Sei sulla pagina 1di 48

FACTORIES AND MACHINERY

ACT 1967 (FMA 1967)


Chapter 3

Objective:

Control of factories operationswith


respect to safety, health and welfare of
persons
Registration and inspectionof machinery

FKM, UTM

Application

OSHA 1994 supersedes the FMA 1967 in the


event of any conflict
FMA 1967 applies to mainly factories and
construction sites
FMA and OSHA enabling act (give power to
minister to gazette detail regulations)
Contains some general provision on safety,
health and welfare

FKM, UTM

Application
1. FMA - limited to manufacturing industry,
mining and quarrying and construction
2. do not contain detail provisions on specific
matters

Detail provisions are stipulated under the


regulations

FKM, UTM

Arrangement
FMA 1967 divided into 6 parts:

Part 1 Preliminary
Part 2 Safety, health and welfare
Part 3 Persons-in-charge and certificates of
competency
Part 4 Notification of accidents, dangerous occurrence
and dangerous diseases
Part 5 Notice of occupation of factory and registration
and use of machinery
Part 6 General
FKM, UTM

Part 1: Preliminary
Definition of a factory:
a) There must be premises and its boundaries can be
defined;
b) Within the premises there is manual labor doing
process
c) The process must involve the making, altering,
repairing, ornamenting, finishing, cleaning, washing,
breaking up demolition or adapting for sale any article;
andPart I building operations, hoisting machine,
machinery, steam
d) The processes must be for trading.
(Other definitions in boiler)
FKM, UTM

Part 2: Safety, Health and


Welfare
Key points:
1. Premises must be structurally sound with safe access
to work areas, materials and goods must be safely
stacked (Section 10)
2. Machinery must be of sound construction and
dangerous parts must be fenced (Section 14, 15, 16)
3. Employees must not misuse safety and health
equipment (Section 20)
4. Employees not to endanger himself or other person

FKM, UTM

Part 2: Safety, Health and


Welfare
Key points:
5. Premises must be kept in clean state, with
adequate work space, ventilation, lighting and
toilets (Section 22)
6. Persons must be supplied with adequate
facilities for clothing, storage, drinking, water,
first aid and washing facilities (Section 25)
7. Employees must be trained on the safety of
machinery (Section 26)
FKM, UTM

Part 3: Persons-in-charge and


Certificates of Competency
Key points:
Machinery operators must be adequately
trained or under the supervision of a
trained person (Section 26);
Young persons(< 16 years) must not
operate machinery (Section 28)

FKM, UTM

Part 4: Notification of Accidents, Dangerous


Occurrence and Dangerous Diseases
1. The occupier must notify the nearest inspector
of accidents and diseases. Accidents include:
Loss of life;
Injury to a person who loses more than 4 days work
(loss time injury LTI);
Serious damage to machinery or other property
(Section 31).

2. Inspectors may investigate accidents and


dangerous occurrence and hold enquiries into
more serious cases (Section 33)
FKM, UTM

10

Part 5: Notice of Occupation of Factory


and Registration and Use of Machinery
1. Notify Department of Occupational Safety ad Health
(DOSH) within 3 months of the intended start date
(Section 34)
2. Building operations must be notified if last more than 6
weeks (Section 35)
3. Changes to the use of factory or machinery must be
notified to DOSH
4. Fills a standard form together with (a) layout plan of the
factory; (b) list of products to be manufactured; (c) list of
machines to be used; (d) list of chemicals, toxic or
flammable substances to be used, and (e) detail flow
chart of the processes.
FKM, UTM

11

Part 6: General
1. General penalty RM2,000.00
2. Certain sections is RM5,000.00 (Section
51)

FKM, UTM

12

Schedules
Schedule 1
Defines dangerous occurrences to machinery
that need to be notified

Schedule 2
Describes the types of injury that may be
classified as serious bodily injury

Schedule 3
Lists notifiable industrial diseases
FKM, UTM

13

Regulations under the Act


1. Factories and Machinery (Certificates of
Competency Examinations) Regulations,
1970
2. Factories and Machinery (Electric Passenger
and Goods Lift) Regulations, 1970
3. Factories and Machinery (Fencing of
Machinery and Safety) Regulations, 1970
4. Factories and Machinery (Notification of
Fitness and Inspections) Regulations, 1970

