Technical Specification:
This specification covers Reinforced Cement Concrete ( RCC ) bored
Cast in-Situ end bearing Piles by Conventional Method using Tripods,
Bailer, Chisel, Piling Rigs and Drilling Mud Circulation ( DMC ) System
for stabilization of Bore holes sides beyond Guide casing .
Also, including all related items of work like chipping off a small length
at the top, conducting Load tests on single respective Piles, as per
relevant Parts of IS : 2911 ( Latest revisions ).
Contractor's Scope:
The scope of the Contractor, unless otherwise specified, shall include but
not be limited to the following:
a) Providing all labour, supervision, services, materials, piling equipment,
tools, Plants, transportation etc. required for the work for pile
foundations confirming to the detailed approved Construction drawings
or as may be specified, including all surveying and setting out
arrangements necessary for fixing correct locations of piles, etc.
b) The identification plan showing the proposed sequence of piling will be
prepared on the basis of the basic plan furnished by the Engineer, and
the same approved from the competent authority before commencing pile
work.
c) Submission of Daily Progress Report, in the prescribed format, of piling
work done giving all information, as required by the engineer in charge.
d) Furnish details of the pile driving system and casting equipment giving
all salient dimensions and loads.
e) Carry out load tests to the satisfaction of the engineer in charge
including formation of sound Pile Heads and submit the test results in
prescribed data sheet in pursuance to provision under clause 7.13.2 of
IS 2911 (Part I/Sec 2) latest revision.
f) Executing necessary earthwork and approaches for movement of the
equipment for excavation and cleaning up of the work Sites.
TECHNICAL SPECIFICATIONS -PILING
Page 1 of 16
ii)
iii)
v)
IS: 5121 Safety code for Piling and other deep foundations.
vi)
Also, other IS Codes pertaining to the items of Piling work and not listed
above shall deem to come under the purview of this clause.
TECHNICAL SPECIFICATIONS -PILING
Page 2 of 16
Soil data:
The information, as Project Data mentioned vide Scope of Work in good
faith and general guidance only. The Client / Employer will not be
responsible for any discrepancy or inaccuracies therein and shall not
entertain any claim whatsoever from the Contractor on the basis of the
same.
Other data:
Nothing contained in this Contract document or these specifications
shall not relieve the contractor from the responsibility of obtaining the
approval from the engineer in charge, the pile installation procedure to
be followed by him.
During the execution of the work, should any error or inconsistency
appear in any of the contract documents, the contractors shall not
proceeds with the work before obtaining instruction/clarifications from
the engineer in charge.
TECHNICAL SPECIFICATIONS -PILING
Page 3 of 16
Site inspection:
The contractor is directed to inspect the site and satisfy himself about
the working conditions, approach, facilities of water, power utility
services, etc. and he shall deem to be aware of all the site conditions in
so far as the requirements of carrying out pile foundation is concerned.
MATERIALS:
CEMENT:
Sand, to be used for Concreting work shall generally conform to the IS383 and it shall be of approved quality and Zone, clean sharp and free
from injurious amounts of dust, mica, shale, organic matter etc.
COURSE AGGREGATE:
The water shall be clean, free from oil, acid, alkali, organic or other
deleterious MATERIALS and shall conform to IS 456 (latest revision).
REINFORCEMENT IN PILES:
Page 4 of 16
Page 5 of 16
Page 6 of 16
The top surfaces of the piles will be kept rough and treated by keeping
wet and application of near cement coat, before concreting of pile cap to
ensure bond with the pile cap concrete in which they will be ultimately
embedded.
7. In case, the casing is directed to be removed, care shall be taken to
ensure that there is no gap left in the concrete of the pile and that the
reinforcement is not displaced.
INSPECTION AND QUALITY CONTROL:
For cast-in-situ bored RCC Piles, the Contractor shall get inspected the
Bore Hole by the Engineer in Charge for proper Plumb, location, pressure
of water and other requisites.
The diameter of the Bore Hole also to be checked in the case of Bentonite
Slurry circulated Bored Piles by lowering a guide ring through the depth
of the hole.
The depth of the bore hole shall be measured by means of a chain to
which a Plumb Bob weighing not less than 250 gm is attached.
The Contractor shall provide all the equipment required for the above
inspection and he shall co-ordinate this work with the Engineer in
charge.
Concreting shall start only after the Engineer has approved the bore
hole.
