Sei sulla pagina 1di 17

Polaris

Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 1 of 17


PAINTING - PROCESS EQUIPMENT AND PIPING

TABLE OF CONTENTS PAGE


I. SCOPE 2

II. REFERENCES 2

III. GENERAL 3

IV. SURFACE PREPARATION 5

V. GALVANIZING 6

VI. APPLICATION OF COATINGS 7

VII. MATERIAL 9

VIII. CLEANLINESS 9

IX. INSPECTION 10

X. SAFETY 11

XI. PAINTING SYSTEMS AND COLOR CODES 11

APPENDIX A DAILY COATING INSPECTION REPORT 12

APPENDIX B EQUIPMENT PAINTING SUMMARY 13

TABLE 1 PAINTING SYSTEMS AND COLOR CODES 14



Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 2 of 17


PAINTING - PROCESS EQUIPMENT AND PIPING

I. SCOPE

This Standard, together with the Project Painting Schedule, covers surface
preparation and priming, in addition to the subsequent field touch-up of prime coats,
and field application of finish protective coatings for processing equipment, structural
steel and piping. It is intended that all steel will be shop blasted and primed, at a
minimum, before erection. This Standard allows for shop finishing of processing
equipment , structural steel and piping where practical.

This Standard also covers the requirements for Hot Dip Galvanizing of Steel surfaces
where applicable.

II. REFERENCES

The following Steel Structures Painting Council (SSPC) publications are to be used
with this Standard, as applicable:

A. Volume 1 - Good Painting Practice

B. Volume 2 - Systems and Specifications:

1. SSPC-PA1 Shop, Field and Maintenance Painting

2. SSPC-PA2 Measurement of Dry Paint Thickness with Magnetic Gages

3. SSPC-AB1 Mineral and Slag Abrasives

4. SSPC-SP1 Solvent Cleaning

5. SSPC-SP2 Hand Cleaning

6. SSPC-SP3 Power Tool Cleaning

7. SSPC-SP5 White Metal Blast Cleaning

8. SSPC-SP6 Commercial Blast Cleaning

9. SSPC-SP7 Brush-Off Blast Cleaning

10. SSPC-SP8 Pickling



Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 3 of 17


11. SSPC-SP10 Near-White Blast Cleaning

12. SSPC-SP11 Power Tool Cleaning To Bare Metal

III. GENERAL

A. This Standard covers the general and specific requirements for painting
processing equipment, outlining type, color, grade and number of coats of paint
required and its application. The number and identification of such items are
indicated in the Project Painting Schedule. Equipment and piping shall be
painted according to the indicated color code.

B. All exposed steel surfaces and steel surfaces under fireproofing shall be painted
unless noted otherwise. The inside surface of towers and vessel skirts shall be
prepared, primed and finished coated. Those items requiring fireproofing shall
require surface preparation, prime coat and barrier coat.

C. The following shall not be painted unless specifically required by the Client or
otherwise noted in the Project Painting Schedule and/or Project Specifications:

1. Concrete and fireproofing surfaces

2. Brick work

3. Transite material

4. Aluminum, stainless steel, galvanized or corrosion resistant surfaces (see
III. K below)

5. Machined surfaces and finished metal operating parts of machinery, valves
or other equipment, such as valve stems, shafts, etc.

6. Glass, tile or ceramic surfaces

7. Contact surfaces of structural steel members to be connected by high
strength bolts in friction type connections may be primed only with
inorganic zinc.

8. Inside surfaces of towers, exchangers, vessels, apparatus and piping except
in specific cases shown in Project Specifications or drawings.

9. Factory finished items that are coated to CLIENT Standards or an
approved alternate system.


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 4 of 17



10. Insulation surfaces

11. Windows, gauge glasses, nameplates, meter faces and related surfaces

12. Fiberglass or other plastic surfaces

13. (see J. below)

The above surfaces must be left clean and free of paint resulting from the
painting operation.