FKM, UTM

14

Regulations under the Act


5. Factories and Machinery (Person-In-Charge)
Regulations, 1970
6. Factories and Machinery (Safety, Health and
Welfare) Regulations, 1970
7. Factories and Machinery (Steam Boiler and
Unfired Pressure Vessel) Regulations, 1970
8. Factories and Machinery (Administration)
Regulations, 1970

FKM, UTM

15

Regulations under the Act


9. Factories and Machinery (Compounding of
Offences) Rules, 1978
10. Factories and Machinery (Compounding of
Offences) Regulations, 1978
11. Factories and Machineries (Lead) Regulations,
1984
12. Factories and Machineries (Asbestos Process)
Regulations, 1986

FKM, UTM

16

Regulations under the Act


13. Factories and Machinery (Building Operations
and Works of Engineering Construction)
(Safety) Regulations, 1986
14. Factories and Machinery (Noise Exposure)
Regulations,1989
15. Factories and Machinery (Mineral Dust)
Regulations, 1989

FKM, UTM

17

Factories and Machinery


(Certificates of Competency
Examinations) Regulations, 1970

Factories and Machinery (Certificates of


Competency Examinations) Regulations, 1970
1. Set up the framework for the certificates of competency
required under Factories and Machinery (Persons-InCharge) Regulations
2. Laid down pre-requisite for the application for a
certificate of competency and the examination
procedure
3. All certificates of competency have requirements for
experience and an examination pass before they can be
granted
4. Certificates of competency can be suspended or
cancelled if the holder is medically unfit or in case of
serious misconduct or if judged unfit after an enquiry or
FKM, UTM
19
a court case

Factories and Machinery


(Electric Passenger and Goods
Lift) Regulations, 1970

Factories and Machinery (Electric Passenger


and Goods Lift) Regulations, 1970
1. All new lifting machines (cranes, crab, winch) and
lifting appliances (pulley and chain blocks) have a
manufacturers certificate specifying safe working load
with design drawing and load calculations
2. Apply to lifts used to carry persons and goods
3. Owner to provide detail design to obtain approval from
DOSH (Regulation 6)
4. Capacity of a lift is based on lift car floor area and
displayed clearly on each lift car (Regulation 7)
FKM, UTM

21

Factories and Machinery (Electric Passenger


and Goods Lift) Regulations, 1970
5. Specifications for the following components of
a lift system:
Machine room (Regulation 9)
Lift well (Regulation 10)
Landing doors (Regulation 12 and 13)
Lift car (Regulation 14 to 19)
Suspension system (Regulation 20 to 29)

FKM, UTM

22

Factories and Machinery (Electric Passenger


and Goods Lift) Regulations, 1970
6. Duties of lift owner to maintain the lift (3
monthly inspections and monthly service by
competent person)
7. Enter details of all inspections and
maintenance activities in lift register
(Regulation 31)
8. Owner must display certificate of registration
in the lift car or at the bottom of the landing
(Regulation 32)
FKM, UTM

23

Factories and Machinery


(Notification of Fitness and
Inspections) Regulations, 1970

Factories and Machinery (Notification of


Fitness and Inspections) Regulations, 1970

Details of notification, certificate of fitness


and inspections carried out by DOSH

FKM, UTM

25

Part 1
Specify the forms that must be used to
notify the DOSH officer of a new
occupancy of a factory, the start of
building work, the installation of certain
machinery and the notification of accidents
and diseases

FKM, UTM

26

Part 2
Describes the certificateof fitness that
must be held for steam boilers, UPV and
hoisting machines
Certificateof fitness is valid for 15 months
from the date of inspection (Regulation 10)

FKM, UTM

27

Part 3
1. Governs the inspection of factory or
machinery by DOSH
Factory and machinery inspected at regular
intervals (15 months but up to 36 months at
the discretion of DOSH Regulation 14)
DOSH give advance notice of the inspection
to the occupier
Occupier prepare machinery for inspection
FKM, UTM

28

Part 3
2. DOSH may direct not complying factory
to improve the situation (Regulation 27)
3. Stop work notice may be issued for
machinery without a current certificate of
fitness (Regulation 28)

FKM, UTM

29

Part 4
Inspection fees charged by DOSH

FKM, UTM

30

Factories and Machinery


(Fencing of Machinery and
Safety) Regulations, 1970

Factories and Machinery (Fencing of


Machinery and Safety) Regulations, 1970

1. Safeguarding of machinery
2. All dangerous parts of machine including
the power source and transmission must
be guarded
3. methods of guarding described for
various parts of machine:

Part 2: Prime mover (power source)

Part 3: Transmission machinery

Part 4: Driven machinery


FKM, UTM

32

Part 4 specifies the methods for


guarding different types of machinery:
1. Abrasive and grinding machinery
2. Machinery using rolls
3. Saws
4. Planers
5. Spindle moulders
6. Grooving and tenoning machine
7. Chain-mortice machine
FKM, UTM

33

Part 4 specifies the methods for


guarding different types of machinery:
8. Mixers
9. Grinding mills
10.Centrifuges
11.Presses
12.Guillotines
13.Conveyors
FKM, UTM

34

Other machinesmust also be securely fenced


Other form of guardings switches and
interlocks
Workers trainedin the operation of certain
dangerous machines and aware of the dangers
of such machines
Six schedules gives further specificationfor the
materials and dimensions of machine guards
FKM, UTM

35

Factories and Machinery


(Person-In-Charge)
Regulations, 1970

Factories and Machinery (Person-InCharge) Regulations, 1970


1. Specify persons-in-charge of certain
machinery require certificate of competency
including:
X Steam boiler

X Steam engine

X Internal combustion engine


X Dredge

FKM, UTM

37

Factories and Machinery (Person-InCharge) Regulations, 1970


2. Steam boiler include UPV (pressure v/l) with
steam connected to it
3. Steam boiler and steam engine require steam
boiler drivers certificate of competency or a
steam engine drivers certificate of competency
for smaller boilers (<2000 square feet heating
surface)
4. Larger boiler need an engineers certificate of
competency for steam boiler and steam engine
(Regulation 5)
FKM, UTM

38

Factories and Machinery (Person-In-Charge)


Regulations, 1970
5. IC engines < 100 hp need a holder of IC engine drivers
certificate
6. Larger IC engine need a holder of an IC engine
engineers certificate in charge
7. Dredge operated by steam or IC engine must have a
person who holds an engineers (steam) certificate of
competency or an engineers (IC engine) certificate of
competency or dredgemasters certificate of
competency (Regulation 7)
8. Requirement to provide instruction and training to
operators of certain machinery

Each operator must have a course of instruction and 10 days of


supervision by an experienced operator (Regulation 20)
FKM, UTM

39

Factories and Machinery (Person-In-Charge)


Regulations, 1970

9. Schedule 1 lists machineries that require


a trained operator:
Presses
Saws

Metal working machines


Hoisting machines

FKM, UTM

40

Factories and Machinery


(Safety, Health and Welfare)
Regulations, 1970

Factories and Machinery (Safety, Health


and Welfare) Regulations, 1970

Deal with factory premises and various safety,


health and welfare requirements

FKM, UTM

42

Factories and Machinery (Safety, Health


and Welfare) Regulations, 1970
Key points:
1. Safe means of access and safe place of
employment, provision of edge protection on floor
openings and stairs (Regulation 7, 8)
2. All stairways and floors must be of good construction
and properly maintained; ladders must be of
adequate construction and maintained in a sound
condition (Regulations 9 to 11)
3. Persons must be protected from falls of more than
10 feet by the use of safety belts or ropes
(Regulation 12)
FKM, UTM

43

Factories and Machinery (Safety, Health


and Welfare) Regulations, 1970
Key points:
4. Adequate protection are necessary before
working inside a confined space (Regulation
13)
5. Flammable and dangerous liquids must be
securely stored and precautions taken
against fire and explosion (Regulations 14 to
17, 21, 22)
FKM, UTM

44

Factories and Machinery (Safety, Health


and Welfare) Regulations, 1970
6. Materials and finished goods must be
securely stacked and stored (Regulations
19, 20)
7. Specifications are laid down for cleaning of
surfaces inside factory (Regulation 23)
8. Lighting, ventilation and climate
requirements are all detailed (Regulations
24-29)
FKM, UTM

45

Factories and Machinery (Safety, Health


and Welfare) Regulations, 1970
Key points:
9. Working clothes and protective
equipment (Regulation 32)
10.Welfare facilities such as toilets, drinking
water, washing facilities and first aid
(Regulation 33 to 38)

FKM, UTM

46

Four Schedules of the regulations:

First Schedule specify classes of factories


that do not need internal surfaces white
washed every 12 months;
Second Schedule describes the level of
lighting required in different parts of the factory
Third Schedule lists work activities that need
eye protection or protective screens
Fourth Schedule contents of first aid box