All Facilities, equipment and labour required for inspection by the
Engineer mentioned above shall be provided by the Contractor promptly
and free of cost
One test of Cubes shall be cast for each Pile to be installed. Tests of all
cubes shall be carried out in presence of Engineer in charge or his
Representative.
The Contractor shall maintain control quality for all items of work
including materials and every stage as may be directed by the Engineer,
to ensure compliance with contract specifications and shall maintain and
submit to the Engineer, records of the same.
The Quality Control requirements stipulated under relevant clauses vide
IS 2911 and IS 456 for Plain and Reinforced Cement Concrete, wherever
relevant.
Page 7 of 16
Piles that are defective or where the deviation in alignment of the tube or
base is more than that tolerance specified, shall be pulled out or left in
place as per the directions of the Engineer-in-charge. Additional pile
shall be driven to replace them and/or the pile cap shall be redesigned
and built at no extra cost to the client. In case the pile/ casing can not
be removed.
It shall be cut out as may be directed by the Engineer-in-charge. Voids
Resulting from rejected borings or extraction of the pile or casing shall be
filled with gravel or sand unless other piles are installed in such voids.
The contractor shall also not be paid for any expenses incurred by him,
in extracting and rejected pile/ casing and refilling if so required.
Page 8 of 16
In order to determine the carrying capacity of pile, static load tests shall
be undertaken by the contractor on single pile as indicated on drawings.
Piles to be tested shall be Cast in Situ at least 30 days before loading,
before any load test is made, the proposed arrangement of the structure
and Kent ledge to be used in making the load test shall have to be
approved by the Engineer-in-charge.
All load tests shall be made under the supervision of the Engineer-incharge.
All responsibilities for conducting the test safely and properly shall rest
with the contractor.
Preparation of Pile Head for Test:
The Pile head shall be chipped of carefully till sound concrete is met with
and the reinforcement shall either be cut off for initial test or bent
sideways and the top shall be capped by means of a suitably RCC cap. A
bearing plate may be embedded on the top to receive the loading jack.
Procedure for Load Testing:
Page 9 of 16
The reaction to be made available for the test shall be at least 25% more
than the final test load proposed to be applied.
The settlement shall be recorded at least with three dial gauges for single
piles and four dial gauges for group of test piles and positioned at equal
distances along the periphery of the pile and held normally by Datum
bars resting on immovable supporters at least 5 x D, subject to a
maximum 2.5 m away from the test pile periphery where D is the
diameter of the test pile shaft.
Each stage of loading shall be maintained till the rate of movement of the
pile top is less than 0.1 mm per hour in sandy soils and 0.02 mm per
hour in clayey soils.
For this purpose, the soil met with at the tip of the pile shall be
considered. The estimated safe working load on the pile shall be kept in
position for at least 24 hours and during this period settlement readings
shall be recorded every hour.
Each stage of application of the load increment shall be smooth and free
from jerks, time and settlement observations shall be made at the
commencement and completion of the load increment.
Settlement observations shall be made when each increment of load had
been maintained for at least 15 minutes.
The loading shall continue for the specified load for the type of test in
question or failure of the pile, should this occur earlier.
After the proposed working load had been applied and from each
increment thereafter, the test load shall remain in place until there is no
settlement in two hours period.
The total test load shall remain in place until settlement does not exceed
1/2 of a millimetre in 48 hours.
The total test load shall be removed in decrements not exceeding 1/5 of
the total test load.
The rebound shall be recorded after each decrement is affected and the
final rebound shall be recorded after 24 hours from the entire test load
had been removed.
A complete record in triplicate shall be filled with the Engineer or the
loads and readings obtained, duly verified and countersigned by the
Engineer.
Page 10 of 16
Acceptance Criteria:
1. For Routine Vertical Load Tests:
a) This test shall be conducted as far as possible at the cut off level of
the Piles.
In case of pile groups the test shall be conducted after providing
Caps such that the required condition of actual use fulfilled.
(b) The test may be conducted by introducing a hydraulic jack, with
gauge between two piles or pile groups under test or the reaction may be
suitable obtained otherwise these tests may also be done by applying
Lateral pull by a suitable set up. If it is conducted by jack located
between two piles or groups, the full load imposed by the jack shall be
taken as the lateral resistance of each pile or group. I he loading should
be applied in increments of about 20% of the estimated safe load.
(c) After applying each increment of load, the next increment of load shall
be applied after the rate of 0.1 mm / hr in sandy soil and 0.02 mm per
Hour in Clayey soil or two hour which ever is earlier.
(d) Displacements shall be measured by using at least two dial gauge
spaced at 30 cm and kept horizontally one above the other on each pile.