D. In general, and where practical, all shop fabricated structural steel, shop
fabricated pipe, shop fabricated equipment and lengths of un-fabricated pipe
shall be shipped with the prime coat applied in accordance with the requirements
of the appropriate paint system, based on operating temperature.

E. Steel surfaces which have not been shop primed shall receive the same surface
preparation and prime coats in the field as specified for shop applied prime coats.

F. Paint Manufacturer's recommendations for mixing and application methods shall
be followed.

G. No two consecutive coats can be the same color.

H. All non-galvanized metal to metal surface cracks and openings that are not seal
welded shall be caulked with a polyurethane sealant or a high temperature
sealant.

I. At least one responsible supervisor who is thoroughly familiar with the specified
painting, materials and methods, shall be present at all times to direct the work.

J. Prior to abrasive blasting and /or painting, all parts of controls, valves, sight
glasses, name tags, machinery, etc., that are not to be blasted and painted and are
subject to damage from either the blast or the abrasive material, shall be properly
protected by the Contractor. All items, units, or materials so damaged either shall
be repaired or replaced by the contractor at no cost to the Client. Particular
protection shall be provided for manufacturers' identification plates on pressure
vessels and similar units. These plates shall not be removed, but thoroughly
protected in place.

K. When Galvanized or Cadmium plated fasteners are used to connect painted
structural steel or painted flanged pipe and where galvanized steel shoes are


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 5 of 17


attached to painted pipe, they shall be coated in accordance with Table 1 System
XIII.


IV. SURFACE PREPARATION

A. New Steel Surfaces:

1. Remove all grease, oil or other surface contaminants in accordance with
SSPC-SP1 and/or high pressure water washing at 2500 psi minimum.

2. All surfaces to be coated shall be grit blasted to a "near white" finish as
defined by SSPC-SP10.

B. Shop Primed Surfaces:

1. Remove all grease, oil or other surface contaminants in accordance with
SSPC-SP1 and/or high pressure water washing at 2500 psi minimum.

2. All weld seams and new steel and areas of coating failure or erection scars
to bare metal, shall be abrasive blasted to a "near white finish" in
accordance with SSPC-SP10. Primer shall be inorganic zinc applied in
accordance with Table 1. Adjacent areas shall be masked to protect
previously primed sections from overblast and overspray.

3. Whenever abrasive blasting is not feasible and the Client approves, all
weld seams, erection scars and areas of coating failure shall be cleaned in
accordance with SSPC SP-11 Power Tool Cleaning to Bare Metal. Primer
shall be a high build epoxy maintenance primer applied by brush to a dry
film thickness of 3-5 mils for surfaces up to 180 F, Dampney 261-09 for
surfaces 181-500 F and Dampney 245 for surfaces 501- 1000 F.

C. Abrasive blasted surfaces shall have an anchor pattern (surface profile) of the
blasted steel to meet MANUFACTURERS' recommendation.

D. Compressed air blasting abrasive shall be a silica free material and be free of all
dust, dirt, salts and other foreign material. The abrasive shall be kept dry at all
times and shall not be reused. For centrifugal wheel blasting, S230 or S280 steel
shot shall be mixed with G-40 grit to obtain sharp, angular G-4 profile.

E. All compressed air used for sandblasting or painting shall be free of oil and
moisture. Suitable aftercoolers, air filters and traps shall be installed on all
sandblasting and spray-painting pots. The air will be filtered and cleaned to the


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 6 of 17


degree that contaminants still present in the filtered air, such as moisture, oil,
dust or other foreign particles, will pass the white blotter test. To test for the
presence of contaminants, an 8-1/2" x 11" white blotter shall be held 18 inches
from the air supply for a period of two minutes prior to the start of each
operation. Only minimal contaminants shall be visible on the blotter at the end
of this test. Compressed air shall be supplied at a minimum nozzle pressure of
90 psig (as measured by a needle gauge), or as determined by the equipment
being used and the material being applied.

