At the onset, a project originates as which of the following?

A statement of work (SOW


A Gantt chart
A series of milestones
Critical path method (CPM)

A work breakdown structure is


a Cost and Performance tracking schedule
a simple list of the activities making up a project
a hierarchy of tasks, subtasks, and work packages
a structure that is incompatible with the Critical Path Method

A Responsibility Chart specifically identifies which of the following?


Customer satisfaction
Commitment to quality
Planning the tasks for a project
Level of inventory

Consulting firms typically use which of the following techniques to plan and monitor the engagements
of the firm or specific projects?
Qualitative forecasting
Quantitative layout
Materials requirements planning (MRP)
CPM/PERT

Which project progress technique includes the essential features of a project plan, budgeted cost of
work scheduled and budgeted cost of work performed?
Gantt chart
Cost analysis
Critical path method
Earned value management
Which of the following would be the result of subdividing a project?
Job categories
Job orders
Work events
Tasks
The vertical axis on a Gantt chart is usually which of the following?
Activities
Cost
Time
Profit

An example of a graphic project report utilized within project management is:


Project proposal
Cost and performance tracking schedule
Humphrey chart
Equipment and supplies chart

Which of the following identifies a key principle of Reengineering?


Merge information-processing work into the real work that produces the information.

Capture information both at the source and where it is interpreted.


Organize around tasks.
Downsize (lay-off) workers and do the same amount of work as before.