Q.1 (a).
Q.1 (b).
Q.1 (c).
Q.1 (d).
Q.1 (e).
Q.2
: ET ZC432
: QUALITY CONTROL ASSURANCE & RELIABILITY
: Open Book
: 60%
No. of Pages
=2
: 3 Hours
No. of Questions = 5
: 29/03/2008 (FN)
The number of errors per 200 transactions is a characteristic of interest in a bank. Table 1,
shows the errors for 20 observations randomly selected from all transactions, where each
observation deals with 200 transactions. Comment on the stability of the process in
controlling these errors by constructing an appropriate control chart. If any observation is
outside the control limits assume that the special cause is identified and find the revised
control limits. Is it feasible to expect an error free performance from this system?
[10]
Table 1
Obsevations
Obsevations Errors
1
5
11
2
3
12
3
4
13
4
6
14
5
5
15
6
3
16
7
5
17
8
4
18
9
12
19
10
5
20
Q.3
[4 X 5 = 20]
Errors
4
5
6
5
2
3
2
11
4
3
An optical sensor has a Weibull time to failure distribution with a scale parameter of 250
h and shape parameter of 0.5. What is the reliability of the sensor after 600 h operation?
Find the mean time to failure. If the shape parameter is 1, then what would be the
reliability and MTTF?
[10]
ET ZC432
Page 1 of 2
PAGE 2
Q.4
Determine the single sampling plans that will reject lots that are 1.3% non conforming 8%
of the time. Use acceptance numbers of 1, 3 and 5. From a consumers point of view,
which of these three plans would you choose?
[10]
Q.5
(a)
(b)
(c)
(d)
Find a 99% confidence interval for the ratio of the variances of the delay times for
the two vendors.
What assumptions are needed to solve part a?
Can we conclude that the first vendor has a smaller variability regarding delay
times than the second? Use significance level of 0.05.
Which vendor would you select and why?
[10]
********
ET ZC432