F. Surfaces cleaned by sandblasting shall be primed as soon as practicable, but no
later than the end of the same working day and before any visible rusting occurs.
Any steel not primed as noted above shall be re-blasted.

G. The blasting and painting sequence shall be planned to prevent dusting and
contamination of freshly coated surfaces.

H. The sandblasted or cleaned surface shall be rendered dust-free prior to the
application of the primer. This can be accomplished by blowing off the surface
with clean, dry air or by using an industrial vacuum cleaner.

V. GALVANIZING

A. The galvanizing of ladders, ladder cages, platform steel, handrails and all
necessary bolting for these surfaces shall conform to the following ASTM
Standards:

1. ASTM A 123 Specification for Zinc (Hot-Dip Galvanized)
Coating on Iron and Steel Products (structural steel
members over 1/8 inch thick)

2. ASTM A 1536 Specification for Zinc Coating (Hot-Dip) on Iron
and Steel Hardware (anchor bolts and bolts, nuts
and washers used for general structural bolting)

3. ASTM A 325 Specification for High-Strength Bolts for Structural
Steel Joints (bolts, nuts and washers used for high-
strength structural bolting)

4. ASTM A 525 Specification for General Requirements for Steel
Sheet, Zinc Coated (Galvanized) by the Hot-Dip
Process (structural steel members or steel sheet less
than 1/8 inch thick in accordance with coating
Class G 235)


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 7 of 17



5. ASTM A 563 Specification for Carbon and Alloy Steel Nuts

B. A good fit of zinc coated fasteners is required. To assure a good fit any or all of
the following operations shall be performed:

1. Threads in nuts for general structural or high strength bolting shall be
tapped over size after galvanizing in accordance with ASTM A 563.

2. Bolt threads shall be cleaned of excess zinc by cutting, rolling or finish
tooling as required.

3. Washers shall be separated and reamed out when necessary to assure a
good fit over the bolt.

C. Hot dipped galvanized surfaces which have been field welded, burned, or
damaged in any way, shall be power tool cleaned and touched up with two coats
of a high build epoxy primer. The minimum dry film thickness of the primer
coating shall be 6 mils.

D. When service conditions dictate, the Painting Schedule will specify the coating
of galvanized steel components. In these cases, coatings shall be applied in
accordance with Table 1 System XIII or an alternate where specified.

VI. APPLICATION OF COATINGS

A. Except where this Standard provides otherwise coatings shall be applied in
accordance with the Manufacturer's recommendations.

B. Coatings may be applied by spray, brush or roller using Manufacturer's
recommended equipment and approved by the Client, however, regardless of
Manufacturer's recommendations, inorganic zinc coatings shall be applied by
spray, with properly agitated equipment over an abrasive blasted (SSPC-SP10)
surface.

C. Spray painting will only be permitted when conditions permit and the Client
approves after the following have been considered.

1. When weather conditions, including wind speed and direction are
favorable.
2. Adjacent or downwind equipment is protected from overspray.
3. Only spray painting is practical to reach difficult areas or painting hot
surfaces.


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 8 of 17


4. The type of coating dictates the need for spraying.

D. Surfaces shall not be painted during wet, damp or foggy weather; when the
relative humidity is over 85%; when the metal surface temperature is less than
5F above the dew point or whenever the Client judges the conditions are not
favorable. Paint shall not be applied when the metal surface or ambient
temperature is below 50F or above 110F unless specifically approved by the
Manufacturer as being acceptable and Client approves.

E. Paint shall not be applied when the ambient temperature is expected to drop
below 32F before the coating has had time to cure.

F. Paint shall not be applied when extremely windy or dusty conditions exist.

G. The Manufacturer's recommendations for thinning, mixing, handling and
application of the products are considered a part of this Standard.

