Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Dated: 05.11.2014
November 2014
Page 1 of 69
RFP
CONTENTS
ARCHITECTURAL, DESIGN AND PROJECT MANAGEMENT
CONSULTANCY SERVICES FOR CONSTRUCTION OF
CONSTRUCTION OF SHRAMODAYA VIDHYALAYA AT
BHOPAL, INDORE, JABALPUR AND GWALIOR
SECTION
TITLE
NOTICE INVITING TENDER
SECTION 1
SECTION 2
LETTER OF INVITATION
INSTRUCTION TO CONSULTANTS
Electronic Tendering System- Guidelines
PAGE NO.
03-04
05
06-13
14-16
DATASHEET
17-19
ANNEXURE I
20-21
ANNEXURE II
22-23
SECTION 3
24-32
SECTION 4
33-37
SECTION 5
TERMS OF REFERENCE
38-48
SECTION 6
49-51
SECTION 7
52-58
SECTION 8
59-66
SECTION 9
APPENDICES I
67
APPENDICES II
68
Page 2 of 69
RFP
Name of Work
Bid Security
(EMD)
(in Rs.)
Cost of
Bid
Document
(in Rs.)
6.00 lacs
15,000/-
6
months
for
Architectural
and
Design Consultancy +
24
Months
for
Construction work +
12 Months of Defect
Liability Period
221
The dates for purchase, submission, etc. are mentioned in the key dates. Tender forms
can be purchased online only upt o 1730 hrs . on 08.12.2014 from website
www.mpeproc.gov.in. The bidders have to submit the Financial Bids online only.
The Addendum/Corrigendum (if any) shall only be published on the website of
ww w. m p rd c. ni c.i n and/or ww w.m pe p ro c. gov .i n only. If holiday is declared by
Govt. of M.P. on the date of physical submission or on the date of opening, the same will
automatically be shifted to subsequent working days.
MPRDC reserves the right to accept/reject any/ all tenders without assigning any
reason thereof.
Managing Director
Page 3 of 69
RFP
MADHYA PRADESH ROAD DEVELOPMENT CORPORATION LIMITED
(Govt. of M.P. Undertaking)
Date: /2014
S.No.
Particulars
Expiry
(End) Date
& Time
Purchase of Tender
10.11.2014
1730 hrs.
08.12.2014
1730 hrs.
09.12.2014
1730 hrs.
10.12.2014
1730 hrs.
Envelopes
Envelope A,
Envelope B,
Envelope C
Envelope A,
Envelope B
Envelope A,
Envelope B
18.12.2014
1030 hrs.
Envelope C
Page 4 of 69
RFP
SECTION 1 - LETTER OF INVITATION (LOI)
1. Govt. of Madhya Pradesh intends to construct Shramodaya Vidhyalaya building at
Bhopal, Indore, Jabalapur & Gwalior for Directorate Public Instruction (Lok
Shikshan Sanchalanalaya, Bhopal.. The main objective for construction of
Shramodaya Vidhyalaya is to provide Education to School Children for Class 6 to 12th
Standard. The Building should have class rooms, Hostels, Laboratory, Library,
Administrative office Play ground, Meeting Hall, Swing pool etc.
2. M.P. Road Development Corporation Ltd. (MPRDC), a company fully owned by Govt.
of M.P., has been assigned the execution of this work
3.
MPRDC (Employer) invites proposals to engage Consultants of repute for above work,
having a full fledged office, with proven experience for Architectural, Design and
Project Management Consultancy. The Consultancy assignment is broadly divided into
the following two major phases. The Consultant shall function as:
(A) Architect to do detailed Engineering Survey including Boring/Trial pit, obtain
approval from competent authorities for any permission related to the work, preparation
of detailed layout plan of complete scheme, design and prepare conceptual/working
drawings for Architectural, Structural & other allied services, preparation of Detailed
Cost Estimate, Bill of Quantities (BOQ), Bid Documents and Technical Specifications
for all works.
(B) Project Management Consultant as the Engineer which involves Project
Management in terms of Detailed Planning, Monitoring, Coordination with other
department/agencies, Supervision of Work , Contract Management, Quality Assurance,
Timely Engineering decision and approval thereof from Employer, Recording of
Measurement/Bills, Assisting in arbitration & litigation cases and all other necessary
steps/decision required for timely completion of Project.
More details on the Services are provided in the attached Terms of Reference.
RFP
SECTION 2 - INSTRUCTIONS TO CONSULTANTS
1. INTRODUCTION
Definitions
1.1
1.2
1.3
1.4
(a)
Page 6 of 69
RFP
1.5
1.6
1.6.1
1.6.2
1.6.3
1.7
(a)
(b)
(c)
Consultant shall bear all costs associated with the preparation and submission
of their proposals and contract negotiation. The Client is not bound to accept
any proposal, and reserves the right to annul the selection process at any time
prior to Contract award, without thereby incurring any liability to the
Consultant.
The client requires that consultants provide professional, objective, and
impartial advice and at all times hold the Clients interest paramount, without
any consideration for future work, and strictly avoid conflicts with other
assignments or their own corporate interests.
A Consultant (including its Personnel) or any of its affiliates shall not be hired
for any assignment that, by its nature, may be in conflict with another
assignment of the Consultant to be executed for the same or for another Client.
For example, a Consultant hired to prepare engineering design for an
infrastructure project shall not be engaged to prepare an independent
environmental assessment for the same project.
A Consultant (including its Personnel) that has a business or family relationship
with a member of the Clients staff who is directly or indirectly involved in any
part of (i) the preparation of the Terms of Reference of the assignment, (ii) the
selection process for such assignment, or (iii) supervision of the Contract, may
not be awarded a Contract, unless the conflict stemming from this relationship
has been resolved in a manner acceptable to the client throughout the selection
process and the execution of the Contract.
Consultants have an obligation to disclose any situation of actual or potential
conflict that impacts their capacity to serve the best interest of their Client, or
that may reasonably be perceived as having this effect. Failure to disclose said
situations may lead to the disqualification of the Consultant or the termination
of its Contract.
It is the Clients policy that the consultants observe the highest standard of
ethics during the selection and execution of such contracts. In pursuance of this
policy, the Client:
defines, for the purpose of this paragraph, the terms set forth below as follows:
(i)
corrupt practice means the offering, giving, receiving, or
soliciting, directly or indirectly, of anything of value to influence the
action of a public official in the selection process or in contract
execution;
(ii)
fraudulent practice means a misrepresentation or omission of
facts in order to influence a selection process or the execution of a
contract;
(iii) collusive practices means a scheme or arrangement between two
or more consultants with or without the knowledge of the Client,
designed to establish prices at artificial, noncompetitive levels;
(iv)
coercive practices means harming or threatening to harm, directly
or indirectly, persons or their property to influence their participation
in a procurement process, or affect the execution of a contract.
will reject a proposal for award if it determines that the Consultant
recommended for award has, directly or through an agent, engaged in corrupt,
fraudulent, collusive or coercive practices in competing for the contract in
question;
will declare a firm ineligible, either indefinitely or for a stated period of time, to
be awarded a contract if it at any time determines that the firm has engaged in
Page 7 of 69
RFP
(d)
1.8
1.9
1.10
2.0
2.1
2.2
3.
3.1
3.1 A
Page 8 of 69
RFP
3.2
3.3
Technical Proposal
In preparing the Technical Proposal, consultants are expected to examine the
documents comprising this RFP in detail. Material deficiencies in providing the
information requested may result in rejection of a Proposal.
While preparing the Technical Proposal, consultants must give particular
attention to the following:
(i)
3.4
3.4.1
Page 9 of 69
RFP
3.4.2
3.5
Audio visual Presentation by top Seven (7) ranked Consultants for best
illustrated completed building project of same type & nature.
The Technical Proposal shall not include any financial information. A
Technical Proposal containing financial information may be declared non
responsive.
Financial Proposal
3.6
3.7
3.8
In preparing the Financial Proposal, Consultants are expected to take into account
the requirements and conditions of the RFP documents. The Financial Proposal
should follow Standard Form (Section 4). It shall include all costs associated
with the Assignment, including remuneration for staff and other incidental
expenses; which is a major component of the assignment. The rates to be
quoted shall be inclusive of all taxes, duties, cess, etc. (Excluding Service
Tax). The rates are to be filled in Indian National Rupees only.
The Financial Proposal should clearly identify as a separate amount, the local
taxes (including social security), duties, fees, levies and other charges imposed
under the applicable law, on the Consultants and their personnel (other than
nationals or permanent residents of the Employers country); unless the Data
Sheet specifies otherwise.
