Sei sulla pagina 1di 3

SN

RFIT NO.

REV

DESCRIPTION

167

2781A-AKT-IRF-02PL-0081

Substrate Preparation and inspection


of Plastering Accessories

LOCATION

Pour 8
G-P/26
Basement

ITP NO.

2781A-AKTITP-02PL0001 REV.D

ACTIVITY
NO.

ASTAD /
KEO
ORIGINATOR
INSPECTIO
N TYPE

Loukia

QC ENGR

DATE &
TIME
RECEIVED
BY KEO

ACTUAL
INSPECTION
DATE & TIME

STATUS

DATE
RECEIVED
BACK FROM
KEO

COMMENTS

STATUS as of
12.6.14

Joan

28-Sep-13

29 Sept-13
15:00

Approved as
Noted

30 Sept-12
15:30

Resubmit

Approved as
Noted

IRFTs
send to
NDIA

missing

168

2781A-AKT-IRF-02PL-0082

Substrate Preparation and inspection


of Plastering Accessories

Pour 4B
T-V/24-29
Basement

2781A-AKTITP-02PL0001 REV.D

Loukia

Joan

29-Sep-13

30 Sept-13
09:00

Approved as
Noted

3 Oct-12
15:30

Resubmit

Rev B Approved
as noted
missing

169

2781A-AKT-IRF-02PL-0082

Substrate Preparation and inspection


of Plastering Accessories

Pour 4B
T-V/24-29
Basement

2781A-AKTITP-02PL0001 REV.D

Loukia

Joan

7-Oct-13

7-Oct-13

Approved as
Noted

8-Oct-13

Resubmit

Approved as
Noted
missing

184

2781A-AKT-IRF-02PL-0088

Substrate Preparation and inspection


of Plastering Accessories

Pour 6
C-D/6-22
GF

2781A-AKTITP-02PL0001 REV.D

Loukia

Joan

2-Oct-13

3 Oct-13
10:30

Approved as
Noted

3 Oct-12
15:30

Resubmit

Rev B Approved
as Noted
missing

185

2781A-AKT-IRF-02PL-0088

Substrate Preparation and inspection


of Plastering Accessories

Pour 6
C-D/6-22
GF

2781A-AKTITP-02PL0001 REV.D

Loukia

Joan

7-Oct-13

7 Oct-13
10:30

Approved as
Noted

8 Oct-12
15:30

Not approved

17 Aug-14
16:00

Resubmit

Approved as
Noted
missing

Pour 8
Refer to attached
plan
BL

479

2781A-AKT-IRF-02PL-0253

Inspection of existing works prior to


abortive works for incorporation of
changes

581

2781A-AKT-IRF-02PL-0312

Works prior to screed casting


(Surface preparation and filler board
installation)

618

2781A-AKT-IRF-02PL-0333

Inspection of existing works prior to


abortive works for incorporation of
changes

619

2781A-AKT-IRF-02PL-0333

Inspection of existing works prior to


abortive works for incorporation of
changes

626

2781A-AKT-IRF-02PL-0339

Inspection of Mock -up regarding field


joints.

Pour 4B
Refer to attached
plan
4F

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

23-Jan-14

23 Jan-14
17:00

Not
Approved

627

2781A-AKT-IRF-02PL-0340

Inspection of existing works prior to


abortive works for incorporation of
changes

Pour 1, 4A, 4B,5,6,


7A, 7B & 8
Refer to attached
plan
1F

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

25-Jan-14

25 Jan-14
17:00

Not
Approved

628

2781A-AKT-IRF-02PL-0340

Inspection of existing works prior to


abortive works for incorporation of
changes

Pour 1, 4A, 4B,5,6,


7A, 7B & 8
Refer to attached
plan
1F

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

1-Feb-14

2 Feb-14
17:00

Approved as
Noted

629

2781A-AKT-IRF-02PL-0341

Inspection of existing works prior to


abortive works for incorporation of
changes

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

25-Jan-14

25 Jan-14
17:00

Not
Approved

630

2781A-AKT-IRF-02PL-0341

Inspection of existing works prior to


abortive works for incorporation of
changes

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

1-Feb-14

2 Feb-14
17:00

Approved as
Noted

Pour 7A
G-Q/1-6
GF
Pour 1, 4A, 4B,5, 7A,
7B & 8
Refer to attached
plan
Pour 1, 4A, 4B,5, 7A,
7B & 8
Refer to attached
plan