H. Equipment and piping may be painted before the hydrostatic test (hydrotest);
however, all field joints, welds and threaded connections may be primed only,
with inorganic zinc, until the test has been completed and approved by the
Client. In cases where piping is painted before hydrostatic test (hydrotest) each
successive coat of paint will be stopped two inches before the preceding coat at
each joint to allow for proper tie-in of subsequent coats.

I. Pipe flanges with an operating temperature less than 180F shall be caulked with
a polyurethane caulk prior to the application of the final coat.

J. Pipe flanges with an operating temperature of 181F to 500F shall be caulked
with Dow Corning 732 silicone caulking compound after the final paint coat has
been applied.

K. All coatings shall be uniformly applied to form a smooth continuous film free of
sags, runs, spots or other blemishes. Weld seams, edges, crevices, nuts, and
threaded studs shall be striped by brush to assure complete coverage without
holidays.

L. Prior to the application of any coat, all damage done to the previous coat shall be
touched up with the corresponding specified coating. If an entire system is
damaged after completion of the finish coat, then the damaged area shall be re-
blasted and refinished with the entire system.



Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 9 of 17


M. Prior the application of any coat, all contamination, including grease, dirt, salt, or
other substances which might affect intercoat adhesion, shall be cleaned in
accordance with Section IV. A. 1.

VII. MATERIAL

A. Primer and topcoats shall be as specified in Table 1.

B. Primers (whether shop or field applied) and topcoats for any given application
shall be compatible materials.

C. It is recommended that paint be purchased in five gallon pails rather than 55
gallon drums, to facilitate handling in the field. Drums may be used when
painting large areas such as tanks.

D. Paint shall be stored in a well-ventilated area due to its flammability. This
storage area must be kept clean and free from any accumulation of partially
filled paint containers, oily waste, rags, etc.

E. When paint is stored for any length of time, the containers shall be turned per the
Manufacturer's recommendations to prevent undue settlement of the pigments.
All paint stocks shall be rotated to utilize old material first (first in/first out).
Manufacturer's shelf life limits shall be strictly followed.

F. All containers shall be tightly covered at all times to prevent skinning of the
surface. If skinning does occur, it shall be removed before stirring. If necessary,
paint from partially filled containers shall be strained before being applied to
remove foreign matter which may be present.

VIII. CLEANLINESS

A. Sufficient drop cloths, shields and other protective devices shall be used to
prevent spray or drops from fouling surfaces not being painted.

B. Empty containers, saturated rags and waste shall be removed from the work area
at the end of each day and disposed of properly to ensure that the possibility of
combustion is eliminated. Waste paint and solvent shall be disposed of in
accordance with CLIENT Procedure 4217 Refinery Waste Handling Procedure
(Environmental Procedure #S001) and CLIENT Procedure 0171 Satelite
Accumulation Procedure (Environmental Procedure #S-004).

C. Spent blast abrasive shall be swept and piled up before the end of each work day
and piles shall not be left to accumulate.


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 10 of 17



D. Upon job completion, all debris and trash shall be removed, and adjacent
surfaces which have been marred, oversprayed or spotted, shall be cleaned or
repaired to restore them to their original condition.

E. Masking tape and other protective covers shall be completely removed after
completion of painting.

IX. INSPECTION

A. The Contractor is responsible for providing inspection to assure that the
requirements of this standard are met. The Client or Client's Representative
may, at his discretion, inspect the work at any stage of completion. Inspection
for final acceptance will be done by the Client or Client's representative.

B. Inspection Hold points - There will be an inspection hold point between each
phase of the work (surface preparation, prime coat, intermediate coat, finish
coat etc.) where the Contractor's inspector and the Client's inspector shall both
have an opportunity to inspect all portions of the work in progress. Any
deficiencies found during either the Contractor's or Clients inspection shall be
corrected before work proceeds to the next step of the operation. Contractor
shall make all parts of the work accessible to the Client or Client's
Representative to perform inspections.