The Consultant is required to quote rates, including all taxes and duties but
excluding service tax as below;
Architectural and Design Consultancy:- In terms of Percentage (%) of the
total value of works awarded to complete the project. However, till
finalization of the Work Contracts, the initial payment to the consultant as
per the schedule mentioned in the Terms of Reference will be made on the
basis of Probable Amount of Work and the balance amount, if any, will be
adjusted in subsequent payments based on the value of works awarded. This
shall include all office expenditure, traveling charges of experts/staff to
project site, offices of other departments in Bhopal or outside to obtain any
type of permissions/clearances , MPRDC office at Bhopal, all perks payable
to experts/staff, out of pocket expenses and any other charges payable to
experts/staff.
Project Management Consultancy: - In terms of remuneration of
professional field staff designated at S.No. 6 to 10 in Annexure-I on Man
month basis. Remuneration shall include Salary, all type of perks to be paid
by the firm to the staff, any type of taxes and all other incidental expenses to
be born by the staff.
3.9
The Financial Proposal should be submitted online only and shall not be
considered by any other mode.
4.
4.1
4.2
Page 10 of 69
RFP
4.3
For each Proposal, the consultant should prepare the number of copies indicated in
the Data Sheet. Each Technical Proposal should be marked Original. If there are
any discrepancies between the original and the copies of the Proposal, the original
governs.
4.4
First envelop shall contain Earnest Money Deposit. The original and all copies of the
TECHNICAL PROPOSAL shall be placed in a sealed envelope clearly marked
TECHNICAL PROPOSAL The envelopes containing the EMD and Technical
Proposals shall be placed into an outer envelope and sealed. This outer envelope
shall bear the submission address, reference number and be clearly marked DO NOT
OPEN, EXCEPT IN PRESENCE OF THE OFFICIAL APPOINTED, BEFORE [insert the
time and date of the submission deadline indicated in the Data Sheet]. The Client
shall not be responsible for misplacement, losing or premature opening if the outer
envelope is not sealed and/or marked as stipulated. This circumstance may be case
for Proposal rejection. If the Financial Proposal is submitted physically, this will
constitute grounds for declaring the Proposal non-responsive. The completed
Technical Proposal must be delivered at the submission address on or before
the time and date stated in the Key Dates (Physical Submission (EMD and
Technical Bids) in the Office of MPRDC, Bhopal). Any Proposal received after
the closing time for submission of proposals shall be returned unopened.
4.5
At the time of opening of proposals, outer envelope shall be opened and the
envelope containing the EMD shall be opened first and if found in order the
Technical Proposal shall be opened by the evaluation committee. The date and time
of opening the Technical Proposal is specified in the Data Sheet/Key Dates. Online
Financial offers of the technically qualified firms shall be publicly opened.
5.
PROPOSAL EVALUATION
5.1
5.2
General
5.3
First Stage Evaluation :- The evaluation committee will evaluate the proposals on the
basis of their responsiveness to the Terms of Reference, applying the evaluation
criteria, and point system specified in the Data Sheet. A proposal shall be rejected at
this stage if it does not respond to important aspects of the Terms of Reference or if
it fails to achieve the minimum technical score indicated in the Data Sheet. Top (7)
seven ranked consultant shall be considered for the Second stage evaluation. EMD
of unsuccessful consultant shall be returned. Each responsive proposal will be given
a technical score based on the following criteria .
Page 11 of 69
RFP
5.4
Second stage Evaluation: - Top (7) Seven ranked consultants are required to
demonstrate Audio Visual Presentation for the proposed building and the best
illustrated completed project of same type & nature before the high power committee
appointed by the Govt. of M.P./Client along with the submission of the hard copy of
presentation on the date and time mention in the Data Sheet. Submissions done by
the consultants (Soft and Hard copy) shall be the property of employer. Consultants
qualified for this stage shall be paid an honorarium of Rs. 50, 000/- (Rupees Fifty
thousand only). Honrarium of successful consultant shall be adjusted from their fee
during the course of consultancy services.
5.4.1 The High Power Committee will evaluate the proposals on the basis of their
presentation and top three ranked consultancy selected for opening of their financial
offer.
5.5
The date and time of opening of the financial proposal is mentioned in the Key
Dates.
Public Opening and Evaluation of financial Proposals; Ranking
5.6
The opening date should allow Consultants sufficient time to make arrangements for
attending the opening. The financial proposals of non qualified firms (except top
three ranked firms) will not be opened.
5.7
The Financial Proposals shall be opened publicly in the presence of the consultants
representatives who choose to attend. The name of the consultant, the proposed
prices shall be read aloud and recorded when the Financial Proposals are opened.
The Client shall prepare minutes of the public opening.
The Evaluation Committee will correct any computational errors. When correcting
computational errors, in case of discrepancy between a partial amount and the total
amount, or between word and figures the formers will prevail. In addition to the
above corrections, as indicated under para. 3.6, activities and items described in the
Technical Proposal but not priced, shall be assumed to be included in the prices of
other activities or items. In case an activity or line item is quantified in the Financial
Proposal differently from the Technical Proposal, (i) if the Time-Based form of
contract has been included in the RFP, the Evaluation Committee shall correct the
quantification indicated in the Financial Proposal so as to make it consistent with
that indicated in the Technical Proposal, apply the relevant unit price included in the
Financial Proposal to the corrected quantity and correct the total Proposal cost, (ii) if
the Lump-Sum form of contract has been included in the RFP, no corrections are
applied to the Financial Proposal in this respect. The evaluation shall exclude those
taxes, duties, fees, levies, and other charges imposed under the applicable law;
The firm offered lowest Financial Proposal shall be invited for negotiations.
5.8
5.9
6.
6.1
6.2
NEGOTIATIONS
Negotiations will be held at the date and address indicated in the Data Sheet.
Negotiations will include a discussion of the Technical Proposal, the proposed
technical approach and methodology, work plan, and organization and staffing, and
any suggestions made by the Consultant to improve the Terms of Reference. The
Client and the Consultants will finalize the Terms of Reference, staffing schedule,
Page 12 of 69
RFP
6.3
6.4
6.5
7.
7.1
7.2
8.
8.1
work schedule, logistics, and reporting. These documents will then be incorporated
in the Contract as Description of Services. Special attention will be paid to clearly
defining the inputs and facilities required from the Client to ensure satisfactory
implementation of the assignment. The Client shall prepare minutes of negotiations,
which will be signed by the Client and the Consultant.
It is the responsibility of the Consultant, before starting financial negotiations, to
contact the local tax authorities to determine the local tax amount to be paid by the
Consultant under the Contract. The financial negotiations will include a clarification
(if any) of the firms tax liability in the Clients country, and the manner in which it
will be reflected in the Contract; and will reflect the agreed technical modifications
in the cost of the services. Unless there are exceptional reasons, the financial
negotiations will involve neither the remuneration rates for staff nor other proposed
unit rates.
Having selected the firm on the basis of least cost, the Client expects the submission
of CVs of the experts designated in the Proposal at the time of contract negotiation.
During contract negotiations, the Client will require assurances that the experts will
be actually available.
Negotiations will conclude with a review of the draft Contract. To complete
negotiations the Client and the Consultant will initial the agreed Contract. If
negotiations fails, the Client may invite the Consultant to negotiate a Contract whose
Financial Proposal is the second lowest.
AWARD OF CONTRACT
After completion of negotiations with the consultants, the Client shall award the
Contract to the selected Consultant. Within 15 days from the date of issue of Letter
of Acceptance and before signing the agreement, the selected consultant has to
submit a Performance Guarantee as mentioned in the General Conditions of the
Contract. If the selected Consultant fails to submit the Performance Guarantee within
the time prescribed above, the EMD of the selected consultant will be forfeited and
the proposal of selected consultant will be rejected. Once the agreement is signed
with the successful agency the EMD of all agencies shall be refunded.
The firm is expected to commence the Assignment on the date and at the location as
instructed by the client.
CONFIDENTIALITY
Information relating to evaluation of proposals and recommendations concerning
awards shall not be disclosed to the consultants who submitted the proposals or to
other persons not officially concerned with the process, until the winning firm has
been notified that it has been awarded the contract.
Page 13 of 69
RFP
For more details please contact: Tata Consultancy Services, 5th Floor, D.B. Mall, M.P.Nagar,
Bhopal (M.P). Tel.: 18002748484,18002745454 08965065346,
03. Digital Certificate
Page 14 of 69
RFP
The Bidders are strictly advised to follow the time schedule (Key
Dates) of the Tender for their side for tasks and responsibilities to
participate in the Tender, as all the stages of each Tender are
locked before the start time and date and after the end time and date
for the relevant stage of the Tender as set by the concerned
Department Official.
07. Purchase of
Tender Documents
The Bidders have to prepare their Bids online, encrypt their Bid
Data in the Bid Forms and submit Bid in all the envelopes and
documents required to be uploaded related to the Tender as per the
time schedule mentioned in the key dates of the Notice Inviting
Tenders after signing of the same by the Digital Signature of their
authorized representative.
The Bidder shall submit the following in three separate envelopes
online:
1.
