY (1975).
14. Spangler, M. G., "The Structural Design of Flexible Pipe Culverts," Bulletin 153, Iowa
Engineering Experiment Station, Ames, IA (1941).
15. Spangler, M. G. and R. L. Handy, Soil Engineering, Intext Educational Publ., New
York, NY (1973).

215

HANDBOOK OF PVC PIPE

16. Standard Practice for Structural Design of Corrugated Steel Pipe, Pipe Arches, and
Arches for Storm and Sanitary and Other Buried Applications, ASTM A796,
American Society for Testing and Materials, West Conshohocken, PA (1993).

216

Potrebbero piacerti anche