C. The film thickness of each coating shall be checked by each of the following
methods:

1. Immediately after application, wet film thickness readings shall be taken
with a wet film thickness gauge.

2. After curing, film thicknesses of each coat shall be measured by the
procedure described in SSPC-PA2

D. Contractor will provide the Client with a daily schedule detailing where all
painting activities are being performed and will give as much notice as is
practical to schedule inspections so as not to interfere with the flow of the
Contractors work.

E. The Contractor shall provide daily Coating reports using the form shown in
Appendix A or an approved alternate for all areas being worked on. Contractor
shall also provide a Summary Coating Report for every major piece of
equipment (Drums, Towers, Vessels, Exchangers, Pumps etc..) upon
completion of the work as shown in Appendix B or an approved alternate.


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 11 of 17



F. Defective work shall be corrected by the Painting Contractor at his sole
expense.

G. No inspection tolerance or allowance will be made for the skill of the workmen.


X. SAFETY

A. All necessary and prudent precautions shall be taken to ensure the safety of
personnel and property. Heavy concentrations of volatile or toxic fumes shall be
avoided. In confined spaces, blowers or exhaust fans may be necessary. Where
good practice dictates, masks, non-sparking tools and other such special
equipment shall be used. Blasters shall use approved hoods with an air supply
that conforms with Grade D Breathing Air Standards.

XI. PAINTING SYSTEMS AND COLOR CODES

The painting system and color codes to be used shall be indicated on the Project
Painting Schedule and are described in Table 1.


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 12 of 17


APPENDIX A

Area: Date:
Equipment: Inspector:
J ob Description: Contractor:
Foreman/Sup.:
Ambient Conditions
TIME
RELATIVE HUMIDITY
DRY BULB
WET BULB
STEEL TEMP.
DEW POINT
WIND SPEED
WEATHER
(C) CLEAR, (PC) P. CLDY, (R) RAIN
EQUIPMENT
AIR SUPPLY Y N Y N
BLOTTER TEST PERFORMED? EQUIPMENT MEETS COATING MFG. RECOMMENDATIONS
MOISTURE TRAPS/AFTERCOOLERS IN USE WORKING AGITATORS ON PAINT POTS FOR PRIMER APPLICATION
MINIMUM OF 90 PSI FOR ALL BLASTING OPERATIONS OTHER (SPECIFY)_______________________________________
SURFACE PREPARATION
INSPECTION OF COATING APPLICATION
COMMENTS (CONCERNS ABOUT QUALITY, PRODUCTIVITY, EQUIPMENT, SAFETY ETC..)
COMMENT
DAILY COATING INSPECTION REPORT
COMMENTS
ACT. WFT BATCH #
ITEM SPEC. STANDARD ACCEPT REJ ECT
ACCEPT REJ ECT COATING APPLIED ITEM REQ'D WFT SYSTEM
SUR. PROFILE


Polaris
Engineering
Standard
1400.1
Rev.: 6
Date: 01/19/05
Page: 13 of 17


APPENDIX B

Area/Unit: Date:
Equipment Number: Foreman/Sup.:
Equipment Name: Contractor:
EQUIPMENT DATA
External Operating Temperature Insulated (Y/N)
Specified Coating System Fireproofed (Y/N)
Coating Data - External Coating
Prime Coat
Intermediate Coat
Intermediate Coat
Finish Coat
Coating Data - Internal Coating (if applicable)
Prime Coat
Intermediate Coat
Intermediate Coat
Finish Coat
Comments:
Final Acceptance By:
Mils (total) Inspected Name & Co.
Print Name Company Signature Date
(Mfg. and Name) # Preparation Field Applied
EQUIPMENT PAINTING SUMMARY
Shop or Avg. DFT Date Inspector
Avg. DFT
Mils (total) Field Applied
Shop or Surface
Preparation
Coating Batch Surface
Batch
#
Coating
(Mfg. and Name)
Inspector
Name & Co.
Date
Inspected
POLARIS ENGINEERING STANDARD 1400.1
REV: 6
TABLE 1 - PAINTING SYSTEMS AND COLOR CODES PAGE: 14 OF 17
DATE: 01/28/05