Bid Security (Scanned Copy)
-Envelope 'A'
2.
Technical Bid
-Envelope 'B'
3.
Financial Bid
-Envelope 'C'
Page 15 of 69
RFP
to be submitted Online only and shall not be considered by
any other mode.
09. Withdrawal,
Substitution, and
Modification of
Bids
10. Opening of
Tenders
Page 16 of 69
RFP
DATA SHEET
(This Section consists of provisions that are specific to and supplement the information
or requirements included in Section 2 Instruction to Consultants)
Clause
Description
Reference
1.1
1.1
1.2
Name of Assignment :
Name of Work
1.2
EMD (INR)
6.00 lacs
1.3
Contacting Person :
Dy. General Manager (Procurement)
1.4
1.10
2.1
2.1
Page 17 of 69
RFP
3.1
3.1 A
3.1 A
3.3 (i)
3.3 (ii)
The estimated number of professional staff required for the work is enclosed at
Annexure-II
3.3 (iii)
3.7
The rates quoted under the financial proposal shall be inclusive of all statutory
duties, taxes, levies, octoroi, cess, etc. but excluding service tax. Consultants are
requested to consult tax consultants for details.
4.3
4.4
4.4
4.5
5.3
5.3
RFP
A firm to be qualified in the technical evaluation shall have to attain a
minimum technical score of 750 marks (75% of 1000).
5.4
6.1
7.2
Page 19 of 69
RFP
ANNEXURE-I
II
III
I.(a)
Description
Max.
Points
600
50
250
100
1000
I.(b)
Note: More than one awards for a single project shall be treated as one award
only.
Page 20 of 69
RFP
II.
III.
C.
D.
E.
Second Stage Evaluation:- Top7 ranked consultant shall be invited for second stage
I.
II.
COMPLETED
Page 21 of 69
RFP
Annexure-II
BROAD QUALIFICATION AND EXPERIENCE REQUIREMENTS
OF PROFESSIONAL STAFF
Broad qualifications and experience of the professionals given below are clients' perception
in respect of the specific requirement of the project. Consultants are advised to prepare the
CVs of their proposed personnel specifically highlighting the qualification and experience in
the related area of expertise as per requirements. The CVs should also highlight higher
education, training and publication of technical papers etc., by the personnel in the related
field as well as their experience in providing training in the related fields. The CVs of the
proposed personnel should reflect size of the project handled in terms of costs, duration for
which services were provided, type of contract document used etc. Broadly speaking,
qualification and experience higher than the minimum requirement will be given higher
weightage.
TABLE 1
Sn.
Particulars
No. of
Persons
Minimum
Qualification
Minimum
Experience
Duration
Requirement
Deduction
per day for
non
deployment
-
Principal
Architect
Cum Team
Leader
01
Bachelors in
Architecture
and
Membership in
Council of
Architecture or
Indian Institute
of Architects
15 years
(5 yrs in
Building
Projects)
Full duration
(Intermittently)
Structural
Design
Engineer
01
M.Tech/ME in
Structural
Engineering
Full duration
(Intermittently)
Design
Electrical
Engineer and
BMS Expert
01
B.E. Electrical
As and when
required
(Intermittently)
Assistant
Engineer
(Civil)
04
Bachelors
Degree in Civil
Full Time
(24 Months)
Junior
Engineer
(Electrical)
04
Bachelors
Degree in
Electrical
Assistant
Architect
04
Bachelors
Degree in
Architecture
10 years
( 5 yrs in
Building
Projects)
10- years
( 5 yrs in the
field of
Electrical
design of
Buildings
10 years
( 5 yrs in
Building
Projects)
7 years
(5 yrs in
Building
Projects)
05 years
(3 yrs in
Building
Projects)
1.25 times
the
Remunerati
on quoted
1.25 times
the
Remunerati
on quoted
1.25 times
the
Remunerati
on quoted
Full Time
(24 Months)
10 Months
Page 22 of 69
RFP
7
Field
Engineer
04
Diploma in
Civil
Lab
Technician
04
Diploma in
Civil/BSc
5 years
(3 yrs in
Building
Projects)
5 years
(3 yrs in the
field of
Material
Testing)
Full Time
(24 Months)
Full Time
(24 Months)
1.25 times
the
Remunerati
on quoted
1.25 times
the
Remunerati
on quoted
Note:
1. It is desirable that the majority of the professional staff proposed be permanent
employees of the firm or have an extended and stable working relation with it.
2. At least two CVs for each proposed following Professional Staff shall be
submitted at the time of contract negotiation. Professional staff securing 750 or
more marks shall be called for personal interview with all original documents. If,
for any designation, no Professional staff secures 750 or more marks, new CVs
shall be submitted. Professional staff selected in interview can only be deployed
for his respective assignment on this project.
Each expert is to be evaluated against the tasks assigned in accordance
with following three main criteria:
(i) General qualification: (20%)
(ii) Total, Relevant Task and Project related experience: (75%)
(iii)Permanent Employment : (5 %) Only if they have worked for the current
employer on a regular/permanent full-time basis continuously for the last 12
months.
3. Maximum age limit for all professionals is 60 Years.
4. Input of Professional Staff at Sn. 3, 4, 5 shall be for full duration during the
Architectural, Design Consultancy period and thereafter intermittently as and
when required during the execution of their related work.
5. Remuneration of Professional Staff at Sn. 1 to 5 and any other Professional
expert, in addition to above mentioned, shall be included in the Fee quoted for
Architectural, Design Consultancy.
6. Professional Staff at Sn. 1 to 5 are expected to visit the Project Site at regular
interval during the execution of their related work to ensure the execution of
work as per specification.
7. Professional Staff at Sn. 1 to 5 are expected to be present during the inspection of
Employers authority.
Page 23 of 69
RFP
SECTION 3. TECHNICAL PROPOSAL STANDARD FORMS
3A
3B
Firms references
3C
3D
3E
Description of the methodology and work plan for performing the assignment
3F
3G
3H
Page 24 of 69
RFP
3A.
To,
The Managing Director,
M.P. Road Development Corporation Ltd.
45-A, Arera Hills, Bhopal (M.P.)
Subject: Technical proposal for Architectural, Design and Project Management
Consultancy Services for Construction of Shramodaya Vidhyalaya at Bhopal, Indore,
Jabalpur and Gwalior.
Sir/ Madam,
We, the undersigned, offer to provide the consulting services for Architectural,
Design and Project Management Consultancy Services for Construction of Shramodaya
Vidhyalaya at Bhopal, Indore, Jabalpur and Gwalior in accordance with your Request for
Proposal dated ............... We are hereby submitting our Proposal, which includes
Technical Proposal and a Financial Proposal sealed under a separate envelope.
If negotiations are held during the period of validity of the Proposal, we undertake
to negotiate on the basis of the proposed staff. Our Proposal is binding upon us and subject
to the modifications resulting from contract negotiations.
We understand you are not bound to accept any Proposal you receive.
We remain,
Yours sincerely,
Authorised Signatory
Name and Title of Signatory:
Name of Firm:
Address:
Page 25 of 69
RFP
3B-FIRMS REFERENCES
Relevant Services Carried out in the Last Five Years
Which Best Illustrate Qualifications
Using the format below, provide information on each reference assignment for which your
firm/entity, either individually as a corporate entity or as one of the major companies within
an association/JV, was legally contracted.
Assignment Name:
Assignment Period :
Name of Employer :
Actual
Start Actual Completion Value of Consultancy Services Received
(Date /Month / (Date/ Month / (In INR):
Year)
Year)
No. of Staff Provided by the Firm:
No. of Staff Months Provided by the Firm:
Name of Association Firm(s) if any :
Page 26 of 69
RFP
3C.
2011-2012
2012-2013
2013-2014
Average
Page 27 of 69
RFP
3D.
3E.
Page 28 of 69
RFP
3F.
1.
Personnels:
Sn.
Name
1.
To be
assigned later
Position
Principal Architect Cum
Team Leader
Structural
Engineer
Design
Engineer
Expert
Assistant
(Civil)
Engineer
Junior
(Electrical)
Engineer
6
7
8
Task
Design
Electrical
and BMS
Assistant Architect
Field Engineer
Lab Technician
Page 29 of 69
RFP
3G.
Proposed Position:__________________________________________________
Name of Firm: ______________________________________________________
Name of Staff;______________________________________________________
Professional Qualification:_____________________________________________
Date of Birth________________________________________________________
Nationality_______________________
Years with Current Firm/Entity _________________________
Membership in Professional Societies _____________________________________
Detailed Tasks Assigned _______________________________________________Key Qualifications:
(Give an outline of staff members experience and training most pertinent to tasks an
assignment. Describe degree of responsibility held by staff member on relevant previous
assignments and give dates and locations. Use about half a page).
