Installation Testing
3
www.ElectaCourse.com
REMEMBER
Visual inspection must precede all testing
4
www.ElectaCourse.com
REMEMBER
Dead testing precedes
Testing
5
www.ElectaCourse.com
Dead Testing
6
www.ElectaCourse.com
Isolate
before carrying
out dead tests
7
www.ElectaCourse.com
Approved voltage indicator
to GS 38
8
www.ElectaCourse.com
Maximum of 4mm on exposed prods
Preferably not more than 2mm
Fused leads
Finger guards
9
www.ElectaCourse.com
Continuity Testing
10
www.ElectaCourse.com
Continuity
Low-resistance
ohmmeter
11
www.ElectaCourse.com
Battery operated instrument
Low voltage
d.c.
d.c.
12
www.ElectaCourse.com
200 mA
4-24V
13
www.ElectaCourse.com
Verifying Continuity
Method 1
14
www.ElectaCourse.com
Caution
Supply must be isolated
15
www.ElectaCourse.com
Temporary Link
Instrument
measures (R
1
+R
2
)
16
www.ElectaCourse.com
Along with verification of the cpc, state
the TWO other tests which are
automatically undertaken when carrying
out this test
17
www.ElectaCourse.com
The value of (R
1
+ R
2
)
Polarity
18
www.ElectaCourse.com
Unacceptable practice of connecting c.p.c.
to outgoing side of fuse or circuit breaker
19
www.ElectaCourse.com
Why is it unacceptable?
20
www.ElectaCourse.com
Unacceptable practice
of connecting c.p.c. to
outgoing fuse or
circuit breaker way
21
www.ElectaCourse.com
Verifying Continuity
Method 2
22
www.ElectaCourse.com
Caution
Caution
Supply must be isolated
23
www.ElectaCourse.com
24
www.ElectaCourse.com
State TWO disadvantages of using
Method 2, as compared to Method 1
25
www.ElectaCourse.com
Use of long wander lead
Value of R2 only obtained
26
www.ElectaCourse.com
What consideration should be given to
the long wander lead?
Its resistance must be measured and
deducted from the measured value
of R
2
27
www.ElectaCourse.com
Continuity of bonding
conductors
28
www.ElectaCourse.com
29
www.ElectaCourse.com
Why is it necessary to remove one end
of a bonding conductor when verifying
its continuity?
30
www.ElectaCourse.com
To avoid the possibility of parallel
earth paths
31
www.ElectaCourse.com
Break in c.p.c.
Parallel path
32
www.ElectaCourse.com
Continuity
of ferrous enclosures
33
www.ElectaCourse.com
Continuity of ferrous enclosures
visual inspection
low resistance ohmmeter
high current test
34
www.ElectaCourse.com
High current test
25A
50 Volt maximum
35
www.ElectaCourse.com
High current-
low-resistance
ohmmeter
36
www.ElectaCourse.com
Insulation Testing
Instrument must be
capable of producing a
short-circuit current of 1mA
37
www.ElectaCourse.com
Caution
Caution
Supply must be isolated
38
www.ElectaCourse.com
Prior to insulation resistance testing
close main switch if testing from tails
fuses in circuit breakers closed
local switches closed/operate two-way
switches during test
neon's/capacitors disconnected
remove voltage sensitive equipment
39
www.ElectaCourse.com
Insulation resistance
testing between live
conductors
40
www.ElectaCourse.com
Insulation resistance
testing between live
conductors and earth
41
www.ElectaCourse.com
State the test voltage and minimum value of
insulation permitted for the following circuits
230V domestic lighting circuit
3 phase, 400V motor circuit
12V SELV circuit
750V discharge lighting circuit
50V FELV circuit
25V PELV circuit
500V - 0.5M
500V - 0.5M
250V - 0.25M
250V - 0.25M
1000V - 1.0M
500V - 0.5M
BS 7671 Table 71A - Page 172
42
www.ElectaCourse.com
Live Testing
43
www.ElectaCourse.com
Measurement of external impedance Ze
impedance
tester
Main switch
open
Earthing conductor
disconnected
.35
44
www.ElectaCourse.com
Why MUST the supply be isolated
before disconnecting the earthing
conductor?
45
www.ElectaCourse.com
Because if you dont you could possibly kill
somebody. If there is a defect with the
insulation, and phase touches exposed
metalwork, the whole of the installation
earthing could become live
46
www.ElectaCourse.com
State THREE other instances where
earth-fault loop impedance testing would
be required.
At the furthest point in every final circuit
At every distribution board
At every socket outlet
47
www.ElectaCourse.com
What precautions should be observed
when undertaking impedance tests within
a circuit?
Ensure that persons or livestock are
not in contact with exposed metalwork
48
www.ElectaCourse.com
- - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Measurement of prospective earth fault current
Prospective fault
current tester
Bonding conductors
connected
49
www.ElectaCourse.com
Measurement of prospective short circuit fault current
Prospective fault
current tester
50
www.ElectaCourse.com
Why is it necessary to verify the value
of prospective fault current at the origin
of an electrical installation?
To ensure the rated breaking capacity
of the main switch and overcurrent devices
are capable of breaking the prospective
fault current level