NORM MAX SURFACE WET DRY WET DRY WET DRY
SYSTEM EQUIPMENT TEMP TEMP PREPARATION PRIMER MILS MILS INTERMEDIATE MILS MILS FINISH MILS MILS COLOR SERVICE

I.A
STRUCTURAL STEEL,
EQUIPMENT & UNINSULATED
HORIZONTAL VESSELS,
SHELLS & TUBE
EXCHANGERS
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-9 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 HESS GREEN
STRUCTURAL STEEL,
STANCHIONS, PUMPS,
MOTORS, COMPRESSORS,
SEE NOTES 3 AND 4
I.B
GENERAL EQUIPMENT, GAS
TURBINE HOUSING AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 SURF GRAY
GAS TURBINE HOUSINGS
SEE NOTES 3 AND 4
I.C
LADDERS & PLATFORMS
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 SURF GRAY
PLATFORMS, LADDERS, FIN-
FAN PLENUMS, ELECTRICAL
CONDUIT
SEE NOTES 3 AND 4
I.D
UNINSULATED PIPING,
CLEAN OIL TANKS (SHELL
AND STAIRS), UNINSULATED
VERTICAL VESSELS,
COMPRESSOR BUILDINGS
(EXTERIOR)
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
WILLOW
GREEN
ALL PROCESS PIPING &
OFFSITE PIPING: GASOLINE,
BENZENE, TOLUENE, XYLENE,
NAPHTHA, C9, BALLAST, 2 OIL,
UTILITY
SEE NOTES 3 AND 4
I.E
UNINSULATED PIPING,
WATER PIPING AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
SAFETY
GREEN
ALL TYPES OF WATER:
TEMPERATE, WELL, DESAL,
SOUR, PROCESS AND OFFSITE
SEE NOTES 3 AND 4
I.E.2
UNINSULATED PIPING,
WATER PIPING AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300 /
B56-301 BAND
3.5-5 2-3
SAFETY
GREEN /
YELLOW
BAND
PROCESS WATER
SEE NOTES 3 AND 4
I.E.3
UNINSULATED PIPING,
WATER PIPING AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300 /
BG56-300 BAND
3.5-5 2-3
SAFETY
GREEN /
ORANGE
BAND
SOUR WATER
SEE NOTES 3 AND 4
I.F
UNINSULATED PIPING, FUEL
GAS AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 YELLOW
FUEL GAS
SEE NOTES 3 AND 4
I.G
UNINSULATED PIPING, FIRE
WATER, FIRE HYDRANTS &
MONITORS
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 SWIFT RED
FOAM, FIRE WATER
SEE NOTES 3 AND 4
I.H
AIR DRIERS, RECEIVERS &
PIPING AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
AIRLINE
BLUE
AIR
SEE NOTES 3 AND 4
POLARIS ENGINEERING STANDARD 1400.1
REV: 6
TABLE 1 - PAINTING SYSTEMS AND COLOR CODES PAGE: 15 OF 17
DATE: 01/28/05


NORM MAX SURFACE WET DRY WET DRY WET DRY
SYSTEM EQUIPMENT TEMP TEMP PREPARATION PRIMER MILS MILS INTERMEDIATE MILS MILS FINISH MILS MILS COLOR SERVICE