Education
(Summarize college/university and other specialized education of staff member, giving
names of schools, dates attended ,proof of degrees obtained and documentary evidence of
age proof)
Employment Record
(Starting with present position, list in reverse order every employment held). List all
positions held by staff member since graduation, giving dates, names of employing
orgnizations, titles of positions held, source of funding for the projects handled, types of
activities performed and client reference, where appropriate.)
Languages :
(For each language indicate proficiency excellent, good fair or poor, in speaking reading
and writing)
Page 30 of 69
RFP
Summary of the CV
(Furnish a summary of the above CV. The information in the summary shall be precise
and accurate. The information in the summary will have bearing on the evaluation of
the CV).
A)
Education:
i)
Field of Diploma/Graduation and year
ii)
Field of Graduation/Post graduation and year
iii)
Any other specific qualification
B)
Experience
Total experience in Building Project:
Responsibilities held :
S.No.
Position Held
____________ Yrs
Period
From
To
Assignment period
Undertaking :
I, the undersigned certify that to the best of my knowledge and belief, these data correctly
describe me, my qualifications, and my experience. Further I certify that I am available for
the assignment and shall be willing to work for the client for the entire duration of the
position. I have also not left any ongoing project of the client with out its approval and
have not been debarred by the client in past.
Date (Day/Month/Year) :________
Signature of staff member
Note:- CVs should be originally signed in blue ink on each page by both the proposed
professional staff and the authorized representative of the firm along with the proof of age
and qualification. Key information should include number of years working for the
firm/entity, and degree of responsibility held in various assignments. Photocopy or unsigned
CV shall not be considered.
Page 31 of 69
RFP
3H.
Item of
Monthwise Program (in form of Bar Chart)
st nd
Activity (work) [1 , 2 , etc. are months from the start of assignment]
1st 2nd 3rd 4th 5th 6th
Frequency
Every month
By 10th of following Month (3 copies)
Every Quarter
By 10th day of April, July, October and
January
(3 copies)
3. Supervision Manual
4. Completion report
On completion of construction (3
copies)
Once
On completion of Defect Liability
Period(3 copies)
Page 32 of 69
RFP
SECTION 4. FINANCIAL PROPOSAL STANDARD FORM
(On letter head of the firm)
(Location, Date)
To,
The Managing Director,
M.P. Road Development Corporation Ltd.
45-A, Arera Hills, Bhopal (M.P.)
Subject:
Financial Proposal for Consultancy services for Architectural
Consultancy and Project Management Consultancy Services for Construction of
Shramodaya Vidhyalaya at Bhopal, Indore, Jabalpur and Gwalior
.
Sir/Madam,
We, the undersigned offer to provide the services for Architectural, Design and
Project Management Consultancy for Construction of Shramodaya Vidhyalaya at
Bhopal, Indore, Jabalpur and Gwalior in accordance with your Request for Proposal
dated .(Date).. and our proposal (technical & financial).
Our Total financial quote for this job is as under:
Particular
Total Cost for Architectural, Design
and
Project
Management
Consultancy Services including all
taxes, duties, cess, etc. but
excluding service tax
Amount (INR) in
figure
Page 33 of 69
RFP
4A.
SUMMARY OF COSTS
No.
Description
II
Amount in
figures (in INR)
Amount in words
(in INR)
Note: The Payments will be made as per stipulations of the Special Conditions of Contract.
Page 34 of 69
RFP
MPRDC
4B BREAKUP OF COSTS
Particular
PAC
Percenta
ge on
PAC( in
INR)
Amount in
figures (Rs)
23.00
Crore
23.00
Crore
23.00
Crore
23.00
Crore
Total
Note :- 1. The Fee shall be calculated on the basis of Probable Amount of works
initially. Any increase/decrease in Probable Amount of works in
comparison to the awarded value shall subsequently be regulated in line
with awarded value of works.2. This shall include which Architect,
Design and Project Management Consultancy Firm have to incur to
prepare the design and drawings of Civil, Electrical, Mechanical, Air
Conditioning, Intelligent Building Management System, Fire
fighting/Security System, Land Scaping and all other allied services
required to complete the work in all respect including preparation of
BOQ, Bid Document, Technical Specification etc. including cost of
Page 35 of 69
RFP
MPRDC
engaging specialist Consultants for any of these services. Firm has to
submit detailed schedule of payment, on award of work, based on
different services required to be rendered and get approval of the
Employer for reimbursement of claim under this head. The payment will
be regulated according to the approved schedule of payment subjected to
satisfactory completion of particular services.
2.
Page 36 of 69
RFP
MPRDC
Designation of
Professional Staff
Man
months
No. of
Persons
Assistant
Engineer (Civil)
24
04
Junior Engineer
(Electrical)
24
04
10
04
24
04
24
04
3
4
5
Assistant Architect
Field Engineer
Lab Technician
Remuneration
Rate per Man
month in INR
in words
Page 37 of 69
RFP
MPRDC
Architectural, Design
Consultancy Fee
Project Management
Consultancy Fee (Remuneration
for professional Staff)
Percentage/No.
Rate in (INR)
Total
Minus
Advance Repayment
Page 38 of 69
RFP
MPRDC
BACKGROUND
1.1
Building Location
The location of Plot is at Bhopal, Indore, Jabalpur and Gwalior.
2.1
2.2
2.3
Broad Scope of Work of the Professional firm:The selected Consultant is required to do detailed Engineering Survey
including Boring (at least one Bore upto 20 meter depth)/Trial pit, obtain approval
from competent authorities for any permission related to the work, preparation of
Page 39 of 69
RFP
MPRDC
detailed layout plan of complete scheme, design and prepare conceptual/working
drawings, elevation proposals with 3D modeling & renders for Architectural,
Structural & other allied services, preparation of Detailed Cost Estimate, Bill of
Quantities (BOQ), Bid Documents and Technical Specifications for Shramodaya
Vidhyalaya at Bhopal. For other location, the architectural shall be replicated with
suitable modifications as per availability of land, soil survey, geotechnical
investigations, etc. as mentioned below. The Consultant has to submit separate
concept plans, drawings, budgets, Bill of Quantities for each location. However, as
regards Project Management Consultancy, the selected Consultant has to deploy
separate team for each location.
The scope of work of the Consultant may include but not limited to the following.
i. Arranging site survey and all Geo-technical investigation required for structural
design and other purposes, soil investigation etc.
ii. Preparation of Inception reports
iii. Preparation of Concept/Master Plan (2-3 proposal till the satisfaction of
employer)
iv. Preparation of Detailed Project Report on the basis of various proposed schemes
v. The consultant has to prepare sections and elevation drawings of all items, 3D
view/model/computer walk through etc for work(s).
vi. Preparation of budget estimates for review and administrative approval
vii. Preparation of detailed Bill of Quantities, detailed estimates and drawings for
review and approval.
viii. Rate analysis of all the items on the basis of CPWD/MORTH and latest PWD
schedule of rates and for items not covered by PWD SOR, on the basis of
market rate with supporting documents in the standard format/pattern
ix. Preparation of tender documents including tender drawings, BOQ, technical
specification, furnishing copies in sufficient numbers to enable MPRDC call
for tenders.
x. Evaluation of tenders and preparation of tabulation, taking up clarification and
submitting recommendation to MPRDC for award of work.
xi.
Issue of good for construction drawings to the contractor after award of
work.
xii. Site Management and supervision of work at site and quality control by
engaging qualified and experienced site personnel.
xiii. Taking joint measurement of works completed and certification of
Bills for payment by MPRDC.
xiv.
Progress monitoring, reporting and preparing / advising action plan for
expediting the work.
xv. Advising on safety measures.
xvi. Preparation of time lines and programme for project implementation.
xvii. Liaising with Government and local bodies.
xviii. Providing all assistance for statutory approvals.
Page 40 of 69
RFP
2.6
MPRDC
EMPLOYER now invites proposals to engage Consultants of repute with
proven experience for Architectural Consultancy and Construction Management
for the above work.
3. SCOPE OF WORK:
The scope of consultancy services for each major areas includes, but
shall not be limited to following activities broadly divided into the following two
major phases. The Consultant shall function as
(1) Architect to do detailed Engineering Survey including Boring (at least one
Bore upto 20 meter depth)/Trial pit, obtain approval from competent authorities for
any permission related to the work, preparation of detailed layout plan of complete
scheme, design and prepare conceptual/working drawings, elevation proposals with
3D modeling & renders for Architectural, Structural & other allied services,
preparation of Detailed Cost Estimate, Bill of Quantities (BOQ), Bid Documents
and Technical Specifications for all works.
(2) Project Management Consultant as the Engineer which involves Project
Management in terms of Detailed Planning, Monitoring , Coordination with other
department/agencies, Supervision of Work , Contract Management, Quality
Assurance, Timely Engineering decision and approval thereof from Employer,
Recording of Measurement/Bills, Assisting in arbitration & litigation cases and all
other necessary steps/decision required for timely completion of Project.
