Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
26,September 22-25,2002
Keywords
Kenya, Olkaria Ill, %dimensional numerical model, early
generation plant, ORMAT Energy Converter
ABSTRACT
The Olkaria 111geothermal project is the first private geothermal project in Kenya. The field development of the project
was managed by ORMAT geothermal group and included flow
testing of wells drilled in the past by a subsidiary of the Kenya
National ElectricityAuthority - Kenya Power Company (KPC);
field analysis including a three-dimensionalnumerical simulation model of the reservoir and the successful drilling of nine
new wells. The field development is a combined effort of
ORMAT and some of the leading geothermalengineering groups
worldwide.
In parallel with the field development,ORMAT constructed
an early generation power plant based on binary type
ORMAT@Energy Converters (OECs) which, in addition to the
generation and sale of electricity at an early stage of the project,
has enabled testing of old and new wells for an extended period
of time. This has allowed for on-going and continuous updating
of the field parameters during the conceptual design and detailed engineering phases of the project.
Introduction
OrPower 4, a special purpose project company, has secured
the right to develop and operate the Olkaria 111geothermal development concession within the Rift Valley in Kenya. This
concession has an area of approximately 12.4 km2 and encompasses the West Olkaria geothermal resource which was first
confiied to exist with the drilling of exploration well OW301 in 1983.
The Olkaria 111(West Olkaria) area lies 3 km to the west
of the 45 MWe Olkaria I (Olkaria East) geothermal development area where the first 15 MWe unit came on line in June
1981 and the third and final unit started operation in March
561
562
I nratinn F Im\
in the centre of the eastern half of the concession area. The exploration wells in the Concession area (other than well OW401) generally indicate increasing temperature with depth, with
near isothermal conditions through the shallow reservoir zone
(1500 - 800 masl) indicating good vertical permeability. However, the temperature gradients below this depth range are typically conductive suggesting that the deeper zone permeabilities
are not high.
Geothermal fluids from the deep, high temperature reservoir
zone rise in the centre of the eastern half of the Concession area,
through limited permeability, into the shallower reservoir which
has good vertical and horizontal permeWest
ability. The models suggested good 225001
phase high enthalpy production would
be obtained from wells drilled into the
2000
zone centred on this postulated upflow.
Figure 2 presents a summary crosssection through the conceptual model.
1500
Drilling
New Wells
Phase I in the well drilling program
was commenced in February 2000, utilizing Nabors Drilling International
Limited of USA as drilling contractor,
with the drilling of five new wells as
part of the field appraisal program as
defined by the tender issued by the
Government of Kenya (GOK), followed by Phase I1 drilling, the comple-
East
1000
500
-500
I
192000
192500
193000
193500
194000
194500
195000 195500
Location E (m)
196000
196500
5 63
197w)O
197500
191
Conclusion
The Olkaria III field development program met all its
planned goals as far as budget
and timetable were concerned.
The average productivity
achieved from each of the
wells exceeded initial expectations and as a result a reduced
number of wells were required
to be drilled to support the
power plant as planned.
It is considered that the primary reasons for the better
than expected results were
~ombiningof pe~odicallyupdated the field modeling with
good well planning and good well drilling programming and
management,This successful field developmenthas been a combined effort by ORMAT and some of the leading engineering
groups in the geothermal world: PB power of New Zealand,
Orkostufnon of Iceland and GeothermEx of the USA, as well
as the geothermal experts in various disciplines of KenGen of
Kenya.
LoceUon E (m)
During the period March 2001 to March 2002, four additional wells were drilled, completed and tested, and two wells
were commenced but not completed. See Figure 3 for well locations.
The production success rate of the wells was far in excess
of expectations,thus allowing termination of the drilling operations in March 2002.
Each well was i n i t i ~ l ydischarged
vertically for a few hours to clear cuttings
Proven Indiaative Capacity to Date -with 1st order NCO Correation
to 4 April 2002
Tested Available Steam I Water
from the well-bore prior to diverting the
I
flow through a horizontal discharge pipeAvailable Available
Total
line; a Russell James lip pressure pipe;
Stestm
Water TotaIF30
WCG
Themat Thennal Available
Power
Thermal
P,,E t & , M u w , How Mass Flow Enthalp; gvt %) Power
Weit
and into an atmospheric cyclone separaSteam
Water
Power
CapciQ
(Barn)
(barn)
W S )
W S )
0
Mwe
torhilencer fitted with a weir box to al(Wt)
OIMWt) (Mwt)
low monitoring of the separated water I
~~~~~~
564