I.J
UNINSULATED PIPING, TANK
ROOFS, BULLETS, SPHERES,
COMPRESSOR BUILDINGS
(INTERIOR)
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 WHITE
OFFSITE PIPING: PROPANE,
BUTANE, J ET FUEL, KERO, TEL,
SEE NOTES 3 AND 4
I.J .2
UNINSULATED PIPING, TANK
ROOFS, BULLETS, SPHERES,
COMPRESSOR BUILDINGS
(INTERIOR)
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300 /
B56-301 BAND
3.5-5 2-3
WHITE /
BLUE BAND
OFFSITE PIPING: NITROGEN
SEE NOTES 3 AND 4
I.J .3
UNINSULATED PIPING, TANK
ROOFS, BULLETS, SPHERES,
COMPRESSOR BUILDINGS
(INTERIOR)
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300 /
B56-300 BAND
3.5-5 2-3
WHITE /
ORANGE
BAND
OFFSITE PIPING: ANHYDROUS
AMMONIA VESSELS AND
PIPING
SEE NOTES 3 AND 4
I.K
UNINSULATED PIPING
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 BLACK
OFFSITE PIPING: 6 OIL,
BUNKERS, CAT FEED, FLARE
LINES, HAGO
SEE NOTES 3 AND 4
I.L
DELETED

OFFSITE PIPING: PARAXYLENE
I.M
UNINSULATED PIPING,
BLACK OIL TANKS (SHELL &
STAIRS)
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
FOLIAGE
GREEN
OFFSITE PIPING: BTX SLOP,
CRUDE OIL
SEE NOTES 3 AND 4
I.N

CAUSTIC AND ACID PIPE
AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
CANYON
SAND
CAUSTIC AND ACID PIPING
SEE NOTES 3 AND 4
I.P
DELETED


I.Q
DELETED


I.R
CAUSTIC HANDLING
STATIONS, SAFETY SHOWERS AMB
TO 180
F
225 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-10 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3
SAFETY
ORANGE
ALL
SEE NOTES 3 AND 4
POLARIS ENGINEERING STANDARD 1400.1
REV: 6
TABLE 1 - PAINTING SYSTEMS AND COLOR CODES PAGE: 16 OF 17
DATE: 01/28/05


NORM MAX SURFACE WET DRY WET DRY WET DRY
SYSTEM EQUIPMENT TEMP TEMP PREPARATION PRIMER MILS MILS INTERMEDIATE MILS MILS FINISH MILS MILS COLOR SERVICE

II.A
DELETED


II.B
CONCRETE BLOCK
BUILDINGS
AMB AMB SSPC-SP10
SHERWIN-
WILLIAMS HEAVY
DUTY BLOCK
FILLER
18-34 10-18
SHERWIN-
WILLIAMS
METALATEX S-G
4-11 1.5-4
SHERWIN-
WILLIAMS
METALATEX S-G
4-11 1.5-4
CANYON
SAND W/
HESS GREEN
DADO
ALL EXTERIOR SURFACES
II.C
CONCRETE GUARDS
AMB AMB SSPC-SP10
SHERWIN-
WILLIAMS
METALATEX S-G
4-11 1.5-4
SHERWIN-
WILLIAMS
METALATEX S-G
4-11 1.5-4 YELLOW
ALL
III.
UNINSULATED STACKS,
PIPING, EXPOSED PARTS OF
EXCHANGERS, & OVERHEAD
CONDENSER BUNDLES
181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 261-03 3.5-4 2-2.5
ALUMINUM
GRAY
ALL EXPOSED FLANGES,
VALVES, SMALL
CONNECTIONS AND STEEL
SURFACES
IV.A
UNINSULATED PIPING
181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 268-10 3.5-4 2-2.5 AQUA
PROCESS PIPING - ALL
IV.B
UNINSULATED HORIZONTAL
VESSELS & EXCHANGERS 181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 268-33 3.5-4 2-2.5 HESS GREEN
ALL
IV.C
UNINSULATED VERTICAL
VESSELS & EXCHANGERS 181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 268-28 3.5-4 2-2.5
VISTA
GREEN
ALL
V.
UNINSULATED PIPING
181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 267-12 3.5-4 2-2.5
FUEL GAS
YELLOW
FUEL GAS
VI.
HEATERS & BOILERS
181 F
TO
500 F
550 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5 DAMPNEY 262 3.5-4 2-2.5 BLACK
ALL
VII.
UNINSULATED STACKS
PIPING & EXPOSED PARTS OF
VESSELS & EXCHANGERS 501+ F 1000 F SSPC-SP10 DAMPNEY 245 4.5-6 1.5-2 DAMPNEY 231-03 7.5-10 1.5-2
ALUMINUM
GRAY
ALL
POLARIS ENGINEERING STANDARD 1400.1
REV: 6
TABLE 1 - PAINTING SYSTEMS AND COLOR CODES PAGE: 17 OF 17
DATE: 01/28/05