3.A.
1.
2.
3.
4.
5.
6
7.
8.
9.
RFP
MPRDC
10.
3.B.
1.
DESIGN / TECHNICAL
The scope of work shall include preparation of detailed structural design of
Building and other services. All structural design shall be got vetted by
structural Engineering department of MANIT, Bhopal or any other reputed
engineering collage suggested by MPRDC.
Consultant shall insure that all design and drawing are prepared in
accordance with relevant by-laws of statutory authority, Indian Electricity act
and Indian standard specification.
3.
4.
5.
6.
7.
QUALITY CONTROL
To finalise construction related procedures such as Technical Specifications,
Construction Practices and Quality Assurance.
To prepare, submit and implement a system of Quality Assurance of works;
ensure quality of materials and sources of materials; formulate and implement
sampling and testing procedure and Quality Control measures to ensure required
standards and consistency in quality.
Supervise & approve the setting up of laboratory (including calibration of
equipments) and field tests carried out by the Contractor. Consultant has to get
conducted 100% of the field test in their presence.
Undertake special tests of materials and/or completed works, undertake removal
and substitution of improper materials and /or works as required.
To issue orders for Stoppages of part of work or removal of any unapproved /
rejected work or materials and also covering work which has not been inspected
for acceptance or rejected as unacceptable from site forthwith, recording
reasons for rejection etc.
To advise Employer on progress and quality of the works being executed by the
contractor on Monthly basis in the form of Monthly Progress Report, to the
satisfaction of employer.
Inspect and approve the materials at site as per specifications before they are
used in work.
Page 42 of 69
RFP
MPRDC
8.
3.D.
1.
CONSTRUCTION SUPERVISION
To supervise and monitor that the construction works are in accordance with the
approved technical specifications, Environmental provisions and other
stipulation of contract documents. The construction methods proposed are in
compliance with the stipulations particularly, in relation to construction
equipment and other resource deployment.
To scrutinize and certify whenever required, contractors materials
reconciliation statements prepared by contractor.
To supervise all site work(s), to approve the actions taken by the contractor and
works executed by the contractor. Employer shall take suitable action on the
suggestions deemed fit/all deviations, in terms of, as pointed out by the
Consultant.
A detailed list of pending defects to be carried out by the Contractor will be
handed over to Employer before withdrawal of manpower by the Consultant, in
case of fore closure of the Consultant/contract agreement.
Whenever final measurements are to be made, the Consultants Team Leader
will inform the contractor and Employer 7 days in advance, the Employer may
authorized his representative who will be empowered to participate and check,
if so wishes, any measurements.
Getting the rectification of defects (if any) in the works carried out through the
respective contractor till payment of Final Bill.
Defect Labiality Period is 1 year after the completion.
During the Defect Liability Period, the Principal Architect cum Team Leader,
Structural Engineer of Consultant has to inspect the Building quarterly and
submit the report along with the remedial measures. Consultant will ensure for
rectification of the defects by the Contractor during the defect liability period
and issue Defect Liability Certificate.
Shall be responsible for obtaining good workmanship with respect to lines,
levels, plumb, finish, etc. Shall check all centerlines, dimensions, levels and
plumb at all stages of work with reference to working drawings and shall ensure
correct dimensions of all elements.
Inspection and certification of equipment at manufacturers works for HVAC,
Electrical, Communication, Fire fighting systems or any other equipment will
be planned in coordination with the officer designated by the Employer who
may depute his representative for the inspection.
The consultant should ensure proper functioning of all system before the
eompletion of DLP.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
3.E.
1.
2.
PROJECT MANAGEMENT
To approve construction schedule, method statements material sources,
manpower/machinery deployment plans submitted contractor and review the
same periodically as per PERT.
CONSULTANT shall provide manpower at site timely and only experienced
persons will be provided at site.
Page 43 of 69
RFP
3.
4.
5.
6.
7.
8.1
8.2
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
MPRDC
Review and approve contractors proposed Personnel for positions nominated in
contract.
Approve/suggest modifications in contractors work programme, method
statement and material sources etc.
To prepare manual for maintenance and operation of the facilities during and
after execution of the project submitted by the contractor.
To prepare and issue working drawings timely at site or requisition
new/supplementary drawings, which are not provided.
Check contractor setting out for conformance with the good for
construction/working drawing.
To work out the savings on material and ensure that this benefit/tax concession
passes on to the Employer.
To maintain necessary record like measurement book including taking all
measurement as per PWD system of measurement
Prepare variations calculated by appropriate rate analysis for non-priced works,
using prevailing schedule of Rates as far as possible. The variations proposed to
employer for approval shall have proper reasoning justifying its necessity along
with expected financial implication on the project.
Identify Construction delays and recommend to the contractor the remedial
measure to expedite the progress under intimation to EMPLOYER.
To monitor Project for compliance to the Plans and Designs as detailed in the
estimates, for timely completion and within the Cost Estimates.
To monitor and check the day to day work/activities and certify for payment
when the quality of the works is satisfactory and the quantities are correct
To take measurements required for the purpose of Bill Payments and carry out
all calculation in a manner that Interim Payment Certificate is submitted to the
employer on monthly basis. The IPC shall reach the employer for payment by
First week of every month.
Consultant has to take prior approval of Employer in issuing / approving
variation in quantity exceeds 10% variation of individual items or aggregate
variation exceeds 5% of the contract value. Employers approval should also be
obtained for issuing / approving /sanction of additional cost, sums or cost and
variation of rate and prices.
To maintain a site order book issued by Employer in duplicate at site for the
issuance of time to time instructions and compliance reports which shall be the
property of Employer and shall be duly certified by the Consultant. A copy of
site order book should accompany the IPC along with the copy of the test
reports relevant to IPC.
Maintain record such as good for construction /working /as built drawing, test
data, details of variation, correspondence and diaries in format approved /
specified by Employer. They should also keep measurement record including
measurement books issued by the Employer.
Update cost estimates till completion (25%, 50%, 75% and 100%) of the project
period and submit variation statements as and when required.
To certify and re commend extension to be given to the contractor for delay in
contract for reasons not attributable to the contractor, or else. After approval
from the employer, the Consultant shall issue necessary orders for time
extension.
To issue on behalf of Employer, notes, damages, claims, claims of interest,
penalty etc. wherever applicable to the contractor for Contract Administration.
Page 44 of 69
RFP
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
31.1
MPRDC
Any other activity as per provision of the Agreement.
Analyze, any claims submitted by contractor, and prepare report based on
contractual documents addressing technical & financial issues, and propose
recommendations. Also prepare reply on behalf of Employer.
To mediate and assist in timely resolving disputes between EMPLOYER and
contractor during constructions and also after completion.
Assisting in Arbitration and Litigation cases with contractors/suppliers
including preparation of replies etc.
Submit all relevant details including replies and assist the Employer with
respect to arbitration, litigation etc., and to mediate in resolving disputes
between Employer, Consultant & Contractor.
Assist in replying audit queries and also suggest interpretations of technical
specifications and other contract documents.
Shall preserve field books and measurement books supplied by Employer in
safe custody and shall return the same to Employer after completion of project
or as advised by Employer.
Shall ensure safety of structure by taking all necessary precautions and by not
allowing excessive construction loads such as dumping of excessive materials,
overcrowding on floors and shall avoid such other factors which will endanger
the safety of structure during construction.
Shall ensure that safety of personnel working at site/ inspecting the site by
taking precautions by putting barricades, night lamps, near trenches, pits, open
shafts, lift shafts, edge of floors, terraces and such other places and to insist on
compliance of safety code such as use of helmets, etc, on work site.
The CONSULTANT shall see that advance action is taken by the contractor to
decoration, make suitable provisions for inserts during construction of civil
works for various services like electricity, air conditioning, water supply,
sewage system, interior ventilation etc.
Shall ensure that work proceeds smoothly and not hampered for want of
decisions/ drawings/ clarifications.
A detailed Contract Completion/ Final Report in 6 copies are to be submitted to
the Employer. The Consultant will prepare a comprehensive final completion
report of the construction contract package after completion of the work. The
report shall incorporate summary of the method of construction, the
construction supervision performed, as built construction drawings for all
works, problems encountered and solutions undertaken thereon and
recommendations for future projects of similar nature to be undertaken by the
employer. The Consultant shall submit the self appraisal report within the
prescribed time summarizing the following details:
a. Details of Personnel including substitution made during the assignment.
b. Details of variation orders issued.
c. Details of extension of time granted to the Contractor.
d. Details of Quality Assurance System.
e. Quality observed at site by the Consultant.
f. Details of claims.
g. Special preventive measures for maintenance suggested by the Consultant.
A Quality Assurance Manual in 7 copies, detailing all QA/QC procedures, to be
submitted within 30 days of commencement of services.
Page 45 of 69
RFP
31.2
MPRDC
34.