Where it is not possible to locate one of the dial gauges in the line of jack
axis then the two dial gauges may be kept at a distance of 30 cm at a
suitable Location from similar triangles.
Page 11 of 16
Acceptance Criteria:
The safe lateral load on a pile shall be taken as the least of the following:
(a) Fifty percent of the final load at which total displacement increases
to 12 mm.
(b) The load at which the displacement is equal to 5 mm.
(c) Load corresponding to any other displacement specified and dictated
by Performance requirements.
3. Pull out Test:
For initial load Tests, the load applied shall be two times the estimated
Safe load on the pile. The safe load shall be taken as the least of the
following:
(a) One half the load at which the displacement is 12 min or
corresponding to the specified displacement.
(b) One half the load at which the load displacement curve shows a clear
Page 12 of 16
break.
Routine test load shall be carried out to 1.5 times the allowable load, pull
out load in the pile or the load corresponding to 12 mm, pull whichever
is earlier.
(a) Excavation by the Contractor for Pile Cut off shall be done to the
depth Specified on the drawings. These excavations shall be co-ordinated
with the Engineer-in-charge, so that they will remain open for a
minimum possible time and the pile cap concrete is placed as soon as
possible there after.
(b) Any additional excavation carried out due to pile stripping being
required to be carried out below the cut off elevation to obtain dense
Concrete and the backfilling of all such excavation shall be done by the
Contractor at hi own cost.
Cleaning of Work Site:
Page 13 of 16
(b) All excavated material and left over drilling mud shall be disposed off
as may directed by the Engineer-in-charge away from the site and the
cost of all such cleanup operations shall be included by the contractor in
his Rates for piling work and no separate payment will be made for the
same.
MEASUREMENTS:
Measurements:
(a) For the purpose of measurements, the length of the Pile shall be
measured from the termination level of Pile up to Cut off Level plus the
length of Foam / Waste Concrete for each diameter of the Pile installed in
position as per these specifications.
The measurement shall be based on the assumption that the boring of
the pile done by means of a normal bailer through soft soil such as Clay,
Silt, Sand, Soft and Hard Murrum, Gravel and boulders not more than
150 mm in diameter or a mixture thereof .
(b) Measurement of total Bore Depth will be done by lowering down a
Chain with a heavy weight attached at the end, through the Bore Hole
left by driving, before the reinforcement cage is lowered and concreting
commences.
Measurement for the specified depth from Ground Level up to
Termination Level shall be considered.
(c) Empty boring through overburden and though soils of all types
between the Cut off Level of Piles and Ground Level shall be paid per
meter for empty bore.
(d) Reinforcement placed in the Pile shall be measured separately for the
actual Quantity of reinforcement placed in the Pile exclusive of wastage,
avoidable overlaps, couplings, and welded joints, spacer bars and
16 SWG annealed Steel Binding Wire for binding as stipulated in the
relevant avoidable specification for reinforcement.
(e) Load Test to be done as per instruction of JSW/ JSWs engineer.
(f) The Test shall be accepted only if pile test passes load test, otherwise
it will be rejected and the cost shall be borne by the contractor.
XXXXXX
Page 14 of 16
General
Drilling Mud, corresponding to basic properties given under appendix A
under Clause 4.3 of Part I-IS 2911, Sec-2, shall be used to keep the sides
of the bore holes established.
Mud shall have THIXOTROPIC properties i.e. Gel forming property.
The Drilling Mud shall have such properties as to permit the formation of
filter cake on the sides of the bore holes, the thickness of which would
depend on the nature of the subsoil deposit. Sodium based Bentonite
have ideal properties suitable for use as Drilling Mud.
Specifications/ Properties:
The suspension used for Pile Boring work shall satisfy the following
requirements:
Required properties of fresh Sodium based Bentonite:
a) The Liquid Limit shall be more than 300% when tested in accordance
with IS: 2720 (Part V) and less than 450%.
b) The PH value of 5% Bentonite suspension shall be between 8 and
11.5.
c) The free water standing after 24 hours of 10% suspension of 100 0c
shall be only a thin veil of water.
d) Sand content of Bentonite powder shall not be more than 7%.
e) The Marsh Viscosity of 5% suspension when tested by mash concrete
should be around 37 sec.
f) The 10 minute Gel Strength of fresh 5% Bentonite should be between
10 to 75 kg/Sqm
g) The Specific Gravity of the Bentonite solution should be above 1.1 1.
Page 15 of 16
Page 16 of 16