Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
TheStructuralEngineer
November 2014
Project focus
Arena Fonte Nova
23/10/2014 11:07
www.thestructuralengineer.org
11
Synopsis
The new Arena Fonte Nova in Salvador de Bahia, Brazil offers an innovative
lightweight solution for a large-span roof. The spoke-wheel system is
enhanced by drawing on stiffness and load-bearing capacity from bracings
in the vertical plane of the tension rings and in the horizontal plane of the
compression ring. This allows prestressing to be reduced to 50% of the
usual level.
Other important features that simplify the design and reduce costs are
concave radial cables with compression elements, using fewer arches with
non-uniform membrane prestress, and a at overall roof slope. The low
prestress brings cost savings both by reducing the weight of all primary
structural elements and also by incurring smaller forces during installation.
Introduction
Design criteria for stadia have expanded signicantly
in the past 50 years: to the basic requirements for
stands and circulation has been added the need
for numerous extended features and facilities for
spectators around the sports venue. The stadium
roof, which must provide effective protection for all
stands against sun and rain, has become one of the
primary aspects of stadia design, in terms of both
architectural quality and cost.
An obvious criterion for roof structures, which
cover ever greater spans, is roof self-weight, which is
related to costs. In the past two decades, spokewheel systems have allowed designers to achieve
record-low self-weights for roofs spanning ever
greater distances. Work to develop and optimise
this type of structure continues, giving rise to a large
number of new and sometimes unique solutions
each year.
One such solution is the Arena Fonte Nova (Figure
1) in Salvador de Bahia, Brazil, which was inaugurated
in April 2013. The design of the arena, which hosted
several matches during the 2013 Confederations
Cup and 2014 FIFA World Cup, includes a lightweight
roof based on a spoke-wheel system. This relies
on the combination of a steel structure and cable
system with comparatively low prestress. As the
authors show, its hybrid structural system employs a
series of features that make the Arena Fonte Nova a
unique stadium, not least in terms of cost.
Background
On 25 November 2007, only a month after being
named one of the venues for the 2014 World Cup,
a tragic accident occurred at the existing Estadio
Fonte Nova, with the failure of part of the concrete
stands. The accident killed seven people and injured
40. Faced with the need to nd a solution quickly,
the authorities decided to demolish the old stadium
and build a new one, with a capacity of 56 500. An
23/10/2014 11:07
Project focus
Arena Fonte Nova
TheStructuralEngineer
November 2014
12
Figure 1
Arena Fonte Nova
roof viewed from inside
Figure 2
Longitudinal
section of stadium
Figure 3
Plan of roof
RFR
23/10/2014 11:07
www.thestructuralengineer.org
13
Figure 5
Convexconcave
study results
RFR
Figure 4
Typical crosssection of roof
Figure 6
Two-chord horizontal compression ring and two braced tension rings
RFR
Membrane roof
Reducing self-weight in a large span requires a
cladding material which is light and exible, yet
strong and durable. Membrane textiles such as
PTFE-coated glass bre comply with all these
requirements: weighing only 1.3kg/m, PTFEcoated glass bre is non-combustible and has a
lifespan of 25 years. Some claddings are still in use
even after 30 years or more of service. However,
special care needs to be taken during handling and
transportation. Only limited folding of glass bre
RFR
Wind loads
Stadium roofs which include form-found membrane
cladding rarely conform to the standard geometries
found in either the codes or the literature for
assessing wind loads. Factors such as roof shape,
concrete bowl shape, openings and scale of the
structure may result in incorrect assumptions being
made about wind load. In particular, in the case of the
Arena Fonte Nova, the large opening at the south end
of the stands meant that strong winds were expected
to be funnelled into the stadium, creating high uplifts
on the north side; these would not be covered by the
codes.
A wind tunnel test (Figure 8) was therefore carried
out by specialist engineers (Wacker Ingenieure,
Germany). Based on the architectural and structural
drawings, Wacker built a 3D physical model of the
roof and concrete bowl at its laboratory at a scale of
1:300.
The most important aspects of the stadiums
immediate topography were also modelled. Rough
elements on the tunnel oor were used to simulate
the wider surroundings in order to provide an
accurate assessment of the wind speed prole and
turbulence of the approaching wind. 450 pressure
taps were installed on the top and bottom surfaces of
the cladding.