Pour 1, 4A, 4B,5, 7A,


7B & 8
Refer to attached
plan
2F
Pour 1, 4A, 4B,5, 7A,
7B & 8
Refer to attached
plan
2F

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

16-Aug-14

16 Aug-14
16:00

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

14-Jan-14

14 Jan-14
09:00

Approved as
Noted

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

21-Jan-14

22 Jan-14
4:00

Not
Approved

2781A-AKTITP-02PL0002 REV.B

Loukia

Joan

28-Jan-14

29 Jan-14
4:00

Approved as
Noted

Resubmit RFIT

Not approved

15 Jan-14
14:00

Resubmit RFIT

Rev B issued

23 Jan-14
20:00

Resubmit

Rev B Approved
as Noted

2 Feb-14
16:00

Resubmit

Approved as
Noted

26 Jan-14
20:00

Resubmit

Not Approved

25 Jan-14
20:00

Resubmit

Rev B Approved
as Noted

2 Feb-14
16:00

Resubmit

Approved as
Noted

25 Jan-14
20:00

Resubmit

Rev B Approved
as Noted

2 Feb-14
16:00

Resubmit

Approved as
Noted

639

2781A-AKT-IRF-02PL-0349

Works prior to screed casting


(Surface preparation and filler board
installation)

Pour 2 & 3
E-G/7-23
BL

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

26-Jan-14

27 Jan-14
17:00

Not
Approved

643

2781A-AKT-IRF-02PL-0352

Works prior to screed casting with


slopes to floor drains prior to
waterproof (Mock-up)

Pour 1
J-L/23-25
GF

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

28-Jan-14

28 Jan-14
20:00

Approved as
Noted

740

2781A-AKT-IRF-02PL-0426

Works prior to screed casting


(Surface preparation & filler board
installation)

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

23-Feb-14

23 Feb-14
16:00

Approved as
Noted

974

2781A-AKT-IRF-02PL-0595

Works prior to screed casting


(Surface preparation & filler board
installation)

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

26-Apr-14

3 May-14
16:00

Approved as
Noted

1007

2781A-AKT-IRF-02PL-0619

Works prior to screed casting


(Surface preparation & filler board
installation)

2781A-AKTITP-02PL0002 REV.B

Michopoulos

Ajay

3-May-14

5 May-14
14:00

1053

2781A-AKT-IRF-02PL-0652

Michopolous

Ajay

15-May-14

1074

2781A-AKT-IRF-02PL-0673

Michopolous

Ajay

1082

2781A-AKT-IRF-02PL-0681

Michopolous

1105

2781A-AKT-IRF-02PL-0700

1118

2781A-AKT-IRF-02PL-0711

Works prior to screed casting


(Surface preparation & filler board
installation)

1124

2781A-AKT-IRF-02PL-0717

Works prior to screed casting


(Surface preparation & filler board
installation)

1125

2781A-AKT-IRF-02PL-0717

Works prior to screed casting


(Surface preparation & filler board
installation)

Works prior to screed casting


(Surface preparation & filler board
installation)
Works prior to screed casting
(Surface preparation & filler board
installation)
Works prior to screed casting
(Surface preparation & filler board
installation)
Works prior to screed casting
(Surface preparation & filler board
installation)

Pour 7B
S-V/6-9
GF

All area
Refer to attached
plan
3F

Area 1,
GL. H-Q / 28 -29
1F

Area 7B, Refer


2781A-AKTattached drawing,
ITP-02PL2F
0004 REV.C
Area-7B & 4B / GL. 2781A-AKTSee attached
ITP-02PLdrawing, 2F
0004 REV.C
Area 1, Refer to
2781A-AKTattached plan, Level ITP-02PL1
0004 REV.C
2781A-AKTAll Area, Refer to
ITP-02PLattached plan, GF
0004 REV.C
Area 7
2781A-AKTRefer to attached
ITP-02PLplan
0004 REV.C
GF
Pour 9C Ramp
2781A-AKTRefer to attached
ITP-02PLplan
0004 REV.C
GF-1F
Pour 9C Ramp
2781A-AKTRefer to attached
ITP-02PLplan
0004 REV.C
GF-1F