3.F.
GENERAL
1.
31.3
32.
33.
2.
3.
4.
5.
6.
Page 46 of 69
RFP
7.
8.
9.
10.
11.
MPRDC
The CONSULTANT shall be responsible for any damage or loss on account of
neglect of professional duty or conduct on the part of such staff or Engineers or
others. To this effect, the CONSULTANT shall indemnify Employer.
The Employer shall not be liable for any injury/ death, caused to any official,
employee, representative or agent of the CONSULTANT or their Consultants
working at the site or damage to their properties for any reason whatsoever and
Employer shall not entertain any claim from any person on that behalf. It would
be the responsibility of the CONSULTANT to get their officials, employees,
representatives, agents or their Consultants insured against the possible risks
involved in the discharge of their duties at the work site.
CONSULTANT shall make their own arrangements facilities in the site office
for their staff like furniture, telephone/ fan, Computer, e-mail facility, Fax
etc. The CONSULTANT at their cost will install PCs with requisite software's
for Project Management on site. Electricity for lights, Fan, PC etc. for the site
office will have to be arranged by CONSULTANT.
The CONSULTANT shall not have any objection to Employer maintaining any
Engineering staff at its own cost at the site of work to carry out work and duties
allotted to them by Employer, in respect of all the work at site or other areas
outside the scope of CONSULTANT works for overall surveillance, security
and verifications.
Except with the prior written consent by the Employer, the CONSULTANT and
their representatives shall not any time communicate to any person or entity any
confidential information disclosed to them for the purpose of the services. The
CONSULTANT shall not publicize any information pertaining to Employer
which is discussed with them during course of execution of work in the interest
of project completion.
Particulars
Principal Architect cum Team Leader
Structural Design Engineer
HVAC Design Expert
Design Electrical Engineer and BMS Expert
Fire fighting Expert
Assistant Engineer (Civil)
Junior Engineer (Electrical)
Assistant Architect
Field Engineer
Lab Technician
Page 47 of 69
RFP
MPRDC
3.G.2 The total implementation period for Construction Supervision and Project
Management Consultancy Services will consist of (i) the construction period of
24 months (ii) a Defect Liability Period of 12 months, as per the arrangement
proposed. The site supervision team would be mobilized on the date of actual
commencement of works by the Consultant as decided by the Employer. During
the defect liability period, the Principal Architect cum Team Leader along with
other staff, will be required to inspect the work quarterly.
3.G.3 After award of the contract the Employer expects all the proposed personnel to
be available during implementation of the contract as per the agreed staffing
schedule. The Employer will not consider substitutions during contract
implementation except under compelling circumstances (such as death and/or
extreme nature of ailment for which Medical Certificate shall be produced from
Hospital/Nursing Home). In case of such replacements, the Consultant will
ensure that there is a reasonable overlap between the staff to be replaced and
replacement wherever feasible/possible. Replacement of Professional staff
/personnel shall invite penalty. The new personnel/professional staff shall be
paid @ 90% of the agreed billing rates.
3.H.
DEFICIENCY OF SERVICES:
Deficiencies in the services on part of supervision Consultants may attract penal
provisions in the form of fines, up to a maximum amount of 10% of contract
price and/or debarment etc. by the client. Sample deficiencies include but are
not limited to the following:
Not acting impartially or acting in collusion with contractor in award of
variation, fixation of new rates, etc.
Not keeping proper records regarding quality control, inspection,
rejection/ rectification of work, etc.
Failure to give proper and timely advice to client/contractor to enable
correction during execution.
Delay in design and withholding approvals, etc.
Recommending extension to the contractor with a view to extending
duration of supervision services.
Refusing to give reasons for decisions when called for by the client.
Not being fully conversant with manuals, specifications, standards,
client's/ Ministry's guidelines and requirement of the project to be
followed during construction.
Certifying substandard work for payment.
Not exercising required scrutiny/non approval of temporary
stretch/works.
Lack of proper coordination with contractors and Project Manager/
client's representative other agencies like Municipal Corporation of
Bhopal/Electricity Board etc. to ensure smooth implementation of
projects.
Permitting subletting of any part/ major works without authorisation.
Delay in mobilisation of required staff at any stage of the contract.
Indulging in corrupt, fraudulent, coercive or collusive practices.
Lack of providing expert personnels for work(s)
Page 48 of 69
RFP
MPRDC
3.I.
SUPPORT FROM EMPLOYER
1. The Employer shall provide assistance to the Consultant wherever deemed
necessary, in the form of issuing letters to concerns.
4.
4.1
4.2
Page 49 of 69
RFP
MPRDC
Between
_________________________________________
(Name of Client)
And
___________________________
(Name of Consultant)
Dated:
# This is a draft Contract for Consultancy Services. In case of any ambiguity, the
provisions of TOR / RFP will prevail while framing the Contract Agreement.
Page 50 of 69
RFP
MPRDC
1. FORM OF CONTRACT
COMPLEX TIME BASED ASSIGNMENTS
This CONTRACT (hereinafter called the Contract) is made the _____day of
the
Month
of
_________,
200
____,
between,
on
the
one
hand
_______________(hereinafter
Called the Client) and, on the other hand,
Consultants).
[Note* : If the Consultants consist of more than one entity, the above should be
partially amended to read as follows:
(hereinafter called the Client) and, on the other hand, a joint venture consisting
of the following entities, each of which will be jointly severally liable to the Client for
all the Consultants obligations under this Contract, namely,
_____________________and ________________________(hereinafter called
Consultants)]
WHEREAS
(a) the Client has requested the Consultants to provide Architectural
Consultancy and Project Management Services as defined in the General
Conditions of Contract attached to this Contract (hereinafter called the
Services);
(b) the Consultants, having represented to the Client that they have the required
professional skills, personnel
provide the Services on the terms and conditions set forth in this Contract;
NOW THEREFORE the parties hereto hereby agree as follows:
1.
2.
(a)
(b)
Addendum/Corrigendum;
(c)
RFP Document;
(d)
Technical Submissions.
(e)
Financial Submissions.
(f)
The mutual rights and obligations of the Client and the Consultants shall be as
set forth in the Contract; in particular
Page 51 of 69
RFP
MPRDC
(a)
The Consultants shall carry out the Services in accordance with the
provisions of the Contract; and
(b)
The Client shall make payments to the Consultants in accordance with the
Provisions of the Contract.
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in
their respective names as of the day and year first above written.
Authorized Signatory
For and on behalf of the
MP Road Development Corporation Ltd.
Authorized Signatory
For and on behalf of
M/s .
(.)
Dy. General Manager (Procu.)
()
Authorized Signatory
2. Signature
Name
Name
Page 52 of 69
RFP
MPRDC
2.
2.1.
RFP
MPRDC
2.2.
3.
3.1
4.
4.1.
4.2.
5.
5.1.
5.2.
5.3.
5.4.
6.
RFP
MPRDC
(s) shall be got approved by the consultant from Employer. The Bank
Guarantee (s) shall be released after satisfactory completion of the assignment
and defect liability period.
7
7.1
7.2
8.
8.1.
8.2.
8.3.
8.4.
ARTICLE - 7: CONFIDENTIALITY:
Consultant/MPRDC shall treat all matters in connection with the Contract
as strictly confidential and undertakes not to disclose, in any way,
information, documents, technical data, experience and know-how given to
him by MPRDC / Consultant without the prior written consent of the later.
Consultant further undertakes to limit the access to confidential information
to those of its employees, implementation-partners who reasonably require
the same for the proper performance of the Contract provided however that
Consultant shall ensure that each of them has been informed of the
confidential nature of the confidentiality and non-disclosure provided for
hereof.
ARTICLE - 8: TAXES & DUTIES
Consultant shall pay any and all taxes, duties, levies, etc. which are payable in
relation to the performance of the Contract. The quoted price shall be
inclusive of all such taxes and duties [except Service Tax]. Service Tax shall
be reimbursed by MPRDC as per actual.
Statutory variation in taxes [C.S.T., L.S.T., W.C.T., Withholding Tax,
Service Tax, etc.] and duties, if any, within the contractual 'Completion
Period' shall be borne by MPRDC. No variation in taxes, duties or levies,
other than statutory taxes and duties, shall be payable.
MPRDC shall deduct 'Income Tax' at source at applicable rates.
SERVICE TAX
Quoted prices should be inclusive of all taxes and duties, except Service Tax.
