Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Concept Information
Results of
URS ArcGIS
Location Suitability
Screening Study
-1-
Point Thomson
Central Pad
Compression
Utilities
Process
Power
Generation
Potential
Pipeline Routes
Alaska LNG
Pipeline Elevation Design Example
GIS
Suitability
Areas
8 Recommended
Sites Based on
Analysis of GIS
Reconciled List of 8
Common Sites
Initial
List of
21 Sites
Marine
Pipeline
Approach
LNG Siting
Site
Acceptability
Stakeholder
Impacts
ERL
Geotechnical
Location Shift To
Match Terrain
VMT Co-location
Considered
Conceptual
Engineering for
5 Validated
Rep. Locations
Expert Input to
Support
Evaluation
Continued Expert
Input to Support
Evaluation
QRA for
Representative
Sites
Lead Site
Selected
A parallel path Site Selection process that uses independent approaches and provides checks & balances.
-5-
Prudhoe Bay
Continued data capture/analysis of PBU gas
composition
Preliminary CO2
Re-Injection
Design
Pipeline
Refined route from PBU to Livengood, finalizing
route from Livengood to Cook Inlet
Working special design areas
- Atigun Pass
- Yukon River
- Cook Inlet
COOK INLET
10
Results of
URS ArcGIS
Location Suitability
Screening Study
11
Cultural Resource
Survey Areas
Back-Up Material
Attachments to Oct-12 Letter to Governor Parnell
Attachment 1
Technical
Committee
Concept Team
Lead: ExxonMobil
Producing Fields
Pipelines
LNG Plant
Integration Team
Lead: BP
Lead: ConocoPhillips
Lead: ExxonMobil
Attachment 2
Liquefaction Plant
Capacity:
15 18 million tonnes per annum (MTA)
3 trains (5-6 MTA / train)
Potential areas: 22 sites assessed in Cook Inlet, Prince
William Sound and other Southcentral sites
Footprint:
400 - 500 acres
Peak Workforce: 3,500 - 5,000 people
Required Steel: 100,000-150,000 tons
Storage / Loading
Pipeline
Gas Treating
Located at North Slope or Southcentral LNG site
Remove CO2 and other gases and dispose / use
Footprint:
150 - 250 acres
Peak Workforce: 500 - 2,000 people
Required Steel: 250,000 - 300,000 tons
Among largest in world
Attachment 3
PTU
Settlement,
Joint Work
Agreements
GO
Concept
Selection
Decision
GO
PreFEED
FEED
GO
Decision
(Front-End
Engineering &
Design)
Decision
to Build the
Project
EPC
GO
(Engineering,
Procurement &
Construction)
(Today)
Peak Staffing:
Cost ($):
~200
400 - 500
500 1,500
9,000 15,000
Tens of Millions
Hundreds of Millions
Billions
Tens of Billions
12 - 18 Months
2 - 3 Years
5 - 6 Years
Activities
Progress:
Complete:
Preliminary engineering to
refine concept
Business structure
Financing plan
Execute:
Final engineering
Financing
Procurement
Fabricate / Logistics / Construct
Prepare for Operations
Implement business
structure & agreements
Commission / start-up
* NOTE: Duration of various phases may be extended by protracted resolution of fiscal terms, permitting and regulatory delays, legal challenges,
changes in commodity market outlook, time to secure long-term LNG contracts, labor shortages, material & equipment availability, weather, etc.
LNG Project
Operations