28 Jan-14
20:00

Resubmit

Rev B issued

4 Feb-14
14:00

Resubmit RFIT

Rev B issued

1 Mar-14
11:00

Resubmit RFIT

Rev B issued

04 May-14
17:00

Resubmit

Rev B issued

Approved as
Noted

6 May-14
17:00

Resubmit

Rev B issued

17 May-14
11:00

Not approved

22 May-14
17:00

Resubmit

Rev B issued

22-May-14

26 May-14
16:00

Not approved

27 May-14
17:00

Resubmit

Not approved

Ajay

29-May-14

31 May-14
16:00

Approved as
Noted

3 June-14
14:00

Resubmit

Rev B issued

Michopolous

Ajay

11-Jun-14

12 June-14
16:00

Not approved

16 June-14
16:00

Resubmit

Rev B issued

Michopolous

Ajay

22-Jun-14

26 June14
20:00

Approved as
Noted

30 June-14
17:00

Resubmit

Rev B issued

Kostas

Ajay

17-Jul-14

19 July-14
11:00

Not approved

19 July-14
20:00

Resubmit

Rev B Not
Approved

Kostas

Ajay

3-Aug-14

3 Aug-14
16:00

Not approved

4 Aug-14
16:00

Resubmit

Not approved

SN

RFIT NO.

REV

DESCRIPTION

167

2781A-AKT-IRF-02PL-0081

Substrate Preparation and inspection of


Plastering Accessories

169

2781A-AKT-IRF-02PL-0082

Substrate Preparation and inspection of


Plastering Accessories

185

2781A-AKT-IRF-02PL-0088

479

2781A-AKT-IRF-02PL-0253

581

2781A-AKT-IRF-02PL-0312

619

2781A-AKT-IRF-02PL-0333

626

2781A-AKT-IRF-02PL-0339

628

2781A-AKT-IRF-02PL-0340

630

2781A-AKT-IRF-02PL-0341

639

2781A-AKT-IRF-02PL-0349

643

2781A-AKT-IRF-02PL-0352

740

2781A-AKT-IRF-02PL-0426

974

2781A-AKT-IRF-02PL-0595

1007

2781A-AKT-IRF-02PL-0619

1053

2781A-AKT-IRF-02PL-0652

1074

2781A-AKT-IRF-02PL-0673

1082

2781A-AKT-IRF-02PL-0681

1105

2781A-AKT-IRF-02PL-0700

1118

2781A-AKT-IRF-02PL-0711

1125

2781A-AKT-IRF-02PL-0717

LOCATION
Pour 8
G-P/26
Pour 4B
T-V/24-29

Substrate Preparation and inspection of


Pour 6
Plastering Accessories
C-D/6-22
Inspection of existing works prior to
Pour 8
abortive works for incorporation of
Refer to attached
changes
plan7A
Pour
Works prior to screed casting (Surface
G-Q/1-6
preparation and filler board installation)
GF
Inspection of existing works prior to
Pour 1, 4A, 4B,5,
abortive works for incorporation of
7A, 7B & 8
changes
Refer to attached
Pour 4B
Inspection of Mock -up regarding field
Refer to attached
joints.
plan
Inspection of existing works prior to
Pour 1, 4A, 4B,5,6,
abortive works for incorporation of
7A, 7B & 8
changes
Refer to attached
Inspection of existing works prior to
Pour 1, 4A, 4B,5,
abortive works for incorporation of
7A, 7B & 8
changes
Refer to attached
Pour 2 & 3
Works prior to screed casting (Surface
E-G/7-23
preparation and filler board installation)
BL
Works prior to screed casting with
Pour 1
slopes to floor drains prior to waterproof
J-L/23-25
(Mock-up)
GF
Pour 7B
Works prior to screed casting (Surface
S-V/6-9
preparation & filler board installation)
GF
Works prior to screed casting (Surface
All area
preparation & filler board installation)
Refer to attached
Works prior to screed casting (Surface
Area 1,
preparation & filler board installation)
GL. H-Q / 28 -29
Area 7B, Refer
Works prior to screed casting (Surface
attached drawing,
preparation & filler board installation)
2F
Area-7B & 4B / GL.
Works prior to screed casting (Surface
See attached
preparation & filler board installation)
drawing, 2F
Area 1, Refer to
Works prior to screed casting (Surface
attached plan, Level
preparation & filler board installation)
1
Works prior to screed casting (Surface All Area, Refer to
preparation & filler board installation)
attached plan, GF
Area 7
Works prior to screed casting (Surface
Refer to attached
preparation & filler board installation)
plan
Pour 9C Ramp
Works prior to screed casting (Surface
Refer to attached
preparation & filler board installation)
plan