Please note that the responsibility of payment of Service Tax lies with the
Service Provider only. In case Service Tax is applicable for the Tendered
Work, Consultant shall claim the Service Tax indicating rate of
abatement/deduction allowed as per "Service Tax Act" in the 1st Invoice
itself. Consultant providing taxable service shall issue an Invoice, a Bill or as
the case may be, a Challan which is signed, serially numbered, and shall
contain the following:
(a)
Name, Address & Registration No. of such Person/Consultant
(b)
Name & Address of the Person/Consultant receiving Taxable Service
(c)
Description, Classification & Value of Taxable Service provided
(d)
Service Tax Amount
Payments to Service Provider for claiming Service Tax amount will be
made provided the above formalities are fulfilled. In case of statutory
variation in Service Tax during currency of the Contract, the
Consultant shall submit a copy of the 'Government Notification' to
evidence the rate as applicable on the date of submission of Bid and on
the date of revision. Claim for payment of Service Tax / statutory
variation in Service Tax, should be raised within two [02] months
from the date of issue of 'Government Notification' for payment
of differential Service Tax, otherwise claim in respect of above shall
not be entertained for payment of arrears.
Page 55 of 69
RFP
9.
9.1.
9.2.
MPRDC
10.
10.1
11.
11.1.
11.2.
11.3.
11.4.
11.5.
RFP
MPRDC
13.
ARTICLE - 13: ASSIGNMENT
13.1. Consultant shall not have the right to assign or transfer the benefit and
obligations of the Contract or any part thereof to a third party without the prior
expressed approval in writing of MPRDC, which it shall do at its discretion.
However, in event of that, all legal / contractual obligations shall be binding
on Consultant only.
14.
ARTICLE - 14: INDUSTRIAL & INTELLECTUAL PROPERTY
14.1. In order to perform the services, Consultant must obtain at its sole
account, the necessary assignments, permits and authorizations from the
titleholder of the corresponding patents, models, trademarks, names or other
protected rights and shall keep MPRDC harmless and indemnified from and
against claims, proceedings, damages, costs and expenses [including but not
limited to legal costs] for and/or on account of infringements of said patents,
models, trademarks, names or other protected rights.
14.2. All documents, report, information, data, etc. collected and prepared by
Consultant in connection with the scope of work submitted to MPRDC, will
be the property of MPRDC
14.3. Consultant shall not be entitled either directly or indirectly to make use of the
documents, reports given by MPRDC for carrying out of any services with any
third party.
14.4. Consultant shall not, without the prior written consent of MPRDC, be entitled
to publish studies or descriptive article with or without illustrations or data in
respect of or in connection with the performance of services.
15.
ARTICLE - 15: LIABILITIES
15.1. Without prejudice to any express provision in the Contract, Consultant shall
be solely responsible for any delay, lack of performance deficiency in
services, breach of agreement and/or any default under this Contract.
15.2. Consultant shall remain liable for any damages due to its gross negligence
within the next 'twelve [12] months' after the issuance of the provisional
acceptance certificate of the Contract.
15.3. The amount of liability will be limited to 10% of the Contract value.
16.
ARTICLE - 16: TERMINATION OF CONTRACT
16.1. Termination for Default:
MPRDC reserves its right to terminate / short close the Contract, without
prejudice to any other remedy for breach of Contract, by giving one [01]
month's notice if Consultant fails to perform any obligation(s) under the
Contract, and if Consultant, does not cure his failure within a period of 'thirty
[30] days' [or such longer period as MPRDC may authorise in writing] after
receipt of the default notice from MPRDC.
16.2. Termination for Insolvency:
MPRDC may at any time terminate the Contract by giving written
notice without compensation to Consultant, if Consultant becomes bankrupt
or otherwise insolvent, provided that such termination will not prejudice or
affect any right of action or remedy which has accrued or will accrue thereafter
to MPRDC.
Page 57 of 69
RFP
MPRDC
18.
18.1
19.
19.1
19.2
19.3
War / hostilities
Riots or Civil commotion
Earthquake, flood, tempest, lightening or other natural physical disasters
Restrictions imposed by the Government or other statutory bodies,
which prevents or delays the execution of the Contract by Consultant
Consultant shall advise MPRDC by a registered letter, duly certified by the
local Chamber of Commerce or statutory authorities, the beginning and end of
the above causes of delay within 'seven [07] days' of the occurrence and
cessation of such Force Majeure conditions. In the event of delay lasting over
'one [01] month', if arising out of causes of Force Majeure, MPRDC
reserves the right to cancel the Contract and the provisions governing
termination stated under Article-16 shall apply.
For delays arising out of Force Majeure, Consultant shall not claim extension
in completion date for a period exceeding the period of delay attributable to the
causes of Force Majeure and neither MPRDC nor Consultant shall be liable
to pay extra costs provided it is mutually established that Force Majeure
conditions did actually exist.
Consultant shall categorically specify the extent of Force Majeure
conditions prevalent in their works at the time of submitting their Bid and
whether the same have been taken into consideration or not in their quotations.
In the event of any force majeure cause, Consultant or the MPRDC shall not be
liable for delays in performing their obligations under this order and the
completion dates will be extended to Consultant without being subject to price
reduction for delayed completion, as stated elsewhere.
Page 58 of 69
RFP
MPRDC
20
20.1
21
21.1
22
22.1
22.2
23
23.1
Page 59 of 69
RFP
MPRDC
GENERAL INFORMATION
The "Scope of Work and Special Conditions of Contract [SCC]" shall be read in
conjunction with the "General Conditions of Contract [GCC]", "Financial
Proposals" and any other document forming part of the Contract, wherever the
context so requires. Notwithstanding the sub-divisions of the documents into
separate sections, each part shall be deemed to be supplementary of every other
part, and shall be read with and into the Contract so far as it may be practicable
to do so. Where any portion of the GCC is repugnant to or at variance with any
provisions of the SCC, unless a different intention appears the provisions of the
SCC shall be deemed to override the provisions of GCC, and shall to the extent
of such repugnancy or variations, prevail. In case of any contradiction, the
decision of the "Employer/Engineer-in-Charge [EIC]" will be final and binding
on the Contractor.
2.0
ORDER OF PRECEDENCE
In the case of ambiguity in Financial Proposal, Special terms, General
Conditions of Contract, Scope of work etc., the following order of precedence
will prevail:
a)
Fax of Intent / detailed Letter of Award along with statement of agreed
variations and its enclosures and any corrigendum / addendum.
b)
Special terms in conjunction with Scope of Work.
c)
General Conditions of Contract.
3.0
LOCATION
The bidders are requested to visit the site and accustom themselves with the
actual site conditions.
4.0
4.1
RFP
MPRDC
will the fees be deducted up to a variation of + 10% of the awarded cost
as compare to executed cost. However, if the executed cost of each
tender package has more than + 10% variation in comparison to the
awarded cost, the additional fees will be paid / deducted at the quoted
rate of fee on pro-rata basis on the amount beyond + 10% of the awarded
cost subject to a ceiling limit of + 25% of the awarded cost.
In case, if the work is not executed / abandoned / stopped during
any stage of work then the Architectural / Construction Supervision
fees shall be paid up to the stage of work done as per Clause 9.0, Terms
of Payment of special conditions of contract of the tender on the basis of
the awarded cost (if the work has not been awarded then on the basis of
the approved estimated cost).
g)
5.0
The quoted fees shall be inclusive of charges for visit to site, local
transportation and other expenses & all types of taxes, etc. excluding
Service Tax.
TIME SCHEDULE
The following time schedule will be applicable for the tender package.
1.01 (a)
Within 30 days
notification of award.
of
Within 45 days
notification of award.
of
1.02
Within 90 days
notification of award.
of
1.03
Within
120 days
notification of award.
of
1.04(a)
Within
150 days
notification of award.
of
1.04 (b)
1.01(b)
Page 61 of 69
RFP
MPRDC
1.05
To be issued along
with award of work and to
be revised as per the
progress of work and as
per the requirement at site.
1.06
Construction
Management
and
supervision by deploying necessary
technical manpower to ensure
planned progress.
1.07 (a)
1.07 (b)
Within 60
days
after completion of the
work.
NOTE:
The above time schedule will be strictly adhered. However, the same may
deviate on account of authentic valid reasons to be recorded and approved by
EMPLOYERMPRDC.
In case of delay in any of the above stage, the Price Reduction Schedule shall be
applicable on the corresponding stage payment to be paid as per clause 9.0
6.0
6.1
6.2
FINANCIAL PROPOSAL
The "Financial Proposal" shall be read in conjunction with "Scope of Work and
SCC", GCC and any other document forming a part of this Contract.
EMPLOYER agrees that fees quoted by Consultant and accepted by
EMPLOYER shall be paid to them. In case, any activity, though specifically not
covered in the Financial Proposal, but the same is covered under "Scope of
Work and SCC", etc., no extra claim on this account shall be entertained [as
Financial Proposal is to be read in conjunction with other documents forming
part of the Contract].
7.0
8.0
8.1
RFP
MPRDC
8.2
The rates quoted in the Financial Proposal shall be inclusive of all equipments
[if any], supervision, transportation, overheads, profits, etc.
9.0
9.1
TERMS OF PAYMENT
The Architects quoted professional fee for Architectural Design & Project
Management Consultancy Services will be paid based on the awarded cost of
the work as accepted by MPRDC for award of work.