The wind pressure coefficients obtained from
the test were later combined with the expected
reference pressure at the project location over the
structural life of the stadium, i.e. a 50-year period. This
resulted in a design gust wind pressure of 0.70KN/m
at a height of 40m. Wacker then produced a series of
plots showing wind pressure and wind suction from
eight different directions, distributed on roof loading
regions. The vertical loads were all multiplied by a
resonance factor of 1.05 a gure calculated from
the eigenfrequencies of the roof.
In addition, a study was carried out on the different
erection phases of the membrane roof. An installation
sequence was agreed upon with the membrane
contractor, and a set of wind loads was provided for
the chosen sequence. This made it possible to detect
critical stages and determine the sizing of temporary
bracing elements.
Figure 7
3D rendering of
structural system of roof
RFR
SCHULITZ
23/10/2014 11:07
14
Project focus
Arena Fonte Nova
TheStructuralEngineer
November 2014
Figure 8
3D model
at 1:300 scale of
stadium within
wind tunnel of
12m length, 2.5m
width and 1.85m
height
Figure 9
Membrane
geometry isoheight
lines and lines of greatest
slope
RFR
Figure 10
Load paths within
typical panel unit (blue:
downward acting loads;
red: upward acting loads)
Robustness
The roof structure, with its two inner tension rings
connected to the outer compression ring, offers a
clear primary load path. Failure somewhere along
this path represents one of the critical scenarios.
However, should an element fail, the roof also offers
several alternative load paths: multiple tension
cables, the ying cross-bracing between the ying
RFR
WACKER
Installation
Erection sequence
In order to provide access to the stands and pitch
23/10/2014 11:07
www.thestructuralengineer.org
15
Figure 13
Installation phases
Figure 11
Check for
structural robustness
a) Start of
phase 1
b) End of phase
1 pinning of
upper system
c) Start of phase 2
ying columns in place,
lower system lifts off
RFR
Figure 12
Installation of freestanding compression ring
RFR
RFR
23/10/2014 11:07
16
Project focus
Arena Fonte Nova
TheStructuralEngineer
November 2014
Figure 14
Intermediate
stage of
installation
ying columns
being installed;
lower cable resting
on platform,
waiting to be
connected to ying
columns
RFR
Figure 15
Force
diagram of big
lift (red: upper
tension ring; blue:
lower tension ring
Figure 16
Jacking
forces for two
sequences (green
ultimately chosen)
RFR
RFR
E
Jacking strategy
The Arena Fonte Nova has only 36 inner roof axes and benets from a
comparably low prestress level. This made it possible to use 28 small
120t jacks and 8 220t jacks for the lifting operation. The jacking strategy
(Figure 16) involved:
Acknowledgments
Client: Arena Fonte Nova consortium (joint venture between OAS and
Odebrecht)
scenarios
pinning the corner axes M2 and M3 with the taller 220t jacks
Conclusion
The new Arena Fonte Nova in Salvador de Bahia offers an innovative
lightweight solution for a large span roof. The spoke-wheel system is
enhanced by mobilising resources in stiffness and load-bearing capacity
from bracings in the vertical plane of the tension rings and in the horizontal
plane of the compression ring. This allows prestressing to be reduced
to 50% of the usual level. Other important features which simplify the
structure and reduce costs are concave radial cables with compression
elements, the use of fewer arches with non-uniform membrane prestress,
and a at overall roof slope. The low prestress level brings cost savings
both by reducing the tonnage of all the primary structural elements,
and due to the smaller forces involved in the installation procedure. The
project involved the use of 1300t of steel, 200t of cables and 28 000m2 of
membrane.
To contact the authors, email: jorge.chenevey@rfr-stuttgart.de,
yu.hui@rfr-shanghai.com or mathias.kutterer@rfr-stuttgart.de
Main contractors:
Steel: Martifer
Cables: Redaelli
Membrane: Taiyo Birdair
Lifting operations: VSL
Supervisors:
Structure: Nelson Szilard Galgoul
Lifting: Schlaich, Bergermann und Partner
Membrane: Tensys
RFR team:
Project director: Mathias Kutterer
Project managers: Yu Hui, Jorge Chenevey Planella
Engineering: Yu Hui, Jorge Chenevey Planella, Michael Bauer,
Pranjal Saraswat
Draftsmen: Illya Osherov, Volker Hass, Hartmut Haker,
Ccile Gosselin-Neubert
23/10/2014 12:05