NORM MAX SURFACE WET DRY WET DRY WET DRY
SYSTEM EQUIPMENT TEMP TEMP PREPARATION PRIMER MILS MILS INTERMEDIATE MILS MILS FINISH MILS MILS COLOR SERVICE

VIII.
HEATERS, BOILERS & STACKS
501+ F 1000 F SSPC-SP10 DAMPNEY 245 4.5-6 1.5-2 DAMPNEY 232 7.5-10 1.5-2 BLACK
ALL
IX.
INSULATED EXCHANGERS,
VESSELS & PIPING AND ALL
STEEL SURFACES UNDER
FIREPROOFING
AMB
TO
250 F
250 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
SHERWIN-
WILLIAMS
PHENICON HS
7-8 5-6 WHITE
ALL - SEE NOTE 1
X.
INSULATED EXCHANGERS,
VESSELS & PIPING 251 F
TO
700 F
750 F SSPC-SP10
SHERWIN-
WILLIAMS
ZINC-CLADII
B 69V 3/B69 D 11
5-8 3-5
ALL
XI.
INSULATED EXCHANGERS,
VESSELS & PIPING
701 F 1000 F SSPC-SP10 DAMPNEY 245 4.5-6 1.5-2
ALL
XII.
UNDERGROUND PIPING
N/A 325 F SSPC-SP10
SHERWIN-
WILLIAMS
TARGUARD COAL-
TAR EPOXY
B69B60/B69V60
9.5-12 7-9
SHERWIN-
WILLIAMS
TARGUARD COAL-
TAR EPOXY
B69B60/B69V60
9.5-12 7-9 BLACK
ALL
XIII.
GALVANIZED STEEL, PIPING
AND CONDUIT - SEE NOTE 2 AMB
TO
180 F
225 F SSPC-SP7
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
3.5-6
(spot)
3-5
(spot)
SHERWIN-
WILLIAMS
EPOLON MASTIC
GRAY, LT. GREEN
OR WHITE
6-9 5-7.5
SHERWIN-
WILLIAMS
STEEL MASTER 9500
B56-300
3.5-5 2-3 VARIES
ALL SERVICES WHERE
SPECIFICALLY INCLUDED IN
THE PAINTING SCHEDULE SEE
NOTES 3 AND 4

Notes:
1. If steel under fireproofing is galvanized delete primer and apply finish only.
2. If the galvanizing is weathered surface preparation should be a light SSPC-SP7, with a spot prime coat to corroded areas, intermediate and finish as shown. If the galvanizing is in shiny new condition then the ace
surface preparation will be SSPC-SP1 followed by a prime coat of Dampney Endcor 400 Wash Primer at 0.25-0.33 mils DFT followed by Intermediate and Finish coats as above.
3. Finish coat (Steelmaster 9500) thickness in excess of the recommended maximumwill slow final cure considerably. Care should be exercised to avoid excess filmthickness, especially when applying Steelmaster
9500 by airless spray. 9500 by airless spray.
4. When applying Epolon Mastic by brush or roller, two coats will be necessary to obtain the required coating thickness.

Potrebbero piacerti anche