The following are the mode of payment for various stages (As defined in clause
no. 5 of SCC) of work for different sections of work. The stage-wise percentage
(%) payment will be applicable as and when the stage-wise service is completed
in all respect.
No.
Stage
%age payment of quoted
Professional Fee
I
5%
II
15%
III
25%
IV
5%
5%
VI
30%
1.
2.
3.
4.
9.2
9.3
9.4
9.5
5%
10%
RFP
9.6
9.7
10.0
10.1
10.2
10.3
11.0
MPRDC
permission / approval, the same shall be borne by MPRDC. In case the fee /
deposit was made by the architects, the same shall be reimbursed to
Architects on production of documentary evidence having paid / deposit the fee
to statutory authorities in connection with work.
Remuneration of Professional Staff will be paid on man month basis.
During Defect Liability Period Principal Architect cum Team Leader and
Assistant Engineer (Civil) have to visit the site, monthly and submit their report.
A additional visit on the written request of client have to be arranged for which
remuneration will be made @ Rs. 3000/- (Three Thousand Only) per visit and @
Rs. 1000/- (One Thousand Only) per day respectively.
TAX LIABILITIES
The prices quoted in the Financial Proposal should be inclusive of all expenses
of transportation, overheads, profits, etc. The same should also be inclusive of
all taxes [except Service Tax, and cess thereon], duties, levies, statutory
payments, license fees, etc., imposed by the Government of MP Works
Contracts, etc. While quoting the prices, the Bidder shall take into account all
these aspects and no separate payment on any account shall be payable to the
Consultant at a later date.
Consultant shall be liable for timely payment of all taxes, duties & levies
imposed by any Government / Government Department / Agency / Body
including local autonomous bodies from time to time without any extra claim
from EMPLOYER.MPRDC. However, Service Tax payable by the Consultant,
if any, shall be reimbursed on production of receipt thereof.
EMPLOYERMPRDC shall have no liability on these accounts if Consultant
informs EMPLOYER MPRDC for such liability after closing of the agreement.
Income Tax deductions shall be made from all payments to the Consultant as per
rules and regulations in force in accordance with the "Income Tax Act"
prevailing from time to time. However, Consultant shall be entitled to get the
"TDS Certificate" for the amount so deducted in the format prescribed by the
'Income Tax Department'.
DEVIATION
Tender must be submitted without making any additions /alterations. The
bidders shall submit quotation based strictly on terms and conditions and
specifications contained in the Tender Document and not to stipulate any
deviations. Deviations in any manner against any clauses of this tender
document are not allowed and any such deviation if indicated any where
will render the offer non- responsive and shall liable to be rejected .
NOTE: The right to accept the offer will rest with the EMPLOYER.
EMPLOYERMPRDC. MPRDC, however, does not bind himself to accept the
lowest offer and reserves to itself the Authority to reject any / all the offers
received without assigning any reason whatsoever.
12.0
LIABILITIES
The Consultant shall be responsible for any discrepancies, errors or omissions
in the drawings, prepared and supplied by them whether the same shall
Page 64 of 69
RFP
MPRDC
have been approved by Employer or not which shall not be treated as extra
work as per clause 22.4. Upon employers request, Consultant
shall
promptly rectify the deficiency by amending/ replacing/supplementing the
deficient drawings/documents as appropriate at their own expense or else it may
be treated as sufficiency in services as per clause 3.4 of scope of work..
13.0
14.0
FAULTY DESIGN
In case there is any loss or collapse of structure due to the faulty design,
drawings, calculations and specifications, the Architect shall make good these
losses from the total fees payable. The decision of owner in this regard shall be
final and binding.
15.0
15.1
ENGINEER-IN-CHARGE [EIC]
EMPLOYERMD / Chief Engineer of MPRDC" shall nominate the "Engineerin-Charge [EIC]" for the work under the Contract.
The EIC shall look after general supervision and directions of the work. He will
be authorized to stop the work with due permission of EMPLOYER MPRDC,
whenever such stoppage may be necessary to ensure proper execution of the
Contract. He shall also have authority to reject all works, which do not conform
to the specifications.
15.2
15.3
15.4
16.0
SUPERVISION OF WORK
The Architect shall be fully responsible for the soundness of the design of the
works including that of specialized Consultants engaged by him and also for the
progress and quality of works carried out by various contractors at site. They
shall ensure by continuous supervision and inspection of works, as may be
necessary, that the works are carried out strictly in accordance with the approved
drawings and specifications issued by them and as per owners instructions
issued in writing from time-to-time.
17.0
WORKING HOURS
Work may be carried out on all days of the week, including Sundays &
Holidays (excluding restricted Holidays), and extra hours including nights. If
contractor carried out work in shifts to achieve the project completion schedule,
Consultant has to arrange staff, deployed for the work, accordingly. Consultant
Page 65 of 69
RFP
MPRDC
should ensure that all the safety precautions have been followed by the
contractor during the execution of the work.
18.0
19.0
IDENTITY CARDS
The Consultant shall issue 'Identity-Cards' of their personnel to be
deployed inside premises, which shall be required to display prominently
during the period of their stay within the premises and the 'Identity- Cards' shall
have the information as demanded by EMPLOYER MPRDC authorities.
19.0
19.1
20.0
20.1
20.2
20.3
EMPLOYERMPRDC will not be responsible for any accident / mishap with the
Contractor's/ / Consultants employees. The Contractor/ Consultant shall take
necessary action for his employees in case of any incidents.
20.4
EMPLOYERMPRDC shall not provide any medical assistance and shall have
no other liability whatsoever except as expressly provided under the Contract.
21.0
TERMINATION OF AGREEMENT
The Agreement with Architect / Consultant may be terminated at any time on
one months notice by EMPLOYERMPRDC without assigning any reason,
therefore, such termination notwithstanding, the Consultant shall be entitled to
remuneration in accordance with Clause No.5 for works actually done by them
prior to such termination and shall be liable to pay to the EMPLOYERMPRDC
Page 66 of 69
RFP
MPRDC
all damages which, EMPLOYERMPRDC may have become entitled to for
omission or commission on their part upon termination of the Agreement subject
to maximum of 10% of the total fee payable.
22.0
22.1
22.2
22.3
22.4
23.0
Page 67 of 69
RFP
MPRDC
SECTION : 9 - Appendices-I
FORM OF PERFORMANCE SECURITY
(PERFORMAMANCE BANK GUARANTEE)
Bank Guarantee no. . Date
Name of Beneficiary: The Managing Director, Madhya Pradesh Road Development
Corporation Ltd., 45 A, Arera Hills, Bhopal
WHEREAS ___________________ [Name and address of Consultants]1
(hereinafter called the consultants) has undertaken, in pursuance of Contract
No._________________ dated _________ to provide the services on terms and
conditions set forth in this Contract ___________________ [Name of contract and
brief description of works) (hereinafter called the the Contract).
AND WHEREAS it has been stipulated by you in the said Contract that the
Consultants shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligations in accordance with the
Contract;
AND WHEREAS we have agreed to give the Consultants such a Bank
Guarantee; NOW THEREOF we hereby affirm that we are the Guarantor and
responsible to you, on behalf of the Consultants up to a total of ___________ [amount
of Guarantee] ____________________[in words], such sum being payable in the types
and proportions of currencies in which the Contract Price is payable, and we undertake
to pay you, upon your first written demand and without cavil or argument, any sum or
sums within the limits of __________________[amount of Guarantee] as aforesaid
without your needing to prove or to show grounds or reasons for your demand for the
sum specified therein. We hereby waive the necessity of your demanding the said
debt from the Consultants before presenting us with the demand. We further
agree that no change or addition to or other modification of the terms of the
Contract or of the services to be performed there under or of any of the Contract
documents which may be made between you and the Consultants shall in any way
release us from any liability under this guarantee, and we hereby waive notice of
any such change, addition or modification. The liability of the Bank under this
Guarantee shall not be affected by any change in the constitution of the
consultants or of the Bank. Notwithstanding anything contained herein before,
our liability under this guarantee is restricted to Rs.__________
(Rs.__________________) and the guarantee shall remain valid till ________.
Unless a claim or a demand in writing is made upon us on or before ____________
all our liability under this guarantee shall cease. This guarantee shall be valid
until 365 days after the date of issue of the Defects Liability Certificate.
Signature and Seal of the Guarantor ____________
In presence of
Name and Designation 1._____________________ 2. __________________
Signature
Name, address, seal, Phone & Fax no. of the Bank _________________________
Date ______________________________________
1
Give names of all partners if the Consultants is a Joint Venture.
Page 68 of 69
RFP
MPRDC
Appendices-II
Bank Guarantee
........................................................ Banks Name, and Address of Issuing Branch or Office .................................
must be
Page 69 of 69